CN212528126U - Box culvert mould - Google Patents
Box culvert mould Download PDFInfo
- Publication number
- CN212528126U CN212528126U CN202020997089.4U CN202020997089U CN212528126U CN 212528126 U CN212528126 U CN 212528126U CN 202020997089 U CN202020997089 U CN 202020997089U CN 212528126 U CN212528126 U CN 212528126U
- Authority
- CN
- China
- Prior art keywords
- box culvert
- box
- mould
- culvert mould
- side form
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Sewage (AREA)
Abstract
The utility model discloses a box culvert mould for the holding steel reinforcement cage and pour the box culvert, it includes die block and a plurality of side form, die block and a plurality of side form enclose synthetic upper portion open-ended box, the box culvert mould is still including seting up a plurality of locating holes on the side form, wear to locate the connecting piece in the locating hole, the connecting piece is including being located the first link in the box and being located the outer second link of box, first link can be the complex be connected with the main muscle of steel reinforcement cage, the box culvert mould is still including connecting on the second link and can be fixed in the mounting on the side form with the connecting piece that can the complex. The utility model discloses a box culvert mould is through seting up the locating hole on the side form to set up the connecting piece in the locating hole, can effectually carry out the location connection to the main part reinforcing bar of cast-in-place lane board, guaranteed that the reinforcing bar interval in the cast-in-place lane board meets the requirements.
Description
Technical Field
The utility model relates to a box culvert preparation field, concretely relates to box culvert mould.
Background
The prefabricated middle box culvert is an important internal component of the super-large-diameter road shield tunnel and plays a role in providing a construction channel for a tunnel construction period and providing a traffic lane foundation and a function partition for an operation period. On the basis of the prefabricated box culvert, cast-in-place lane boards are applied to two sides of the box culvert, and the cast-in-place lane boards are combined to form a complete traffic lane.
Because the cast-in-place roadway plate is made of concrete poured by steel bars, the quality of the cast-in-place roadway plate is influenced by the distance between the steel bars. At present, for the construction of a cast-in-place roadway plate, a plurality of reinforcing steel bar connectors are usually sleeved on main ribs of a steel bar cage of a box culvert in advance in the manufacturing process of the prefabricated box culvert, the other end interfaces of the connectors are dug out at corresponding positions respectively after the box culvert is poured, the main reinforcing steel bars of the roadway plate are connected to the interfaces, and then concrete is poured to form the cast-in-place roadway plate.
However, the above construction method has many disadvantages: firstly, when the reinforcing bar connector is sleeved on a main reinforcing bar of a box culvert reinforcing cage, the connecting position of the reinforcing bar connector is usually selected by the experience of a constructor, so that the positioning of the reinforcing bar connector possibly has deviation, the spacing of the reinforcing bars in the subsequent cast-in-place roadway plate construction process has deviation, and the construction quality is influenced; secondly, in order to prevent concrete from permeating the interface of the reinforcing bar connector, a cap is usually arranged at the interface at the other end of the reinforcing bar connector, and during the concrete pouring and vibrating process of the box culvert, the cap of the connector is easy to fall off, so that the concrete permeates the interface, the failure of the individual reinforcing bar connector is caused, and the difficulty is caused to the subsequent construction of the cast-in-place track slab; finally, the excavation of the interface at the other end of the connector is usually performed by means of memory of the connector sleeving position in the preceding step by a constructor, which may have deviation, thereby bringing difficulty to the excavation of the interface and affecting the construction efficiency.
Disclosure of Invention
The utility model aims at overcoming the not enough of prior art, provide a can effectively fix a position cast-in-place lane board's bar linkage position and connect convenient box culvert mould.
In order to achieve the above purpose, the utility model adopts the technical scheme that:
the utility model provides a box culvert mould for the holding steel reinforcement cage and pour the box culvert, it includes die block and a plurality of side form, the die block with a plurality of side forms enclose synthetic upper portion open-ended box, the box culvert mould is still including seting up in a plurality of locating holes on the side form, wear to locate connecting piece in the locating hole, the connecting piece is including being located first link in the box and being located the outer second link of box, first link can the complex with the main muscle of steel reinforcement cage is connected.
Preferably, the positioning holes are formed in the two opposite side dies on the box body.
Preferably, the positioning holes are arranged on the side die at intervals along the vertical direction.
Further preferably, the plurality of positioning holes are combined into two positioning hole groups, and the two positioning hole groups are arranged on the side die side by side along the horizontal direction.
Preferably, the box culvert mould is still including inlaying and locating the sealing washer in the locating hole, the connecting piece can the complex wear to locate in the sealing washer.
Further preferably, the sealing ring is concentrically arranged with the positioning hole.
Preferably, the connecting piece includes hollow connecting body, sets up in the first screw thread of connecting body inner wall, main muscle tip cover is equipped with the spiral shell head, the main muscle pass through spiral shell head threaded connection in connecting body.
Further preferably, the box culvert mould still including can the complex connect in the second connecting end on and can with the connecting piece is fixed in mounting on the side form, the mounting includes the mounting body, locates the locking cap of mounting body one end, along the length direction spiral of mounting body is seted up in second screw thread on the mounting body, the mounting body passes through the second screw thread with connecting body looks threaded connection, just the locking cap can the complex laminate in locating hole week outside portion on the side form.
Because of above-mentioned technical scheme's application, compared with the prior art, the utility model have the following advantage: the utility model discloses a box culvert mould is through seting up the locating hole on the side form to set up the connecting piece in the locating hole, can effectually carry out the location connection to the main part reinforcing bar of cast-in-place lane board, guaranteed that the reinforcing bar interval in the cast-in-place lane board meets the requirements.
Drawings
Fig. 1 is a schematic view of the connection between a box culvert mold and a main reinforcement in the embodiment of the present invention;
FIG. 2 is a schematic surface structure of a side mold;
fig. 3 is a schematic view of the connection of the connector to the main bar and the fastener, respectively.
Wherein: 1. bottom die; 2. side mould; 3. positioning holes; 31. positioning a hole group; 4. a connecting member; 41. a first connection end; 42. a second connection end; 43. a connecting body; 44. a first thread; 5. a seal ring; 6. a fixing member; 61. a fixing member body; 62. a fixing cap; 63. a second thread; 7. a screw head;
100. and (5) main ribs.
Detailed Description
The technical solution of the present invention will be further explained with reference to the accompanying drawings.
The utility model relates to an improvement to box culvert mould, box culvert mould after the improvement can effectually carry out the location connection to cast-in-place lane board's main part reinforcing bar, has guaranteed that the reinforcing bar interval in the cast-in-place lane board meets the requirements
Specifically, referring to fig. 1, a box culvert mould is shown, which comprises a bottom mould 1 and a plurality of side moulds 2, wherein the bottom mould 1 and the plurality of side moulds 2 enclose a box body with an upper opening. The box body is used for accommodating a reinforcement cage and casting the box culvert, wherein the bottom die 1 is used for bearing the reinforcement cage during casting.
In this embodiment, as shown in fig. 1-2. The box culvert mould further comprises a plurality of positioning holes 3 formed in the side moulds 2 and connecting pieces 4 penetrating through the positioning holes 3, wherein the positioning holes 3 are formed in the two opposite side moulds 2 on the box body, and the box culvert mould is positioned by laser cutting, so that the position is accurate, and holes are smooth. The connecting member 4 comprises a first connecting end 41 positioned in the box body and a second connecting end 42 positioned outside the box body, and the first connecting end 41 can be matched and connected with the main reinforcement 100 of the reinforcement cage.
Here, through set up locating hole 3 on side form 2 to set up connecting piece 4 in locating hole 3, can be effectual carry out the location connection to the main part reinforcing bar of cast-in-place track board, guaranteed that the reinforcing bar interval in the cast-in-place track board meets the requirements. As shown in fig. 3, the box culvert mould further comprises a fixing member 6 which is connected to the second connecting end 42 in a matched manner and can fix the connecting member 4 on the side mold 2, and the fixing member 6 can ensure that the connecting member 4 is fixed on the side mold 2 in the box culvert pouring process, so that the port of the second connecting end 42 is prevented from permeating concrete in the pouring process.
Specifically, after the box culvert is poured, the fixing pieces 6 are removed, and then the side molds 2 are removed, so that the first connecting ends 41 of the connecting pieces 4 are poured into the box culvert, and the second connecting ends 42 of the connecting pieces extend outwards; then, the box culvert is lifted to the specified position of the tunnel and turned over, and the main body steel bars of the cast-in-place roadway plate are connected to the second connecting end 42.
Preferably, the positioning holes 3 are combined into a positioning hole group 31, and two positioning hole groups 31 are arranged on the side die 2 side by side along the horizontal direction. A plurality of positioning holes 3 in the positioning hole group 31 are arranged on the side die 2 at intervals in the vertical direction. Here, the box culvert is poured in the mould and is accomplished the back, with its handling to the tunnel in, later need overturn the box culvert and install, make its opening direction the same with the extending direction in tunnel, consequently, after the upset, arrange the box culvert lateral part in the extending direction in tunnel through connecting piece 4 of locating hole 3 location, can be used for connecting the main part reinforcing bar of lateral part cast-in-place lane board. The arrangement distance of the positioning holes 3 and the distance between the positioning hole groups 31 are flexibly set according to the design requirements of the specific lane plate.
In this embodiment, as shown in fig. 2, the box culvert mold further includes a sealing ring 5 embedded in the positioning hole 3, and the connecting member 4 can be inserted into the sealing ring 5 in a matching manner, wherein the sealing ring 5 is concentrically arranged with the positioning hole 3. The sealing ring 5 is a rubber sealing ring, and concrete can be prevented from seeping out of the positioning hole 3 and affecting the connecting port of the second connecting end 42 through the arrangement of the sealing ring 5.
Here, as shown in fig. 3, the connecting member 4 specifically includes a hollow connecting body 43, and a first screw thread 44 opened on an inner wall of the connecting body 43, wherein a screw head 7 is sleeved on an end of the main rib 100, and the main rib 100 is screwed into the connecting body 43 through the screw head 7. The screw head 7 here has a thread. The fixing member 6 includes a fixing member body 61, a fixing cap 62 provided at one end of the fixing member body 61, and a second thread 63 spirally provided on the fixing member body 61 along the length direction of the fixing member body 61, the fixing member body 61 is screwed with the connecting body 43 through the second thread 63, and the fixing cap 62 can be fitted to the side mold 2 at the outer side of the positioning hole 3.
In this embodiment, the connecting member 4 is a reinforcing bar connector, the fixing member 6 is a connecting bolt, and one end of the reinforcing bar connector is fixed to the side mold 2 through the connecting bolt, so as to prevent the port of the connector from penetrating into concrete during the box culvert pouring process.
The above embodiments are only for illustrating the technical concept and features of the present invention, and the purpose of the embodiments is to enable people skilled in the art to understand the contents of the present invention and to implement the present invention, which cannot limit the protection scope of the present invention. All equivalent changes and modifications made according to the spirit of the present invention should be covered by the protection scope of the present invention.
Claims (8)
1. The utility model provides a box culvert mould for the holding steel reinforcement cage pours the box culvert, and it includes die block (1) and a plurality of side form (2), die block (1) with a plurality of side form (2) enclose synthetic upper portion open-ended box, its characterized in that: the box culvert mould is characterized by further comprising a plurality of positioning holes (3) formed in the side mould (2) and a connecting piece (4) arranged in the positioning holes (3) in a penetrating mode, wherein the connecting piece (4) comprises a first connecting end (41) located in the box body and a second connecting end (42) located outside the box body, and the first connecting end (41) can be matched with a main rib (100) of the steel reinforcement cage to be connected.
2. The box culvert mould of claim 1, characterized in that: the positioning holes (3) are formed in the two opposite side dies (2) on the box body.
3. The box culvert mould of claim 1, characterized in that: the positioning holes (3) are arranged on the side die (2) at intervals along the vertical direction.
4. A box culvert mould according to claim 1 or 3, characterized in that: a plurality of locating holes (3) make up into positioning hole group (31), positioning hole group (31) have two sets ofly, and along the horizontal direction set up side by side with on the side form (2).
5. The box culvert mould of claim 1, characterized in that: the box culvert mould is still including inlaying and locating sealing washer (5) in locating hole (3), connecting piece (4) can the complex wear to locate in sealing washer (5).
6. The box culvert mould of claim 5, characterized in that: the sealing ring (5) and the positioning hole (3) are arranged concentrically.
7. The box culvert mould of claim 1, characterized in that: connecting piece (4) include hollow connecting body (43), set up in first screw thread (44) of connecting body (43) inner wall, main muscle (100) tip cover is equipped with spiral shell head (7), main muscle (100) pass through spiral shell head (7) threaded connection in connecting body (43).
8. The box culvert mould of claim 7, characterized in that: the box culvert mould still including can the complex connect in second link (42) on and can with connecting piece (4) are fixed in mounting (6) on side form (2), mounting (6) include mounting body (61), locate mounting body (61) a tip fixed cap (62), along the length direction spiral of mounting body (61) is seted up in second screw thread (63) on mounting body (61), mounting body (61) pass through second screw thread (63) with connecting body (43) looks threaded connection, just fixed cap (62) can the complex laminate in locating hole (3) week outside portion on side form (2).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202020997089.4U CN212528126U (en) | 2020-06-03 | 2020-06-03 | Box culvert mould |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202020997089.4U CN212528126U (en) | 2020-06-03 | 2020-06-03 | Box culvert mould |
Publications (1)
Publication Number | Publication Date |
---|---|
CN212528126U true CN212528126U (en) | 2021-02-12 |
Family
ID=74640234
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202020997089.4U Active CN212528126U (en) | 2020-06-03 | 2020-06-03 | Box culvert mould |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN212528126U (en) |
-
2020
- 2020-06-03 CN CN202020997089.4U patent/CN212528126U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN210389584U (en) | Novel replaceable channel groove making mold | |
CN211368727U (en) | Connection structure and reinforced concrete of fender post and waist rail | |
CN207998860U (en) | A kind of assembled pipe gallery | |
CN212528126U (en) | Box culvert mould | |
CN208981527U (en) | Assembly concrete connection structure | |
CN110805274A (en) | Steel mould of Y-shaped column and pouring method thereof | |
CN211735041U (en) | Water drain pipe suitable for pre-installation | |
CN103015328A (en) | Continuous splicing construction method of pier column for jacking broken beam of bridge | |
CN203066101U (en) | Combined prefabricated column foundation core die | |
CN102383425A (en) | Integrated concrete pile tip and manufacturing method thereof | |
CN203373964U (en) | Formwork structure of settlement joint of cast-in-place concrete wall | |
CN207823873U (en) | A kind of railway cartridge system for casting and pouring and railway cartridge production line | |
CN101134339B (en) | Arch bottom mold | |
CN102995613B (en) | Connection method and structure for casting wall body and plate girder of powerhouse of hydropower station by stages | |
CN202280057U (en) | Integrated concrete pile tip | |
CN214328961U (en) | Pile plate type retaining wall structure | |
CN108772941A (en) | Mold and its processing method for holding mold device and concrete component | |
CN105804058B (en) | A kind of diaphram wall and its construction method | |
CN210151577U (en) | Assembled track beam concrete post-cast groove mouth and template | |
CN206987373U (en) | Core column concrete pours mouth mold tool | |
CN212312302U (en) | Combined type universal template assembly for prefabricated reinforced concrete beam | |
CN115288705B (en) | Construction method of transition part of junction section of bifurcation tunnel and ultra-large span | |
CN104947799A (en) | Soft cable connection piece, prefabricated member and wallboard | |
CN208410187U (en) | A kind of pile top mold | |
CN204676886U (en) | House column apparatus for pouring |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |