CN212078599U - Building engineering scaffold support device - Google Patents
Building engineering scaffold support device Download PDFInfo
- Publication number
- CN212078599U CN212078599U CN201921992270.XU CN201921992270U CN212078599U CN 212078599 U CN212078599 U CN 212078599U CN 201921992270 U CN201921992270 U CN 201921992270U CN 212078599 U CN212078599 U CN 212078599U
- Authority
- CN
- China
- Prior art keywords
- bearing plate
- groove
- balance seat
- joint groove
- base
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
The utility model discloses a building engineering scaffold puts up strutting arrangement, its structure is including consolidating the fork arm, base, installation piece, bracing piece, protector, joint groove, tank frame, the utility model discloses improve current scaffold frame superstructure to the bearing plate at protector middle part is used as main backup pad, and wall butt joint sealing layer about the joint groove, embedded a plurality of dispersible support weight reach the branch of effective pressure, and upper and lower surface covers has the skid resistant course that improves frictional resistance, controls the first balanced seat of position and the second balanced seat middle part rigid coupling sleeve post of standing vertically, can effectively improve the installation fixity of structure, and the balancing nature is good and have resistance to compression protectiveness about the mounting structure, can effectively improve scaffold frame and use bearing performance.
Description
Technical Field
The utility model relates to a building engineering scaffold puts up strutting arrangement belongs to scaffold frame and supports technical field.
Background
The scaffold refers to various supports which are erected for workers to operate and solve vertical and horizontal transportation on a construction site and is commonly used for construction on a construction site. The existing upper supporting surface of the scaffold is single, and both sides of the scaffold are easily affected by external factors, so that the integral supporting effect is poor.
SUMMERY OF THE UTILITY MODEL
Not enough to prior art exists, the utility model aims at providing a building engineering scaffold puts up strutting arrangement to solve current scaffold frame upper portion holding surface comparatively single, then both sides very easily receive external factor's influence, lead to the relatively poor problem of wholeness support effect.
In order to achieve the above purpose, the present invention is realized by the following technical solution: the utility model provides a building engineering scaffold puts up strutting arrangement, its structure is including consolidating fork arm, base, installation piece, bracing piece, protector, joint groove, cell-frame, bracing piece both sides upper end rigid coupling is on the cell-frame picture left side back position joint, the cell-frame is arranged the interval and is located on the joint groove bottom left and right sides position, the joint groove is fixed unchangeable with the high interval of base that the below branch was established about, the bracing piece is vertical to be located and is consolidated the fork arm picture and lean on left side position, consolidate the fork arm branch and locate about the cell-frame both sides concave wall on a little, the lower extreme fulcrum of the locating point as consolidating the fork arm about the base surface, the continuous protector of position assembly about the bracing piece.
Further, the protector includes sealing layer, skid resistant course, cover post, first balanced seat, bearing plate, branch, second balanced seat, the sealing layer is filled in and is located joint groove and bearing plate left and right sides recess, the embedded branch of a plurality of interval arrangements of bearing plate, second balanced seat is located on the wall about the bearing plate with first balanced seat branch, the cover post is hung and is established on being fixed in first balanced seat and second balanced seat middle part position, on the skid resistant course covers the upper and lower surface position of pasting the bearing plate, on the truss of position about first balanced seat and the fixed connection of second balanced seat bottom.
Furthermore, the slot frame mounting surface corresponds to the lower base in a vertical mode.
Furthermore, the surfaces of the two sides of the base are provided with mounting blocks positioned on the left side wall surface.
Furthermore, the mounting block groove is vertically connected with the corresponding lower end of the support rod.
Further, the supporting rod is positioned inside the upper outer wall sealing layer and the lower outer wall sealing layer.
Further, the bearing plate is transversely arranged between the tops of the left and right reinforcing fork rods.
Advantageous effects
The utility model relates to a building engineering scaffold puts up strutting arrangement, improve current scaffold frame superstructure, use as main backup pad with the bearing plate at protector middle part, wall butt joint sealing layer about the joint groove, embedded a plurality of dispersible support weight reach the branch of effective pressure, the upper and lower surface covers has the skid resistant course that improves frictional resistance, control the first balanced seat of position and the second balanced seat middle part rigid coupling sleeve post of standing upright, can effectively improve the installation fixity of structure, the equilibrium is good and have resistance to compression protectiveness about the mounting structure, can effectively improve scaffold frame service support performance.
Drawings
Other features, objects and advantages of the invention will become more apparent upon reading of the detailed description of non-limiting embodiments with reference to the following drawings:
fig. 1 is a schematic structural view of a scaffold support device for construction engineering according to the present invention;
fig. 2 is a schematic view of the assembly structure of the protector of the present invention.
In the figure: the device comprises a reinforcing fork rod-1, a base-2, a mounting block-3, a support rod-4, a protector-5, a sealing layer-A1, an anti-skid layer-B2, a sleeve column-C3, a first balance seat-D4, a bearing plate-E5, a support rod-F6, a second balance seat-G7, a joint groove-6 and a groove frame-7.
Detailed Description
In order to make the technical means, creation features, achievement purposes and functions of the present invention easy to understand, the present invention is further described below with reference to the following embodiments.
Referring to fig. 1-2, the present invention provides a technical solution: the utility model provides a scaffold support device for building engineering, its structure includes reinforcing fork arm 1, base 2, installation piece 3, bracing piece 4, protector 5, joint groove 6, truss 7, 4 upper ends rigid couplings in truss 7 picture left rear position joint of bracing piece both sides, truss 7 arranges the interval and locates on joint groove 6 bottom left and right sides position, joint groove 6 and below divide about setting base 2 height interval fixed unchangeable, bracing piece 4 vertically locates on reinforcing fork arm 1 picture near left side position, reinforcing fork arm 1 divides to locate on truss 7 both sides concave wall left and right points, base 2 surface left and right sides setpoint is as the lower extreme fulcrum of reinforcing fork arm 1, bracing piece 4 left and right sides position assembly links protector 5, protector 5 includes sealing layer A1, skid resistant layer B2, pocket post C3, first balance seat D4, bearing plate E5, branch lever F6, second balance seat G7, the sealing layer A1 is filled in the left and right grooves of the joint groove 6 and the bearing plate E5, a plurality of support rods F6 which are arranged at intervals are embedded in the bearing plate E5, the second balance seat G7 and the first balance seat D4 are respectively arranged on the left wall surface and the right wall surface of the bearing plate E5, the sleeve column C3 is vertically fixed on the middle position of the first balance seat D4 and the second balance seat G7, the anti-skid layer B2 is adhered on the upper and lower surfaces of the bearing plate E5, the first balance seat D4 and the second balance seat G7 are fixedly connected on the groove frame 7 at the left and right positions, the mounting surface of the slot frame 7 is vertically corresponding to the lower base 2, the surfaces of the two sides of the base 2 are provided with mounting blocks 3 positioned on the left side wall surface, the groove of the mounting block 3 is vertically connected with the corresponding lower end of the supporting rod 4, the supporting rod F6 is positioned inside the upper and lower outer wall sealing layer A1, and the bearing plate E5 is transversely arranged between the tops of the left and right reinforcing fork rods 1.
The anti-skid layer B2 is made of rubber and has raised friction resistance and thus high anti-skid effect.
For example: when using, improve current scaffold upper structure, use as main backup pad with the bearing plate E5 at protector 5 middle part, wall butt joint sealing layer A1 about joint groove 6, embedded a plurality of dispersible supporting weight reach the branch F6 of effective pressure, the upper and lower surface covers has the skid resistant course B2 that improves frictional resistance, the first balanced seat D4 of controlling the position and the second balanced seat G7 middle part standing department rigid coupling sleeve post C3, can effectively improve the installation fixity of structure, the equilibrium is good and have resistance to compression protectiveness about the mounting structure, can effectively improve scaffold use support performance.
The utility model provides a problem be current scaffold frame upper portion holding surface comparatively single, then both sides very easily receive the influence of external factor, lead to the wholeness supporting effect relatively poor, the utility model discloses a combination of each other of above-mentioned parts improves current scaffold frame superstructure to the bearing plate at protector middle part is used as main backup pad, and the equilibrium is good and have resistance to compression protectiveness about the mounting structure, can effectively improve the scaffold frame and use the support performance.
The basic principles and the main features of the invention and the advantages of the invention have been shown and described above, it will be evident to those skilled in the art that the invention is not limited to the details of the foregoing illustrative embodiments, but that the invention may be embodied in other specific forms without departing from the spirit or essential characteristics of the invention. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.
Furthermore, it should be understood that although the present description refers to embodiments, not every embodiment may contain only a single embodiment, and such description is for clarity only, and those skilled in the art should integrate the description, and the embodiments may be combined as appropriate to form other embodiments understood by those skilled in the art.
Claims (4)
1. The utility model provides a building engineering scaffold puts up strutting arrangement, its structure is including consolidating fork arm (1), base (2), installation piece (3), bracing piece (4), protection ware (5), joint groove (6), truss (7), its characterized in that:
the upper ends of the two sides of the supporting rod (4) are fixedly connected to a joint at the left rear position of a drawing of a groove frame (7), the groove frames (7) are arranged at intervals at the left and right positions of the bottom of a joint groove (6), the joint groove (6) and a left base (2) which is arranged below the joint groove are fixed at intervals, the supporting rod (4) is vertically arranged at the left position of the drawing of a reinforcing fork rod (1), the reinforcing fork rod (1) is arranged at left and right points of concave walls at the two sides of the groove frame (7), left and right positioning points on the surface of the base (2) are used as lower end fulcrums of the reinforcing fork rod (1), and a protector (5) is assembled and connected at the left and right positions of the supporting rod; the protector (5) comprises a sealing layer (A1), an anti-skid layer (B2), a sleeve column (C3), a first balance seat (D4), a bearing plate (E5), supporting rods (F6) and a second balance seat (G7), wherein the sealing layer (A1) is filled in grooves on the left and right sides of a joint groove (6) and the bearing plate (E5), the supporting rods (F6) which are arranged at intervals are embedded in the bearing plate (E5), the second balance seat (G7) and the first balance seat (D4) are respectively arranged on the left and right wall surfaces of the bearing plate (E5), the sleeve column (C3) is vertically fixed on the middle positions of the first balance seat (D4) and the second balance seat (G7), the anti-skid layer (B2) is attached to the upper and lower surface positions of the bearing plate (E5), and the first balance seat (D4) and the second balance seat (G7) are fixedly connected to the upper and lower surface frame (7) on the left and right side groove positions.
2. A construction scaffolding support as claimed in claim 1, in which: the mounting surface of the slot frame (7) is perpendicular to the base (2) below the slot frame.
3. A construction scaffolding support as claimed in claim 1, in which: the surface of the two sides of the base (2) is provided with a mounting block (3) positioned on the wall surface of the left side.
4. A construction scaffolding support as claimed in claim 1, in which: the groove of the mounting block (3) is vertically connected with the corresponding lower end of the support rod (4).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921992270.XU CN212078599U (en) | 2019-11-18 | 2019-11-18 | Building engineering scaffold support device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921992270.XU CN212078599U (en) | 2019-11-18 | 2019-11-18 | Building engineering scaffold support device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN212078599U true CN212078599U (en) | 2020-12-04 |
Family
ID=73555688
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201921992270.XU Expired - Fee Related CN212078599U (en) | 2019-11-18 | 2019-11-18 | Building engineering scaffold support device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN212078599U (en) |
-
2019
- 2019-11-18 CN CN201921992270.XU patent/CN212078599U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205711776U (en) | A kind of supporting bracket of bridge construction | |
CN212078599U (en) | Building engineering scaffold support device | |
CN205662758U (en) | Multi -functional external clothes hanger that dries in air | |
CN214532071U (en) | Reinforced structure during ancient building wall body migration | |
CN205036062U (en) | A cantilever frame that is used for building interior to choose kenozooecium position construction | |
CN210369739U (en) | Anti-cracking floor heating solid wood composite floor | |
CN211013468U (en) | Diagonal wall support bearing capacity detection device | |
CN208564575U (en) | Platform is used in a kind of displaying of subway segment | |
CN207376812U (en) | A kind of steel-structure factory building cantilevered structure | |
CN211949469U (en) | Reinforced supporting structure for constructional engineering | |
CN210662160U (en) | Fixing device for steel pipe arch bridge measuring prism | |
CN207893262U (en) | A kind of high-rise total concrete pump pipe corner fixing support rack | |
CN206090977U (en) | Junior unit couple formula stone material curtain wall construction | |
CN201292613Y (en) | Upper layer plate-rib hanger | |
CN207761296U (en) | A kind of removable concrete pump pipe supporting structure | |
CN205077800U (en) | Mounting structure of wall | |
CN216476191U (en) | Scaffold convenient to fixed mounting | |
CN210369810U (en) | Scaffold for high-rise building construction | |
CN214401438U (en) | Bridge engineering bent cap construction bracket | |
CN211368758U (en) | Firm foundation structure for building | |
CN204609297U (en) | Large-scale high-altitude load-bearing Cantilever Beams device | |
CN215889293U (en) | High-stability construction support frame for building technology | |
CN211898948U (en) | Building steel structure device | |
CN218436638U (en) | Through type steel pipe concrete tied arch bridge steel pipe arch main arch assembling support | |
CN216239030U (en) | Assembled beam slab connection structure for construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20201204 Termination date: 20211118 |