CN212427096U - Piling device for building construction - Google Patents

Piling device for building construction Download PDF

Info

Publication number
CN212427096U
CN212427096U CN202020383333.8U CN202020383333U CN212427096U CN 212427096 U CN212427096 U CN 212427096U CN 202020383333 U CN202020383333 U CN 202020383333U CN 212427096 U CN212427096 U CN 212427096U
Authority
CN
China
Prior art keywords
pile
rod
limiting plate
building construction
horizontal limiting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020383333.8U
Other languages
Chinese (zh)
Inventor
王久明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenmu Tongsheng Pile Foundation Engineering Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202020383333.8U priority Critical patent/CN212427096U/en
Application granted granted Critical
Publication of CN212427096U publication Critical patent/CN212427096U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The utility model relates to the field of building construction, in particular to a piling device for building construction, which comprises a mounting seat, a telescopic rod, a hydraulic cylinder and a pile hammer; the lower surface of the mounting seat is fixedly provided with a plurality of vertical telescopic rods, the lower ends of the telescopic rods are fixedly provided with horizontal limiting plates, the side walls of the horizontal limiting plates are fixedly provided with a plurality of fixing seats, the fixing seats are provided with steel drill holes, and vertical fixing steel drills penetrate through the steel drill holes; a pile rod limiting disc is detachably mounted on the corresponding horizontal limiting plate under the pile hammer, and a pile rod limiting hole is formed in the center of the pile rod limiting disc. The utility model makes the device stick on the ground by arranging the horizontal limiting plate which is contacted with the ground, thereby avoiding the inclination; the detachable and replaceable pile rod limiting disc arranged on the horizontal limiting plate is convenient to replace as required, adapts to different pile rod requirements, guarantees that the pile rod cannot incline in the piling process, and ensures that the building quality meets the requirements.

Description

Piling device for building construction
Technical Field
The utility model relates to a construction field specifically is a pile device for construction.
Background
Since the ground building is built on the ground and the ground is subjected to a great pressure, the ground must have sufficient strength against the pressure, which is difficult to achieve, and therefore the ground bearing the building must be reinforced or the bearing way of the ground is improved, so that it is conceivable to pile the ground to transfer most of the weight of the building to a position deep below the ground through the pile, because the ground bearing capacity of the position is much larger than that of the ground.
The pile driving device that construction operation was used is exactly the device that is used for piling the ground, and the pile driving device that present construction used strikes on the stake through the pile hammer, but because the device is fixed insecure at the pile driving in-process for the striking position of pile hammer takes place the skew, makes the stake receive the impact of slope, makes the stake slope, influences building safety.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a construction is with pile device to solve the problem that proposes in the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme:
a piling device for building construction comprises a mounting seat, a telescopic rod, a hydraulic cylinder and a pile hammer; the hydraulic cylinder is vertically and fixedly arranged on the mounting seat and is positioned in the center of the mounting seat, an output shaft of the hydraulic cylinder vertically and downwards penetrates through the mounting seat, a vertical connecting rod is fixed at the tail end of the output shaft of the hydraulic cylinder, the pile hammer is fixedly arranged at the lower end of the connecting rod, and the hydraulic cylinder drives the pile hammer to move up and down to realize piling; the lower surface of the mounting seat is fixedly provided with a plurality of vertical telescopic rods, the height of the mounting seat from the ground can be changed through the telescopic rods, and the hammering range of the pile hammer is adjusted; the lower end of the telescopic rod is fixedly provided with a horizontal limiting plate, and the horizontal limiting plate is contacted with the ground, so that the device is kept stable on the ground; the side wall of the horizontal limiting plate is fixedly provided with a plurality of fixing seats, the fixing seats are provided with steel drill rod holes, vertical fixing steel drill rods penetrate through the steel drill rod holes, the horizontal limiting plate is fixed on the ground through the fixing steel drill rods, and the device is prevented from shaking and shifting in the piling process; the utility model discloses a pile driving device, including pile hammer, pile driver and the like.
Further: at least one vertical guide rod is fixedly installed on the pile hammer, a vertical guide hole is formed in the installation seat corresponding to the guide rod, the guide rod penetrates through the guide hole in a sliding mode, the guide rod is enabled to move up and down in the guide hole, the pile hammer is kept to move in the vertical direction, and downward hammering of the pile hammer in the vertical direction is guaranteed.
Further: the lower surface fixed mounting of horizontal limiting plate has a plurality of ability non-slip raised, and the non-slip raised is the circular cone structure of invering, through the friction of non-slip raised increase and ground, especially is fit for using on soil ground.
Further: through threaded connection between stake pole spacing dish and the horizontal limiting plate, can dismantle it from the horizontal limiting plate through rotatory stake pole spacing dish.
Further: the device is characterized in that a horizontal top plate is arranged right above the mounting seat, the top plate and the mounting seat are fixedly connected through a plurality of supporting rods, a plurality of rollers are mounted on the upper surface of the top plate, and when the device needs to be moved, the rollers can be moved towards the ground to push the device to move.
Further: the storage box is arranged on the top plate, tools required by operation of the device can be placed in the storage box, and the storage box is convenient to store and use.
Compared with the prior art, the beneficial effects of the utility model are that: the utility model discloses a set up the horizontal limiting plate who contacts with ground and make the device paste subaerial, avoid inclining to fix through the drill rod on the fixing base, avoid piling the skew of emergence in-process; the detachable and replaceable pile rod limiting disc arranged on the horizontal limiting plate is convenient to replace as required, adapts to different pile rod requirements, guarantees that the pile rod cannot incline in the piling process, and ensures that the building quality meets the requirements.
Drawings
Fig. 1 is a schematic structural view of a piling device for building construction.
Fig. 2 is an enlarged schematic view of a in fig. 1.
Fig. 3 is a schematic structural diagram of a horizontal limiting plate in a piling device for building construction.
In the figure: 1-mounting seat, 2-telescopic rod, 3-support rod, 4-top plate, 5-hydraulic cylinder, 6-pile hammer, 7-guide rod, 8-guide hole, 9-connecting rod, 10-horizontal limiting plate, 11-anti-slip bulge, 12-fixing seat, 13-fixing steel chisel, 14-pile rod limiting disc, 15-pile rod limiting hole, 16-storage box and 17-steel chisel hole.
Detailed Description
Example 1
Referring to the drawings, in the embodiment of the present invention, a piling device for building construction includes a mounting base 1, an expansion link 2, a hydraulic cylinder 5 and a pile hammer 6; the hydraulic cylinder 5 is vertically and fixedly installed on the installation seat 1 and is located at the center of the installation seat 1, an output shaft of the hydraulic cylinder 5 vertically and downwards penetrates through the installation seat 1, a vertical connecting rod 9 is fixed at the tail end of the output shaft of the hydraulic cylinder 5, the pile hammer 6 is fixedly installed at the lower end of the connecting rod 9, the pile hammer 6 is driven by the hydraulic cylinder 5 to move up and down, so that pile driving is achieved, at least one vertical guide rod 7 is fixedly installed on the pile hammer 6, a vertical guide hole 8 is formed in the installation seat 1 corresponding to the guide rod 7, the guide rod 7 slides and penetrates through the guide hole 8, so that the guide rod 7 moves up and down in the guide hole 8 and keeps moving in the vertical direction, and the pile hammer 6 is guaranteed to be hammered downwards in the; a plurality of vertical telescopic rods 2 are fixedly arranged on the lower surface of the mounting seat 1, the height of the mounting seat 1 from the ground can be changed through the telescopic rods 2, and the hammering range of the pile hammer 6 is adjusted; the lower extreme fixed mounting of telescopic link 2 has horizontal limiting plate 10, through horizontal limiting plate 10 and ground contact, the holding device is stable subaerial.
The lower surface of the horizontal limiting plate 10 is fixedly provided with a plurality of anti-skid protrusions 11, the anti-skid protrusions 11 are of inverted cone structures, friction between the anti-skid protrusions 11 and the ground is increased, and the anti-skid device is particularly suitable for being used on the soil ground; a plurality of fixing seats 12 are fixedly mounted on the side wall of the horizontal limiting plate 10, steel drill holes 17 are formed in the fixing seats 12, vertical fixing steel drills 13 penetrate through the steel drill holes 17, the horizontal limiting plate 10 is fixed on the ground through the fixing steel drills 13, and the device is prevented from shaking and deviating in the piling process; a pile rod limiting disc 14 is detachably mounted on a corresponding horizontal limiting plate 10 right below the pile hammer 6, a pile rod limiting hole 15 is formed in the center of the pile rod limiting disc 14, a pile rod needing to be driven penetrates through the pile rod limiting hole 15, the pile rod limiting hole 15 can be selected according to the size of the pile rod, the pile rod is in clearance fit with the pile rod limiting hole 15, the pile rod moves downwards along the pile rod limiting hole 15, and inclination is avoided; preferably, the stake limiting plate 14 is connected with the horizontal limiting plate 10 through threads, and the stake limiting plate 14 can be detached from the horizontal limiting plate 10 through rotation.
Example 2
On the basis of the embodiment 1, a horizontal top plate 4 is arranged right above the mounting seat 1, the top plate 4 is fixedly connected with the mounting seat 1 through a plurality of support rods 3, a plurality of rollers are arranged on the upper surface of the top plate 4, and when the device needs to be moved, the rollers face the ground to push the device to move; the storage box 16 is arranged on the top plate 4, and tools required by device operation can be placed in the storage box 16, so that the storage and the use are convenient.
When the device is used, the horizontal limiting plate 10 is placed on the ground, so that the pile rod limiting hole 15 is opposite to a piling position, the horizontal limiting plate 10 is fixed on the ground through the anti-skidding protrusions 11 and the fixing steel rods 13, and the device is prevented from moving in the piling process; the shape of the pile rod limiting hole 15 can be selected according to the size of a required pile rod, the pile rod penetrates through the pile rod limiting hole 15 during piling, the hydraulic cylinder 5 is started to enable the pile hammer 6 to hammer on the pile rod downwards, the pile rod vertically downwards enters the ground, the pile rod limiting hole 15 is matched with the pile rod, the pile rod is prevented from inclining in the hammering process, the pile rod is guided, and the accuracy of piling is guaranteed.
Furthermore, it should be understood that although the present description refers to embodiments, not every embodiment may contain only a single embodiment, and such description is for clarity only, and those skilled in the art should integrate the description, and the embodiments may be combined as appropriate to form other embodiments understood by those skilled in the art.

Claims (6)

1. A piling device for building construction comprises a mounting seat (1), a telescopic rod (2), a hydraulic cylinder (5) and a pile hammer (6); the hydraulic cylinder (5) is vertically and fixedly installed on the installation seat (1) and is located at the center of the installation seat (1), an output shaft of the hydraulic cylinder (5) vertically penetrates through the installation seat (1) downwards, a vertical connecting rod (9) is fixed at the tail end of the output shaft of the hydraulic cylinder (5), and the pile hammer (6) is fixedly installed at the lower end of the connecting rod (9); the device is characterized in that a plurality of vertical telescopic rods (2) are fixedly mounted on the lower surface of the mounting seat (1), a horizontal limiting plate (10) is fixedly mounted at the lower end of each telescopic rod (2), a plurality of fixing seats (12) are fixedly mounted on the side wall of each horizontal limiting plate (10), steel drill holes (17) are formed in the fixing seats (12), and vertical fixing steel drills (13) penetrate through the steel drill holes (17); the pile rod limiting plate is characterized in that a pile rod limiting plate (14) is detachably mounted on a horizontal limiting plate (10) corresponding to the position under the pile hammer (6), and a pile rod limiting hole (15) is formed in the center of the pile rod limiting plate (14).
2. The piling device for building construction according to claim 1, wherein: at least one vertical guide rod (7) is fixedly installed on the pile hammer (6), a vertical guide hole (8) is formed in the installation seat (1) corresponding to the guide rod (7), and the guide rod (7) penetrates through the guide hole (8) in a sliding mode.
3. The piling device for building construction according to claim 1, wherein: the lower surface of the horizontal limiting plate (10) is fixedly provided with a plurality of anti-skid protrusions (11), and the anti-skid protrusions (11) are of inverted conical structures.
4. The piling device for building construction according to claim 1, wherein: the pile rod limiting disc (14) is connected with the horizontal limiting plate (10) through threads.
5. A piling device for building construction according to any one of claims 1 to 4, wherein: a horizontal top plate (4) is arranged right above the mounting seat (1), the top plate (4) and the mounting seat (1) are fixedly connected through a plurality of supporting rods (3), and a plurality of rollers are mounted on the upper surface of the top plate (4).
6. The piling device for building construction according to claim 5, wherein: and a storage box (16) is arranged on the top plate (4).
CN202020383333.8U 2020-03-24 2020-03-24 Piling device for building construction Active CN212427096U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020383333.8U CN212427096U (en) 2020-03-24 2020-03-24 Piling device for building construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020383333.8U CN212427096U (en) 2020-03-24 2020-03-24 Piling device for building construction

Publications (1)

Publication Number Publication Date
CN212427096U true CN212427096U (en) 2021-01-29

Family

ID=74292242

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020383333.8U Active CN212427096U (en) 2020-03-24 2020-03-24 Piling device for building construction

Country Status (1)

Country Link
CN (1) CN212427096U (en)

Similar Documents

Publication Publication Date Title
CN212427096U (en) Piling device for building construction
CN102587826A (en) Drill arm assembly for multifunctional road pile drilling machine
CN201460885U (en) Self-shield static pressure type coal winning machine
CN213867806U (en) Municipal works are with pile device
CN212317869U (en) Static hydraulic pile machine additionally provided with drill tower base
KR100824688B1 (en) Bogie for reinforcing underground structure
CN201411693Y (en) Efficient pile driver tower
CN217681551U (en) Simple gravity type hole leading machine
CN210105767U (en) Broken group anchor rope drilling rig support
CN202544738U (en) Drilling arm assembly of multifunctional road pile drilling machine
CN215482956U (en) Municipal works are with pile device
CN112281837A (en) Pile driving device for precast pile construction
CN219218992U (en) Pile driver with high accuracy
CN214005640U (en) Foundation bearing capacity detection device
CN219974379U (en) Damping and energy-absorbing construction device for pile foundation punching
CN219451088U (en) Steel structure node member
CN212249839U (en) Small square rod screw drilling machine for construction engineering construction
CN218816389U (en) Non-blasting formula excavation device of rock
CN217378862U (en) Drilling tool suspension device for bidirectional mixing pile machine
CN211285600U (en) Pile pressing machine with damping device for constructional engineering
CN216041148U (en) Upright column structure of engineering pile machine
CN214363467U (en) Pile driving device for engineering construction
CN218030064U (en) Drilling equipment for tunnel
CN219731990U (en) Pile driver
CN216286273U (en) Automatic control equipment for electromechanical system of highway

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20211208

Address after: 719300 No. 7, commercial and residential building, Binhe Road, Shuilong village, Shenmu town, Yulin City, Shaanxi Province

Patentee after: Shenmu Tongsheng Pile Foundation Engineering Co.,Ltd.

Address before: 151600 Santun, Dongfeng Village, Qinggang Town, Qinggang County, Suihua City, Heilongjiang Province

Patentee before: Wang Jiuming