CN211949120U - An installation structure of a fully prefabricated floor slab - Google Patents

An installation structure of a fully prefabricated floor slab Download PDF

Info

Publication number
CN211949120U
CN211949120U CN202020517428.4U CN202020517428U CN211949120U CN 211949120 U CN211949120 U CN 211949120U CN 202020517428 U CN202020517428 U CN 202020517428U CN 211949120 U CN211949120 U CN 211949120U
Authority
CN
China
Prior art keywords
prefabricated
mounting
floor slab
holes
mounting holes
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020517428.4U
Other languages
Chinese (zh)
Inventor
王�琦
冯波
杨强
阳昌辉
李静
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xin Ye Jiaotou Shancheng (Chengdu) Construction Technology Co., Ltd.
Original Assignee
Cmcc Investment Shanzhu Chengdu Prefabricated Building Technology Development Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Cmcc Investment Shanzhu Chengdu Prefabricated Building Technology Development Co ltd filed Critical Cmcc Investment Shanzhu Chengdu Prefabricated Building Technology Development Co ltd
Priority to CN202020517428.4U priority Critical patent/CN211949120U/en
Application granted granted Critical
Publication of CN211949120U publication Critical patent/CN211949120U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Panels For Use In Building Construction (AREA)

Abstract

The utility model discloses an installation structure of a full precast floor slab, which comprises a supporting structure, a precast slab, a first installation hole, a second installation hole and a stable hole; the first mounting holes and the second mounting holes are respectively formed in two side walls in the width direction of the prefabricated slab, the stabilizing holes are uniformly formed in the prefabricated slab, the supporting structure is arranged at the bottom of the prefabricated slab, and the supporting structure is connected with the stabilizing holes; the full-prefabricated floor slab has strong out-of-plane rigidity and strength, the floor slab has enough supporting length on the beam during installation, temporary support is not required to be arranged during field installation, construction cost is reduced, construction speed is increased, the conditions that the floor slab slides off and cracks in the construction process and the like are avoided, and construction safety factor is high.

Description

一种全预制楼板的安装结构An installation structure of a fully prefabricated floor slab

技术领域technical field

本实用新型涉及建筑施工领域,尤其涉及一种全预制楼板的安装结构。The utility model relates to the field of building construction, in particular to an installation structure of a fully prefabricated floor slab.

背景技术Background technique

目前装配式混凝土建筑结构中楼板通常采用混凝土叠合板,这种做法主要是将楼板的下部在工厂预制,四周外伸钢筋,现场安装时将叠合楼板作为模板,浇筑上部混凝土。并且,为了配合楼板的连接通常需要在预制梁、预制剪力墙等构件上预留叠合层,且在构件上方外伸钢筋。At present, the floor slabs in the prefabricated concrete building structure are usually made of concrete composite slabs. This method is mainly to prefabricate the lower part of the floor slab in the factory, and extend the steel bars around it. During the on-site installation, the composite floor slab is used as a formwork, and the upper part of the concrete is poured. In addition, in order to cooperate with the connection of the floor slabs, it is usually necessary to reserve a superimposed layer on components such as prefabricated beams and prefabricated shear walls, and extend steel bars above the components.

由于需要大量外伸钢筋,预制构件生产时需要在模板上预留孔洞,构件生产极为不便。并且,构件安装时现场的混凝土浇筑量较大,从而也就降低了现场的施工速度。另一方面,由于叠合楼板仅下部在工厂预制,预制混凝土板的厚度较低,预制楼板的刚度和强度较低,构件吊装时预制楼板容易开裂。为了解决这一问题,通常需要在板的上方增加桁架钢筋,提高预制楼板的刚度和强度,但是这一做法增加了预制楼板的含钢量,从而也就提高了楼板的成本。Due to the need for a large number of overhanging steel bars, holes need to be reserved on the formwork during the production of prefabricated components, which is extremely inconvenient for component production. In addition, the amount of concrete pouring on site during component installation is relatively large, thereby reducing the construction speed on site. On the other hand, since only the lower part of the laminated floor is prefabricated in the factory, the thickness of the prefabricated concrete slab is low, and the rigidity and strength of the prefabricated floor slab are low, and the prefabricated floor slab is easy to crack when the components are hoisted. In order to solve this problem, it is usually necessary to add truss steel bars above the slab to improve the rigidity and strength of the prefabricated slab, but this approach increases the steel content of the prefabricated slab, thereby increasing the cost of the slab.

全预制楼板则整块楼板均在工厂生产,楼板的刚度和强度较大,因此无需再增加桁架钢筋。但是全预制楼板目前应用并不广泛,主要原因是缺乏简便可靠的连接形式,目前的做法是在板四周外伸钢筋,同时在梁的上部预留叠合层,现场安装时将楼板外伸钢筋伸入到梁上部叠合层,而后浇筑混凝土。这种做法同样无法避免楼板四周需要外伸钢筋的弊端,同时存在着楼板钢筋锚固不足的风险。The full prefabricated floor slab is produced in the factory, and the rigidity and strength of the floor slab are high, so there is no need to add truss reinforcement. However, fully prefabricated floor slabs are not widely used at present. The main reason is that there is a lack of simple and reliable connection forms. The current practice is to extend steel bars around the slab, and at the same time, a superimposed layer is reserved on the upper part of the beam. Reach into the upper superimposed layer of the beam, and then pour concrete. This approach also cannot avoid the disadvantages of the need for overhanging steel bars around the floor, and at the same time, there is a risk of insufficient anchoring of the floor steel bars.

实用新型内容Utility model content

针对上述问题,本实用新型提出了一种全预制楼板的安装结构。该结构在预制板内部和侧壁上设置有连接节点,使构件稳固连接,且预制混凝土构件无需外伸钢筋且现场浇筑量较小,施工速度快。In view of the above problems, the utility model proposes an installation structure of a fully prefabricated floor slab. In the structure, connection nodes are arranged inside the prefabricated slab and on the side walls, so that the components are firmly connected, and the prefabricated concrete components do not need overhanging steel bars, the on-site pouring amount is small, and the construction speed is fast.

本方案是这样进行实现的:This scheme is implemented as follows:

一种全预制楼板的安装结构,括支撑结构、预制板、第一安装孔、第二安装孔和稳固孔;所述第一安装孔和第二安装孔分别设置在预制板宽度方向的两侧壁上,所述稳固孔在预制板上均匀设置,所述支撑结构设置在预制板的底部位置,所述支撑结构与稳固孔进行连接。An installation structure for a fully prefabricated floor plate, comprising a support structure, a prefabricated plate, a first installation hole, a second installation hole and a stabilization hole; the first installation hole and the second installation hole are respectively arranged on both sides in the width direction of the prefabricated plate On the wall, the stabilization holes are evenly arranged on the prefabricated plate, the support structure is arranged at the bottom of the prefabricated plate, and the support structure is connected with the stabilization holes.

作为优选的,所述第一安装孔和第二安装孔在同一预制板的同一侧壁上交替设置为多个,且在同一预制板的同一侧壁上交替设置的第一安装孔和第二安装孔高度位置设置不同。Preferably, a plurality of the first mounting holes and the second mounting holes are alternately arranged on the same side wall of the same prefabricated board, and the first mounting holes and the second mounting holes are alternately arranged on the same side wall of the same prefabricated board The height and position of the mounting holes are set differently.

作为优选的,所述第一安装孔和第二安装孔在同一预制板的对立侧壁上相配设置为多个,且同一预制板的对立侧壁上相匹配设置的第一安装孔和第二安装孔高度位置设置相同。Preferably, a plurality of the first mounting holes and the second mounting holes are matched on the opposite side walls of the same prefabricated board, and the first mounting holes and the second mounting holes are matched on the opposite side walls of the same prefabricated board. The height and position of the mounting holes are set the same.

作为优选的,所述支撑结构包括预制混凝土梁和预埋钢筋,所述预埋钢筋一端设置在预制混凝土梁内,另一端突出预制混凝土梁的上表面设置,所述预埋钢筋突出预制混凝土梁的一端设置有螺纹。Preferably, the support structure includes a precast concrete beam and a prefabricated steel bar, one end of the prefabricated concrete beam is arranged in the prefabricated concrete beam, the other end is arranged protruding from the upper surface of the prefabricated concrete beam, and the prefabricated concrete beam protrudes from the prefabricated concrete beam. One end is provided with a thread.

作为优选的,所述稳固孔在预制板上设置有多个,且稳固孔贯穿预制板设置,所述稳固孔的位置与支撑结构的位置相匹配。Preferably, a plurality of the stabilization holes are provided on the prefabricated plate, and the stabilization holes are arranged through the prefabricated plate, and the positions of the stabilization holes match the positions of the support structure.

作为优选的,所述第一安装孔和第二安装孔后端设置有安装槽,所述第一安装孔和第二安装孔之间设置有螺杆。Preferably, the rear ends of the first mounting holes and the second mounting holes are provided with mounting grooves, and a screw rod is provided between the first mounting holes and the second mounting holes.

作为优选的,所述预制板的侧壁为阶梯形,同侧预制板上的第一安装孔和第二安装孔在不同的阶梯位置上。Preferably, the side wall of the prefabricated board is stepped, and the first mounting hole and the second mounting hole on the same side of the prefabricated board are at different stepped positions.

作为优选的,所述预埋钢筋设置在预制混凝土梁的一端成勾形结构。Preferably, the pre-embedded steel bars are arranged at one end of the precast concrete beam to form a hook-shaped structure.

作为优选的,所述稳固孔的孔形状为上方下圆;在楼板侧边设置倒角,方便后期防水处理。Preferably, the shape of the stabilizing hole is round at the top and round at the bottom; chamfers are provided on the sides of the floor slab to facilitate the waterproof treatment in the later stage.

与现有技术相比,本实用新型的有益效果是:Compared with the prior art, the beneficial effects of the present utility model are:

1、全预制楼板本身具备较强的平面外刚度和强度,安装时楼板在梁上有足够的支撑长度,现场安装时无需设置临时支撑,降低了施工成本,提高了施工速度,并且避免了楼板在施工过程中发生滑落以及楼板开裂等情况,施工安全系数高。1. The fully prefabricated floor slab itself has strong out-of-plane rigidity and strength. The floor slab has sufficient support length on the beam during installation. There is no need to set temporary support during on-site installation, which reduces the construction cost, improves the construction speed, and avoids the floor slab. In the process of construction, slippage and floor cracking occur, and the construction safety factor is high.

2、楼板受力合理,传力明确。楼板连接完成后,企口位置的上、下部螺栓和楼板混凝土共同作用可以提供抗弯能力。预制梁内预埋的带丝口钢筋可以限制楼板与预制梁的相对位移。整个楼板连接完成后支座位置具备承受弯矩的能力,可以形成连续楼板体系,从而降低了楼板的配筋量和变形量。2. The force of the floor is reasonable and the force transmission is clear. After the slab connection is completed, the upper and lower bolts at the tongue and groove position and the slab concrete work together to provide bending resistance. The prefabricated steel bars with wire openings in the prefabricated beams can limit the relative displacement between the floor slab and the prefabricated beams. After the entire floor is connected, the support position has the ability to bear the bending moment, which can form a continuous floor system, thereby reducing the amount of reinforcement and deformation of the floor.

3、楼板和预制梁均不需要向外伸出钢筋,降低了施工难度,并且现场仅在矩形槽等位置后浇混凝土,现场混凝土浇筑量很小,进一步提高了现场的施工速度。3. Neither the floor slab nor the prefabricated beams need to protrude steel bars, which reduces the difficulty of construction, and the site is only poured concrete in the rectangular groove and other positions, and the amount of on-site concrete pouring is small, which further improves the construction speed on site.

附图说明Description of drawings

图1是本实用新型安装结构的部分剖面结构示意图;Fig. 1 is the partial sectional structure schematic diagram of the installation structure of the present utility model;

图2是本实用新型整体的俯视结构示意图;Fig. 2 is the top view structure schematic diagram of the whole of the present utility model;

图3是本实用新型预制板之间密拼详图;Figure 3 is a detailed view of the close-fitting between the prefabricated boards of the present utility model;

图中:1、支撑结构;2、预制板;3、第一安装孔;4、第二安装孔;5、稳固孔;6、螺杆;7、安装槽;11、预制混凝土梁;12、预埋钢筋。In the figure: 1. Supporting structure; 2. Prefabricated plate; 3. First mounting hole; 4. Second mounting hole; 5. Stabilizing hole; 6. Screw; 7. Mounting slot; 11. Precast concrete beam; Buried steel.

具体实施方式Detailed ways

为了使本实用新型的目的、技术方案及优点更加清楚明白,以下结合附图及实施例,对本实用新型进行进一步详细说明。应当理解,此处所描述的具体实施例仅仅用以解释本实用新型,并不用于限定本实用新型。In order to make the purpose, technical solutions and advantages of the present utility model more clearly understood, the present utility model will be further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention, and are not intended to limit the present invention.

在本实用新型的描述中,需要理解的是,术语“长度”、“宽度”、“上”、“下”、“前”、“后”、“左”、“右”、“竖直”、“水平”、“顶”、“底”“内”、“外”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本实用新型和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本实用新型的限制。此外,在本实用新型的描述中,“多个”的含义是两个或两个以上,除非另有明确具体的限定。In the description of the present invention, it should be understood that the terms "length", "width", "upper", "lower", "front", "rear", "left", "right", "vertical" , "horizontal", "top", "bottom", "inside", "outside" and other indicated orientations or positional relationships are based on the orientations or positional relationships shown in the accompanying drawings, only for the convenience of describing the present utility model and simplifying the description, Rather than indicating or implying that the indicated device or element must have a particular orientation, be constructed and operate in a particular orientation, it should not be construed as a limitation of the present invention. In addition, in the description of the present invention, "plurality" means two or more, unless otherwise expressly and specifically defined.

实施例1Example 1

请参阅图1-3,本实用新型提供一种技术方案:Please refer to Figures 1-3, the utility model provides a technical solution:

一种全预制楼板的安装结构,包括支撑结构1、预制板2、第一安装孔3、第二安装孔4和稳固孔5;所述第一安装孔3和第二安装孔4分别设置在预制板2宽度方向的两侧壁上,所述稳固孔5在预制板2上均匀设置,所述支撑结构1设置在预制板2的底部位置,所述支撑结构1与稳固孔5进行连接。An installation structure for a fully prefabricated floor slab, comprising a support structure 1, a prefabricated plate 2, a first installation hole 3, a second installation hole 4 and a stabilization hole 5; the first installation hole 3 and the second installation hole 4 are respectively arranged in On the two side walls in the width direction of the prefabricated board 2 , the stabilization holes 5 are evenly arranged on the prefabricated board 2 , the support structure 1 is arranged at the bottom of the prefabricated board 2 , and the support structure 1 is connected with the stabilization holes 5 .

通过支撑结构1与稳固孔5进行稳固连接,使全预制楼板稳固的安装在支撑结构1上,相邻的全预制楼板通过其相邻位置上不同全预制楼板上对应的第一安装孔3和第二安装孔4进行固定连接,使相邻的全预制楼板进行稳固连接,保证整体全预制楼板安装结构的稳固性。The fully prefabricated floor slab is stably installed on the supporting structure 1 through the stable connection between the supporting structure 1 and the stabilizing hole 5, and the adjacent fully prefabricated floor slabs pass through the corresponding first installation holes 3 and The second installation holes 4 are fixedly connected, so that the adjacent fully prefabricated floor slabs are firmly connected, and the stability of the overall fully prefabricated floor slab installation structure is guaranteed.

通过本方案,可以使全预制楼板本身具备较强的平面外刚度和强度,安装时楼板在梁上有足够的支撑长度,现场安装时无需设置临时支撑,降低了施工成本,提高了施工速度,并且避免了楼板在施工过程中发生滑落以及楼板开裂等情况,施工安全系数高。Through this scheme, the fully prefabricated floor slab itself can have strong out-of-plane rigidity and strength, and the floor slab has sufficient support length on the beam during installation, and there is no need to provide temporary support during on-site installation, which reduces the construction cost and improves the construction speed. In addition, the sliding of the floor slab and the cracking of the floor slab during the construction process are avoided, and the construction safety factor is high.

全预制楼板连接完成后,第一安装孔3、第二安装孔4、螺杆6和楼板混凝土共同作用可以提供抗弯能力。预制梁内预留的稳固孔5可以限制楼板与预制梁的相对位移。整个楼板连接完成后支座位置具备承受弯矩的能力,可以形成连续楼板体系,从而降低了楼板的配筋量和变形量。After the fully prefabricated floor slab is connected, the first installation hole 3, the second installation hole 4, the screw 6 and the floor concrete work together to provide bending resistance. The stable hole 5 reserved in the prefabricated beam can limit the relative displacement of the floor slab and the prefabricated beam. After the entire floor is connected, the support position has the ability to bear the bending moment, which can form a continuous floor system, thereby reducing the amount of reinforcement and deformation of the floor.

所述第一安装孔3和第二安装孔4之间设置有螺杆6,通过螺杆6进行固定连接。A screw rod 6 is provided between the first installation hole 3 and the second installation hole 4 , and the screw rod 6 is used for fixed connection.

所述第一安装孔3和第二安装孔4在同一预制板2的同一侧壁上交替设置为多个,且在同一预制板2的同一侧壁上交替设置的第一安装孔3和第二安装孔4高度位置设置不同。The first mounting holes 3 and the second mounting holes 4 are alternately arranged on the same side wall of the same prefabricated board 2 , and the first mounting holes 3 and the second mounting holes 3 are alternately arranged on the same side wall of the same prefabricated board 2 . The height and position of the two mounting holes 4 are set differently.

所述第一安装孔3和第二安装孔4在同一预制板2的对立侧壁上相配设置为多个,且同一预制板2的对立侧壁上相匹配设置的第一安装孔3和第二安装孔4高度位置设置相同。The first mounting holes 3 and the second mounting holes 4 are matched in multiples on the opposite side walls of the same prefabricated board 2 , and the first mounting holes 3 and the second mounting holes 3 are matched on the opposite side walls of the same prefabricated board 2 . The height and position of the two mounting holes 4 are set to be the same.

基于上述结构,相邻的预制板2通过第一安装孔3和第二安装孔4在结合螺杆6进行连接,但是由于预制板2的侧壁较薄,如果将不同预制板连接时所对应的所有的第一安装孔3和第二安装孔4上下对齐设置,会使上、下螺杆对齐会截面削弱过大,应力集中,因此需要上、下螺杆错开布置,即将不同预制板连接时所对应的上下第一安装孔3和第二安装孔4交错设置,上下均要有螺杆连接是为了抵抗连接部位的弯矩。Based on the above structure, the adjacent prefabricated boards 2 are connected through the first mounting hole 3 and the second mounting hole 4 in combination with the screw 6. However, since the side wall of the prefabricated boards 2 is relatively thin, if different prefabricated boards are connected, the corresponding All the first mounting holes 3 and the second mounting holes 4 are aligned up and down, which will cause the alignment of the upper and lower screws to weaken the cross-section and cause stress concentration. Therefore, it is necessary to stagger the arrangement of the upper and lower screws, that is, when the different prefabricated boards are connected, the corresponding The upper and lower first mounting holes 3 and the second mounting holes 4 are staggered, and there are screw connections at the top and bottom to resist the bending moment of the connection part.

所述第一安装孔3和第二安装孔4后端设置有安装槽7,在吊装作业,将第一安装孔3和第二安装孔4的位置相对,然后通过其后端安装槽7将螺杆6进行连接,然后锁紧。The rear ends of the first installation hole 3 and the second installation hole 4 are provided with installation grooves 7. During the hoisting operation, the positions of the first installation hole 3 and the second installation hole 4 are opposite, and then the rear end installation groove 7 The screw 6 is connected and then locked.

所述预制板2的侧壁为阶梯形,同侧预制板2上的第一安装孔3和第二安装孔4在不同的阶梯位置上。The side wall of the prefabricated board 2 is stepped, and the first installation hole 3 and the second installation hole 4 on the prefabricated board 2 on the same side are at different stepped positions.

所述支撑结构1包括预制混凝土梁11和预埋钢筋12,所述预埋钢筋12一端设置在预制混凝土梁11,另一端突出预制混凝土梁11的上表面设置,所述突出预制混凝土梁11设置的预埋钢筋12上设置有与稳固孔5相配的螺纹,通过预埋钢筋12与稳固孔5进行连接,使支撑结构1为预制板2提供支撑和限位。The support structure 1 includes a prefabricated concrete beam 11 and a prefabricated steel bar 12, one end of the prefabricated concrete beam 12 is arranged on the prefabricated concrete beam 11, the other end is arranged protruding from the upper surface of the prefabricated concrete beam 11, and the protruding prefabricated concrete beam 11 is arranged The pre-embedded steel bars 12 are provided with threads matching the stabilization holes 5, and the pre-embedded steel bars 12 are connected with the stabilization holes 5, so that the support structure 1 provides support and limit for the prefabricated panels 2.

所述预埋钢筋12设置在预制混凝土梁11的一端成勾形结构,通过勾形结构可以保证预埋钢筋在混凝土内的锚固强度,防止钢筋拔出,使预制板2与预制混凝土梁11连接更加稳固。The embedded steel bar 12 is arranged at one end of the precast concrete beam 11 to form a hook-shaped structure. The hook-shaped structure can ensure the anchoring strength of the embedded steel bar in the concrete, prevent the steel bar from being pulled out, and connect the precast slab 2 with the precast concrete beam 11. more stable.

所述稳固孔5在预制板2上设置有多个,且稳固孔5贯穿预制板2设置,所述稳固孔5的位置与支撑结构1的位置相匹配。A plurality of the stabilization holes 5 are provided on the prefabricated board 2 , and the stabilization holes 5 are provided through the prefabricated board 2 , and the positions of the stabilization holes 5 match the positions of the support structure 1 .

所述稳固孔5的孔形状为上方下圆;在楼板侧边设置倒角,方便后期防水处理。The shape of the stabilizing hole 5 is round at the top and bottom; chamfers are provided on the sides of the floor slab to facilitate the later waterproof treatment.

在宽度方向相邻的预制板2通过密封胶进行嵌缝,使连接处无缝衔接,预埋钢筋在与稳定孔进行连接时,通过预埋钢筋上部预留的螺纹、螺帽以及垫板使预制楼板与预制梁连接到一起,保证楼板与预制混凝土梁不发生相对位移。The adjacent prefabricated panels 2 in the width direction are caulked by sealant to make the joints seamless. When the embedded steel bars are connected with the stable holes, the threads, nuts and pads reserved on the upper part of the embedded steel bars are used to make the connection seamless. The prefabricated floor slab and the prefabricated beam are connected together to ensure that the floor slab and the prefabricated concrete beam do not have relative displacement.

本结构的安装方法:How to install this structure:

将预制板2吊装在支撑结构1上,安装时使预制梁上的预埋带丝口钢筋穿过楼板稳定孔,达到将楼板与预制梁连接到一起的目的。吊装时还应注意使相邻预制板2的第一安装孔3和第二安装孔4搭接到一起,保证预制板连接处的螺栓孔对齐,然后通过螺栓使第一安装孔3和第二安装孔4连接,使相邻的预制板2固定连接,在预留安装槽7以及稳固孔5等位置后浇微膨胀细石混凝土,并在板倒角位置打密封胶,提高楼板防水性能,完成安装作业。The prefabricated slab 2 is hoisted on the support structure 1, and the pre-embedded steel bars with wire openings on the prefabricated beams pass through the floor stabilization holes during installation, so as to achieve the purpose of connecting the floor slab and the prefabricated beams together. When hoisting, care should also be taken to make the first installation hole 3 and the second installation hole 4 of the adjacent prefabricated panels 2 overlap together to ensure that the bolt holes at the connection of the prefabricated panels are aligned, and then use the bolts to make the first installation hole 3 and the second installation hole 3. The installation holes 4 are connected to make the adjacent prefabricated slabs 2 fixedly connected, and the micro-expanded fine stone concrete is poured after the reserved installation slots 7 and the stabilization holes 5, and the sealant is applied at the chamfered position of the slab to improve the waterproof performance of the floor. Complete the installation job.

以上仅为本实用新型的较佳实施例而已,并不用以限制本实用新型,凡在本实用新型的精神和原则之内所作的任何修改、等同替换和改进等,均应包含在本实用新型的保护范围之内。The above are only preferred embodiments of the present utility model, and are not intended to limit the present utility model. Any modifications, equivalent replacements and improvements made within the spirit and principles of the present utility model shall be included in the present utility model. within the scope of protection.

Claims (9)

1. The utility model provides a mounting structure of full precast floor slab which characterized in that: the prefabricated slab comprises a supporting structure, a prefabricated slab, a first mounting hole, a second mounting hole and a stabilizing hole; the first mounting holes and the second mounting holes are respectively formed in two side walls in the width direction of the prefabricated slab, the stabilizing holes are uniformly formed in the prefabricated slab, the supporting structure is arranged at the bottom of the prefabricated slab, and the supporting structure is connected with the stabilizing holes.
2. The installation structure of a full precast floor slab according to claim 1, wherein: the first mounting holes and the second mounting holes are alternately arranged on the same side wall of the same prefabricated plate in a plurality, and the first mounting holes and the second mounting holes alternately arranged on the same side wall of the same prefabricated plate are arranged at different heights.
3. The installation structure of a full precast floor slab according to claim 2, wherein: the first mounting holes and the second mounting holes are arranged on the opposite side walls of the same prefabricated plate in a plurality of numbers, and the height positions of the first mounting holes and the second mounting holes which are arranged on the opposite side walls of the same prefabricated plate in a matching mode are the same.
4. A mounting structure of a full precast floor slab according to claim 1, 2 or 3, wherein: the supporting structure comprises a precast concrete beam and embedded steel bars, one end of each embedded steel bar is arranged on the precast concrete beam, the other end of each embedded steel bar protrudes out of the upper surface of the precast concrete beam, and threads are arranged on the embedded steel bars protruding out of the precast concrete beam.
5. A mounting structure of a full precast floor slab according to claim 1, 2 or 3, wherein: the prefabricated plate is provided with a plurality of stabilizing holes, the stabilizing holes penetrate through the prefabricated plate, and the positions of the stabilizing holes are matched with the positions of the supporting structures.
6. A mounting structure of a full precast floor slab according to claim 1, 2 or 3, wherein: the rear ends of the first mounting hole and the second mounting hole are provided with mounting grooves, and a screw rod is arranged between the first mounting hole and the second mounting hole.
7. A mounting structure of a full precast floor slab according to claim 1, 2 or 3, wherein: the side wall of the prefabricated plate is in a step shape, and the first mounting hole and the second mounting hole in the prefabricated plate on the same side are in different step positions.
8. The installation structure of a full precast floor slab according to claim 4, wherein: the embedded steel bars are arranged at one end of the precast concrete beam to form a hook structure.
9. A mounting structure of a full precast floor slab according to claim 1, 2 or 3, wherein: the hole shape of the stabilizing hole is an upper circle and a lower circle; set up the chamfer at the floor side, make things convenient for later stage water repellent.
CN202020517428.4U 2020-04-10 2020-04-10 An installation structure of a fully prefabricated floor slab Active CN211949120U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020517428.4U CN211949120U (en) 2020-04-10 2020-04-10 An installation structure of a fully prefabricated floor slab

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020517428.4U CN211949120U (en) 2020-04-10 2020-04-10 An installation structure of a fully prefabricated floor slab

Publications (1)

Publication Number Publication Date
CN211949120U true CN211949120U (en) 2020-11-17

Family

ID=73160765

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020517428.4U Active CN211949120U (en) 2020-04-10 2020-04-10 An installation structure of a fully prefabricated floor slab

Country Status (1)

Country Link
CN (1) CN211949120U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113638533A (en) * 2021-09-14 2021-11-12 腾达建设集团股份有限公司 A prefabricated floor slab, removable steel-concrete composite floor and construction method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113638533A (en) * 2021-09-14 2021-11-12 腾达建设集团股份有限公司 A prefabricated floor slab, removable steel-concrete composite floor and construction method thereof
CN113638533B (en) * 2021-09-14 2025-08-26 腾达建设集团股份有限公司 Prefabricated floor slab, detachable steel-concrete composite floor and construction method thereof

Similar Documents

Publication Publication Date Title
CN104652671B (en) Prefabricated assembly-type concrete outer-hanging wallboard fixing device and installation method
CN105863275B (en) Assembled ring muscle fastens concrete shear wall system construction method
CN113482208B (en) Dry-wet combined connecting structure of precast concrete floor slab and construction method
CN204960038U (en) Precast concrete shear wall structure
CN108708452B (en) U-shaped integral prefabricated bay window component, assembled bay window node structure and construction method thereof
CN110468968A (en) A kind of the fixation device and fixing means of laminated floor slab overhanging type steel
CN211949120U (en) An installation structure of a fully prefabricated floor slab
CN110424574A (en) A kind of dry wall, dry wall and site concrete horizontal connecting node and construction method
CN118933186B (en) One-time installation of dry-connected concrete shear wall/irregular column structure and construction method
CN220225867U (en) Mould-free support-free laminated slab and connecting structure thereof
CN113417361A (en) Prefabricated bay window and connecting method
CN212670968U (en) Composite floor and building
CN105040823A (en) Partition plate and floor beam connecting structure for scissors staircase and construction method of partition plate and floor beam connecting structure
CN113957993A (en) Assembly system and construction method thereof
CN212104748U (en) Connection structure of firm installation of full precast floor
CN209703805U (en) A new type of composite floor suitable for H-shaped steel beams in steel structures
CN216949007U (en) Multi-steel web concrete flange combined prestressed concrete laminated slab
CN220565527U (en) Assembled rib plate structure
CN101245642A (en) A two-way laminated concrete slab with strip-shaped block bottom slab
CN216892798U (en) Bolt connection full precast concrete assembled house
CN201162299Y (en) A two-way laminated concrete slab with one-way floor
CN216740000U (en) Assembly system
CN114457949A (en) Laminated slab bottom plate with concave and convex plate ends and without ribs and mounting structure
CN116411654A (en) A prefabricated shear wall connection structure for prefabricated buildings
CN116357129A (en) Prefabricated rural residential structure system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 641400 Chengnan Industrial Park, Jianyang Industrial Development Zone, Chengdu, Sichuan Province

Patentee after: Wuyi Jiaotou Shancheng (Chengdu) Construction Technology Co.,Ltd.

Country or region after: China

Address before: 641400 Chengnan Industrial Park, Jianyang Industrial Development Zone, Chengdu, Sichuan Province

Patentee before: CMCC investment Shanzhu Chengdu prefabricated building technology development Co.,Ltd.

Country or region before: China

CP03 Change of name, title or address

Address after: 641400 Chengnan Industrial Park, Jianyang Industrial Development Zone, Chengdu, Sichuan Province

Patentee after: Xin Ye Jiaotou Shancheng (Chengdu) Construction Technology Co., Ltd.

Country or region after: China

Address before: 641400 Chengnan Industrial Park, Jianyang Industrial Development Zone, Chengdu, Sichuan Province

Patentee before: Wuyi Jiaotou Shancheng (Chengdu) Construction Technology Co.,Ltd.

Country or region before: China