CN212562375U - Civil engineering is with construction support - Google Patents

Civil engineering is with construction support Download PDF

Info

Publication number
CN212562375U
CN212562375U CN202020804677.1U CN202020804677U CN212562375U CN 212562375 U CN212562375 U CN 212562375U CN 202020804677 U CN202020804677 U CN 202020804677U CN 212562375 U CN212562375 U CN 212562375U
Authority
CN
China
Prior art keywords
plate
civil engineering
bottom plate
construction bracket
top plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202020804677.1U
Other languages
Chinese (zh)
Inventor
吕淑丽
刘向丽
蒋嘉奇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202020804677.1U priority Critical patent/CN212562375U/en
Application granted granted Critical
Publication of CN212562375U publication Critical patent/CN212562375U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Revetment (AREA)

Abstract

The utility model relates to the technical field of civil engineering, in particular to a construction support for civil engineering, which comprises a bottom plate, wherein the left side and the right side of the bottom plate are both provided with a roller, the left side and the right side of the top of the bottom plate are both provided with a support plate, each support plate is provided with a slide rail, the support plates are connected through a top plate, the left side and the right side of the top plate are both in sliding contact with the slide rails, the top plate is connected with the bottom plate through a mutually movable connecting frame, the left side and the right side of the bottom of the top plate are both provided with a thick pipe, a thin pipe is sleeved inside the circumference of each thick pipe, the left side and the right side of the thick pipe are both provided with through holes, bolts are arranged in the through holes, one end of each bolt passes through hole to be in contact with one end of the thin pipe, and the height that conveniently wants according to the workman passes in and out the adjustment, reduces the limitation.

Description

Civil engineering is with construction support
Technical Field
The utility model relates to a civil engineering's technical field specifically is a civil engineering uses construction support.
Background
As is well known, the term is a general term of science and technology for building various engineering facilities, and refers to not only applied materials and equipment, but also technical activities such as surveying, designing, constructing, maintaining and repairing, and the like, and also refers to objects of engineering construction, such as houses, roads, railways, pipelines, tunnels, bridges, canals, dams, ports, power stations, airports, ocean platforms, water supply and drainage, protection projects, and the like.
When using, the construction support for the existing civil engineering is built beside a building through manpower, the construction support for the existing civil engineering is found in the using process, the support is complex to mount and dismount, and the limitation is high due to the fact that the construction support is inconvenient to adjust according to the height required by workers in an entering and exiting mode.
SUMMERY OF THE UTILITY MODEL
Technical problem to be solved
Not enough to prior art, the utility model provides a support need not the installation and dismantles to the high business turn over adjustment that the convenience was wanted according to the workman reduces the civil engineering of limitation with construction support.
(II) technical scheme
In order to achieve the above object, the utility model provides a following technical scheme: a construction support for civil engineering comprises a bottom plate, wherein idler wheels are arranged on the left side and the right side of the bottom plate, support plates are arranged on the left side and the right side of the top of the bottom plate, slide rails are arranged on the support plates, the support plates are connected through a top plate, the left side and the right side of the top plate are in sliding contact with the slide rails, the top plate is connected with the bottom plate through a connecting frame which is movable with each other, thick pipes are arranged on the left side and the right side of the bottom of the top plate, thin pipes are sleeved inside the circumference of each thick pipe, through holes are formed in the left side and the right side of each thick pipe, bolts are arranged in the through holes, one end of each bolt penetrates through the through holes to be in contact with one end of each thin pipe, lifting rings are arranged on the left side and the right side of the top of the, and the bottom of support frame is connected with the top of backup pad to the left end and the right-hand member of each backup pad all are provided with the horizontal pole, and the one end of each horizontal pole all rotates and is provided with the runner, connect through the stay cord between rings, gear and the runner.
Preferably, the mounting end of each gyro wheel all passes the bottom plate and extends to the inside of bottom plate to the mounting end of each gyro wheel all is provided with the spring, and the one end of each spring all is connected with the inside bottom of bottom plate, and the bottom of bottom plate is provided with the jack, and the gyro wheel is connected with the jack cooperation, and one side of each gyro wheel all is provided with fixing device.
Preferably, one end of each support plate is provided with a first transverse pipe, a second transverse pipe is arranged inside the circumference of each first transverse pipe in a threaded manner, and each second transverse pipe penetrates through the rotating wheel and extends to the outside of the rotating wheel.
Preferably, the top end of the top plate is provided with a non-slip mat.
Preferably, the top end of the top plate is provided with a protection frame in a rectangular shape.
Preferably, the fixing device comprises a vertical plate, an inserting rod is arranged on the vertical plate, and one end of the inserting rod penetrates through the vertical plate and extends to the mounting end of the roller.
Preferably, each rotating wheel is provided with a rotating handle, and each rotating handle is provided with a handle sleeve.
Preferably, the left end and the right end of bottom plate all are provided with the fixed plate to all be provided with the rivet on each fixed plate.
Preferably, each pull rope is provided with scale marks.
(III) advantageous effects
Compared with the prior art, the utility model provides a civil engineering is with construction support possesses following beneficial effect:
this construction support for civil engineering through rotating the runner, the rotation of runner will be stretched and draw, and the stay cord draws the gear to draw rings, thereby the roof upwards mentions through the slip with the slide rail, then upwards mentions of roof and drives the rising of link, drives the thick pipe simultaneously and upwards mentions, and the support need not the installation and dismantles, and the convenience is adjusted according to the high business turn over that the workman wanted.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic view of a portion of the enlarged structure of FIG. 1;
FIG. 3 is a schematic structural view of the connection between the pull rope and the scale mark of the present invention;
FIG. 4 is a schematic top view of the connection between the top plate and the non-slip mat according to the present invention;
FIG. 5 is a schematic side view of the support plate of the present invention;
fig. 6 is a schematic view of the bottom side structure of the bottom plate of the present invention.
In the figure: 1. a base plate; 2. a roller; 3. a support plate; 4. a slide rail; 5. a connecting frame; 6. a thick pipe; 7. a thin tube; 8. a bolt; 9. a hoisting ring; 10. a gear; 11. a support frame; 12. a cross bar; 13. a rotating wheel; 14. pulling a rope; 15. a spring; 16. a jack; 17. a first cross tube; 18. a second cross tube; 19. a non-slip mat; 20. a protective frame; 21. a vertical plate; 22. inserting a rod; 23. turning a handle; 24. covering the handlebar; 25. a fixing plate; 26. riveting; 27. scale lines; 28. a top plate.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-6, a construction bracket for civil engineering comprises a base plate 1, rollers 2 are arranged on the left side and the right side of the bottom end of the base plate 1, support plates 3 are arranged on the left side and the right side of the top end of the base plate 1, slide rails 4 are arranged on the support plates 3, the support plates 3 are connected through top plates 28, the left side and the right side of each top plate 28 are in sliding contact with the slide rails 4, the top plates 28 are connected with the base plate 1 through connecting frames 5 which are movable with each other, thick pipes 6 are arranged on the left side and the right side of the bottom end of the top plates 28, thin pipes 7 are sleeved inside the circumference of each thick pipe 6, through holes are arranged on the left side and the right side of each thick pipe 6, bolts 8 are arranged in the through holes, one end of each bolt 8 is in contact with one end of each thin pipe 7 through the through hole, and rings 9, and the top end of each supporting plate 3 is provided with a gear 10, the front end and the rear end of the gear 10 are both provided with a supporting frame 11, the bottom end of the supporting frame 11 is connected with the top end of the supporting plate 3, the left end and the right end of each supporting plate 3 are both provided with a cross rod 12, one end of each cross rod 12 is rotatably provided with a rotating wheel 13, the hanging ring 9, the gear 10 and the rotating wheel 13 are connected through a pull rope 14, the rotating wheel 13 rotates to pull the gear 10, the pull rope 14 pulls the gear 10, so as to pull the hanging ring 9, the top plate 28 is lifted upwards through sliding with the sliding rail 4, then the lifting of the top plate 28 drives the connecting frame 5 to lift upwards, and simultaneously drives the thick pipe 6 to lift upwards, the support does not need to be installed and disassembled, and is convenient to adjust according to the height that a worker wants, the installation end of each roller 2 passes through the bottom plate 1 and extends, and the mounting end of each roller 2 is provided with a spring 15, one end of each spring 15 is connected with the inner bottom end of the bottom plate 1, the bottom end of the bottom plate 1 is provided with a jack 16, the rollers 2 are connected with the jacks 16 in a matching way, and one side of each roller 2 is provided with a fixing device for preventing the rollers 2 from sliding, so that the rollers 2 are conveniently folded, one end of each supporting plate 3 is provided with a first transverse pipe 17, a second transverse pipe 18 is arranged inside the circumference of each first transverse pipe 17 in a screwing way, each second transverse pipe 18 penetrates through the rotating wheel 13 and extends towards the outside of the rotating wheel 13, the rotating wheel 13 is fixed to prevent the rotating wheel 13 from rotating, so that the pulling ropes 14 are scattered, so that the pulling ropes 14 are wound together, the top end of the top plate 28 is provided with an anti-skid pad 19 for increasing the friction between the feet of workers and the top plate 28 and increasing the anti-skid property, the top, protect workman's personal safety, prevent that the workman from when carrying out the construction, roll-off roof 28, fixing device includes riser 21 to be provided with inserted bar 22 on the riser 21, and the one end of inserted bar 22 passes riser 21 and extends to the installation end of gyro wheel 2, fixes gyro wheel 2, all is provided with on each runner 13 and changes 23, and all is provided with on each commentaries on classics 23 and overlaps 24. The runner 13 is conveniently rotated to increase the travelling comfort of hand and runner 13, the left end and the right-hand member of bottom plate 1 all are provided with fixed plate 25, and all be provided with rivet 26 on each fixed plate 25, increase holistic stability, all be provided with scale mark 27 on each stay cord 14, conveniently make the stay cord 14 draw the length unanimous that draws, make roof 28 keep balance.
To sum up, when the construction bracket for civil engineering is used, the construction bracket is driven to the vicinity of a building through rolling of the roller 2, then the whole construction bracket is inclined towards one side, the inserted rod 22 is taken out of the roller 2, the roller 2 is matched and connected with the insertion hole 16 through the expansion and contraction of the spring 15, then the rivet 26 is hammered into the ground layer, then a worker holds the rotating handle 23 to rotate clockwise, the pull rope 14 is tensioned through clockwise rotation, the rotation of the rotating handle 23 drives the rotating wheel 13 to rotate, so that the pull rope 14 is pulled, the pull rope 14 pulls the gear 10, so that the hanging ring 9 is pulled, then the top plate 28 is lifted upwards through sliding of the sliding rail 4, then the top plate 28 is lifted upwards to drive the connecting frame 5 to lift upwards, meanwhile, the thick pipe 6 is driven to lift upwards, so that the scale lines 27 on the pull ropes 14 at two sides are kept consistent, and then the bolt 8 is screwed into the, the thick tube 6 and the thin tube 7 are clamped, then the second transverse tube 18 is screwed out of the first transverse tube 17, the second transverse tube 18 is inserted into the rotating wheel 13, and then a worker can use the device.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (9)

1. The utility model provides a construction support for civil engineering which characterized in that: comprises a bottom plate (1), rollers (2) are arranged on the left side and the right side of the bottom end of the bottom plate (1), supporting plates (3) are arranged on the left side and the right side of the top end of the bottom plate (1), slide rails (4) are arranged on the supporting plates (3), the supporting plates (3) are connected through a top plate (28), the left side and the right side of the top plate (28) are in sliding contact with the slide rails (4), the top plate (28) is connected with the bottom plate (1) through a connecting frame (5) which is movable with each other, thick pipes (6) are arranged on the left side and the right side of the bottom end of the top plate (28), thin pipes (7) are sleeved inside the circumference of each thick pipe (6), through holes are formed in the left side and the right side of each thick pipe (6), bolts (8) are arranged in each through hole, one end of each bolt (8) passes through the through hole to be in contact with, and the top left side and the right side on top all are provided with rings (9), and each the top of backup pad (3) is provided with gear (10), and the front end and the rear end of gear (10) all are provided with support frame (11), and the bottom of support frame (11) is connected with the top of backup pad (3), and the left end and the right-hand member of each backup pad (3) all are provided with horizontal pole (12), and the one end of each horizontal pole (12) all rotates and is provided with runner (13), connect through stay cord (14) between rings (9), gear (10) and runner (13).
2. The construction bracket for civil engineering as claimed in claim 1, wherein: the installation end of each gyro wheel (2) all passes bottom plate (1) and extends to the inside of bottom plate (1), and the installation end of each gyro wheel (2) all is provided with spring (15), and the one end of each spring (15) all is connected with the inside bottom of bottom plate (1), and the bottom of bottom plate (1) is provided with jack (16), and gyro wheel (2) are connected with jack (16) cooperation, and one side of each gyro wheel (2) all is provided with fixing device.
3. The construction bracket for civil engineering as claimed in claim 1, wherein: one end of each supporting plate (3) is provided with a first transverse pipe (17), a second transverse pipe (18) is arranged inside the circumference of each first transverse pipe (17) in a threaded mode, and each second transverse pipe (18) penetrates through the rotating wheel (13) and extends towards the outside of the rotating wheel (13).
4. The construction bracket for civil engineering as claimed in claim 1, wherein: the top end of the top plate (28) is provided with a non-slip mat (19).
5. The construction bracket for civil engineering as claimed in claim 1, wherein: the top end of the top plate (28) is provided with a protection frame (20) in a rectangular shape.
6. The construction bracket for civil engineering as claimed in claim 2, wherein: the fixing device comprises a vertical plate (21), an inserting rod (22) is arranged on the vertical plate (21), and one end of the inserting rod (22) penetrates through the vertical plate (21) and extends to the installation end of the roller (2).
7. The construction bracket for civil engineering as claimed in claim 1, wherein: each rotating wheel (13) is provided with a rotating handle (23), and each rotating handle (23) is provided with a handle sleeve (24).
8. The construction bracket for civil engineering as claimed in claim 1, wherein: the left end and the right end of the bottom plate (1) are both provided with fixing plates (25), and each fixing plate (25) is provided with a rivet (26).
9. The construction bracket for civil engineering as claimed in claim 1, wherein: and each pull rope (14) is provided with a scale mark (27).
CN202020804677.1U 2020-05-14 2020-05-14 Civil engineering is with construction support Expired - Fee Related CN212562375U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020804677.1U CN212562375U (en) 2020-05-14 2020-05-14 Civil engineering is with construction support

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020804677.1U CN212562375U (en) 2020-05-14 2020-05-14 Civil engineering is with construction support

Publications (1)

Publication Number Publication Date
CN212562375U true CN212562375U (en) 2021-02-19

Family

ID=74624549

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020804677.1U Expired - Fee Related CN212562375U (en) 2020-05-14 2020-05-14 Civil engineering is with construction support

Country Status (1)

Country Link
CN (1) CN212562375U (en)

Similar Documents

Publication Publication Date Title
CN103123016B (en) Construction method for laying gas pipelines along bridge
CN206280086U (en) A kind of adjustable height tunnel reinforcement trolley
CN209891696U (en) Rain-proof hanging flower basket for building
CN212562375U (en) Civil engineering is with construction support
CN111609209B (en) Supporting device for pipe jacking construction
CN210530715U (en) Crawling ladder for electric power laying
CN110939069B (en) Construction method of suspension bridge catwalk
CN212224199U (en) Scaffold convenient to adjust for power equipment overhaul
CN203354455U (en) Slide rail device for hanging window cleaning machine suspended working platform
CN201730624U (en) Construction work vehicle for subway region tunnel
CN211573364U (en) Hydraulic engineering overhauls cat ladder
CN210263847U (en) Stride and establish portable construction platform on subway U type groove
CN210177919U (en) Civil engineering construction support
CN112875526A (en) Combined type hoisting device for constructional engineering
CN207047698U (en) A kind of equipment for the construction of bridge bottom wall
CN203913735U (en) A kind of stair climbing trolley luggage with feet
CN219521110U (en) Photovoltaic board flexible support installation device
CN108302251B (en) Pipeline support that municipal construction used based on lever drive
CN219032850U (en) Rubble bed course leveling device
CN217840841U (en) High-altitude movable ladder-hanging type auxiliary construction system
CN219386075U (en) Safe and convenient construction device for municipal road sewage inspection well
CN214464168U (en) Hanging scaffold fixing device in vertical shaft construction
CN219840355U (en) Hanging basket device suitable for arc-shaped structure
CN214462364U (en) Scaffold frame for fitment construction that can freely go up and down
CN217841133U (en) Novel well head enclosure device for municipal road drainage system maintenance

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210219

Termination date: 20210514

CF01 Termination of patent right due to non-payment of annual fee