CN212611977U - Protective shed frame crossing railway line - Google Patents
Protective shed frame crossing railway line Download PDFInfo
- Publication number
- CN212611977U CN212611977U CN202020380966.3U CN202020380966U CN212611977U CN 212611977 U CN212611977 U CN 212611977U CN 202020380966 U CN202020380966 U CN 202020380966U CN 212611977 U CN212611977 U CN 212611977U
- Authority
- CN
- China
- Prior art keywords
- ceiling
- railway
- cross
- sliding rails
- upright columns
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Tents Or Canopies (AREA)
Abstract
The utility model discloses a stride protection rack of railway line, include: the railway track comprises upright columns, cross beams, sliding rails and a ceiling, wherein the upright columns are distributed on two sides of a railway line in parallel, the cross beams are installed on the top ends of the upright columns along the railway extending direction, the sliding rails with upward openings are installed on the top ends of the cross beams, the ceiling is installed at the upper ends of the sliding rails, at least four sliding blocks are arranged at the bottom of the ceiling, and the sliding blocks freely slide inside the sliding rails. The movable sectional ceiling is adopted, so that the movable sectional ceiling can be moved, and the ceiling can be installed and disassembled in a sectional manner, so that the movable sectional ceiling is practical and convenient, and saves manpower; because the cooperation of slide rail and slider is used, can follow the ceiling that slides from beginning to end in certain direction, and pass through the connecting rod through first through-hole and the second through-hole on the slider and connect, can fix a position fast and fixed ceiling, avoid the ceiling to slide along the slide rail.
Description
Technical Field
The utility model relates to a technical field at construction appurtenance, more specifically say, the utility model relates to a stride protection rack of railway line.
Background
With the construction of large-scale roads and bridges, in order to not influence the smoothness of the existing roads, temporary protective shed frames are usually erected on the existing roads. At present, a hoisting method for binding I-shaped steel by using a steel wire rope is adopted when construction units carry out construction, workers often have difficulty in dismounting when binding or removing the steel wire rope on a protective shed frame, the workers are dangerous in picking up the steel wire rope in high-altitude operation, and the time and the work efficiency are low. However, when the protective shed frame is removed after the construction of the newly-built line is completed, the newly-built line is formed, and the hoisting equipment cannot directly stretch into the shed roof to remove the shed frame, so that great trouble is caused to the engineering construction, and the safety risk in the removal process is extremely high.
In order to ensure that the installation and disassembly and assembly processes are completed in a short time, so that the influence on the railway passage is reduced to the greatest extent, the construction cost is reduced, the short-time construction requirement is met, and a novel protective shed frame is urgently needed.
SUMMERY OF THE UTILITY MODEL
It is an object of the present invention to solve at least the above problems and to provide at least the advantages which will be described later.
It is yet another object of the present invention to provide a sliding ceiling which is simple and secure to prevent the ceiling from moving back and forth.
In order to achieve these objects and other advantages in accordance with the purpose of the invention, there is provided a protection shed frame crossing a railway line, comprising: the railway track comprises upright columns, cross beams, sliding rails and a ceiling, wherein the upright columns are distributed on two sides of a railway line in parallel, the cross beams are installed on the top ends of the upright columns along the railway extending direction, the sliding rails with upward openings are installed on the top ends of the cross beams, the ceiling is installed at the upper ends of the sliding rails, at least four sliding blocks are arranged at the bottom of the ceiling, and the sliding blocks freely slide inside the sliding rails.
Preferably, the slide block is provided with a first through hole, a plurality of pairs of corresponding second through holes are drilled on two side walls of the slide rail at equal intervals, and the first through hole and the second through hole are connected through a connecting rod.
Preferably, a rubber layer is arranged at a position corresponding to the sliding block inside the two side walls of the sliding rail.
Preferably, the ceiling is a sectional ceiling, and the length of each sectional ceiling is 3 meters.
Preferably, the ceiling is provided with a drainage slope.
Preferably, the cross beam is H-shaped steel.
Preferably, the sliding block is a steel sliding block.
Preferably, a cross brace is arranged between the upright posts.
The utility model discloses at least, include following beneficial effect: the movable sectional ceiling is adopted, so that the ceiling can be installed and disassembled in a moving mode in a sectional mode, and the movable sectional ceiling is practical and convenient and saves labor; because the cooperation of slide rail and slider is used, can follow the ceiling that slides from beginning to end in certain direction, and pass through the connecting rod through first through-hole and the second through-hole on the slider and connect, can fix a position fast and fixed ceiling, avoid the ceiling to slide along the slide rail.
Additional advantages, objects, and features of the invention will be set forth in part in the description which follows and in part will become apparent to those having ordinary skill in the art upon examination of the following or may be learned from practice of the invention.
Drawings
FIG. 1 is a front view of a protective canopy frame according to an embodiment of the present invention;
fig. 2 is a schematic view illustrating the connection between the slide rail and the slide block according to an embodiment of the present invention;
reference numerals: 1. a column; 2. a cross beam; 3. a slide rail; 31. a second through hole; 4. a ceiling; 5. a slider; 51. a first through hole; 6. a connecting rod.
Detailed Description
The present invention is further described in detail below with reference to the drawings so that those skilled in the art can implement the invention with reference to the description.
It will be understood that terms such as "having," "including," and "comprising," as used herein, do not preclude the presence or addition of one or more other elements or groups thereof.
Fig. 1 shows an implementation form according to the present invention, which includes: stand 1, crossbeam, 2, slide rail 3 and ceiling 4, stand 1 distributes in the railway line both sides that need protect parallelly, crossbeam 2 along the railway extending direction install in the top of stand 1, the length of crossbeam 2 equals the length that stand 1 distributes along the railway line, the ascending slide rail 3 of opening is installed along its length direction in the top of crossbeam 2, ceiling 4 install in the upper end of slide rail 3, just the bottom of ceiling 4 is equipped with four at least sliders 5, slider 5 supports ceiling 4, and can follow slide rail 3 takes ceiling 4 freely slides.
According to the technical scheme, various materials of the protective shed frame can be prefabricated and processed in the early stage and then transported to a construction site for installation, during installation, the plurality of upright columns 1 are installed on two sides of a railway line needing to be protected in parallel, the cross beam 2 is installed at the top ends of the upright columns 1 along the railway extending direction, the slide rails 3 are installed at the top ends of the cross beams 2, the ceiling 4 is hoisted to the slide rails 3 by a crane and then moved to a specified position along the slide rails 3, and after the ceiling 4 is moved along the slide rails 3 until all railway lines needing to be protected are covered, the protective shed frame installation across the railway line is completed. When the roof is dismounted, the ceiling 4 is firstly slid to dismount, and then the sliding rails 3, the cross beams 2 and the upright posts 1 are sequentially dismounted.
Fig. 2 shows an implementation form of the present invention, wherein a first through hole 51 is provided on the slider 5, a plurality of pairs of corresponding second through holes 31 are drilled equidistantly on two side walls of the slide rail 3, and the first through hole 51 and the second through holes 31 are connected by a connecting rod 6. When in use, the positions of the second through holes 31 can be arranged according to a fixed distance, the sizes of the first through holes and the second through holes can be slightly larger than that of steel rods used in construction, and steel rods left on site can be used for sequentially penetrating through the second through holes, the first through holes and the second through holes in construction to be connected and fixed; the first through hole and the first through hole can also be threaded holes, and after alignment, the screw rod is used for connection and fixation.
One implementation manner of the slide rail 3 in the above scheme is as follows: rubber layers are arranged at positions corresponding to the sliding blocks 5 in the two side walls of the sliding rail 3. The rubber layer can be tightly attached to the sliding block 5, so that the sliding block 5 is prevented from moving before the connecting rod 6 is used, and the sliding block 5 is prevented from moving in the width direction of the sliding rail 3 after the connecting rod is fixedly connected.
One implementation of the ceiling 4 in the above scheme is as follows: the ceiling 4 is a sectional ceiling, and the length of each section of ceiling is 3 meters. With the sectional type ceiling, the multi-section type ceiling can be transported to the site in batches, can be installed and disassembled section by section, and is connected by using the connecting pieces to form an integral structure.
One implementation of the ceiling 4 in the above scheme is as follows: and a drainage slope is arranged on the ceiling 4. When meeting rainfall scheduling problem in the use, can in time discharge the rainwater on the ceiling, avoid the rainwater to pile up the pressure that increases the ceiling top, cause the problem that ceiling life reduces and easily corrodes.
One implementation manner of the beam 2 in the above scheme is as follows: the beam is H-shaped steel. The H-shaped steel is an economic section efficient section with more optimized cross-sectional area distribution and more reasonable strength-to-weight ratio, and has the advantages of strong bending resistance, simplicity in construction, cost saving, light structure weight and the like.
One implementation manner of the slider 5 in the above scheme is as follows: the sliding block 5 is a steel sliding block. The steel slide block has stronger bearing capacity compared with other materials, and can support the ceiling 4 and drive the ceiling to move.
One implementation way of the protective shed frame crossing the railway line in the scheme is as follows: and a cross brace is arranged between the upright posts 1. The cross brace is the diagonal brace of protection canopy frame, plays the vertical stable effect to protection canopy frame, strengthens vertical rigidity, improves whole steady setting.
The number of apparatuses and the scale of the process described here are intended to simplify the description of the present invention. Applications, modifications and variations of the present invention will be apparent to those skilled in the art.
As described above, according to the present invention, since the movable sectional ceiling is adopted, the ceiling can be installed and disassembled in a movable manner, which is practical and convenient and saves manpower; because the cooperation of slide rail and slider is used, can follow the ceiling that slides from beginning to end in certain direction, and pass through the connecting rod through first through-hole and the second through-hole on the slider and connect, can fix a position fast and fixed ceiling, avoid the ceiling to slide along the slide rail.
While embodiments of the invention have been disclosed above, it is not intended to be limited to the applications listed in the specification and the examples. It can be applicable to various and be fit for the utility model discloses a field completely. Additional modifications will readily occur to those skilled in the art. The invention is therefore not to be limited to the specific details and illustrations shown and described herein, without departing from the general concept defined by the claims and their equivalents.
Claims (8)
1. A protective shed frame for crossing railway lines, comprising: the railway track comprises upright columns, cross beams, sliding rails and a ceiling, wherein the upright columns are distributed on two sides of a railway line in parallel, the cross beams are installed on the top ends of the upright columns along the railway extending direction, the sliding rails with upward openings are installed on the top ends of the cross beams, the ceiling is installed at the upper ends of the sliding rails, at least four sliding blocks are arranged at the bottom of the ceiling, and the sliding blocks freely slide inside the sliding rails.
2. The protective shelving across a railway line as claimed in claim 1, further comprising: the slide block is provided with a first through hole, a plurality of pairs of corresponding second through holes are drilled on two side walls of the slide rail at equal intervals, and the first through hole is connected with the second through holes through a connecting rod.
3. The shelter frame for crossing railway lines as claimed in claim 1, wherein a rubber layer is provided inside the two side walls of the slide rail at a position corresponding to the slide block.
4. The shelter frame for a cross-rail line of claim 1, wherein the canopy is a segmented canopy and each segment of canopy is 3 meters in length.
5. The shelter frame for a railway line as claimed in claim 1, wherein a drainage ramp is provided on the roof.
6. The shelter frame for a railway line as claimed in claim 1, wherein the cross-beams are H-section steel.
7. The shelter frame for a cross-rail line of claim 1, wherein the slider is a steel slider.
8. The shelter frame for a cross-rail line of claim 1, wherein cross braces are provided between the uprights.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202020380966.3U CN212611977U (en) | 2020-03-23 | 2020-03-23 | Protective shed frame crossing railway line |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202020380966.3U CN212611977U (en) | 2020-03-23 | 2020-03-23 | Protective shed frame crossing railway line |
Publications (1)
Publication Number | Publication Date |
---|---|
CN212611977U true CN212611977U (en) | 2021-02-26 |
Family
ID=74708627
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202020380966.3U Active CN212611977U (en) | 2020-03-23 | 2020-03-23 | Protective shed frame crossing railway line |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN212611977U (en) |
-
2020
- 2020-03-23 CN CN202020380966.3U patent/CN212611977U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107338868B (en) | Large spherical screen mounting system and construction method thereof | |
CN108360380B (en) | Bridge pier column construction operation platform and construction method thereof | |
CN104929373A (en) | Large-span square steel pipe truss and accumulative sliding construction method thereof | |
CN114961334B (en) | High-altitude large-span overhanging structure closed protection dismantling system and construction method thereof | |
CN205954489U (en) | Stride cast -in -place space of business line steel structure construction protection on bridge and move movable support | |
CN112796528B (en) | Construction method for high-altitude in-situ splicing of large-span steel truss | |
CN107060098A (en) | A kind of high-altitude wire frame Steel Structure Installation method based on sliding platform | |
CN114876239B (en) | High-altitude overhanging structure closed protection dismantling system and construction method thereof | |
CN108412187B (en) | Construction device and construction method for outer frame structure of ultra-high conjoined group tower | |
CN213772972U (en) | Movable telescopic external reinforcing steel bar part assembling platform | |
CN212611977U (en) | Protective shed frame crossing railway line | |
CN112726426A (en) | Novel movable protective shed of bracket and steel pipe column combined gantry type | |
CN106522566A (en) | Roof steel truss slipping rail and dismounting and installing method thereof | |
CN114108480B (en) | Suspension bridge catwalk full-section lower sliding frame arrangement structure and construction method thereof | |
CN210563531U (en) | Steel structure support for building protection | |
CN205955164U (en) | Portable steel truss operation platform | |
CN101457587A (en) | Template mutual-lifting type climbing formwork device and method | |
CN210563326U (en) | Overhead unit type overhead sliding splicing operation platform | |
US4201275A (en) | Means for the renovating and refurbishing of overhead structures | |
CN113202280A (en) | Conversion bracket type steel structure for steel structure high-altitude construction and construction method thereof | |
CN113309008A (en) | Steel case roof beam temporary support construction safety work platform | |
CN112796498A (en) | Double-column type electric construction platform with truss girder and working method thereof | |
CN110761485A (en) | Method for installing C-shaped closed stock ground portal steel frame structure | |
CN111516137A (en) | Hydraulic integral movable prefabricated box girder web plate reinforcing steel bar jig frame and construction method | |
CN216076209U (en) | Adjust nimble outer hanging handling frame of building |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |