CN211621593U - Dry operation cast-in-place pile concrete guide pipe and joint integrated device thereof - Google Patents

Dry operation cast-in-place pile concrete guide pipe and joint integrated device thereof Download PDF

Info

Publication number
CN211621593U
CN211621593U CN201921752702.XU CN201921752702U CN211621593U CN 211621593 U CN211621593 U CN 211621593U CN 201921752702 U CN201921752702 U CN 201921752702U CN 211621593 U CN211621593 U CN 211621593U
Authority
CN
China
Prior art keywords
snap ring
semicircle
movable
pipe
integrated device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921752702.XU
Other languages
Chinese (zh)
Inventor
刘成星
金玲玲
鲁超军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201921752702.XU priority Critical patent/CN211621593U/en
Application granted granted Critical
Publication of CN211621593U publication Critical patent/CN211621593U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a do operation bored concrete pile concrete pipe and connect integrated device thereof mainly contains a steel pipe, a attach fitting, two semicircle rubber seal, a fixed bolt and a movable bolt of constituteing by two semicircle snap rings, attach fitting includes a semicircle snap ring and a movable semicircle snap ring fixed with the pipe, semicircle rubber seal sets up in the semicircle snap ring, and one of them semicircle snap ring carries out fixed connection with the steel pipe, and another semicircle snap ring is the movable snap ring, can follow the outside free rotation of stiff end round pin axle.

Description

Dry operation cast-in-place pile concrete guide pipe and joint integrated device thereof
Technical Field
The utility model relates to a construction technical field especially relates to a do operation bored concrete pile concrete pipe and connect integrated device thereof.
Background
At present, concrete cast-in-place piles are widely applied to various engineering constructions, pile foundations are mainly divided into mechanical hole forming and manual excavation hole forming according to different hole forming modes, and a common method in the concrete cast-in-place pile casting process is a guide pipe method underwater concrete casting construction technology and a string tube method waterless pile casting, namely a dry operation construction technology. Wherein the former is suitable for filling piles with water and the latter is suitable for filling piles without water or with less water infiltration. By consulting the specification and related technical experience, the smaller water seepage amount means 6 mm/min. In actual construction, underground geological conditions are complex, underground water in pile holes has a plurality of seepage points, and the specific seepage amount is difficult to measure.
The concrete pouring of the common dry operation pore-forming cast-in-place pile generally adopts a tube string method, namely, a concrete hopper is fixed by a bracket at the upper opening of a pile hole, and then workers enter the hole to hang tubes string section by section. The length of each section of string barrel is about 1.0-1.5 m, the number of hanging sections is determined according to the hole depth, and the distance between the bottom opening of the last section of string barrel and the hole bottom is more than 1 m. The concrete transport vehicle moves to the orifice, and starts to feed materials into the hopper, constructors inside and outside the orifice are matched with each other during pouring, blanking is stopped when the concrete surface is controlled to be about 30cm, and workers in the orifice fully vibrate by using an inserted vibrating rod to ensure that each layer of concrete is compact; and then, removing the string cylinders section by section along with the rising of the concrete surface until the concrete is poured to the designed elevation and then over-pouring for 5-10 cm (convenient for chiseling out floating slurry later), and removing the hopper to finish concrete pouring.
The method is characterized in that a concrete pile guide pipe method is adopted according to actual field experience, and the method can also be used for a cast-in-place pile for dry operation hole forming, namely, the pipe diameter of the cast-in-place guide pipe is selected according to the hole diameter of the pile, the guide pipe with the diameter of 400mm is generally adopted for a large-diameter hole pile, the installation and connection are carried out section by section at the hole opening of the pile until the concrete begins to be cast about 1m away from the bottom of the hole pile, the concrete is extracted section by section along with the pouring of the concrete, and the extracted guide pipe. The method generally adopts the separated type of the conduit and the connecting joint, has long butt joint time and low working efficiency, and influences the concrete pouring speed.
SUMMERY OF THE UTILITY MODEL
The utility model aims at solving and adopting pipe and attach fitting to be mostly the disconnect-type among the prior art, the butt joint is long, and work efficiency is low, influences the problem of concrete placement speed, and the dry operation bored concrete pile concrete pipe and joint integrated device who provides.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
the utility model provides a do operation bored concrete pile concrete pipe and connect integrated device thereof mainly contains a steel pipe, a attach fitting, two semicircle rubber seal, a fixing bolt and a movable bolt of compriseing two semicircle snap rings, attach fitting includes a semicircle snap ring and a movable semicircle snap ring fixed with the pipe, semicircle rubber seal sets up in the semicircle snap ring, and one of them semicircle snap ring carries out fixed connection with the steel pipe, movable semicircle snap ring is movable snap ring, can follow the outside free rotation of fixing bolt.
Preferably, the fixed semicircular clamping ring is connected with the movable semicircular clamping ring through a connecting iron piece.
Preferably, one of the movable semicircular clamping rings is movably connected with the other end of the other fixed semicircular clamping ring, and the movable semicircular clamping rings can be connected or separated by pulling out or inserting a movable bolt.
Preferably, after the lower opening of the upper section of steel conduit is inserted into alignment with the lower section of steel conduit, the movable semicircular snap ring is closed, and the movable bolt with the anti-skid pin is inserted for connection.
Compared with the prior art, the utility model provides a do operation bored concrete pile concrete pipe and connect integrated device thereof possesses following beneficial effect:
(1) the concrete filling pile guide pipe and the connecting joint are integrated, the operation is simple and convenient, and the labor consumption is reduced.
(2) The installation is dismantled the transportation and is convenient, can reduce the secondary and transport time, improves work efficiency.
(3) The device is simple and convenient in modeling, and the built-in fixed rubber sealing ring reduces the slurry leakage problem.
The device is relatively separated, so that the joint time is reduced, the installation and the disassembly are more convenient, the labor and the force are saved, and the construction efficiency of the cast-in-place concrete pile is greatly improved.
Drawings
FIG. 1 is a structural view of a joint portion of a novel dry work cast-in-place pile concrete guide pipe and a joint integrated device thereof;
FIG. 2 is a rear schematic view of the device after alignment of the next section of conduit with the previous section of conduit;
FIG. 3 is a front schematic view of the device after alignment of the next section of conduit with the previous section of conduit;
FIG. 4 is a schematic view of the next section of conduit abutting the previous section of conduit and the connecting ring snap closed;
in the figure: 1. a concrete steel conduit; 2. a conduit coupling ring clip; 21. fixing a semicircular clamping ring; 22. a movable semicircular snap ring; 23. a rubber seal ring; 24. fixing the bolt; 25. connecting iron pieces; 26. a movable bolt; 27. and an anti-slip pin.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
In the description of the present invention, it is to be understood that the terms "upper", "lower", "front", "rear", "left", "right", "top", "bottom", "inner", "outer", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplicity of description, and do not indicate or imply that the device or element being referred to must have a particular orientation, be constructed and operated in a particular orientation, and therefore, should not be construed as limiting the present invention.
Example one
Referring to fig. 1-2, a dry work bored concrete pile concrete pipe and joint integrated device thereof mainly contains a steel pipe 1, a attach fitting 2, two semicircle rubber seal ring 23, a fixed bolt 24 and a movable bolt 26 of constituteing by two semicircle snap rings, attach fitting 2 includes a fixed semicircle snap ring 21 and a movable semicircle snap ring 22 fixed with pipe 1, semicircle rubber seal ring 23 sets up in the semicircle snap ring, and one of them fixed semicircle snap ring 21 carries out fixed connection with steel pipe 1, the activity semicircle snap ring 22 is the activity snap ring, can follow the outside free rotation of fixed bolt 24.
Example two
On the basis of example 1: fixed semicircle snap ring 21 is connected through connecting ironware 25 with activity semicircle snap ring 22, one of them and the other end of another fixed semicircle snap ring 21 of activity semicircle snap ring 22 is swing joint, and the accessible is extracted or is inserted movable bolt 26 and connect or separate, and last section steel pipe end opening and next section pipe insert align back closed activity semicircle snap ring 22, and insert movable bolt 26 of taking anti-skidding round pin 27 and connect.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.

Claims (4)

1. The utility model provides a do operation bored concrete pile concrete pipe and connect integrated device which characterized in that: mainly contain a steel pipe (1), a attach fitting (2), two semicircle rubber seal rings (23), a fixing bolt (24) and a movable bolt (26) of constituteing by two semicircle snap rings, attach fitting (2) include one with pipe (1) fixed semicircle snap ring (21) and a movable semicircle snap ring (22), semicircle rubber seal ring (23) set up in the semicircle snap ring, fixed semicircle snap ring (21) carry out fixed connection with steel pipe (1), the activity semicircle snap ring (22) are the activity snap ring, can follow fixing bolt (24) and outwards freely rotate.
2. The dry working cast-in-place pile concrete guide pipe and joint integrated device of claim 1, which is characterized in that: the fixed semicircular clamping ring (21) is connected with the movable semicircular clamping ring (22) through a connecting iron piece (25).
3. The dry working cast-in-place pile concrete guide pipe and joint integrated device of claim 2, wherein: one of the movable semicircular clamping rings (22) is movably connected with the other end of the other fixed semicircular clamping ring (21), and the movable semicircular clamping rings can be connected or separated by pulling out or inserting the movable bolt (26).
4. The dry working cast-in-place pile concrete guide pipe and joint integrated device of claim 3, wherein: after the lower opening of the previous section of steel conduit and the next section of steel conduit are inserted and aligned, the movable semicircular snap ring (22) is closed, and a movable bolt (26) with an anti-skid pin (27) is inserted for connection.
CN201921752702.XU 2019-10-18 2019-10-18 Dry operation cast-in-place pile concrete guide pipe and joint integrated device thereof Active CN211621593U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921752702.XU CN211621593U (en) 2019-10-18 2019-10-18 Dry operation cast-in-place pile concrete guide pipe and joint integrated device thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921752702.XU CN211621593U (en) 2019-10-18 2019-10-18 Dry operation cast-in-place pile concrete guide pipe and joint integrated device thereof

Publications (1)

Publication Number Publication Date
CN211621593U true CN211621593U (en) 2020-10-02

Family

ID=72623776

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921752702.XU Active CN211621593U (en) 2019-10-18 2019-10-18 Dry operation cast-in-place pile concrete guide pipe and joint integrated device thereof

Country Status (1)

Country Link
CN (1) CN211621593U (en)

Similar Documents

Publication Publication Date Title
CN104389623B (en) Shield tunnel prefabricated tunnel segment lining back stratum grouting device
CN103122632A (en) Construction method for drilling hole and casting pile in plastic flow stratum or karst cave stratum
CN107261587A (en) A kind of filter screen automatically cleaning dregs filter
CN104912065A (en) Underwater anchor pile construction method
CN101936065A (en) Template with rigid-flexible composite structure and partition wall construction method by retaining roadway along goaf thereof
CN101649744A (en) Device and method for casting concrete continuous walls along gob-side entry retaining by mining working face
CN105442532A (en) Construction method for pile-head-expanded bored pile
CN208235525U (en) A kind of multiple grouting device controlling soil deformation
CN210658751U (en) Waterproof slip casting embedded pipe of overlength underground structure
CN209538258U (en) A kind of construction equipment for replacing bored concrete pile
CN211621593U (en) Dry operation cast-in-place pile concrete guide pipe and joint integrated device thereof
CN104099946A (en) Novel jacking pipe intersegment overhaul well
CN214245694U (en) Pile forming system for large-diameter cast-in-situ bored pile in karst area
CN101250870B (en) Positioning device for filling pile reinforcement cage
CN208778010U (en) A kind of advance reinforcement structure of push pipe inlet and outlet cave
CN103452115B (en) A kind of utilize send at the bottom of bushing type after intubate the construction method that post-grouting device carries out constructing
CN207633342U (en) A kind of bridge pile foundation pile crown abolishes device
CN202323934U (en) Hole forming device for cast-in-situ triangular composite foundation pile
CN209293051U (en) A kind of open caisson reserved opening plugging structure
CN203782685U (en) Special hole forming device for construction of tubular pile
CN207538839U (en) The structure that a kind of quick solution tunnel collapses
CN201169768Y (en) Positioning device for filling pile reinforcing cage
CN205116162U (en) Pile head enlarges drilling bored concrete pile clad steel and protects a section of thick bamboo
CN112144404B (en) Precast concrete cofferdam and pier construction process
CN206635745U (en) Hybrid reinforcement diaphram wall

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant