CN208778010U - A kind of advance reinforcement structure of push pipe inlet and outlet cave - Google Patents

A kind of advance reinforcement structure of push pipe inlet and outlet cave Download PDF

Info

Publication number
CN208778010U
CN208778010U CN201821231431.9U CN201821231431U CN208778010U CN 208778010 U CN208778010 U CN 208778010U CN 201821231431 U CN201821231431 U CN 201821231431U CN 208778010 U CN208778010 U CN 208778010U
Authority
CN
China
Prior art keywords
pipe
push pipe
surrounding
hole
push
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201821231431.9U
Other languages
Chinese (zh)
Inventor
黄杰
张小兵
徐兰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China First Metallurgical Group Co Ltd
Original Assignee
China First Metallurgical Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China First Metallurgical Group Co Ltd filed Critical China First Metallurgical Group Co Ltd
Priority to CN201821231431.9U priority Critical patent/CN208778010U/en
Application granted granted Critical
Publication of CN208778010U publication Critical patent/CN208778010U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

A kind of advance reinforcement structure of push pipe inlet and outlet cave, the Grouting Pipe for reinforcing that guide pipe is provided in the push pipe inlet and outlet cave surrounding earthwork and is squeezed into from the guide pipe.The utility model in the pre-buried guide pipe of push pipe inlet and outlet cave, avoid it is subsequent when needing to squeeze into Grouting Pipe will the concrete to wall abolish punching, simplify process, save the time.Cement slurry is injected into the hole surrounding earthwork by Grouting Pipe, cement slurry reacts with surrounding soil, keep soil body solidification hardened, at hole, surrounding forms one of firm annular curtain, effectively play the role of to push pipe hole surrounding soil stabilization, prevent hole soil body when push pipe export & import from collapsing, situations such as push pipe head upwarps, " kowtowing ".Meanwhile the soil-cement body after reinforcing, have good water-stagnating effect, can effectively reduce hole surrounding underground water and enter in hole.

Description

A kind of advance reinforcement structure of push pipe inlet and outlet cave
Technical field
The utility model relates to jacking construction, in particular to a kind of advance reinforcement structure of push pipe inlet and outlet cave.
Background technique
With the fast development of China's urbanization, ducts engineering is also quickly grown.Pipeline is in passing through building, public affairs When the special areas such as road, railway, traditional open cut pipe laying mode is restricted, and Construction Techniqus of Slurry Pipe Jacking is increasingly Maturation is simultaneously widely applied.In mud hydraulic balance jacking construction, when push pipe export & import, is influenced by ground water pressure, is easily occurred The problems such as underground water is poured in from hole surrounding, push pipe nose drop.Also occur that hole top cubic metre of earth collapses when serious, mud gushes Enter the cave in accident of working pit.
Traditional reinforcing method is to carry out grouting and reinforcing after the broken hole of hole, then to surrounding soil.Break portal Afterwards, due to the reason of underground water, the soil body at portal can usually occurs and collapse, mud pours in the bad accident such as active well.Meanwhile it is broken Soil stabilization is carried out behind hole again, can just play reinforcing after having the function that some strength after needing cement slurry to inject the soil body.
Utility model content
The utility model based on the above situation, has developed a kind of advance reinforcement structure of push pipe inlet and outlet cave, can be to hole Mouthful surrounding soil body carries out advance reinforcement, prevent using when the soil body at portal occur collapse, mud pours in the bad accident such as active well.
In order to achieve the above objectives, specific technical solution used by the utility model is said is as follows:
A kind of advance reinforcement structure of push pipe inlet and outlet cave, be provided in the push pipe inlet and outlet cave surrounding earthwork guide pipe with And the Grouting Pipe for reinforcing squeezed into from the guide pipe.
Preferably, the guide pipe is distributed along the push pipe inlet and outlet cave surrounding in circular ring shape.
Preferably, the guide pipe equidistant interval.
Preferably, clay is filled in the guide pipe, nozzle is sealed using M30 mortar.
Preferably, the slip casting length of tube is 4m-5m.
The beneficial effects of the utility model are as follows:
The utility model in the pre-buried guide pipe of push pipe inlet and outlet cave, avoid it is subsequent will be to wall when needing to squeeze into Grouting Pipe Concrete abolish punching, simplify process, save the time.Cement slurry is injected into the hole surrounding earthwork by Grouting Pipe, Cement slurry reacts with surrounding soil, keeps soil body solidification hardened, and at hole, surrounding forms one of firm annular curtain, effectively Play the role of prevent hole soil body when push pipe export & import from collapsing push pipe hole surrounding soil stabilization, push pipe head upwarps, Situations such as " kowtowing ".Meanwhile the soil-cement body after reinforcing, have good water-stagnating effect, with can effectively reducing hole surrounding It is lauched and enters in hole.
Detailed description of the invention
Fig. 1 is the agent structure schematic diagram that the utility model squeezes into the earthwork
Fig. 2 is the side structure schematic diagram that the utility model squeezes into the earthwork
Fig. 3 is the utility model operating environment figure
In figure: 1 guide pipe, 2 Grouting Pipes, 3 push pipe inlet and outlet caves, 4 active well walls, 5 advance reinforcement slip casting areas
Specific embodiment
Below with reference to specific the drawings and the specific embodiments, the utility model is described in further detail.
Such as Fig. 1,2,3, when carrying out jacking construction operation, in the binding of upper pipe working well structure reinforcing bars in push pipe export & import The mouth pre-buried guide pipe 1 of 3 surroundings;The length of the guide pipe 1 is equal to the thickness of active well wall 4, and the active well wall 4 is pre- Bury after the guide pipe 1 that casting concrete is formed by active well inner wall in the upper pipe working well.Preferably, the guiding Pipe 1 is distributed in a ring in 3 surrounding of push pipe inlet and outlet cave.Circumferential direction is equidistant between the guide pipe 1, it is preferable that described Circumferential distance interval is 30cm.After the guide pipe 1 is pre-buried, the guide pipe 1 is clogged to closely knit, nozzle use with clay Mortar sealing;Since the active well of push pipe is caisson sinking construction mostly, if guide pipe 1 is not filled with sealing when sinking, soil Underground water inside body can flow into foundation pit from guide pipe 1, and rich groundwater when can be with silt particle on the outside of wall locating for guide pipe 1 It is flushed to inside active well together, first is that bringing difficulty to construction, causes analysis empty second is that silt particle outside active well has been taken away, make It is settled at surrounding soil.
After the guide pipe 1 is pre-buried, upper pipe working well Concrete In Structures are poured, upper pipe working wells is waited to sink in place, it is complete After active well back cover, is cleared up in the guide pipe 1 at this time and seal mortar, squeeze into note into pipeline jacking direction along guide pipe 1 Starch pipe 2, it is preferable that 2 length of Grouting Pipe is 4m-5m.Push-bench head length used in practice of construction is generally 4m Left and right length, the length of the Grouting Pipe 2 selects more slightly longer than the head length according to the actual situation.
Then, slip casting is carried out to the Grouting Pipe 2 squeezed into, it is preferable that slip casting uses cement slurry, grout coordinate ratio be 1:0.5~ 1:1.Grouting pressure is less than or equal to 1.5Mpa, and slip casting dilation angle is controlled in 400mm or so.Preferably, slip casting is using interval Grouting mode successively carries out from low to high.After all 2 slip castings of Grouting Pipe, around push pipe inlet and outlet cave 3 formed one circle by Advance reinforcement slip casting area 5 in soil cement annular curtain, that is, Fig. 1, plays the role of sealing and soil mass consolidation.After slip casting, by institute It states the residual slurry in the outside of Grouting Pipe 2 to clean out, cuts off exposed parts, and with mortar 1 nozzle of guide pipe block closely knit.Work as note Slurry region can carry out subsequent job after reaching some strength.
Above embodiments are merely intended for describing the technical solutions of the present application, but not for limiting the present application, although referring to preferred embodiment pair The utility model is described in detail, those skilled in the art should understand that, it can be to the technology of the utility model Scheme is modified or replaced equivalently, and without departing from the objective and range of technical solutions of the utility model, should all be covered In the scope of the claims of the utility model.

Claims (5)

1. a kind of advance reinforcement structure of push pipe inlet and outlet cave, it is characterised in that: in the upper pipe working well inlet and outlet cave surrounding earthwork It is inside provided with guide pipe, squeezes into the Grouting Pipe for reinforcing of certain length along pipeline jacking direction in the guide pipe.
2. a kind of advance reinforcement structure of push pipe inlet and outlet cave according to claim 1, it is characterised in that: the guide pipe It is distributed along the push pipe inlet and outlet cave surrounding in circular ring shape.
3. a kind of advance reinforcement structure of push pipe inlet and outlet cave according to claim 1 or 2, it is characterised in that: described to lead To pipe equidistant interval.
4. a kind of advance reinforcement structure of push pipe inlet and outlet cave according to claim 3, it is characterised in that: the guide pipe Interior to be filled with clay, nozzle is sealed using M30 mortar.
5. a kind of advance reinforcement structure of push pipe inlet and outlet cave according to claim 1, it is characterised in that: the Grouting Pipe Length is 4m-5m.
CN201821231431.9U 2018-08-01 2018-08-01 A kind of advance reinforcement structure of push pipe inlet and outlet cave Expired - Fee Related CN208778010U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821231431.9U CN208778010U (en) 2018-08-01 2018-08-01 A kind of advance reinforcement structure of push pipe inlet and outlet cave

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821231431.9U CN208778010U (en) 2018-08-01 2018-08-01 A kind of advance reinforcement structure of push pipe inlet and outlet cave

Publications (1)

Publication Number Publication Date
CN208778010U true CN208778010U (en) 2019-04-23

Family

ID=66155167

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821231431.9U Expired - Fee Related CN208778010U (en) 2018-08-01 2018-08-01 A kind of advance reinforcement structure of push pipe inlet and outlet cave

Country Status (1)

Country Link
CN (1) CN208778010U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113737771A (en) * 2021-09-24 2021-12-03 广东一新长城建筑集团有限公司 Pipe jacking well opening soil body reinforcing process for soft soil foundation
CN113863937A (en) * 2021-08-31 2021-12-31 中国二十冶集团有限公司 Reinforcing construction method for rectangular pipe jacking tunnel door

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113863937A (en) * 2021-08-31 2021-12-31 中国二十冶集团有限公司 Reinforcing construction method for rectangular pipe jacking tunnel door
CN113737771A (en) * 2021-09-24 2021-12-03 广东一新长城建筑集团有限公司 Pipe jacking well opening soil body reinforcing process for soft soil foundation
CN113737771B (en) * 2021-09-24 2022-06-28 广东一新长城建筑集团有限公司 Pipe jacking well opening soil body reinforcing process for soft soil foundation

Similar Documents

Publication Publication Date Title
CN204112308U (en) A kind of simple and easy sleeve valve grouting device based on bowlder stone, Thief zone coefficient stratum
CN103184734B (en) A kind of construction method implanting slip casting compound pile
CN103526766B (en) Method for plugging relief well of deep foundation pit
CN101525881B (en) Structure of karst strata pile holes protecting wall and method for constructing pile holes
CN102286984A (en) Water-stop curtain and construction method thereof
CN102286981A (en) Waterproof curtain and construction method thereof
CN109026020B (en) Water-rich tunnel karst cave treatment and excavation method
CN209339169U (en) A kind of precipitation well in foundation pit plugging device
CN205742175U (en) A kind of steel construction protection wall of bored pile
CN107747312A (en) A kind of method of sand and gravel stratum well cementing construction
CN202194149U (en) Water-proof curtain
CN105731978B (en) A kind of grouting serous fluid and grouting method for fine sand layer jacking culvert solidifying of the working face
CN208778010U (en) A kind of advance reinforcement structure of push pipe inlet and outlet cave
CN103572764A (en) Ultra-deep manual hole digging pile dado water stop structure and construction method thereof
CN109440757A (en) A kind of foundation reinforcement method for karst region
CN104988914A (en) Cast-in-situ bored pile breakage processing method under water area environment
CN214997645U (en) Be applicable to subway station goes out inlet pipe curtain construction pipe curtain structure
CN107587502A (en) A kind of spiral-digging pore pressure pour water soil occlusion curtain pile construction method
CN102174818A (en) Controlled impermeable leaking stoppage grout-extruding water-stopping technology of strong water permeable stratum of quaternary system
CN101769157B (en) Construction method for tunnel working face counterpressure treatment during tunnel excavation
CN111424695B (en) Seepage-proofing and leakage-stopping method for deep-buried karst pipeline
CN108360542A (en) Waterproof between piles curtain combination stake side sleeve valve barrel grouting water stop construction method
CN104963364A (en) Disposing method for topdown structural slab lower side wall construction joint
CN205296194U (en) Rich irrigated land layer undercut tunnel interlock pipe curtain
CN107975027A (en) The construction method that shield launching is reinforced with reaching end soil body

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190423