CN212202357U - Assembled wind power tower cylinder assembles device fast - Google Patents
Assembled wind power tower cylinder assembles device fast Download PDFInfo
- Publication number
- CN212202357U CN212202357U CN202020266334.4U CN202020266334U CN212202357U CN 212202357 U CN212202357 U CN 212202357U CN 202020266334 U CN202020266334 U CN 202020266334U CN 212202357 U CN212202357 U CN 212202357U
- Authority
- CN
- China
- Prior art keywords
- assembled
- wind power
- assembling
- area
- assembly
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 abstract description 20
- 238000000034 method Methods 0.000 abstract description 8
- 230000009286 beneficial effect Effects 0.000 abstract description 6
- 230000008569 process Effects 0.000 abstract description 6
- 235000017166 Bambusa arundinacea Nutrition 0.000 abstract description 5
- 235000017491 Bambusa tulda Nutrition 0.000 abstract description 5
- 241001330002 Bambuseae Species 0.000 abstract description 5
- 235000015334 Phyllostachys viridis Nutrition 0.000 abstract description 5
- 239000011425 bamboo Substances 0.000 abstract description 5
- 230000002349 favourable effect Effects 0.000 abstract 2
- 238000000638 solvent extraction Methods 0.000 abstract 1
- 238000001514 detection method Methods 0.000 description 2
- 230000008520 organization Effects 0.000 description 2
- 230000009467 reduction Effects 0.000 description 2
- SMEGJBVQLJJKKX-HOTMZDKISA-N [(2R,3S,4S,5R,6R)-5-acetyloxy-3,4,6-trihydroxyoxan-2-yl]methyl acetate Chemical group CC(=O)OC[C@@H]1[C@H]([C@@H]([C@H]([C@@H](O1)O)OC(=O)C)O)O SMEGJBVQLJJKKX-HOTMZDKISA-N 0.000 description 1
- 238000004134 energy conservation Methods 0.000 description 1
- 230000007613 environmental effect Effects 0.000 description 1
- 238000011065 in-situ storage Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000010248 power generation Methods 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
- 238000012876 topography Methods 0.000 description 1
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/70—Wind energy
- Y02E10/72—Wind turbines with rotation axis in wind direction
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/70—Wind energy
- Y02E10/728—Onshore wind turbines
Landscapes
- Wind Motors (AREA)
Abstract
The utility model discloses a device is assembled fast to assembled wind power tower section of thick bamboo, including assembling table and transportation track, device is assembled fast to assembled wind power tower section of thick bamboo is installed in the place, and this place includes that equipment district and a plurality of district of hanging of treating are treated with each and are all provided with the transportation track between the district of hanging. The assembly area is provided with the assembly table, and a tower section of thick bamboo is assembled at the assembly bench completion, and a tower section of thick bamboo and assembly table slide to each and treat the district of hanging along the transportation track. This patent has clear and definite place functional partitioning, reduces the use cost of truck crane in the assembling process, reduces place area occupied, equipment quality is more easily controlled, the track is transported and is practiced thrift the space, the reliability is high, be favorable to improving hoist and mount efficiency and be favorable to beneficial effects such as green construction.
Description
Technical Field
The utility model relates to an assembled wind power tower cylinder assembles device fast.
Background
In recent years, wind power generation is vigorously developed in China, and the corresponding assembled wind power tower barrel is also widely popularized and used. The use of the assembled wind power tower cylinder ensures the construction quality, shortens the construction period, and is beneficial to energy conservation, emission reduction and green construction. The field installation of the existing wind power tower takes independent assembly of each section of the tower as a main part, and is characterized in that the tower sections after assembly are maintained in situ to wait for hoisting. The disadvantages of this construction method are: firstly, construction is restricted by sites, and site problems become important factors influencing assembly efficiency due to the fact that different wind power tower barrel construction sites have large difference in topography and landform. In different field environments, the traveling of the crane, the position of the tower barrel and the assembly mode are greatly different, and normal construction can be influenced under some conditions; secondly, the assembly operation area is large, a truck crane is required to be adopted in the assembly process of the tower drum, and all tower drum sections are assembled in parallel in the assembly process, so that the operation area is increased, and the land cost is increased; the construction organization is complex, which is not beneficial to standardized construction, the existing operation mode has higher requirements on the construction organization, and the site difference of each wind power tower cylinder is larger, which is not beneficial to standardized construction; and fourthly, the hoisting cost is high, after the tower barrel is assembled, the position cannot be moved before hoisting, the posture of the main crane needs to be continuously adjusted according to the position of the tower barrel section, and the operation cost is increased.
Therefore, there is a need to develop a splicing device which can reduce the working area of a truck crane and improve the assembly efficiency.
Disclosure of Invention
The utility model aims at providing a device is assembled fast to assembled wind power tower cylinder.
For realizing the utility model discloses the technical scheme that the purpose and adoption were such, a device is assembled fast to assembled wind power tower cylinder, including assembly table and transportation track.
The device is assembled fast to assembled wind power tower cylinder installs in the place, and this place is including assembling the district and a plurality of district of hanging of treating, and assembling the district and each treat to hang and all be provided with the transportation track between the district.
The assembling area is provided with an assembling platform, the tower drum is assembled on the assembling platform, and the tower drum and the assembling platform slide to each area to be hung along the conveying track.
Furthermore, the splicing table slides along the transportation track under the traction of the winch and the inhaul cable.
The beneficial effects of the utility model reside in that:
1. and (3) field function division is determined: the tower barrel assembly area and the hoisting area are separated, so that functions of all parts of a field are more definite, cross operation is reduced, and construction efficiency is improved;
2. the use cost of the truck crane in the assembling process is reduced: the method has the advantages that all tower tube sections are assembled in an assembly area, so that the working range of the truck crane in the assembly process is reduced, the truck crane is not influenced by environmental changes, the standardization of assembly operation is facilitated, and the cost is reduced;
3. reduce the place area occupied: based on clear site function division and reduction of the working range of the truck crane, the occupied area of a construction site is reduced, and the cost of land utilization can be reduced;
4. the assembly quality is easier to control: the construction process is further subdivided, and the tower barrel is assembled on the assembly platform to be completed, so that the construction quality can be more conveniently and effectively controlled compared with the prior art;
5. the track is transported and is practiced thrift the space, and the reliability is high: the track is transported without using large-scale hoisting equipment, the tower drum reaches the position to be hoisted through the winch, the track occupies small area, and the track has good reliability;
6. the hoisting efficiency is improved: the track transfer is convenient for adjusting the position of the tower drum, so that the attitude adjustment frequency of the main crane is reduced, meanwhile, the occupied area of the main crane can be reduced, and the hoisting efficiency is improved;
7. is beneficial to green construction: this patent the assembly table can adopt the plate equipment of prefabricated circulated use, improves the efficiency of construction, accords with green construction requirement.
Drawings
FIG. 1 is a top view of an assembled wind power tower rapid splicing device;
FIG. 2 is a front view of an assembled wind power tower rapid splicing device;
FIG. 3 is a top view of a tower with supports.
In the figure: splicing table 1, transportation track 2, hoist engine 3, assembly area 4, wait to hang district 5, tower section of thick bamboo 6 and support 7.
Detailed Description
The present invention will be further described with reference to the following examples, but it should not be construed that the scope of the present invention is limited to the following examples. Various substitutions and modifications can be made without departing from the technical spirit of the invention and according to the common technical knowledge and conventional means in the field, and all shall be included in the scope of the invention.
Example 1:
the embodiment discloses a device is assembled fast to assembled wind power tower cylinder, including assembly table 1 and transportation track 2.
Referring to fig. 1, the assembled wind power tower cylinder rapid assembling device is installed in a field, the field comprises an assembly area 4 and a plurality of areas to be hung 5, and a transportation track 2 is arranged between the assembly area 4 and each area to be hung 5. The position of the assembly area 4 is fixed, and the area 5 to be hung can be changed according to design requirements.
The assembling area 4 is provided with an assembling platform 1, the tower drum 6 is assembled on the assembling platform 1, referring to fig. 2 or 3, a plurality of supports 7 are erected in the tower drum 6, and the tower drum 6 is fixed on the assembling platform 1.
Referring to fig. 2, the tower 6 and the splicing table 1 slide to each region to be hoisted 5 along the transportation rail 2 under the traction of the winch 3 and the guy cable. The assembly table 1 can be recycled, and after the assembly and the transportation of the tower drum 6 of one to-be-hung area 5 are completed, the assembly table 1 can be used for the assembly and the transportation of the tower drums 6 of other to-be-hung areas 5.
During construction, the method comprises the following steps:
1) the tower 6 is assembled on the assembly table 1 in the assembly area 4.
2) And a plurality of supports 7 are erected inside the tower tube 6, so that the tower tube 6 is fixed on the assembling table 1.
3) The positions and the number of the areas 5 to be hoisted are determined according to design requirements, and the transportation tracks 2 are laid between the assembly area 4 and each area 5 to be hoisted.
4) And the splicing table 1 is connected with a winch 3 through a guy cable.
5) And starting the winch 3, and transporting the tower drum 6 and the splicing table 1 to the corresponding to-be-hung area 5.
6) After the tower 6 is in place, all the supports 7 are removed.
7) And hoisting the tower 6 of the area 5 to be hoisted.
Wherein, in the step 6), a step of detecting the tower drum 6 is also provided, and if the tower drum 6 is qualified, the step 7) is carried out. If the tower drum 6 is unqualified in detection, fixing the unqualified tower drum 6 again by using the support 7, conveying the unqualified tower drum 6 back to the assembly area 4 for reassembly, and repeating the steps 5) and 6) until the tower drum 6 is qualified in detection, and then turning to the step 7).
Claims (2)
1. The utility model provides a device is assembled fast to assembled wind power tower cylinder which characterized in that: comprises an assembling table (1) and a transportation track (2);
the assembling type wind power tower cylinder rapid assembling device is installed in a field, the field comprises an assembling area (4) and a plurality of areas (5) to be hung, and a conveying track (2) is arranged between the assembling area (4) and each area (5) to be hung;
the assembling area (4) is provided with an assembling platform (1), the tower drum (6) is assembled on the assembling platform (1), and the tower drum (6) and the assembling platform (1) slide to each to-be-hung area (5) along the conveying rail (2).
2. The assembled wind power tower cylinder rapid assembling device according to claim 1, characterized in that: the splicing table (1) slides along the transportation track (2) under the traction of the winch (3) and the inhaul cable.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202020266334.4U CN212202357U (en) | 2020-03-06 | 2020-03-06 | Assembled wind power tower cylinder assembles device fast |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202020266334.4U CN212202357U (en) | 2020-03-06 | 2020-03-06 | Assembled wind power tower cylinder assembles device fast |
Publications (1)
Publication Number | Publication Date |
---|---|
CN212202357U true CN212202357U (en) | 2020-12-22 |
Family
ID=73820237
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202020266334.4U Expired - Fee Related CN212202357U (en) | 2020-03-06 | 2020-03-06 | Assembled wind power tower cylinder assembles device fast |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN212202357U (en) |
-
2020
- 2020-03-06 CN CN202020266334.4U patent/CN212202357U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109057365B (en) | High-altitude sliding installation method for large-span pipe truss roof truss | |
CN201206342Y (en) | Rapid integration communication device | |
CN102635256A (en) | Self-unloading emergency communication base station | |
CN110206067B (en) | Immersed tunnel pipe section floating transportation and sinking position adjusting device and operation method thereof | |
CN109487912A (en) | A kind of construction method of super-span truss-string-structure | |
CN111336071A (en) | Assembled wind power tower cylinder rapid assembling device and construction method | |
CN104389432A (en) | Integral lifting equipment of steel truss-supported concrete house roof system and construction method | |
CN212202357U (en) | Assembled wind power tower cylinder assembles device fast | |
CN101708812B (en) | Self-lifting hoister and using method thereof | |
CN204167849U (en) | Cable trough and cover plate thereof | |
CN107399412B (en) | The method of construction of MOPU | |
CN115289384B (en) | Rail type device and method for mounting ultra-large LNG film tank containment system | |
CN107779530A (en) | The installation method of last furnace shell | |
CN102444139B (en) | Construction method for installing offshore wind power generation fan | |
CN113403951B (en) | Steel truss bridge deck hoisting construction method under limited clearance condition | |
CN114954832A (en) | Main hull total segmentation building method and ship | |
CN102121250B (en) | Construction method of raft foundation reinforcing cage for containment vessel of nuclear power plant | |
WO2010061048A1 (en) | Arrangement and method for erecting tower of wind power plant | |
CN114162735A (en) | Floor hoisting method | |
CN210313200U (en) | Hoisting system for installing shaft pressure steel pipe | |
CN203187315U (en) | Assembled lifting device for high-capacity wind generating set | |
CN106702992B (en) | Offshore construction platform lifts positioning device and its lifting localization method | |
CN102101629A (en) | Hierarchical synchronous hydraulic jacking process for large-tonnage ocean engineering structure | |
CN201530696U (en) | Self-lifting type hanging | |
CN108518075A (en) | A kind of modular architectural Lift-on/Lift-off System and its hanging method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20201222 |