CN212176057U - Box house two-layer floor structure - Google Patents

Box house two-layer floor structure Download PDF

Info

Publication number
CN212176057U
CN212176057U CN201922267805.3U CN201922267805U CN212176057U CN 212176057 U CN212176057 U CN 212176057U CN 201922267805 U CN201922267805 U CN 201922267805U CN 212176057 U CN212176057 U CN 212176057U
Authority
CN
China
Prior art keywords
box
floor structure
layer
room
bottom frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201922267805.3U
Other languages
Chinese (zh)
Inventor
王明军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Honglianzhong Assembled Integrated Housing Hebei Co ltd
Original Assignee
Honglianzhong Assembled Integrated Housing Hebei Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Honglianzhong Assembled Integrated Housing Hebei Co ltd filed Critical Honglianzhong Assembled Integrated Housing Hebei Co ltd
Priority to CN201922267805.3U priority Critical patent/CN212176057U/en
Application granted granted Critical
Publication of CN212176057U publication Critical patent/CN212176057U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Building Environments (AREA)

Abstract

The utility model discloses a box-room two-layer floor structure, which comprises a box-room top frame and a box-room bottom frame, wherein a vertically arranged box-room upright post is connected between the box-room top frame and the box-room bottom frame, at least two box-room upright posts are arranged, and a horizontally arranged two-layer floor structure is connected between the box-room upright posts through a box corner structure; the two-floor structure comprises a two-floor structure bottom frame beam, and box corner structures are arranged around the two-floor structure bottom frame beam; the bottom frame beam of the second floor structure is provided with a wallboard fixing clamping groove, and the wallboard fixing clamping groove is spliced with the first-layer wallboard and the second-layer wallboard; the utility model has the advantages that: the whole steel consumption of the box house structure is reduced, and the water leakage problem of the lower-layer box house roof is avoided.

Description

Box house two-layer floor structure
Technical Field
The utility model relates to a case room floor structure, specifically speaking are two-layer floor structure of case room belongs to case room floor structure field.
Background
The box type house is produced in an modularized design and factory mode, takes the box body as a basic unit, and can be used independently or spliced together. The two-layer structure is formed by additionally installing the standard box body in the traditional box type house, but in the existing mode, the waterproof structure of the top frame of one layer does not play a role, the steel consumption of the box house structure is increased, and the method also causes the water of the two-layer box house to flow to the top frame of one layer, so that the hidden danger of water leakage is generated.
Disclosure of Invention
In order to solve the problem, the utility model discloses a two-storey floor structure of case room has reduced the whole steel volume that uses of case room structure, has avoided the emergence of lower floor's case room roof problem of leaking.
The technical scheme of the utility model is that:
the box room two-layer floor structure comprises a box room top frame and a box room bottom frame, wherein box room stand columns which are vertically arranged are connected between the box room top frame and the box room bottom frame, at least two box room stand columns are arranged, and a horizontally arranged two-layer floor structure is connected between the two box room stand columns through a box corner structure;
the two-floor structure comprises a two-floor structure bottom frame beam, and box corner structures are arranged around the two-floor structure bottom frame beam; the bottom frame beam of the two-layer floor structure is provided with two wallboard fixing clamping grooves which are respectively spliced with the first layer wallboard and the second layer wallboard.
The two-floor structure bottom frame beam is arranged around the two-floor structure and connected with the box corner structure to form the two-floor structure. Wallboard fixed slot can guarantee to insert the fixed of guaranteeing the wallboard in the wallboard draw-in groove structure when one deck wallboard, two layers of wallboard installation. The box house main structure adopts bolted connection, and the frame roof beam adopts the draw-in groove formula to fix in wallboard and the two-storey floor structure.
And a floor leather, a cement fiberboard, a silk floss and rock wool heat preservation layer, a purline, a color steel sheet and a ceiling board are sequentially arranged in the two-layer floor structure from top to bottom. The manufacturing of factory modularization is guaranteed, the way that the ground of a two-layer box house and the suspended ceiling of the top of one layer are taken into account by the two-layer bottom frame is also realized, and then the realization of the two-layer floor structure of the box house is realized.
The wallboard is fixed to have adopted draw-in groove formula connection structure, and ground and furred ceiling board all adopt the self-tapping screw to connect the installation in mill and underframe purlin, and the structure roof beam setting adopts the interior weld forming of mill around frame construction, and this roof beam is accomplished for galvanized sheet material bends, goes up the draw-in groove and is regarded as wallboard fixed action, and the lower part lateral bend is the furred ceiling board mounting.
The utility model has the advantages that: the whole steel consumption of the box house structure is reduced, and the water leakage problem of the lower-layer box house roof is avoided.
The present invention will be further explained with reference to the drawings and examples.
Drawings
FIG. 1 is a schematic view of the installation of the floor slab structure main body of the two-storey box house of the present invention;
FIG. 2 is a schematic view of the installation of the floor structure wall and floor of the two-storey box house of the present invention;
FIG. 3 is a schematic view of the bottom frame beam structure of the floor structure of the two-storey box house of the present invention;
fig. 4 is the internal structure diagram of the two-storey floor structure of the present invention.
Detailed Description
The following description of the preferred embodiments of the present invention is provided for the purpose of illustration and description, and is not intended to limit the invention.
Example 1
As shown in fig. 1-4, a box-room two-layer floor structure comprises a box-room top frame 1 and a box-room bottom frame 2, wherein box-room upright posts 3 which are vertically arranged are connected between the box-room top frame 1 and the box-room bottom frame 2, at least two box-room upright posts 3 are arranged, and a horizontally-arranged two-layer floor structure is connected between the two box-room upright posts 3 through a box corner structure 4;
the two-floor structure comprises a two-floor structure bottom frame beam 5, and box corner structures 8 are arranged around the two-floor structure bottom frame beam 5; the bottom frame beam 5 of the two-layer floor structure is provided with two wallboard fixing clamping grooves 51, and the two wallboard fixing clamping grooves 51 are respectively spliced 7 with a first layer wallboard 6 and a second layer wallboard.
The cross section shown in fig. 3 is a bottom frame beam of a two-storey floor structure, which is arranged around the two-storey floor structure and welded with a box corner structure to form the two-storey floor structure shown in fig. 1 and 4. Wallboard fixed slot can guarantee to insert the fixed of guaranteeing the wallboard in the wallboard draw-in groove structure when one deck wallboard, two layers of wallboard installation. The box house main structure adopts bolted connection, and the frame roof beam adopts the draw-in groove formula to fix in wallboard and the two-storey floor structure.
As shown in fig. 4, a floor leather (floor leather glue) 52 with a thickness of 2mm, a cement fiberboard 53 with a thickness of 18mm, a silk floss and rock wool heat preservation layer 54, purlins 55 with a thickness of C120 x 40 x 15 x 2.0, a color steel sheet 56 with a thickness of 0.27mm, and a ceiling plate 57 are sequentially arranged in the two-layer floor structure from top to bottom. The factory modularization manufacturing can be guaranteed through the arrangement, the ground of a two-layer box house and the way of a one-layer top suspended ceiling are also considered by the two-layer bottom frame, and then the two-layer floor structure of the box house is realized.
The wallboard is fixed to have adopted draw-in groove formula connection structure, and ground and furred ceiling board all adopt the self-tapping screw to connect the installation in mill and underframe purlin, and the structure roof beam setting adopts the interior weld forming of mill around frame construction, and this roof beam is accomplished for galvanized sheet material bends, goes up the draw-in groove and is regarded as wallboard fixed action, and the lower part lateral bend 35mm is the furred ceiling board mounting.
The underframe beam structure is arranged around the two-layer floor structure, C12# C type steel purlins are laid inside, 18mm thick cement boards are laid on the upper portions of the C type steel purlins, the decorative surfaces are manufactured on the upper portions of the cement boards, the frame main beams are 3mm thick steel plate bending pieces, the outline width of the frame is 3000mm, the length is 6055mm, and the height is 210 mm.
The working principle is as follows: top underframe and stand all adopt bolted connection, during the use, the unconventional C type steel sheet of bending of two layers of underframe roof beams for 3mm thick, the profile height is 210mm, width direction can be according to wall way adjustment wallboard draw-in groove width, and this two layers of underframe roof beam compromises furred ceiling board and two layers of ground, and the draw-in groove is connected about wallboard installation and the frame roof beam, and the inside purlin of underframe welds into wholly with the underframe roof beam, and the purlin mainly is responsible for that ground upper portion cement board is fixed and one deck roof furred ceiling board is fixed. This underframe frame adopts the welding jobs to accomplish, and this kind of bilayer structure pipe in water has avoided the one deck box room condition of leaking to take place from the direct one deck end of two-layer top, and this structure has also reduced the whole steel consumption of box room structure, nevertheless will guarantee to lay when laying insulation material tightly, plays thermal-insulated soundproof and heat-proof's effect.

Claims (2)

1. Two-storey floor structure of case room, its characterized in that: the box room structure comprises a box room top frame and a box room bottom frame, wherein vertically arranged box room stand columns are connected between the box room top frame and the box room bottom frame, at least two box room stand columns are arranged, and a horizontally arranged two-layer floor structure is connected between the two box room stand columns through a box corner structure; the two-floor structure comprises a two-floor structure bottom frame beam, and box corner structures are arranged around the two-floor structure bottom frame beam; the bottom frame beam of the two-layer floor structure is provided with two wallboard fixing clamping grooves which are respectively spliced with the first layer wallboard and the second layer wallboard.
2. The box-house two-storey floor structure of claim 1, wherein: and a floor leather, a cement fiberboard, a silk floss and rock wool heat preservation layer, a purline, a color steel sheet and a ceiling board are sequentially arranged in the two-layer floor structure from top to bottom.
CN201922267805.3U 2019-12-17 2019-12-17 Box house two-layer floor structure Active CN212176057U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201922267805.3U CN212176057U (en) 2019-12-17 2019-12-17 Box house two-layer floor structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201922267805.3U CN212176057U (en) 2019-12-17 2019-12-17 Box house two-layer floor structure

Publications (1)

Publication Number Publication Date
CN212176057U true CN212176057U (en) 2020-12-18

Family

ID=73763832

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201922267805.3U Active CN212176057U (en) 2019-12-17 2019-12-17 Box house two-layer floor structure

Country Status (1)

Country Link
CN (1) CN212176057U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117071952A (en) * 2023-08-30 2023-11-17 滕州市政务服务中心 Modularized assembled multi-layer building box house and construction method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117071952A (en) * 2023-08-30 2023-11-17 滕州市政务服务中心 Modularized assembled multi-layer building box house and construction method thereof

Similar Documents

Publication Publication Date Title
CN1158439C (en) Frameless building system
CN105421818B (en) Built-in steel Standard house
CN102704712B (en) Integrated bathroom made of composite material and assembly method of integrated bathroom
CN104179250A (en) Light-board house system and construction method thereof
CN105926982B (en) The light steel House on stilts of assembled
CN212176057U (en) Box house two-layer floor structure
CN105401675A (en) Integrated curtain wall capable of realizing quick construction
CN110629913B (en) Curtain wall structure adopting red brick decoration panel and construction method thereof
CN2580029Y (en) Adjustable building surface steel formwork support combined piece
CN111926946A (en) Improved steel structure assembly type building wall and installation method thereof
CN111197412A (en) Assembled roof with elevator added in existing building and construction process thereof
CN207419732U (en) Modular keel shoe CCA slates cotton outer heat preservation system
CN214461591U (en) Assembled peripheral wall panel of steel structural framework
CN210067136U (en) ALC wallboard composite wall for modular building
CN105442699A (en) Efficient double-slab-column integrated envelope integration building and manufacturing and installing method thereof
CN218405891U (en) External hanging type transverse wall plate module and external hanging wall body structure with window
CN112144719A (en) Assembled loft device
CN212836243U (en) Outer hanging prefabricated outer window containing auxiliary frame wallboard module, external wall panel and housing construction
CN219710645U (en) Fixed knot of assembled wall constructs
CN216075904U (en) Modular wallboard structure
JPS60215957A (en) Wall panel for prefabricated structure and prefabricated structure containing said wall panel
CN107747360A (en) Modular keel shoe CCA slate cotton outer heat preservation systems and its construction method
CN217205586U (en) Corridor module
CN215484217U (en) Bio-based gypsum inner wallboard
CN211646711U (en) Steel construction building and steel column cold bridge prevention structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of utility model: Second floor structure of box house

Effective date of registration: 20210317

Granted publication date: 20201218

Pledgee: Bank of Cangzhou Limited by Share Ltd. Yutian branch

Pledgor: HONGLIANZHONG ASSEMBLED INTEGRATED HOUSING HEBEI Co.,Ltd.

Registration number: Y2021980001755

PC01 Cancellation of the registration of the contract for pledge of patent right
PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20220427

Granted publication date: 20201218

Pledgee: Bank of Cangzhou Limited by Share Ltd. Yutian branch

Pledgor: HONGLIANZHONG ASSEMBLED INTEGRATED HOUSING HEBEI Co.,Ltd.

Registration number: Y2021980001755