CN211839983U - Combined rack for binding steel bars of top plate of precast beam plate - Google Patents

Combined rack for binding steel bars of top plate of precast beam plate Download PDF

Info

Publication number
CN211839983U
CN211839983U CN202020283094.9U CN202020283094U CN211839983U CN 211839983 U CN211839983 U CN 211839983U CN 202020283094 U CN202020283094 U CN 202020283094U CN 211839983 U CN211839983 U CN 211839983U
Authority
CN
China
Prior art keywords
binding
steel bar
running track
plate
precast beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020283094.9U
Other languages
Chinese (zh)
Inventor
苏占玺
关召帅
刘海鹏
程伟峰
孙鑫
陈中洲
张耀阳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC SHB Fourth Engineering Co Ltd
Original Assignee
CCCC SHB Fourth Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC SHB Fourth Engineering Co Ltd filed Critical CCCC SHB Fourth Engineering Co Ltd
Priority to CN202020283094.9U priority Critical patent/CN211839983U/en
Application granted granted Critical
Publication of CN211839983U publication Critical patent/CN211839983U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model belongs to the technical field of engineering machine tool, concretely relates to combination rack for precast beam slab roof reinforcement. The combined rack for binding the steel bars of the top plate of the precast beam plate is provided with a binding base; a flange steel bar binding jig frame is arranged on the binding base; the left running track and the right running track are formed on the edges of the two sides of the wing plate steel bar binding jig frame; the combined rack is also provided with a binding trolley which can move longitudinally along the left running track and the right running track; a positioning caliper is welded at the end of the binding trolley; still be equipped with the mark that is used for marking roof steel bar welding position that forms by the steel bar welding on the positioning caliper. The utility model discloses avoided artificially trampling the damage and the interference to the steel reinforcement cage at reinforcement in-process to ensured roof reinforcement's quality, improved work efficiency, guaranteed construction safety.

Description

Combined rack for binding steel bars of top plate of precast beam plate
Technical Field
The utility model belongs to the technical field of engineering machine tool, concretely relates to combination rack for precast beam slab roof reinforcement.
Background
At present, all bridges are in the construction, almost all will adopt the precast beam, traditional operation mode all is the ligature that directly carries out precast beam board roof reinforcing bar on framework of steel reinforcement, the operating efficiency is low, construction quality guarantee is poor, the safety condition is poor, need to design a platform truck system that can realize batch production ligature urgently, can carry out the ligature of roof reinforcing bar according to standardized reinforcement processing flow, ensure can one shot forming, then whole hoist to predetermine the position in the template, realize roof reinforcement preforming in advance, make precast beam operation more standardized, work efficiency is higher, reinforcement location is more accurate, it is safer to operate.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a combination rack for precast beam slab roof reinforcement to solve a great deal of defect of existence in the current actual construction, make roof shear force reinforcement operation more high-efficient swift, accurate, safety.
In order to accomplish the above object, the utility model adopts the following technical scheme:
a combined rack for binding steel bars of a top plate of a precast beam plate is provided with a binding base; a flange steel bar binding jig frame is arranged on the binding base; the left running track and the right running track are formed on the edges of the two sides of the wing plate steel bar binding jig frame; the combined rack is also provided with a binding trolley which can move longitudinally along the left running track and the right running track; a positioning caliper is welded at the end of the binding trolley; still be equipped with the mark that is used for marking roof steel bar welding position that forms by the steel bar welding on the positioning caliper.
The wing plate steel bar binding jig frame is fixedly connected with the binding base through a comb plate connector; the connector of the comb plate is formed by connecting hinges, and is applicable to binding steel bars of top plates of precast beams and plates of different types through the adjustability of self angles.
And traveling wheels matched with the left traveling track and the right traveling track are arranged at four corners of the binding trolley.
The utility model provides a pair of a combination rack for precast beam board roof reinforcement is applicable to the ligature of precast beam board roof shear force reinforcement skeleton, has formed the fashioned standardized operation production line of the whole ligature of a roof plate reinforcement, and the work efficiency that can solve traditional manual ligature mode and bring is low, and the reinforcement precision is low, tramples the steel reinforcement cage, causes disturbance and damage, the long, the big problem of operation intensity of engineering time to the whole, the utility model discloses the effectual above-mentioned problem of having avoided has structure and easy operation, and the construction is high-efficient, accurate, safe advantage.
Drawings
Fig. 1 is a schematic structural diagram of the present invention.
In the figure, 1, a binding base, 2, a left traveling track, 3, a right traveling track, 4, a binding trolley, 5, traveling wheels, 6, a positioning caliper, 7, a construction platform, 8, a driving device, 9, a comb plate connector and 10, a wing plate steel bar binding jig frame are arranged.
Detailed Description
The present invention will be further explained with reference to the drawings and examples.
As shown in figure 1, the combined rack for binding the steel bars of the top plate of the precast beam plate is provided with a binding base 1; a wing plate steel bar binding jig frame 10 is arranged on the binding base 1; the flange steel bar binding jig frame 10 is of an existing structure in the prior art and is used for laying transverse steel bars of a precast beam plate, and the top plate steel bars are welded on the transverse steel bars; the left running track 2 and the right running track 3 are formed at the edges of the two sides of the wing plate steel bar binding jig frame 10; the combined rack is also provided with a binding trolley 4 which can longitudinally move along the left running track and the right running track; a positioning caliper 6 is welded at the end of the binding trolley 4; still be equipped with the mark that is used for marking roof steel bar welding position that forms by the steel bar welding on the positioning caliper.
The wing plate steel bar binding jig frame is fixedly connected with the binding base 1 through a comb plate connector 9; broach plate connector 9 form by hinge connection, through the controllability of self angle, applicable in the ligature of different grade type precast beam board roof reinforcing bar.
And traveling wheels 5 matched with the left traveling track and the right traveling track are arranged at four corners of the binding trolley.
The combination rack still be provided with drive arrangement 8, accessible remote control system controls drive arrangement 8, makes from the vertical back-and-forth movement of walking platform truck 4 on the ligature base, through the quick fixed reinforcing bar of positioning caliper rule, the last mark that is formed by the steel reinforcement welding that is provided with of positioning caliper rule, can accurately install the reinforcing bar. Broach board connector 9 forms for hinge connection, through the controllability of self angle, applicable in the ligature of different grade type precast beam slab roof reinforcing bar.
Based on the above, utilize broach board connector can adjust the ligature platform truck into the required size of design precast beam board and angle, applicable in the precast beam board of different grade type. The reinforcing steel bar positioning toothed plate processed according to the designed space of the beam plate and the mark formed by welding the reinforcing steel bars are arranged on the self-walking trolley, so that the accuracy of reinforcing steel bar installation can be guaranteed, the self-walking trolley 4 can move along the length direction of the beam plate in a remote control mode, and various components required by transportation, reinforcing steel bar transmission processing and installation can be further transmitted. Utilize this kind of platform truck, through transportation semi-manufactured goods and raw and other materials and quick fixed ligature reinforcing bar, construct into the whole fashioned standardized production line of a precast beam roof reinforcing bar, avoided artificially trampling the interference damage and the inefficiency and the rate of accuracy of steel reinforcement cage at the reinforcement in-process to ensured roof reinforcement's quality, improved the efficiency of construction, guaranteed construction safety.

Claims (3)

1. The utility model provides a combination rack for prefabricated beam slab roof reinforcement, its characterized in that: the combined rack is provided with a binding base; a flange steel bar binding jig frame is arranged on the binding base; the left running track and the right running track are formed on the edges of the two sides of the wing plate steel bar binding jig frame; the combined rack is also provided with a binding trolley which can move longitudinally along the left running track and the right running track; a positioning caliper is welded at the end of the binding trolley; still be equipped with the mark that is used for marking roof steel bar welding position that forms by the steel bar welding on the positioning caliper.
2. The combined rack for binding the steel bars of the top plate of the precast beam plate according to claim 1, wherein: the wing plate steel bar binding jig frame is fixedly connected with the binding base through a comb plate connector; the connector of the comb plate is formed by connecting hinges, and is applicable to binding steel bars of top plates of precast beams and plates of different types through the adjustability of self angles.
3. The combined rack for binding the steel bars of the top plate of the precast beam plate according to claim 1, wherein: and traveling wheels matched with the left traveling track and the right traveling track are arranged at four corners of the binding trolley.
CN202020283094.9U 2020-03-10 2020-03-10 Combined rack for binding steel bars of top plate of precast beam plate Active CN211839983U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020283094.9U CN211839983U (en) 2020-03-10 2020-03-10 Combined rack for binding steel bars of top plate of precast beam plate

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020283094.9U CN211839983U (en) 2020-03-10 2020-03-10 Combined rack for binding steel bars of top plate of precast beam plate

Publications (1)

Publication Number Publication Date
CN211839983U true CN211839983U (en) 2020-11-03

Family

ID=73133680

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020283094.9U Active CN211839983U (en) 2020-03-10 2020-03-10 Combined rack for binding steel bars of top plate of precast beam plate

Country Status (1)

Country Link
CN (1) CN211839983U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117960959A (en) * 2024-02-18 2024-05-03 中铁四局集团有限公司 Reinforcing steel bar installation device and method for penetrating transverse ring bars into longitudinal ring bars

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117960959A (en) * 2024-02-18 2024-05-03 中铁四局集团有限公司 Reinforcing steel bar installation device and method for penetrating transverse ring bars into longitudinal ring bars

Similar Documents

Publication Publication Date Title
CN103452052B (en) Movable mold hanging equipment for closing swivel bridges and closure section construction method
CN102430906B (en) Special portal-type bolster frame assembly manipulator for truck bogie production line
CN110918838B (en) Flexible manufacturing production line and production process for spatial three-dimensional reinforcing mesh
CN211839983U (en) Combined rack for binding steel bars of top plate of precast beam plate
CN104325231B (en) Steel pipe bundle combining structure component automatic assembling welder
CN105618983A (en) Chassis assembling fixture
CN104353937A (en) Automatic assembling and welding device for straight steel pipe bundles
CN103787203B (en) For installing the bracing frame of precast beam jack
CN104400430A (en) Automatic production process and device of steel pipe bundle combined structural component
CN202114438U (en) Truss pitch adjusting mechanism of automatic welding machine
CN110000922B (en) Whole installation device of prefabricated T roof beam pterygoid lamina reinforcing bar of road bridge
CN212925808U (en) Vertical and longitudinal connecting device for bridge erecting machine
CN112719669B (en) Section beam steel bar system installation assembly line
CN208763669U (en) Tunnel widened section construction assembly type trolley
CN210966786U (en) Flexible manufacturing production line for spatial three-dimensional reinforcing mesh
CN204321594U (en) The automated production equipment of steel pipe bundle combining structure component
CN210359866U (en) Full-automatic perforating device of steel construction roof beam
CN209009658U (en) Double-block type sleeper automatic stacking machine
CN204235053U (en) Yi word pattern steel pipe bundle structural elements automatic turning device
CN211679813U (en) Electric walking trolley for binding steel bars of top plate of precast beam
CN202595630U (en) Template construction trolley for steel-frame bridge crossing business line
CN111186016A (en) Electric steel bar pre-binding trolley and construction method thereof
CN214423024U (en) Two-dimensional automatic adjustment track panel of lightweight double-block ballastless track
CN212668982U (en) Device for carrying long rail in limited space
CN204897165U (en) Sleeper mould gallows system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant