CN212216499U - Water conservancy pipeline dredging equipment - Google Patents

Water conservancy pipeline dredging equipment Download PDF

Info

Publication number
CN212216499U
CN212216499U CN202020609993.3U CN202020609993U CN212216499U CN 212216499 U CN212216499 U CN 212216499U CN 202020609993 U CN202020609993 U CN 202020609993U CN 212216499 U CN212216499 U CN 212216499U
Authority
CN
China
Prior art keywords
connecting rod
rotating shaft
water conservancy
conservancy pipeline
fixed pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202020609993.3U
Other languages
Chinese (zh)
Inventor
关宝
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Huahang Water Conservancy Engineering Co ltd
Original Assignee
Anhui Huahang Water Conservancy Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Huahang Water Conservancy Engineering Co ltd filed Critical Anhui Huahang Water Conservancy Engineering Co ltd
Priority to CN202020609993.3U priority Critical patent/CN212216499U/en
Application granted granted Critical
Publication of CN212216499U publication Critical patent/CN212216499U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Sewage (AREA)

Abstract

The utility model discloses a water conservancy pipeline mediation equipment, including pivot two, installing frame and slider, two left ends in pivot are equipped with the motor, and the motor left end is equipped with pivot three, and three upper ends in pivot are equipped with fixed pipe one, and fixed pipe one upside interpolation has connecting rod one, and fixed pipe one and connecting rod swing joint, and the cover is equipped with spring one on the connecting rod one, connecting rod one middle part articulates there is connecting rod two, and two right-hand members in connecting rod articulate has fixed plate three, and three lower extremes in fixed plate are equipped with slide bearing, and slide bearing and two sliding connection in pivot. The utility model discloses during the use, through setting up slider and gag lever post to and adjust the flexible mechanism of scraper, so that dredge the pipeline of equidimension not.

Description

Water conservancy pipeline dredging equipment
Technical Field
The utility model relates to a hydraulic engineering technical field specifically is a water conservancy pipeline mediation equipment.
Background
Hydraulic engineering is an engineering built for controlling and allocating surface water and underground water in nature to achieve the purposes of removing harmful substances and benefiting. Also known as water engineering. Water is a valuable resource essential for human production and life, but its naturally occurring state does not completely meet the needs of human beings. Only when hydraulic engineering is built, water flow can be controlled, flood disasters are prevented, and water quantity is adjusted and distributed to meet the requirements of people on water resources in life and production. Hydraulic engineering needs to build various types of hydraulic buildings such as dams, dikes, spillways, water gates, water inlets, channels, transition troughs, rafts, fishways and the like so as to achieve the aims.
At present, the pipeline that current water conservancy pipeline mediation equipment often can not dredge to the diameter variation in size, and dredge efficiency is lower, can not accomplish mediation and cleaning work simultaneously. Therefore, the utility model provides a water conservancy pipeline mediation equipment to solve the above-mentioned problem of proposing.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a water conservancy pipeline mediation equipment to solve the problem that proposes in the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme:
a water conservancy pipeline dredging device comprises a second rotating shaft, a mounting frame and sliding blocks, wherein a motor is arranged at the left end of the second rotating shaft, a third rotating shaft is arranged at the left end of the motor, a first fixing pipe is arranged at the upper end of the third rotating shaft, a first connecting rod is inserted into the upper side of the first fixing pipe and movably connected with the first connecting rod, a first spring is sleeved on the first connecting rod and positioned in the first fixing pipe, a second connecting rod is hinged at the middle part of the first connecting rod, a third fixing plate is hinged at the right end of the second connecting rod, a sliding bearing is arranged at the lower end of the third fixing plate and is slidably connected with the second rotating shaft, a sleeve is sleeved on the second rotating shaft and is slidably connected with the second rotating shaft, the mounting frame penetrates through the sleeve and is slidably connected with the left side and the right side of the mounting frame, a sliding rail is arranged at the middle part in the mounting frame, the left end, the inclined plane meshing of slider is connected with four gears, and the gear rotates through the connecting axle and is connected with four gag lever posts, and the gag lever post all runs through the upper and lower ends around the installing frame, and the gag lever post upper end all is equipped with the stopper, the gag lever post runs through fixed pipe two, and fixed pipe two is close to the equal fixed connection installing frame of one end of installing frame, the cover is equipped with spring two on the gag lever post, and both ends and fixed pipe two, gag lever post fixed connection about spring two.
As the utility model discloses scheme further again, the slider right-hand member is equipped with connecting rod three, and the mounting frame right-hand member is run through to connecting rod three, and the three right-hand members of connecting rod are equipped with handrail one.
As the utility model discloses scheme further again, correspond two threaded connection in pivot on the sleeve and have butterfly bolt two, and correspond butterfly bolt two on the sleeve and be equipped with screw hole one.
As the utility model discloses scheme further again, equal threaded connection has butterfly bolt one on handrail one and the installing frame, and corresponds butterfly bolt one on installing frame right-hand member and the handrail one and all be equipped with screw hole two.
Compared with the prior art, the beneficial effects of the utility model are that:
1. the utility model discloses during the use, through setting up slider and gag lever post to and adjust the flexible mechanism of scraper, so that dredge the pipeline of equidimension not.
2. The utility model discloses during the use, through set gradually drill bit, scraper and round brush in pivot three to dredge simultaneously and clean, it is more convenient to operate.
Drawings
Fig. 1 is a schematic structural diagram of a water conservancy pipeline dredging device.
Fig. 2 is a left side section structure schematic diagram of a mounting frame in the water conservancy pipeline dredging equipment.
Fig. 3 is an enlarged view of a part A of the water conservancy pipeline dredging device.
In the figure: 1. a drill bit; 2. fixing a first pipe; 3. a first connecting rod; 4. a scraper; 5. rolling and brushing; 6. a first rotating shaft; 7. a first fixing plate; 8. a second fixing plate; 9. a second connecting rod; 10. a first spring; 11. a second rotating shaft; 12. a motor; 13. a sliding bearing; 14. a third fixing plate; 15. a slide rail; 16. installing a frame; 17. a gear; 18. a slider; 19. a limiting block; 20. a limiting rod; 21. a butterfly bolt I; 22. a sleeve; 23. a butterfly bolt II; 24. a first handrail; 25. a third connecting rod; 26. a second fixing pipe; 27. a second spring; 28. and a third rotating shaft.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-3, in the embodiment of the present invention, a water conservancy pipeline dredging apparatus comprises a second rotating shaft 11, a mounting frame 16 and a slider 18, wherein a motor 12 is disposed at the left end of the second rotating shaft 11, a third rotating shaft 28 is disposed at the left end of the motor 12, a first fixed pipe 2 is disposed at the upper end of the third rotating shaft 28, a first connecting rod 3 is inserted into the upper side of the first fixed pipe 2, the first fixed pipe 2 is movably connected with the first connecting rod 3, a second fixed plate 8 is disposed at the upper end of the right end of the first connecting rod 3, a first fixed plate 7 is disposed at the upper end of the second fixed plate 8, a first rotating shaft 6 is rotatably connected to the first fixed plate 7, a rolling brush 5 is disposed at the outer end of the first rotating shaft 6, a drill bit 1 is disposed at the left end of the third rotating shaft 28, a scraper 4 is disposed at the upper end of the first connecting rod 3, a first spring 10 is sleeved, the lower end of the third fixing plate 14 is provided with a sliding bearing 13, the sliding bearing 13 is slidably connected with the second rotating shaft 11, the second rotating shaft 11 is sleeved with a sleeve 22, the second rotating shaft 11 is slidably connected with the sleeve 22, the sleeve 22 is in threaded connection with a butterfly bolt second 23 corresponding to the second rotating shaft 11, the sleeve 22 is provided with a first threaded hole corresponding to the butterfly bolt second 23, the sleeve 22 is penetrated with an installation frame 16, the sleeve 22 is slidably connected with the left side and the right side of the installation frame 16, the middle inside of the installation frame 16 is provided with a sliding rail 15, the left end and the right end of the sliding rail 15 are respectively fixedly connected with the left end and the right end of the inner wall of the installation frame 16, the upper end, the lower end, the front end and the rear end of the sliding rail 15 are respectively slidably connected with four sliding blocks 18, the right end of each sliding block 18 is provided with a third connecting rod 25, and the right end of the mounting frame 16 and the first handrail 24 are respectively provided with a second threaded hole corresponding to the butterfly bolt 21, the inclined plane of the sliding block 18 is engaged with four gears 17, the gears 17 are rotatably connected with four limiting rods 20 through connecting shafts, the limiting rods 20 penetrate through the front and rear upper and lower ends of the mounting frame 16, limiting blocks 19 are arranged at the upper ends of the limiting rods 20, the limiting rods 20 penetrate through the second fixed pipe 26, the second fixed pipe 26 is close to the mounting frame 16, one end of the second fixed pipe 26 is fixedly connected with the mounting frame 16, the second spring 27 is sleeved on the limiting rods 20, and the upper and lower ends of the second spring 27 are fixedly connected with the second fixed pipe 26 and the limiting rods.
The utility model discloses a theory of operation is:
the utility model discloses during the use, in operation, stretch into the pipeline with equipment, promote handrail 24, handrail 24 drives connecting rod three 25 and slider 18 and slides left, slider 18 promotes movable gear 17 and gag lever post 20 and slides to one side of keeping away from installing frame 16, and simultaneously, gear 17 rolls on slider 18, gag lever post 20 compression spring two 27, gag lever post 20 promotes four stoppers 19 and stretches out and make it extrude the inside pipe wall, fix equipment in the pipeline, in screwing in threaded hole two on installing frame 16 with butterfly bolt one 21 again, carry out spacing fixed to gag lever post 20, promote sleeve 22 left, sleeve 22 drives slide bearing 13 and moves left, slide bearing 13 drives connecting rod two 9 under the effect of fixed plate three 14 and promotes connecting rod one 3 and move up, connecting rod one 3 compression spring one 10 simultaneously, connecting rod one 3 drives scraper 4, fixed plate two 8, fixed plate one 7, The rotating shaft I6 and the rolling brush 5 integrally move upwards, the sleeve 22 stops being pushed until the scraper 4 contacts the pipe wall, the butterfly bolt II 23 is rotated, the sleeve 22 and the rotating shaft II 11 are locked, the first connecting rod I3 is prevented from sliding downwards, dredging operation of pipelines with different diameters by workers is facilitated, the starting motor 12 drives the rotating shaft III 28 and the drill bit 1 to rotate, meanwhile, the rotating shaft III 28 drives the scraper 4 and the rolling brush 5 to rotate around the rotating shaft III 28, the rotating shaft II 11 is pushed to enable the rotating shaft II 11 to slide leftwards on the mounting frame 16, the rotating shaft II 11 drives the motor 12 and the rotating shaft III 28 to move leftwards, the drill bit 1 conducts dredging on the pipelines, meanwhile, the scraper 4 and the rolling brush 5 clean dirt on the pipe wall, and the method is convenient.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.

Claims (6)

1. A water conservancy pipeline dredging device comprises a second rotating shaft (11), a mounting frame (16) and a sliding block (18), and is characterized in that a motor (12) is arranged at the left end of the second rotating shaft (11), a third rotating shaft (28) is arranged at the left end of the motor (12), a first fixed pipe (2) is arranged at the upper end of the third rotating shaft (28), a first connecting rod (3) is inserted into the upper side of the first fixed pipe (2), the first fixed pipe (2) is movably connected with the first connecting rod (3), a first spring (10) is sleeved on the first connecting rod (3), the first spring (10) is positioned in the first fixed pipe (2), a second connecting rod (9) is hinged in the middle of the first connecting rod (3), a third fixed plate (14) is hinged at the right end of the second connecting rod (9), a sliding bearing (13) is arranged at the lower end of the third fixed plate (14), the sliding bearing (13) is slidably connected with the second, and the second rotating shaft (11) is connected with the sleeve (22) in a sliding manner, the sleeve (22) is penetrated with an installation frame (16), the sleeve (22) is connected with the left side and the right side of the installation frame (16) in a sliding manner, a sliding rail (15) is arranged in the middle of the installation frame (16), the left end and the right end of the sliding rail (15) are respectively fixedly connected with the left end and the right end of the inner wall of the installation frame (16), the upper end and the lower end of the sliding rail (15) and the front end and the rear end of the sliding rail are respectively connected with four sliding blocks (18), the inclined planes of the sliding blocks (18) are engaged with four gears (17), the gears (17) are rotatably connected with four limiting rods (20) through connecting shafts, the limiting rods (20) are respectively penetrated through the front upper end and the rear end and the lower end of the installation frame (16), the upper ends of the limiting rods (20) are respectively provided with limiting blocks (, and a second spring (27) is sleeved on the limiting rod (20), and the upper end and the lower end of the second spring (27) are fixedly connected with the second fixed pipe (26) and the limiting rod (20).
2. The water conservancy pipeline dredging device according to claim 1, wherein a drill bit (1) is arranged at the left end of the rotating shaft III (28), and a scraper (4) is arranged at the upper end of the connecting rod I (3).
3. The water conservancy pipeline dredging equipment according to claim 1, wherein a second fixing plate (8) is arranged on the upper side of the right end of the first connecting rod (3), a first fixing plate (7) is arranged at the upper end of the second fixing plate (8), a first rotating shaft (6) is rotatably connected to the first fixing plate (7), and a rolling brush (5) is arranged at the outer end of the first rotating shaft (6).
4. The water conservancy pipeline dredging device according to claim 1, wherein a third connecting rod (25) is arranged at the right end of the sliding block (18), the third connecting rod (25) penetrates through the right end of the mounting frame (16), and a first handrail (24) is arranged at the right end of the third connecting rod (25).
5. The water conservancy pipeline dredging equipment according to claim 1, wherein a butterfly bolt II (23) is in threaded connection with the sleeve (22) corresponding to the second rotating shaft (11), and a threaded hole I is formed in the sleeve (22) corresponding to the butterfly bolt II (23).
6. The water conservancy pipeline dredging equipment according to claim 4, wherein the first handrail (24) and the first mounting frame (16) are in threaded connection with a first butterfly bolt (21), and the right end of the mounting frame (16) and the first handrail (24) are provided with a second threaded hole corresponding to the first butterfly bolt (21).
CN202020609993.3U 2020-04-20 2020-04-20 Water conservancy pipeline dredging equipment Expired - Fee Related CN212216499U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020609993.3U CN212216499U (en) 2020-04-20 2020-04-20 Water conservancy pipeline dredging equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020609993.3U CN212216499U (en) 2020-04-20 2020-04-20 Water conservancy pipeline dredging equipment

Publications (1)

Publication Number Publication Date
CN212216499U true CN212216499U (en) 2020-12-25

Family

ID=73906919

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020609993.3U Expired - Fee Related CN212216499U (en) 2020-04-20 2020-04-20 Water conservancy pipeline dredging equipment

Country Status (1)

Country Link
CN (1) CN212216499U (en)

Similar Documents

Publication Publication Date Title
CN111889462B (en) Hydraulic engineering pipeline dredging device and using method
CN213805569U (en) Dredging device for hydraulic engineering convenient to maintenance
CN212976185U (en) Pipeline for hydraulic engineering convenient to desilting
CN112792064A (en) Pipeline maintenance cleaning robot
CN211330586U (en) Hydraulic engineering pipeline surface rust cleaning device
CN212216499U (en) Water conservancy pipeline dredging equipment
CN112593534A (en) Hydraulic engineering is with floating rubbish interception sluice
CN211901953U (en) Hydraulic engineering pipeline butt-joint structural
CN113790273A (en) Hydraulic engineering drain valve of convenient clearance
CN213456211U (en) River water sampling equipment for hydraulic engineering
CN215060008U (en) Pipeline laying auxiliary assembly for hydraulic engineering
CN213740914U (en) Sluice device for hydraulic engineering
CN215844691U (en) A leak protection type water conservancy pipeline for hydraulic engineering
CN112267508B (en) Hydraulic engineering sediment removal device
CN214599665U (en) Raw material particle smashing device for producing efficient environment-friendly energy-saving cleaning agent
CN209040062U (en) A kind of drainage arrangement for hydraulic engineering
CN217253032U (en) Water conservancy drilling equipment
CN216194524U (en) A sealing device for hydraulic engineering construction
CN112872849A (en) Pipeline cutting equipment and method for hydraulic engineering
CN215252777U (en) Leveling device for water conservancy and hydropower foundation treatment
CN212631912U (en) Hydraulic pipeline for hydraulic engineering
CN213897130U (en) Slip casting device for water conservancy construction
CN216130065U (en) Hydraulic engineering slope bearing structure
CN214889545U (en) Pipeline for hydraulic engineering
CN214516553U (en) Hydraulic engineering is with adjustable desilting equipment

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20201225