CN211971501U - Tool clamp for mounting and moving G7.5 substrate glass muffle furnace supporting bricks - Google Patents

Tool clamp for mounting and moving G7.5 substrate glass muffle furnace supporting bricks Download PDF

Info

Publication number
CN211971501U
CN211971501U CN201922182188.7U CN201922182188U CN211971501U CN 211971501 U CN211971501 U CN 211971501U CN 201922182188 U CN201922182188 U CN 201922182188U CN 211971501 U CN211971501 U CN 211971501U
Authority
CN
China
Prior art keywords
brick
muffle furnace
overflow
fixing plate
mounting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201922182188.7U
Other languages
Chinese (zh)
Inventor
乔鹏程
苏双全
郑红宣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Caihong Group Co ltd
Original Assignee
Caihong Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Caihong Group Co ltd filed Critical Caihong Group Co ltd
Priority to CN201922182188.7U priority Critical patent/CN211971501U/en
Application granted granted Critical
Publication of CN211971501U publication Critical patent/CN211971501U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Furnace Housings, Linings, Walls, And Ceilings (AREA)

Abstract

The utility model discloses a G7.5 base plate glass muffle furnace supports brick installation and moves and uses frock clamp, the device is including hanging the mechanism, it sets up fixture to hang the mechanism lower part, it is connected with the crane to hang the mechanism, the last overflow brick of placing of fixture supports the brick. The utility model discloses can effectively solve present overflow brick and support the brick installation, do not have special centre gripping migration equipment, adopt artifical transport, the installation degree of difficulty is bigger, has the problem that supports the brick and break down the risk.

Description

Tool clamp for mounting and moving G7.5 substrate glass muffle furnace supporting bricks
Technical Field
The utility model relates to a migration equipment technical field, in particular to G7.5 base plate glass muffle furnace supporting brick installation is moved and is used frock clamp.
Background
In the installation process of G7.5 liquid crystal substrate glass forming equipment, the supporting bricks are made of compact zirconium materials, are small in size, high in density, strong in brittleness and fragile, and are 60 kg or so in weight, and in the installation process of the existing overflow brick supporting bricks, special clamping and transporting equipment is not available, so that the supporting bricks can be transported only manually, the installation difficulty is high, and the risk of breaking the supporting bricks is also existed.
SUMMERY OF THE UTILITY MODEL
To the technical problem, the utility model provides a G7.5 base plate glass muffle furnace supports brick installation and moves and uses frock clamp can effectively solve present overflow brick and support the brick installation, does not have special centre gripping migration equipment, adopts artifical transport, and the installation degree of difficulty is bigger, has the problem that supports the brick and break into pieces the risk.
In order to achieve the above object, the technical solution of the present invention is specifically as follows:
the utility model provides a G7.5 base plate glass muffle furnace supports brick installation and moves and uses frock clamp, includes and hangs the mechanism, it sets up fixture to hang the mechanism lower part, it is connected with the crane to hang the mechanism, the last overflow brick that places of fixture supports the brick.
The hanging mechanism comprises a hanging ring and a hanging ring fixing plate, and the hanging ring is arranged on the upper portion of the hanging ring fixing plate.
The lower end of the lifting ring is connected with the lifting ring fixing plate in a matched mode through threads.
Fixture includes upper portion mount, anterior mount, lower part fixed plate, the tight screw in top, the vertical anterior mount that sets up of upper portion mount one end, the bottom level of anterior mount sets up the lower part fixed plate, the vertical installation screw that sets up of lower part fixed plate one end, cooperation installation top tight screw on the installation screw, overflow brick support brick's upper portion with the inboard top of upper portion mount is tight, overflow brick support brick's front portion with the inboard top of anterior mount is tight, overflow brick support brick's lower part with the lower part fixed plate upside is tight through the mutual top of a tight screw in top.
The bottom of the front fixing frame is connected with one end of the lower fixing plate through a fastening screw.
And a small fixing plate is vertically arranged at the other end of the upper fixing frame, and the small fixing plate is tightly propped against the rear part of the overflow brick supporting brick.
The small fixing plate is tightly propped against the rear part of the overflow brick supporting brick through a rear bakelite base plate.
And the top of the jacking screw is tightly jacked with the lower part of the overflow brick supporting brick through a lower bakelite base plate.
The utility model has the advantages that: the utility model fixes the overflow brick supporting brick on the clamping mechanism, connects the hanging mechanism with the lifting device, lifts the overflow brick supporting brick by the lifting device and moves the overflow brick supporting brick to the installation area, effectively solves the problem of manual transportation, the installation difficulty is large, the risk of breaking the overflow brick supporting brick exists, improves the production efficiency, accelerates the equipment installation progress, wherein, the upper part of the hanging ring fixing plate of the hanging mechanism is provided with a hanging ring, the lower part is connected with the clamping mechanism, the hanging ring is convenient to be connected with the lifting device, the hanging ring is connected with the clamping mechanism through the hanging ring fixing plate instead of being directly connected with the clamping mechanism, the design can increase the acting area between the hanging ring and the clamping mechanism, improves the mechanical stability, is convenient to maintain, and facilitates the fine adjustment after the lifting device is connected with the hanging ring, the lower end of the hanging ring is connected with the hanging ring fixing plate through screw threads, the clamping mechanism forms a C-shaped structure through the upper fixing frame, the front fixing frame and the lower fixing plate thereof, and is matched with the jacking screw to tightly lock and fix the upper surface and the lower surface of the overflow brick supporting brick, so as to realize the clamping function of the utility model, in order to put the overflow brick supporting brick into the clamping mechanism conveniently, the bottom of the front fixing frame is mutually connected with one end of the lower fixing plate through the fastening screw, the front fixing frame and the lower fixing plate can realize relative rotation only by unscrewing the fastening screw, when the overflow brick supporting brick is required to be put into the clamping mechanism, the upper part and the front part of the overflow brick supporting brick can be clung to the upper fixing frame and the front fixing frame only by rotating the lower fixing plate, the lower fixing plate is rotated again to lead the lower fixing plate to clung to the lower part of the overflow brick supporting brick, and the overflow, in order to make the rear portion that the overflow brick supported the brick also can be fixed by the fixture centre gripping, prevent the migration in-process, the overflow brick supports the brick and drops, the one end of upper portion mount sets up little fixed plate, little fixed plate supports the rear portion top of brick with the overflow brick tightly, in order to prevent the centre gripping in-process, little fixed plate produces the damage to the rear portion that the overflow brick supported the brick, little fixed plate passes through rear portion bakelite backing plate and the rear portion top of overflow brick support brick tightly, in order to prevent that the top tight screw is rotating the tight in-process in top, cause the damage to the lower part that the overflow brick supported the brick, the top tight screw top is supported tightly through lower part bakelite backing plate and overflow brick support the.
Drawings
Fig. 1 is a front view schematically illustrating the structure of the present invention.
Fig. 2 is a side view of fig. 1.
Fig. 3 is a perspective view of the tooling fixture of fig. 1.
The device comprises a lifting ring 1, a lifting ring 2, a lifting ring fixing plate 3, an upper fixing frame 4, a front fixing frame 5, a lower bakelite backing plate 6, a lower fixing plate 7, a jacking screw 8, a fastening screw 9, an overflow brick supporting brick 10 and a rear bakelite backing plate; 11. and a small fixing plate.
Detailed Description
As shown in fig. 1 and 2, the tool clamp for mounting and moving the support bricks of the G7.5 substrate glass muffle furnace comprises a hanging mechanism, wherein a clamping mechanism is arranged at the lower part of the hanging mechanism, the hanging mechanism is connected with a crane, an overflow brick support brick 9 is placed on the clamping mechanism, the hanging mechanism comprises a hanging ring 1 and a hanging ring fixing plate 2, the upper part of the hanging ring fixing plate 2 is provided with the hanging ring 1, the lower end of the hanging ring 1 is in matched connection with the hanging ring fixing plate 2 through threads, and the clamping mechanism comprises an upper fixing frame 3, a front fixing frame 4, a lower fixing plate 6 and a jacking screw 7; the hoisting ring fixing plate 2 is fixedly connected with the upper fixing frame 3. The vertical anterior mount 4 that sets up of 3 one ends of upper portion mount, the bottom level of anterior mount 4 sets up bottom plate 6, the vertical installation screw that sets up of 6 one end of bottom plate, cooperation installation top tight screw 7 on the installation screw, overflow brick supports the upper portion of brick 9 and 3 inboard tops tightly of upper portion mount, overflow brick supports the anterior and 4 inboard tops tightly of anterior mount of brick 9, overflow brick supports the lower part of brick 9 and pushes up tightly each other through top tight screw 7 with 6 upsides of bottom plate, fastening screw 8 interconnect is passed through with 6 one end of bottom plate in the bottom of anterior mount 4, the vertical little fixed plate that sets up of the 3 other ends of upper portion mount, little fixed plate and overflow brick support the rear portion top of brick 9 tightly, little fixed plate passes through rear portion bakelite backing plate 10 and overflow brick support the rear portion top of brick 9 tightly, the top tight screw 7 top is tightly pushed up through lower part bakelite backing plate 5 and overflow brick.
When the utility model is used, firstly the clamp is cleaned up, the lower part bakelite backing plate 5, the rear part bakelite backing plate 10, the jacking screw 8 and the suspension ring 1 are prepared, the fastening screw 8 is unscrewed to loosen the front fixing frame 4 and the lower fixing plate 6, the lower fixing plate 6 can rotate relative to the front fixing frame 4, at the moment, the lower fixing plate 6 is rotated to one side, the overflow brick supporting brick 9 is placed in the clamp, the front part, the upper part and the rear part of the overflow brick supporting brick 9 are respectively tightly propped against the front fixing frame 4, the upper fixing frame 3 and the small fixing plate, meanwhile, the rear part bakelite backing plate 10 is padded between the small fixing plate and the rear part of the overflow brick supporting brick 9, finally, the lower fixing plate 6 is rotated to ensure that the lower fixing plate 6 is mutually contacted with the lower part of the overflow brick supporting brick 9, the fastening screw 8 is screwed, so that the front fixing frame 4 and the lower fixing plate 6, and the lower part bakelite backing plate 5 is padded between the upper end of a fastening screw 9 and the lower part of an overflow brick supporting brick 9, the fastening screw 9 is screwed, the lower part bakelite backing plate 5 is tightly pressed by a jacking screw 8 to achieve the purpose of tightly pressing the lower side of the supporting brick, whether the supporting brick is loosened or not is checked, the check is completed, a lifting ring 1 is screwed (screwed and retreated for a half circle), the lifting ring is locked by a lifting belt, the lifting is carried out at a low speed by a crane, two persons are well protected around, the supporting brick is prevented from swinging too much and being damaged after being lifted, the supporting brick is lifted to a specified position, after the size of the mounting position is confirmed, the fastening screw 9 and the jacking screw 8 are loosened, the lower part bakelite backing plate 5 and the rear part.

Claims (7)

1. A tool clamp for mounting and moving a support brick of a G7.5 substrate glass muffle furnace is characterized by comprising a hanging mechanism, wherein the lower part of the hanging mechanism is provided with a clamping mechanism, the hanging mechanism is connected with a crane, and an overflow brick support brick (9) is placed on the clamping mechanism; fixture includes upper portion mount (3), anterior mount (4), bottom plate (6), top tight screw (7), the vertical anterior mount (4) that sets up of upper portion mount (3) one end, the bottom level of anterior mount (4) sets up bottom plate (6), the vertical installation screw that sets up of bottom plate (6) one end, cooperation installation top tight screw (7) on the installation screw, the upper portion that the overflow brick supported brick (9) with the inboard top of upper portion mount (3) is tight, the overflow brick support the anterior with the inboard top of anterior mount (4) is tight, the overflow brick support the lower part of brick (9) with bottom plate (6) upside pushes up tightly each other through top tight screw (7).
2. The tool clamp for mounting and moving the G7.5 substrate glass muffle furnace supporting brick according to claim 1, wherein: the hanging mechanism comprises a hanging ring (1) and a hanging ring fixing plate (2), and the hanging ring (1) is arranged on the upper portion of the hanging ring fixing plate (2).
3. The tool clamp for mounting and moving the G7.5 substrate glass muffle furnace supporting brick according to claim 2, wherein: the lower end of the lifting ring (1) is connected with the lifting ring fixing plate (2) in a matched mode through threads.
4. The tool clamp for mounting and moving the G7.5 substrate glass muffle furnace supporting brick according to claim 1, wherein: the bottom of the front fixing frame (4) is connected with the other end of the lower fixing plate (6) through a fastening screw (8).
5. The tool clamp for mounting and moving the G7.5 substrate glass muffle furnace supporting brick according to claim 1, wherein: and a small fixing plate (11) is vertically arranged at the other end of the upper fixing frame (3), and the small fixing plate is tightly propped against the rear part of the overflow brick supporting brick (9).
6. The tool clamp for mounting and moving the G7.5 substrate glass muffle furnace supporting brick according to claim 5, wherein: the small fixing plate is tightly propped against the rear part of the overflow brick supporting brick (9) through a rear bakelite base plate (10).
7. The tool clamp for mounting and moving the G7.5 substrate glass muffle furnace supporting brick according to claim 1, wherein: the top of the jacking screw (7) is tightly jacked with the lower part of the overflow brick supporting brick (9) through a lower bakelite base plate (5).
CN201922182188.7U 2019-12-06 2019-12-06 Tool clamp for mounting and moving G7.5 substrate glass muffle furnace supporting bricks Active CN211971501U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201922182188.7U CN211971501U (en) 2019-12-06 2019-12-06 Tool clamp for mounting and moving G7.5 substrate glass muffle furnace supporting bricks

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201922182188.7U CN211971501U (en) 2019-12-06 2019-12-06 Tool clamp for mounting and moving G7.5 substrate glass muffle furnace supporting bricks

Publications (1)

Publication Number Publication Date
CN211971501U true CN211971501U (en) 2020-11-20

Family

ID=73378542

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201922182188.7U Active CN211971501U (en) 2019-12-06 2019-12-06 Tool clamp for mounting and moving G7.5 substrate glass muffle furnace supporting bricks

Country Status (1)

Country Link
CN (1) CN211971501U (en)

Similar Documents

Publication Publication Date Title
CN211971501U (en) Tool clamp for mounting and moving G7.5 substrate glass muffle furnace supporting bricks
CN207876812U (en) A kind of inclination examination board suction cup carrier
CN207811062U (en) A kind of special hanger of nuclear power plant's concrete barrel shape disposal container
CN213085198U (en) Balance hanging beam group lifting appliance
CN214167184U (en) Integral vehicle-mounted automatic loading and unloading device for shelter laboratory
CN212828597U (en) Stone material conveyor
CN211823856U (en) Fixing device for manufacturing quartz ceramic crucible
CN211004189U (en) Box girder template hoist
CN108100857A (en) A kind of special hanger of nuclear power plant's concrete barrel shape disposal container
CN220485286U (en) Module overturning machine
CN216303060U (en) Hoisting platform for construction of steel structure transformer substation
CN219116960U (en) Triangle-shaped glass plate hoist and mount anchor clamps
CN216971727U (en) Purification crucible cover hoisting device
CN220578711U (en) Clamp for transferring workpiece
CN214028725U (en) Moving tool for gypsum board materials
CN212799290U (en) Crucible clamping device
CN218138111U (en) Mechanical arm for transferring
CN211198364U (en) Simple lifting clamp
CN217025022U (en) Stable lifting device for steel structure machining
CN210527814U (en) Unloading device and glass bottle sheath unloader
CN216997257U (en) Hoisting clamp for limiting hoisting and bending of plate
CN209411587U (en) Hard alloy soft paste hoisting board device
CN215578460U (en) Automatic stacking mechanical structure arranged in semiconductor manufacturing equipment
CN116177377B (en) Argil jar hoist, turning device and transfer equipment
CN220485099U (en) Novel aluminum electrolysis cell shell lifting appliance

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Assignee: Hunan Shaohong special glass Co.,Ltd.

Assignor: CAIHONG GROUP Co.,Ltd.

Contract record no.: X2023980042112

Denomination of utility model: A fixture for installing and moving supporting bricks of G7.5 substrate glass muffle furnace

Granted publication date: 20201120

License type: Common License

Record date: 20230922