CN102444139B - Construction method for installing offshore wind power generation fan - Google Patents
Construction method for installing offshore wind power generation fan Download PDFInfo
- Publication number
- CN102444139B CN102444139B CN201110439944.5A CN201110439944A CN102444139B CN 102444139 B CN102444139 B CN 102444139B CN 201110439944 A CN201110439944 A CN 201110439944A CN 102444139 B CN102444139 B CN 102444139B
- Authority
- CN
- China
- Prior art keywords
- tower cylinder
- section
- ring beam
- hydraulic
- working platform
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Wind Motors (AREA)
Abstract
The invention in particular provides a construction method for installing an offshore wind power generation fan, solving the problems that the existing offshore wind power generation fans have high installation costs and the equipment is not easy to rent. The construction method comprises the following steps of: a. erecting support columns with connecting cross beams on a working platform; b. arranging guide columns in the support columns; c. installing winches, arranging support ring beams in the guide columns and arranging hydraulic drive bolts and hydraulic jacks on the inner walls of and below the support ring beams respectively; d. sliding the first section of a tower drum to an installation platform; e. after adopting the winches to hoist the first section of the tower drum to a predetermined height, inserting the hydraulic drive bolts into a ring beam of the first section of the tower drum; f. using the winches to hoist the second section of the tower drum until the hydraulic drive bolts are inserted into a ring beam of the second section of the tower drum and repeating the above steps until tower drum installation is completed; and g. installing vanes and connecting the ring beams of the tower drum with the working platform by reinforcing ropes. The construction method has the following beneficial effects that: the installation cost is reduced while the fan installation requirements are met; and the construction quality is ensured.
Description
Technical field
The present invention relates to Oversea wind power generation construction technology, be specially the construction method that a kind of offshore wind power generation fan is installed.
Background technology
In recent years, Wind Power Generation Industry moves towards ocean from land, the just visual field that has entered people gradually obtained the development of advancing by leaps and bounds of offshore wind farm.The most employings of installation of most blower fan are good by blower fan overall package on land, and installation site is transported in Landed by Lighter, and recycling crane barge is lifted into position by blower fan and carries out installation exercise.This job requirements crane barge has enough crane capacities, and lift by crane the crane barge rent that tonnage is large, all the interior quantity of very expensive and worldwide is more rare.
Summary of the invention
The present invention installs and exists the high and equipment of expense that the problem of lease, the construction method that provides a kind of offshore wind power generation fan to install are provided in order to solve existing offshore wind power generation fan.
The present invention adopts following technical scheme to realize: the construction method that offshore wind power generation fan is installed, step is as follows: a, taking steel pipe pile as basis, set up working platform, the added four groups of support posts that are set in square corners of working platform, install two connecting cross beams that are parallel to each other on support post top; On working platform in b, four groups of support posts, cloth is setting in three guide upright posts in triangle bight, and three guide upright post bottoms are connected between mounting platform, top and overlap; C, hoist engine is arranged on connecting cross beam, in being provided with in three guide upright posts, connects and slide up and down support ring beam in the inner, support ring beam inwall and be provided with hydraulic-driven latch, and support ring beam downside and be placed with hydraulic jack; D, tower cylinder is divided into some joints, mounted first segment tower cylinder and cabin are transported to working platform, then first segment tower cylinder and cabin are slided on three mounting platforms in guide upright post; E, adopt the wire rope of hoist engine that first segment tower cylinder and cabin are risen and winched to after predetermined altitude, hydraulic-driven latch inserts on the ring beam of first segment tower cylinder, then second section tower cylinder is transported on three mounting platforms in guide upright post; F, utilize hydraulic jack fine setting first segment tower cylinder and the docking of second section tower cylinder, the wire rope of the hoist engine second section tower cylinder of slinging, unclamp hydraulic-driven latch, second section tower cylinder continues to rise on the ring beam of hydraulic-driven latch insertion second section tower cylinder, repeats above-mentioned steps to the installation of tower cylinder; G, employing crane barge are installed three blades on top, cabin, and are connected with reinforcing rope between tower cylinder ring beam and working platform.Adopt the method to install offshore wind power generation fan, overcome existing offshore wind power generation fan and installed and exist the high and equipment of expense to be difficult for the problem of lease.
Offshore wind power generation fan construction method of installation of the present invention is rationally reliable, when meeting assembling requirement, reduce mounting cost, and ensured the quality of constructing, and there is easy construction, drop into low and can reuse, can carry out the construction operation of multiple work planes.
Brief description of the drawings
Fig. 1 is structural representation of the present invention;
Fig. 2 is the schematic top plan view of Fig. 1.
In figure: 1-working platform, 2-support post, 3-connecting cross beam, 4-guide upright post, 5-mounting platform, 6-hoist engine, 7-supports ring beam, 8-hydraulic-driven latch, 9-hydraulic jack.
Detailed description of the invention
The construction method that offshore wind power generation fan is installed, step is as follows: a, taking steel pipe pile as basis, set up working platform 1, the added four groups of support posts 2 that are set in square corners of working platform 1, install two connecting cross beams that are parallel to each other 3 on support post 2 tops; On working platform 1 in b, four groups of support posts 2, cloth is connected between mounting platform 5, top and overlaps setting in 4, three guide upright post 4 bottom of three guide upright posts in triangle bight; C, hoist engine 6 is arranged on connecting cross beam 3, in being provided with in three guide upright posts 4, connects and slide up and down support ring beam 7 in the inner, support ring beam 7 inwalls and be provided with hydraulic-driven latch 8, and support ring beam 7 downsides and be placed with hydraulic jack 9; D, tower cylinder is divided into some joints, mounted first segment tower cylinder and cabin are transported to working platform 1, then first segment tower cylinder and cabin are slided on three mounting platforms 5 in guide upright post 4; E, adopt the wire rope of hoist engine 6 that first segment tower cylinder and cabin are risen and winched to after predetermined altitude, hydraulic-driven latch 8 inserts on the ring beam of first segment tower cylinder, then second section tower cylinder is transported on three mounting platforms 5 in guide upright post 4; F, utilize hydraulic jack 9 to finely tune the docking of first segment tower cylinder and second section tower cylinder, the wire rope of the hoist engine 6 second section tower cylinder of slinging, unclamp hydraulic-driven latch 8, second section tower cylinder continues to rise on the ring beam that hydraulic-driven latch 8 inserts second section tower cylinder, repeats above-mentioned steps to the installation of tower cylinder; G, employing crane barge are installed three blades on top, cabin, and are connected with reinforcing rope between tower cylinder ring beam and working platform 1.
In specific implementation process, the height of support post 2 and guide upright post 4 is respectively 30m and 40m, and the cross section of guide upright post 4 is groove type; The quantity of hydraulic-driven latch 8 is 12; The height of tower cylinder is 100m, is respectively Section four to first segment from tower cylinder bottom to top, is highly respectively 15m, 25m, 25m, 35m; Working platform 1 adopts shellfish thunder sheet and eight or three piers to be spliced.
Claims (1)
1. the construction method that offshore wind power generation fan is installed, it is characterized in that: step is as follows: a, taking steel pipe pile as basis, set up working platform (1), the added four groups of support posts (2) that are set in square corners of working platform (1), install two connecting cross beams that are parallel to each other (3) on support post (2) top; The upper cloth of working platform (1) in b, four groups of support posts (2) is setting in three guide upright posts (4) in triangle bight, and three guide upright posts (4) bottom is connected between mounting platform (5), top and overlaps; C, hoist engine (6) is arranged on connecting cross beam (3), in being provided with in three guide upright posts (4), connecing and slide up and down support ring beam (7) in the inner, support ring beam (7) inwall and be provided with hydraulic-driven latch (8), and support ring beam (7) downside is placed with hydraulic jack (9); D, tower cylinder is divided into some joints, mounted first segment tower cylinder and cabin are transported to working platform (1), then first segment tower cylinder and cabin are slided on the mounting platform (5) in three guide upright posts (4); E, adopt the wire rope of hoist engine (6) that first segment tower cylinder and cabin are risen and winched to after predetermined altitude, hydraulic-driven latch (8) inserts on the ring beam of first segment tower cylinder, then second section tower cylinder is transported on the mounting platform (5) in three guide upright posts (4); F, utilize hydraulic jack (9) fine setting first segment tower cylinder and the docking of second section tower cylinder, the wire rope of hoist engine (6) the second section tower cylinder of slinging, unclamp hydraulic-driven latch (8), second section tower cylinder continues to rise on the ring beam of hydraulic-driven latch (8) insertion second section tower cylinder, repeats above-mentioned steps to the installation of tower cylinder; G, employing crane barge are installed three blades on top, cabin, and are connected with reinforcing rope between tower cylinder ring beam and working platform (1).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201110439944.5A CN102444139B (en) | 2011-12-26 | 2011-12-26 | Construction method for installing offshore wind power generation fan |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201110439944.5A CN102444139B (en) | 2011-12-26 | 2011-12-26 | Construction method for installing offshore wind power generation fan |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102444139A CN102444139A (en) | 2012-05-09 |
CN102444139B true CN102444139B (en) | 2014-06-04 |
Family
ID=46007048
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201110439944.5A Active CN102444139B (en) | 2011-12-26 | 2011-12-26 | Construction method for installing offshore wind power generation fan |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102444139B (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102839669B (en) * | 2012-09-26 | 2015-05-27 | 广东力特工程机械有限公司 | Mounting method for foundation ring of marine wind turbine |
CN113023095B (en) * | 2019-12-24 | 2022-09-23 | 江苏金风科技有限公司 | Marine wind power installation tower section of thick bamboo fixing device of ship and tower section of thick bamboo transportation frock |
CN117889045A (en) * | 2023-05-29 | 2024-04-16 | 河南金利重工科技有限公司 | Lifting structure of wind power generation equipment |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5974893A (en) * | 1982-10-19 | 1984-04-27 | 株式会社巴組「鉄」工所 | Jib crane for assembling steel tower |
JP4143517B2 (en) * | 2003-10-20 | 2008-09-03 | 株式会社巴技研 | Construction method of tower structure |
DE102008022654A1 (en) * | 2008-05-07 | 2009-11-12 | Berg, Mario, Dr. | Method and device for mounting a modular structure, such as a wind turbine |
CN101708812A (en) * | 2009-11-09 | 2010-05-19 | 江苏盛裕风电设备有限公司 | Self-lifting hoister and using method thereof |
CN201530696U (en) * | 2009-11-09 | 2010-07-21 | 江苏盛裕风电设备有限公司 | Self-lifting type hanging |
CN102030291A (en) * | 2010-11-04 | 2011-04-27 | 三一电气有限责任公司 | Offshore wind turbine transport and installation platform |
CN202000328U (en) * | 2011-03-21 | 2011-10-05 | 中国船舶工业集团公司第七○八研究所 | Pin-type lifting device with hydraulic cylinder jacking ring beam |
-
2011
- 2011-12-26 CN CN201110439944.5A patent/CN102444139B/en active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5974893A (en) * | 1982-10-19 | 1984-04-27 | 株式会社巴組「鉄」工所 | Jib crane for assembling steel tower |
JP4143517B2 (en) * | 2003-10-20 | 2008-09-03 | 株式会社巴技研 | Construction method of tower structure |
DE102008022654A1 (en) * | 2008-05-07 | 2009-11-12 | Berg, Mario, Dr. | Method and device for mounting a modular structure, such as a wind turbine |
CN101708812A (en) * | 2009-11-09 | 2010-05-19 | 江苏盛裕风电设备有限公司 | Self-lifting hoister and using method thereof |
CN201530696U (en) * | 2009-11-09 | 2010-07-21 | 江苏盛裕风电设备有限公司 | Self-lifting type hanging |
CN102030291A (en) * | 2010-11-04 | 2011-04-27 | 三一电气有限责任公司 | Offshore wind turbine transport and installation platform |
CN202000328U (en) * | 2011-03-21 | 2011-10-05 | 中国船舶工业集团公司第七○八研究所 | Pin-type lifting device with hydraulic cylinder jacking ring beam |
Also Published As
Publication number | Publication date |
---|---|
CN102444139A (en) | 2012-05-09 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP1518053B1 (en) | Method and crane for installing, maintaining, and decommissioning wind turbines | |
US8584429B2 (en) | Tower erection system and method | |
CN103925172B (en) | Integral mounting method for tension leg type offshore floating wind turbine | |
CN102936888B (en) | Self-installation type offshore booster station structure and installation method thereof | |
CN102213033A (en) | Method of building a hybrid tower for a wind generator | |
CN205257825U (en) | Offshore platform fan hoist and mount system | |
CN103669956B (en) | Centralized solar column assembly and method | |
CN102817341B (en) | Construction method for segmented installation of offshore anemometer tower and combination of high-altitude manufactured parts for assembly | |
JP2008232071A (en) | Method and device for mounting nacelle of tower for wind power generation | |
CN101774511B (en) | Climbing type hoist and using method thereof | |
CN101508410A (en) | Large-scale component jacking method | |
CN102444139B (en) | Construction method for installing offshore wind power generation fan | |
CN108951593B (en) | Marine fan installation system and installation method based on four-barrel jacket composite foundation | |
CN114313144B (en) | Lifting bridge passing method for large container ship | |
CN102409650A (en) | Method for mounting shallow water ocean jacket platform | |
CN109057295B (en) | Manufacturing method of steel structure lifting system | |
CN109024660B (en) | Pile foundation dismantling method for offshore foundation and offshore foundation dismantling method | |
CN101580214A (en) | Hydraulic lifting method for large-scale equipment | |
CN112392667A (en) | Method for modifying a wind turbine foundation and wind turbine foundation | |
CN111101497A (en) | Offshore booster station structure capable of being integrally transported and installed | |
CN110745714A (en) | Self-lifting installation method of hoisting tower system | |
CN201901538U (en) | Self-lifting fan-mounted crane and marine fan transporting and mounting equipment | |
CN202390849U (en) | Installation device for offshore wind energy power generating fan | |
CN1250129A (en) | Construction working method for nuclear electric power generation installation | |
CN212452553U (en) | Deep water modularization self-adaptation formula construction platform that sinks |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |