CN212053696U - Steel beam wall high altitude welding safety protection operation platform - Google Patents

Steel beam wall high altitude welding safety protection operation platform Download PDF

Info

Publication number
CN212053696U
CN212053696U CN201922297596.7U CN201922297596U CN212053696U CN 212053696 U CN212053696 U CN 212053696U CN 201922297596 U CN201922297596 U CN 201922297596U CN 212053696 U CN212053696 U CN 212053696U
Authority
CN
China
Prior art keywords
frame
rod
supporting rod
horizontal rod
steel beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201922297596.7U
Other languages
Chinese (zh)
Inventor
高远
常波
管宝华
李博宇
赵鑫
石建福
方凯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangxiao Steel Structure Hebei Construction Co ltd
Tianjin Construction Engineering Main Contracting Co ltd
Original Assignee
Hangxiao Steel Structure Hebei Construction Co ltd
Tianjin Construction Engineering Main Contracting Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangxiao Steel Structure Hebei Construction Co ltd, Tianjin Construction Engineering Main Contracting Co ltd filed Critical Hangxiao Steel Structure Hebei Construction Co ltd
Priority to CN201922297596.7U priority Critical patent/CN212053696U/en
Application granted granted Critical
Publication of CN212053696U publication Critical patent/CN212053696U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Abstract

The utility model discloses a steel beam wall high-altitude welding safety protection operating platform, which comprises an upper frame and at least two tripods, wherein the upper frame is connected and arranged by a side frame, a rear frame and a bottom frame, and steel plates are arranged on the upper surface of the bottom frame and the outer surfaces of the side frame and the rear frame; the top end of a vertical supporting rod of the tripod is connected with the lower surface of the rear end part of the horizontal rod, and the top end of the diagonal supporting rod is connected with the lower surface of the front part of the horizontal rod; the lower end of the vertical supporting rod is connected with the lower part of the inclined supporting rod, the lower end of the inclined supporting rod is connected with the supporting plate, the lower surface of the rear end of the horizontal rod is provided with an inserting rod, bolts are fixedly arranged on one side of the front end part and one side of the rear end part of the horizontal rod, and a hole is formed in the bottom frame of the upper frame. The utility model discloses overall stability is good, and high altitude construction is difficult for producing the displacement, has solved steel bundle wall high altitude welding operation's potential safety hazard, and the spark that the welding produced does not have outside splash phenomenon and takes place, and simple to operate, has shortened the operation period of a project of process.

Description

Steel beam wall high altitude welding safety protection operation platform
Technical Field
The utility model belongs to building engineering steel construction field relates to a steel bundle wall high altitude welding safety protection operation platform.
Background
The steel beam wall residential system is a novel structure system responding to the national vigorous development of an assembly type green building, and belongs to the field of new technologies. The main body of the structural building is a steel structure, and the system has the advantages of greenness, environmental protection, energy conservation, consumption reduction, engineering waste reduction, short construction period, strong earthquake resistance, land resource saving and the like.
The standard steel beam wall is prefabricated into a single-section module in a factory, and the single-section module generally corresponds to a multilayer vertical structure. During on-site installation, the single-section modules of the steel beam wall are assembled in a building block building mode, and the modules are spliced in a welding mode. Because steel bundle wall house system is applied to high-rise residential structure basically, and highly is about one hundred meters, and conventional high altitude concatenation welding operation adopts simple and easy hanging flower basket to solve, this way has two problems: firstly, the hanging basket is installed at high altitude and manually adjusted, so that a large amount of complicated operation is added for field construction personnel, the welding progress is slow, and the work efficiency of workers is reduced; secondly, sparks generated by high-altitude welding cannot be effectively protected, and potential safety hazards are generated to materials and personnel below the device.
SUMMERY OF THE UTILITY MODEL
The utility model aims at overcoming the not enough of prior art, provide a vertical welding safety protection operation platform of steel bundle wall.
The technical scheme of the utility model outlines as follows:
a steel beam wall high-altitude welding safety protection operating platform comprises an upper frame 1 and at least two tripods 2, wherein the upper frame is formed by connecting two side frames 7, a rear frame 8 and a bottom frame 9; the tripod 2 comprises a horizontal rod 10, a vertical supporting rod 3 and an inclined strut 4, the top end of the vertical supporting rod 3 is connected with the lower surface of the horizontal rod 10 close to the rear end, and the top end of the inclined strut 4 is connected with the lower surface of the front part of the horizontal rod 10; the lower end of a vertical supporting rod 3 is connected with the lower part of an inclined strut 4, the lower end of the inclined strut 4 is connected with a supporting plate 5, the lower surface of the rear end of a horizontal rod 10 is provided with an inserting rod 6, bolts 11 are fixedly arranged at one side of the front end part and one side of the rear end part of the horizontal rod 10 in high altitude, a bottom frame 9 of an upper frame 1 is provided with holes 12, and the bolts 11 and the holes 12 are movably connected through bolts and nuts.
The utility model discloses overall stability is good, and high altitude construction is difficult for producing the displacement, has solved steel bundle wall high altitude welding operation's potential safety hazard, and the spark that the welding produced by the utility model discloses steel bundle wall high altitude welding safety protection operation platform catches, and the outward phenomenon of splashing takes place, and simple to operate has shortened the operation period of process.
Drawings
FIG. 1 is a schematic structural view of a steel beam wall high-altitude welding safety protection operating platform.
Fig. 2 is a left-side view schematic diagram of a steel beam wall high-altitude welding safety protection operating platform.
FIG. 3 is a schematic left view of a tripod of a steel beam wall overhead welding safety protection operating platform.
Fig. 4 is a schematic diagram of a bottom frame and tripod horizontal rods 10 of an upper frame of a steel beam wall overhead welding safety protection operating platform.
FIG. 5 is a schematic view of the movable connection between the steel beam wall and the high-altitude welding safety protection operation platform for the steel beam wall.
Detailed Description
The present invention will be further described with reference to the accompanying drawings.
A steel beam wall high altitude welding safety protection operation platform, see fig. 1, 2, 3, 4, includes upper frame 1 and at least two tripods 2 (such as 2, 3 or 4, set up at interval), the upper frame is set up by two side frames 7, back frame 8 and underframe 9 connection, there are steel plates on the upper surface of the underframe, there are steel plates on the outer surfaces of the side frame and back frame; the tripod 2 comprises a horizontal rod 10, a vertical supporting rod 3 and an inclined strut 4, the top end of the vertical supporting rod 3 is connected with the lower surface of the horizontal rod 10 close to the rear end, and the top end of the inclined strut 4 is connected with the lower surface of the front part of the horizontal rod 10; the lower end of the vertical supporting rod 3 is connected with the lower part of the inclined supporting rod 4, the lower end of the inclined supporting rod 4 is connected with a supporting plate 5, the lower surface of the rear end of the horizontal rod 10 is provided with an inserting rod 6, bolts 11 are fixedly arranged on one side of the front end part and one side of the rear end part of the horizontal rod 10, a hole 12 is formed in the bottom frame 9 of the upper frame 1, and the bolts 11 are movably connected with the hole 12 through bolts and nuts.
The horizontal rods and the vertical supporting rods are arranged at 90 degrees, and the vertical supporting rods and the diagonal supporting rods are arranged at 45-60 degrees, such as 45 degrees, 50 degrees, 55 degrees and 60 degrees.
The steel bundle wall is pre-provided with a socket pipe 16, see fig. 5.
During the installation, will with hoisting equipment the utility model relates to a steel beam wall high altitude welding safety protection operation platform's socket pole inserts in the socket pipe that steel beam wall preset, carries out the welding of the interface 14 of upper segment steel beam wall 13 and lower segment steel beam wall 15, treats welding process operation and accomplishes the back, takes out the socket pole from the socket pipe with a kind of steel beam wall high altitude welding safety protection operation platform with the hoisting equipment, wholly shifts to next construction operation face.

Claims (1)

1. A steel beam wall high-altitude welding safety protection operating platform is characterized by comprising an upper frame (1) and at least two triangular supports (2), wherein the upper frame is formed by connecting two side frames (7), a rear frame (8) and a bottom frame (9), a steel plate is arranged on the upper surface of the bottom frame, and steel plates are arranged on the outer surfaces of the side frames and the rear frame; the tripod (2) comprises a horizontal rod (10), a vertical supporting rod (3) and an inclined strut (4), the top end of the vertical supporting rod (3) is connected with the lower surface of the horizontal rod (10) close to the rear end, and the top end of the inclined strut (4) is connected with the lower surface of the front part of the horizontal rod (10); the lower end of a vertical supporting rod (3) is connected with the lower part of an inclined supporting rod (4), the lower end of the inclined supporting rod (4) is connected with a supporting plate (5), an inserting rod (6) is arranged on the lower surface of the rear end of a horizontal rod (10), bolts (11) are fixedly arranged on one side of the front end part and one side of the rear end part of the horizontal rod (10), a hole (12) is formed in a bottom frame (9) of an upper frame (1), and the bolts (11) and the hole (12) are movably connected through bolts and nuts.
CN201922297596.7U 2019-12-19 2019-12-19 Steel beam wall high altitude welding safety protection operation platform Active CN212053696U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201922297596.7U CN212053696U (en) 2019-12-19 2019-12-19 Steel beam wall high altitude welding safety protection operation platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201922297596.7U CN212053696U (en) 2019-12-19 2019-12-19 Steel beam wall high altitude welding safety protection operation platform

Publications (1)

Publication Number Publication Date
CN212053696U true CN212053696U (en) 2020-12-01

Family

ID=73512838

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201922297596.7U Active CN212053696U (en) 2019-12-19 2019-12-19 Steel beam wall high altitude welding safety protection operation platform

Country Status (1)

Country Link
CN (1) CN212053696U (en)

Similar Documents

Publication Publication Date Title
CN206174138U (en) Joint construction suitable for steel house room externally -hanging wallboard and major structure
CN203808484U (en) Integrated cantilevered and attached external scaffolding
CN213329955U (en) Flower basket diagonal rod type overhanging scaffold
CN212053696U (en) Steel beam wall high altitude welding safety protection operation platform
CN207003782U (en) A kind of ceiling support system
CN208201919U (en) A kind of piping lane monoblock type, which is quickly pacified, tears aluminium alloy mould bases support construction open
CN204299022U (en) Prefabricated unit volume grating system
CN214739106U (en) Curtain wall steel frame node
CN210195200U (en) Hanging flower basket device of encorbelmenting of high parapet
CN205132926U (en) Special well word hoist of hydroelectric set tail water ell
CN210507901U (en) Assembled wall module
CN205712637U (en) High-rise oversize stone material molding unit body and grid system thereof
CN102777703A (en) Assembly type light pipeline hanger
CN208718346U (en) Building engineering outer scaffold wall connector
CN208235587U (en) A kind of large-span deep foundation pit underground power house rack assembling construction platform
CN207568333U (en) A kind of economic and environment-friendly, repeatable assembled steel enclosing and enclosing component
CN201274392Y (en) Operating platform on portable adjustable bar
CN210086725U (en) Assembled for building externally-hung wallboard fossil fragments convenient to installation
CN213297406U (en) A rail guard for hydraulic engineering
CN213927840U (en) Assembled enclosure wall
CN204782128U (en) Sound arrester of transformer substation and overall structure of fire wall
CN204676439U (en) A kind of Bailey beam formula can be hung by supertronic tower top
CN218117146U (en) Assembled building outer wall protection frame
CN219753509U (en) Column foot structure of curtain wall
CN215331360U (en) Adjustable simple and easy safe operation platform