CN212105051U - Foldable construction platform - Google Patents
Foldable construction platform Download PDFInfo
- Publication number
- CN212105051U CN212105051U CN202020119620.8U CN202020119620U CN212105051U CN 212105051 U CN212105051 U CN 212105051U CN 202020119620 U CN202020119620 U CN 202020119620U CN 212105051 U CN212105051 U CN 212105051U
- Authority
- CN
- China
- Prior art keywords
- frame
- stair
- side frame
- construction platform
- fixed
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Ladders (AREA)
Abstract
The utility model relates to the construction field, in particular to a foldable construction platform, which comprises a bottom frame, a side frame, a stand column, a top rod, a stair and a platform plate, and has the advantages that when the construction platform is not needed, the stair is firstly rotated and folded to be placed on the bottom frame, the top rod and the stand column are disassembled to enable the top rod to rotate around the side frame, then the stand column is rotated and folded to be placed on the bottom frame, then the side frame is sequentially turned and folded to be placed on the bottom frame, the whole folding of the construction platform can be realized by simple operation, the space occupied by the construction platform is reduced, the convenience of the movement of the construction platform is improved, the setting of the whole construction platform in a folding structure can accelerate the setting speed of the construction platform, thereby the construction efficiency is improved, the stair setting can be convenient for workers to step on the construction platform without vertical climbing, and the risk of accidents of the, the safety of the staff is guaranteed, and the staff is more convenient to carry some working equipment or articles after vacating both hands.
Description
Technical Field
The utility model relates to a construction field especially indicates a folding construction platform.
Background
In the construction process of a high-rise building (such as a bridge), a floor type steel pipe construction platform is often built on the periphery of the building for construction, the construction platform generally needs to be welded or built on site, and the building and dismantling labor intensity is high and is very inconvenient; and it is constituteed by many steel pipes, therefore still has the not convenient to carry scheduling problem, therefore sees that current construction platform flexibility is relatively poor and probably leads to the comprehensive period of time scheduling problem of construction. In addition, the floor type steel pipe construction platform has the problem that tools are inconvenient to carry due to vertical climbing in the using process, and potential safety hazards are easy to bring.
Disclosure of Invention
The utility model provides a folding construction platform to overcome the problem of the construction platform among the prior art transport of not being convenient for.
The utility model adopts the following technical scheme: the utility model provides a folding construction platform, includes underframe, side frame, stand, ejector pin, stair and flat bed board, the side frame is all installed to the both ends upper surface of underframe, all is equipped with the ejector pin on the top corner of two side frames, and is fixed with the landing slab between the ejector pin that is parallel to each other, and the tail end of stair is installed in the underframe upper surface, and the head end of stair is erect in the landing slab surface, all install the stand between ejector pin and the underframe, the side frame is rotatable coupling with the underframe, and the height that the turning point of two side frames was located will differ the thickness of a side frame, and the top corner of side frame is articulated with the head end of ejector pin, and when the ejector pin all was in the horizontality, the end of two symmetrical ejector pins just links up, and the top of stand is for dismantling the connection, and the bottom of stand is articulated with the underframe, and the tail end of underframe and stair is articulated, stair include upper portion, The bottom end of the lower stair is hinged with the bottom frame, the top end of the lower stair is hinged with the bottom end of the upper stair, the top end of the support is hinged with the top end of the lower stair, the bottom end of the support props against the anti-skid plate, the anti-skid plate is fixed on the upper surface of the bottom frame, when the bottom end of the bracket props against the antiskid plate and the top of the upper stair is erected on the surface of the platform plate, the upper stair and the lower stair are positioned on the same inclined straight line, the lower stair comprises pedals, a connecting rod, a chain and a mounting plate, wherein a plurality of pedals are arranged on the mounting plate at equal intervals, one side of each pedal is hinged with the mounting plate, the other side of each pedal is hinged with the connecting rod, the chain is arranged between the top of the connecting rod and the top of the mounting plate, when the chain is in a vertical state, the pedals are in a horizontal state, and the structure of the upper stair is consistent with that of the lower stair.
As further improvement, the last fixed surface of landing slab has a plurality of limiting plate, and the top of the mounting panel of upper portion stair both sides all is fixed with the frame plate, and when upper portion stair top was put up at the landing slab, the frame plate covered in the landing slab upper surface, and the frame plate just imbeds between two adjacent limiting plates.
As further improvement, mutual symmetry is fixed with the sleeve pipe with the frame looks adaptation of side frame on four corners of underframe, and telescopic overlooking is the U type, and when the side frame upwards overturns 90 degrees, side frame and underframe mutually perpendicular, the frame of side frame just passes uncovered embedding cover intraductally, sheathed tube width is greater than the width of the frame of side frame, and the sleeve pipe is close to one side of uncovered one end on the surface can the tilting hinge have spacing hook, and the sleeve pipe is close to the opposite side of uncovered one end on the surface be equipped with the draw-in groove that corresponds with spacing hook, and when the side frame upwards overturns 90 degrees, the frame embedding of side frame is intraductal back, and spacing hook downwards overturns just to imbed in the draw-in groove, and the surface of spacing hook covers in the frame surface of side frame.
As further improvement, the stand includes pole setting and lower pole setting, goes up the pole setting and is articulated with lower pole setting, goes up the top and the ejector pin of pole setting and be connected for dismantling, and the bottom and the underframe of lower pole setting are articulated, the top outside of pole setting is fixed with down the sleeve pipe also is equipped with draw-in groove and spacing hook on the sleeve pipe, and when last pole setting upwards overturn 90 degrees, go up the pole setting and be in the back on the same straight line with lower pole setting, spacing hook upset downwards just imbeds in the draw-in groove, and the surface of spacing hook covers in last pole setting surface.
As a further improvement, the upper vertical rod is of a hollow structure, a clamping block is fixed on one side, close to the stand column, of the surface of the tail end of the ejector rod, and when the upper vertical rod and the lower vertical rod are in a vertical state and the ejector rod is in a horizontal state, the clamping block of the ejector rod is just embedded into the hollow of the upper vertical rod.
As a further improvement, the side frames are internally provided with baffle plates which are detachably connected with the side frames, the baffle plates are respectively arranged between the two side frames and the upright post, one side of each baffle plate is rotatably connected with the side frames, and the other side of each baffle plate covers the surface of the upright post.
As a further improvement, the two sides of the baffle inside the side frame are fixed with positioning pins, the positioning pins are inverted-L-shaped, the surface of the side frame is fixed with a positioning sleeve matched with the positioning pins, the positioning pins can be embedded into the positioning sleeve in a vertical sliding manner, the baffle arranged between the side frame and the upright column is fixed with the positioning pins on one side close to the side frame, the surface of the side frame is fixed with the positioning sleeve matched with the positioning pins, and the positioning pins of the baffle can be movably embedded into the positioning sleeve of the side frame.
From the above description of the structure of the present invention, compared with the prior art, the present invention has the following advantages: when the construction platform is not needed, the stair is firstly rotated downwards and folded to be placed on the bottom frame, the tail end of the ejector rod is detached from the upright post, the head end of the ejector rod is rotated downwards around the top corner of the side frame, then the upright post is rotated downwards and folded to be placed on the bottom frame, then the ejector rod and the side frame on one side are jointly turned downwards and folded to be placed on the bottom frame, finally the ejector rod and the side frame on the other side are jointly turned downwards and placed on the upper surface of the side frame which is folded firstly, the whole folding and the storage of the construction platform can be realized through simple operation, the space occupied by the construction platform is reduced, the moving convenience of the construction platform is improved, meanwhile, the construction speed of the construction platform can be accelerated due to the integral folding structure of the construction platform, the construction efficiency is improved, the stair can be convenient for workers to climb on the construction platform without vertical climbing, and the risk of accidents of the workers is reduced, the safety of the staff is guaranteed, and the staff is more convenient to carry some working equipment or articles after vacating both hands.
Drawings
Fig. 1 is a schematic structural diagram of the present invention.
Fig. 2 is a schematic structural view of the staircase.
Fig. 3 is a schematic structural diagram of a in fig. 1.
Fig. 4 is a schematic structural diagram of C in fig. 1.
Fig. 5 is a schematic structural diagram of B in fig. 1.
Fig. 6 is a schematic structural view of the pillar.
Fig. 7 is a schematic view of the connection structure of the upper vertical rod and the top rod.
Fig. 8 is a schematic view of a connection structure of the side frame and the baffle.
Fig. 9 is a schematic view of the folded structure of the staircase.
Fig. 10 is a schematic structural view of the pillar.
Fig. 11 is a schematic structural view of the construction platform after being folded.
Fig. 12 is a schematic structural view of the construction platform with the baffles.
Detailed Description
The following describes embodiments of the present invention with reference to the drawings.
As shown in the accompanying drawings 1 to 12, a foldable construction platform comprises a bottom frame 1, side frames 2, stand columns 3, ejector rods 4, stairs 5 and a platform plate 6, the side frames 2 are installed on the upper surfaces of the two ends of the bottom frame 1, the ejector rods 4 are arranged on the top corners of the two side frames 2, the platform plate 6 is fixed between the ejector rods 4 which are parallel to each other, the tail end of each stair 5 is installed on the upper surface of the bottom frame 1, the head end of each stair 5 is erected on the surface of the platform plate 6, the stand columns 3 are installed between the ejector rods 4 and the bottom frame 1, the upper surface of the bottom frame 1 is welded with a bottom plate 11, the bottom surface of the construction platform is made to be more stable by the arrangement of the bottom plate 11, and.
As shown in the attached drawing 1, the side frames 2 are rotatably connected with the bottom frame 1, and the height of the rotation point of each of the two side frames 2 is different by the thickness of one side frame 2, so that an abdicating space can be formed for the side frames 2 folded backwards, the two side frames 2 can be overlapped after being turned downwards, and the two side frames 2 are prevented from colliding with each other to tilt the side frames 2 folded backwards. The top corner of side frame 2 is articulated with the head end of ejector pin 4, and when ejector pin 4 all was in the horizontality, the end of the ejector pin 4 of two symmetries just linked up, and the end of ejector pin 4 is for dismantling the connection with the top of stand 3, and the bottom of stand 3 is articulated with underframe 1, and underframe 1 is articulated with the tail end of stair 5. When the construction platform is not needed, the stair 5 is rotated downwards and folded to be placed on the bottom frame 1, the tail end of the ejector rod 4 is detached from the upright post 3, the head end of the ejector rod 4 is rotated downwards by 90 degrees around the top corner of the side frame 2, the upright post 3 is rotated downwards by 90 degrees and folded to be placed on the bottom frame 1, the ejector rod 4 and the side frame 2 on one side are turned downwards by 90 degrees and folded to be placed on the bottom frame 1, and finally the ejector rod 4 and the side frame 2 on the other side are turned downwards by 90 degrees and placed on the upper surface of the side frame 2 which is folded firstly, so that the integral folding and storage of the construction platform can be realized through simple operation, the space occupied by the construction platform is reduced, the moving convenience of the construction platform is improved, the arrangement of the stair can facilitate a worker to climb the construction platform without vertical climbing, the risk of accidents of the worker is reduced, and the safety of the worker is guaranteed, and the staff is more convenient to carry some working equipment or articles after freeing both hands.
As shown in fig. 2 to 4, the staircase 5 includes an upper staircase 51, a lower staircase 52, a bracket 53 and a skid-proof plate 54, the bottom end of the lower staircase 52 is hinged to the bottom frame 1, the top end of the lower staircase 52 is hinged to the bottom end of the upper staircase 51, the top end of the bracket 53 is hinged to the top end of the lower staircase 52, the bottom end of the bracket 53 abuts against the skid-proof plate 54, the skid-proof plate 54 is fixed to the upper surface of the bottom frame 1, when the bottom end of the bracket 53 abuts against the skid-proof plate 54 and the top of the upper staircase 51 is erected on the surface of the landing plate 6, the upper staircase 51 and the lower staircase 52 are in the same inclined straight line, the arrangement of the bracket 53 increases the bearing force of the upper staircase 51 and the lower staircase 52, reduces the risk of loosening or breaking of the upper staircase 51 and the lower staircase 52 during use. Lower part stair 52 includes footboard 521, connecting rod 522, chain 523 and mounting panel 524, the equidistance is equipped with a plurality of footboards 521 on the mounting panel 524, and one side of footboard 521 all articulates with mounting panel 524, and the opposite side of footboard 521 all articulates with connecting rod 522, and installs chain 523 between the top of connecting rod 522 and mounting panel 524, and footboard 521 is the horizontality when chain 523 is in the vertical state, and the staff can find the stress point of sole fast, makes the more steady of staff's walking, reduces the smooth risk that takes place the accident of staff's foot. The structure of upper stair 51 with lower part stair 52 is unanimous, and the length after 5 folding of stair can be reduced in the setting of upper stair 51 and the rotatable structure of lower part stair 52, guarantees that 5 folding of stair can be complete receive in underframe 1 top, avoids because 5 overlengths of stair need dismantle when folding and place to alleviate the work load that 5 folding and expansion of stair.
As shown in fig. 3, the upper surface welding of landing slab 6 has four limiting plates 55, and frame plate 56 is all fixed at the top of the mounting panel 524 of upper portion stair 51 both sides, and when upper portion stair 51 top was put up at landing slab 6, frame plate 56 covered in landing slab 6 upper surface, and frame plate 56 just imbeds between two limiting plates 55, utilizes limiting plate 55 to restrict frame plate 56, prevents that frame plate 56 from removing on landing slab 6 to avoid upper portion stair 51 to rock about on landing slab 6.
As shown in fig. 5, the four corners of the bottom frame 1 are symmetrically welded with the sleeves 61 adapted to the frames of the side frames 2, the sleeves 61 are U-shaped when viewed from above, when the side frames 2 are turned upwards by 90 degrees, and the side frames 2 are perpendicular to the bottom frame 1, the frames of the side frames 2 just penetrate through the opening 62 and are embedded into the sleeves 61, the width of the sleeves 61 is greater than that of the frames of the side frames 2, one side surface of one end of the sleeves 61 close to the opening 62 is hinged with a limit hook 72 in a vertically rotatable manner, the other side surface of one end of the sleeves 61 close to the opening 62 is provided with a slot 71 corresponding to the limit hook 72, when the side frames 2 are turned upwards by 90 degrees, the frames of the side frames 2 are embedded into the sleeves 61, the limit hook 72 is turned downwards and just embedded into the slot 71, the outer surface of the limit hook 72 covers the surface of the frame 2, and the side frames 2 are fixed in the sleeves 61 by the, the stability of the connection of the side frame 2 and the bottom frame 1 is improved, the side frame 2 and the bottom frame 1 are kept in a mutually vertical state, and the risk of rotation of the side frame 2 in the use process is reduced.
As shown in fig. 6 to 7, the upright 3 includes an upper upright 31 and a lower upright 32, the upper upright 31 is hinged to the lower upright 32, the top of the upper upright 31 is detachably connected to the top rod 4, the bottom of the lower upright 32 is hinged to the bottom frame 1, the sleeve 61 is fixed on the outer side of the top of the lower upright 32, the sleeve 61 is also provided with a slot 71 and a limit hook 72, when the upper upright 31 is turned upwards and the upper upright 31 and the lower upright 32 are in the same straight line, the upper upright 31 is embedded into the sleeve 61, the limit hook 72 is turned downwards and just embedded into the slot 71, and the outer surface of the limit hook 72 covers the surface of the upper upright 31, the limit hook 72 is used to fix the upper upright 31 in the sleeve 61, so as to improve the connection stability between the upper upright 31 and the lower upright 32, so that the upper upright 31 and the lower upright 32 are kept in the same straight line, and prevent the upper upright 31 from rotating during use, and the length of the upright post 3 after being folded can be reduced by the arrangement of the rotatable structures of the upper upright post 31 and the lower upright post 32, the upright post 3 can be completely folded above the bottom frame 1 after being folded, and the problem that the upright post 3 needs to be disassembled for placement when being folded due to overlong length is avoided, so that the workload of folding and unfolding the upright post 3 is reduced.
As shown in fig. 6 to 7, the upper vertical rod 31 is a hollow structure, a fixture block 8 is fixed on one side of the end surface of the top rod 4 close to the upright column 3, when the upper vertical rod 31 and the lower vertical rod 32 are in a vertical state and the top rod 4 is in a horizontal state, the fixture block 8 of the top rod 4 is just embedded into the hollow of the upper vertical rod 31, the upper vertical rod 31 and the lower vertical rod 32 play a role in supporting the top rod 4, the bearing capacity of the top rod 4 is improved, and the risk of breaking the top rod 4 in the using process is reduced.
As shown in fig. 8 and 12, the baffle 9 is arranged inside the side frame 2, the baffle 9 is detachably connected with the side frame 2, the baffle 9 is arranged between the two side frames 2 and the upright post 3, one side of the baffle 9 is rotatably connected with the side frame 2, the other side of the baffle 9 covers the surface of the upright post 3, the baffle 9 can be arranged to achieve the purpose of isolating and protecting the working personnel and the stairs 5, and meanwhile, the baffle 9 between the side frame 2 and the upright post 3 can rotate around one side close to the side frame 2 to achieve the effect of a door, so that the working personnel can get in and out conveniently.
As shown in fig. 8 and 12, positioning pins 91 are fixed on two sides of the baffle plate 9 inside the side frame 2, the positioning pins 91 are inverted L-shaped, a positioning sleeve 92 matched with the positioning pins 91 is fixed on the surface of the side frame 2, the positioning pins 91 can be embedded into the positioning sleeve 92 in a vertical sliding manner, only one side of the baffle plate 9 arranged between the side frame 2 and the upright post 3, which is close to the side frame 2, is fixed with the positioning pins 91, the surface of the side frame 2 is fixed with the positioning sleeve 92 matched with the positioning pins 91, the positioning pins 91 of the baffle plate 9 can be movably embedded into the positioning sleeve 92 of the side frame 2, and when the baffle plate 9 is installed, the positioning pins 91 can be embedded into the positioning sleeve 92 from top to bottom to position, so as to facilitate quick installation.
When a construction platform is needed, firstly, the side frame 2 at one side drives the ejector rod 4 to turn upwards by 90 degrees, the side frame 2 is vertical to the bottom frame 1, meanwhile, after the frame of the side frame 2 is embedded into the sleeve 61, the limiting hook 72 on the sleeve 61 is turned downwards to be embedded into the clamping groove 71, the outer surface of the limiting hook 72 covers the surface of the frame of the side frame 2, the side frame 2 is fixed in the sleeve 61 by the limiting hook 72, the connection stability of the side frame 2 and the bottom frame 1 is improved, the side frame 2 and the bottom frame 1 are kept in a mutually vertical state, the risk of rotation of the side frame 2 in the use process is reduced, then the step is repeated to vertically fix the side frame 2 at the other side, the lower upright rod 32 and the upper upright rod 31 on the bottom frame 1 are respectively turned upwards by 90 degrees, when the upper upright rod 31 and the lower upright rod 32 are positioned on the same straight line, and the upper upright rod 31 is embedded into the sleeve 61, the limiting hook 72 on the lower upright rod 32 is turned downwards to be embedded, the upper vertical rod 31 is fixed in the sleeve 61 by the limit hook 72, the connection stability of the upper vertical rod 31 and the lower vertical rod 32 is improved, the upper vertical rod 31 and the lower vertical rod 32 are kept on the same straight line, the upper vertical rod 31 is prevented from rotating in the using process, then the ejector rods 4 on the two side frames 2 are rotated upwards, the fixture blocks 8 of the ejector rods 4 are embedded into the hollow parts of the corresponding upper vertical rods 31, the ejector rods 4 and the upper vertical rod 31 are vertical to each other, then the lower stairs 52 are rotated upwards, the brackets 53 are unfolded to abut against the anti-skid plates 54 to fix the inclination angle of the lower stairs 52, then the upper stairs 51 are turned upwards, the frame plates 56 of the upper stairs 51 are erected on the platform plates 6, the frame plates 56 are just embedded between the two limit plates 55 to realize the fixing of the upper stairs 51, finally, the pedal 521 and the connecting rod 522 are pulled downwards, the chain 523 is straightened in a vertical, accomplish construction platform's expansion operation, when need not use construction platform, the folding of construction platform can be realized once according to the step reverse operation of complaining on, reduce the space that construction platform occupy, the convenience that construction platform removed is improved, construction platform is whole to be foldable structure's setting simultaneously can accelerate construction platform's the speed of building, thereby improve the efficiency of construction, and the staff of can being convenient for of setting up of stair climbs construction platform, and need not the vertical climbing, reduce the risk that accident appears in the staff, guarantee staff's safety, and the staff more portable some working equipment or article after vacating both hands. When the construction platform is horizontally built as required, the welded lug plates 12 on the side frames 2 of the two adjacent construction platforms are butted, screws or pins penetrate through the corresponding lug plates 12 on the two adjacent construction platforms to be fixedly connected, the operation is simple and convenient, the connection stability between the horizontally built construction platforms is improved, the safety of workers is guaranteed, the horizontal building speed of the construction platforms is increased, and the construction efficiency is improved.
The above-mentioned be the utility model discloses a concrete implementation way, nevertheless the utility model discloses a design concept is not limited to this, and the ordinary use of this design is right the utility model discloses carry out immaterial change, all should belong to the act of infringement the protection scope of the utility model.
Claims (7)
1. The utility model provides a folding construction platform, including underframe, side frame, stand, ejector pin, stair and flat board, the side frame is all installed to the both ends upper surface of underframe, all is equipped with the ejector pin on the top corner of two side frames, and is fixed with the landing slab between the ejector pin that is parallel to each other, and the tail end of stair is installed in the underframe upper surface, and the head end of stair is erect on the landing slab surface, all install stand, its characterized in that between ejector pin and the underframe: the side frames are rotatably connected with the bottom frame, the heights of the rotating points of the two side frames are different by the thickness of one side frame, the top corners of the side frames are hinged with the head ends of the ejector rods, when the ejector rods are in a horizontal state, the tail ends of the two symmetrical ejector rods are just connected, the tail ends of the ejector rods are detachably connected with the top ends of the stand columns, the bottom ends of the stand columns are hinged with the bottom frame, the bottom frame is hinged with the tail end of the stair, the stair comprises an upper stair, a lower stair, a support and an anti-slip plate, the bottom end of the lower stair is hinged with the bottom frame, the top end of the support is hinged with the top end of the lower stair, the bottom end of the support is abutted against the anti-slip plate, the anti-slip plate is fixed on the upper surface of the bottom frame, when the bottom end of the support is abutted against the anti-slip plate and the, lower part stair include footboard, connecting rod, chain and mounting panel, the equidistance is equipped with a plurality of footboards on the mounting panel, and one side of footboard all is articulated with the mounting panel, and the opposite side of footboard all is articulated with the connecting rod, and installs the chain between the top of connecting rod and the top of mounting panel, and the footboard is the horizontality when the chain is in the vertical state, the structure of upper portion stair with the structure of lower part stair is unanimous.
2. A collapsible construction platform according to claim 1, wherein: the upper surface of landing slab is fixed with a plurality of limiting plate, and the top of the mounting panel of upper portion stair both sides all is fixed with the frame plate, and when upper portion stair top was put up when the landing slab, the frame plate covered in the landing slab upper surface, and the frame plate just imbeds between two adjacent limiting plates.
3. A collapsible construction platform according to claim 1, wherein: mutual symmetry's sleeve pipe that is fixed with the frame looks adaptation of side frame on four corners of underframe, the sheathed tube overlooks and is the U type, and when the side frame upwards overturns 90 degrees, when side frame and underframe mutually perpendicular, the frame of side frame just passes uncovered embedding cover intraductally, sheathed tube width is greater than the width of the frame of side frame, and the sleeve pipe is close to that one side of open one end can articulated from top to bottom on the surface have spacing hook, and the sleeve pipe is close to that the opposite side of open one end is equipped with the draw-in groove that corresponds with spacing hook on the surface, and when the side frame upwards overturns 90 degrees, the intraductal back of frame embedding cover of side frame, spacing hook upset downwards just imbeds in the draw-in groove, and the surface of spacing hook covers in the frame surface of.
4. A collapsible construction platform according to claim 1, wherein: the stand includes pole setting and lower pole setting, goes up the pole setting and articulates with pole setting down, and the top and the ejector pin of going up the pole setting are for dismantling to be connected, and the bottom and the underframe of pole setting are articulated down, the top outside of pole setting down is fixed with the sleeve pipe, also is equipped with draw-in groove and spacing hook on the sleeve pipe, and when last pole setting upwards overturn 90 degrees, go up the pole setting and be in on the same straight line with pole setting down after, spacing hook overturn downwards just imbeds in the draw-in groove, and the surface of spacing hook covers in last pole setting surface.
5. A collapsible construction platform according to claim 4, wherein: the upper vertical rod is of a hollow structure, a clamping block is fixed on one side, close to the stand column, of the surface of the tail end of the ejector rod, and when the upper vertical rod and the lower vertical rod are in a vertical state and the ejector rod is in a horizontal state, the clamping block of the ejector rod is just embedded into the hollow of the upper vertical rod.
6. A collapsible construction platform according to claim 1, wherein: the side frames are internally provided with baffle plates which are detachably connected with the side frames, the baffle plates are respectively arranged between the two side frames and the upright post, one side of each baffle plate is rotatably connected with the side frames, and the other side of each baffle plate covers the surface of the upright post.
7. A collapsible construction platform according to claim 6, wherein: the utility model discloses a side frame, including side frame, stand column, locating pin and side frame, the both sides of the inside baffle of side frame are fixed with the locating pin, and the locating pin is the style of calligraphy of falling L, and the side frame be fixed with on the surface with the position sleeve of locating pin looks adaptation, in the gliding embedding position sleeve about the locating pin can, the baffle that is equipped with between side frame and the stand only is fixed with the locating pin near one side of side frame, and the side frame fixed surface have with the position sleeve of this position pin looks adaptation, the movable embedding in the position sleeve of side frame of locating.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202020119620.8U CN212105051U (en) | 2020-01-19 | 2020-01-19 | Foldable construction platform |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202020119620.8U CN212105051U (en) | 2020-01-19 | 2020-01-19 | Foldable construction platform |
Publications (1)
Publication Number | Publication Date |
---|---|
CN212105051U true CN212105051U (en) | 2020-12-08 |
Family
ID=73626265
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202020119620.8U Active CN212105051U (en) | 2020-01-19 | 2020-01-19 | Foldable construction platform |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN212105051U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111155751A (en) * | 2020-01-19 | 2020-05-15 | 中交一公局厦门工程有限公司 | Foldable construction platform and construction method |
-
2020
- 2020-01-19 CN CN202020119620.8U patent/CN212105051U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111155751A (en) * | 2020-01-19 | 2020-05-15 | 中交一公局厦门工程有限公司 | Foldable construction platform and construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN111155751A (en) | Foldable construction platform and construction method | |
US8245816B2 (en) | Integral safety system which can be used for construction | |
JPH10506444A (en) | Scaffold assembly | |
CN212105051U (en) | Foldable construction platform | |
CN220848584U (en) | Movable scaffold | |
JP2529662B2 (en) | Folding construction work scaffolding | |
US3788424A (en) | Hoist assembly for use on scaffolds | |
JP2008214983A (en) | Elevating/lowering portable scaffold | |
CN209799310U (en) | Building scaffold convenient to dismantle transportation | |
CN214246528U (en) | Scaffold for building construction | |
CN212613607U (en) | Movable telescopic scaffold | |
CN212201195U (en) | Scaffold for construction | |
JP2000017829A (en) | Moving work scaffold | |
CN109537868B (en) | Portable operation platform for hoisting assembled main beams | |
JP5873348B2 (en) | Suspension scaffold and installation method of suspension scaffold | |
CN217518109U (en) | Multipurpose operation platform that encorbelments | |
JPS623477Y2 (en) | ||
CN219952621U (en) | Scaffold frame | |
CN219491671U (en) | Foldable PC stair construction operation platform | |
CN216664906U (en) | Building support is used in civil engineering construction | |
CN217871757U (en) | Scaffold frame integral type guardrail landing plate | |
CN221703070U (en) | Scaffold for construction engineering | |
JP2000064596A (en) | Built-up type scaffold base | |
CN218933768U (en) | Prefabricated stair mounting rack | |
CN219808941U (en) | Safety cat ladder |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |