Construction platform for super high-rise building
Technical Field
The utility model relates to a construction platform field, more specifically say, relate to a construction platform for super high-rise building.
Background
The super high-rise building refers to a building with more than 40 floors and more than 100 meters in height, and is specified in GB 50352-2005 in China general rules of civil building design: when the building height exceeds 100m, the buildings and public buildings are super high-rise buildings, and the super high-rise buildings are more than 300 m according to the new standard of world super high-rise building institute.
When super high building construction, need set up the construction platform at super high building's outer wall and conveniently construct, the construction platform who uses at present, under construction operation, more sand and soil can be built up on the platform surface, graininess sand and soil is after air-drying, step on and skid easily, lead to the operator to construct very dangerous greatly increased the possibility that drops on it, adopt traditional mode of cleaning, the operation is very inconvenient, also can bring the risk of falling, consequently, the construction platform who uses at present, there is the problem that the sand and soil on its surface is not convenient for handle.
SUMMERY OF THE UTILITY MODEL
1. Technical problem to be solved
To the problem that exists among the prior art, the utility model aims to provide a construction platform for super high-rise building, it can realize the sand and soil on the construction platform, can be convenient and smooth arrange into the ash storage groove in, discharge through arranging the ash groove, keep the relative clean on construction platform main part top, prevent that sand and soil from piling up and leading to skidding, improve construction platform's security greatly.
2. Technical scheme
In order to solve the above problems, the utility model adopts the following technical proposal.
A construction platform for a super high-rise building comprises a construction platform main body, four side edges at the top end of the construction platform main body are fixedly connected with guardrails, a plurality of strip-shaped grooves are formed in the middle of the top end of the construction platform main body in a spaced mode, a dust leaking net plate is fixedly connected to the tops of the inner walls of the strip-shaped grooves, wheel grooves are formed in two side edges of the top end of the construction platform main body in a spaced mode, a transverse plate is arranged on the upper side of the construction platform main body, a fixed rod is fixedly connected to the center of the top end of the transverse plate, grab handles are fixedly connected to the top ends of the fixed rod, supporting legs are fixedly connected to two sides of the bottom end of the transverse plate, wheels are fixedly mounted at the bottom ends of the supporting legs and are in sliding connection with the wheel grooves, a plurality of brush blocks are fixedly connected to the middle of the bottom end of the transverse, can realize the sandy soil on the construction platform, can be convenient and smooth arrange into the ash storage groove in, discharge through the ash discharge groove, keep the relative cleanness on construction platform main part top, prevent that sandy soil from piling up and leading to skidding, improve construction platform's security greatly.
Further, the equal fixedly connected with baffle in bottom of bar groove both sides inner wall, the baffle slant is fixed, and the baffle can lead to falling of sand and soil, prevents simultaneously that strong wind from blowing off the inside sand and soil that accumulates of ash storage tank once more to the top of construction platform main part.
Furthermore, the outer wall of the grab handle is provided with anti-skidding textures, so that friction force is increased, and slipping of the hand holding is prevented.
Further, the bottom inner wall in ash storage groove is the inclined plane, ash storage groove respectively with bar groove and the inside intercommunication in ash discharge groove, the sand and soil can fall into the ash storage groove from the bar groove earlier, then via ash discharge groove discharge.
Further, it is a plurality of brush piece and a plurality of bar groove staggered arrangement, the brush piece can clean the sand and soil between two adjacent bar grooves on leaking grey otter board, and the accumulational possibility of sand and soil that significantly reduces keeps the relative cleanness on construction platform main part top, cleans efficiently.
Furthermore, the ash leakage net plate is made of a metal net material and is more durable, the friction force between the sole of an operator and the top end of the construction platform main body is improved, and the stability of the operator during construction is greatly improved.
3. Advantageous effects
Compared with the prior art, the utility model has the advantages of:
(1) this scheme can realize the sand and soil on the construction platform, can be convenient and smooth arrange into the ash storage groove in, discharge through the ash discharge groove, keep the relative clean on construction platform main part top, prevent that sand and soil from piling up and leading to skidding, improve construction platform's security greatly.
(2) The equal fixedly connected with baffle in bottom of bar groove both sides inner wall, the baffle slant is fixed, and the baffle can lead to falling of sand and soil, prevents simultaneously that strong wind from blowing off the inside sand and soil that accumulates of ash storage tank once more to the top of construction platform main part.
(3) The bottom inner wall in ash storage groove is the inclined plane, and ash storage groove communicates with bar groove and ash discharge inslot portion respectively, and sand and soil can fall into the ash storage groove from the bar groove earlier, then via ash discharge groove discharge.
(4) A plurality of brush pieces and a plurality of bar groove staggered arrangement, the brush piece can clean the sand and soil between two adjacent bar grooves on leaking grey otter board, and the accumulational possibility of sand and soil that significantly reduces keeps the relative cleanness on construction platform main part top, cleans efficiently.
(5) The ash leakage net plate is made of a metal net material and is more durable, the friction force between the sole of an operator and the top end of the construction platform main body is improved, and the stability of the operator during construction is greatly improved.
Drawings
Fig. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic view of the structure at A in FIG. 1;
FIG. 3 is a schematic structural view of the main body of the construction platform of the present invention;
fig. 4 is a schematic side view of the cross-sectional structure of the present invention.
The reference numbers in the figures illustrate:
1 construction platform main part, 2 guardrails, 3 diaphragm, 4 brush pieces, 5 dead levers, 6 grab handles, 7 supporting legs, 8 wheels, 9 wheel grooves, 10 bar grooves, 11 ash leaking otter boards, 12 baffle, 13 ash storage grooves, 14 ash discharge grooves.
Detailed Description
The technical solution in the embodiment of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiment of the present invention; obviously, the described embodiments are only a part of the embodiments of the present invention, and not all embodiments, and all other embodiments obtained by those skilled in the art without any inventive work are within the scope of the present invention based on the embodiments of the present invention.
In the description of the present invention, it should be noted that the terms "upper", "lower", "inner", "outer", "top/bottom", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplification of description, but do not indicate or imply that the device or element referred to must have a specific orientation, be constructed in a specific orientation, and be operated, and thus, should not be construed as limiting the present invention. Furthermore, the terms "first" and "second" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance.
In the description of the present invention, it is to be noted that, unless otherwise explicitly specified or limited, the terms "mounted", "provided", "sleeved/connected", "connected", and the like are to be understood in a broad sense, such as "connected", which may be fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood in specific cases to those skilled in the art.
Example 1:
referring to fig. 1-4, a construction platform for super high-rise buildings comprises a construction platform body 1, four side edges of the top end of the construction platform body 1 are fixedly connected with guardrails 2, a plurality of strip-shaped grooves 10 are chiseled in the middle of the top end of the construction platform body 1 at intervals, the top of the inner wall of each strip-shaped groove 10 is fixedly connected with a dust leaking screen plate 11, wheel grooves 9 are chiseled on two side edges of the top end of the construction platform body 1, a transverse plate 3 is arranged on the upper side of the construction platform body 1, a fixing rod 5 is fixedly connected to the center of the top end of the transverse plate 3, a grab handle 6 is fixedly connected to the top end of the fixing rod 5, supporting legs 7 are fixedly connected to two sides of the bottom end of the transverse plate 3, wheels 8 are fixedly mounted at the bottom ends of the supporting legs 7, the wheels 8 are slidably connected with the wheel grooves 9, a plurality, the bottom on the right side of the construction platform main body 1 is provided with the ash discharging groove 14 in a chiseling mode, sand and soil on the construction platform main body 1 can be discharged into the ash storage groove 13 conveniently and smoothly, the sand and soil are discharged through the ash discharging groove 14, the relative cleanness of the top end of the construction platform main body 1 is kept, the sand and soil are prevented from being accumulated to cause slipping, and the safety of the construction platform is greatly improved.
The equal fixedly connected with baffle 12 in bottom of bar groove 10 both sides inner wall, the baffle 12 slant is fixed, and baffle 12 can lead to falling of sand and soil, prevents simultaneously that the strong wind from blowing off the inside sand and soil that accumulates of ash storage tank 13 once more to the top of construction platform main part 1.
The outer wall of the grab handle 6 is provided with anti-skidding textures, so that friction is increased, and slipping caused by holding is prevented.
The bottom inner wall of ash storage groove 13 is the inclined plane, and ash storage groove 13 communicates with bar groove 10 and ash discharge groove 14 are inside respectively, and the sand and soil can fall into ash storage groove 13 from bar groove 10 earlier, then via ash discharge groove 14 discharge.
A plurality of brush pieces 4 and a plurality of bar groove 10 staggered arrangement, brush piece 4 can clean the sand and soil between two adjacent bar grooves 10 to leak grey otter board 11 on, and the accumulational possibility of sand and soil that significantly reduces keeps the relative cleanness on 1 top of construction platform main part, cleans efficiently.
The ash leakage net plate 11 is made of a metal net material and is more durable, the friction force between the sole of an operator and the top end of the construction platform main body 1 is improved, and the stability of the operator during construction is greatly improved.
When the utility model is used, when an operator carries out construction on the construction platform main body 1, a certain amount of sandy soil can be accumulated at the top end of the construction platform main body 1, wherein a larger part of sandy soil can pass through the ash leaking screen plate 11 at the top of the strip-shaped groove 10, firstly, the sandy soil can fall into the two guide plates 12 and then fall into the ash storage groove 13 through the guide plates 12, the guide plates 12 are obliquely fixed, the falling of the sandy soil can be guided, simultaneously, strong wind or the process of the construction platform main body 1 can be prevented, the sandy soil accumulated in the ash storage groove 13 is blown out to the top end of the construction platform main body 1 again, the inner wall at the bottom end of the ash storage groove 13 is designed into an inclined plane, the accumulated sandy soil can slide under the action of gravity and is finally discharged from the ash discharge groove 14, the sandy soil at the other part at the top end of the construction platform main body 1 can be left between the two adjacent strip-shaped grooves 10, thus, through the removal of dead lever 5 pulling diaphragm 3, thereby drive the wheel 8 of supporting leg 7 bottom and slide in the inside of race 9, diaphragm 3 is from the opposite side of the one side removal at construction platform main part 1 top like this, at the in-process that removes, a plurality of brush pieces 4 can sweep the sand and soil of staying between two adjacent bar grooves 10 to leak grey otter board 11 on, thereby drop in the inside of ash storage tank 13, the operator can clean once at an interval period, keep the relative cleanness on construction platform main part 1 top, can realize the sand and soil on the construction platform main part 1, can be convenient and smooth arrange into in the ash storage tank 13, discharge through ash discharge tank 14, keep the relative cleanness on construction platform main part 1 top, prevent that sand and soil from piling up and leading to skidding, construction platform's security improves greatly.
The above description is only the preferred embodiment of the present invention; the scope of the present invention is not limited thereto. Any person skilled in the art should also be able to cover the technical scope of the present invention by replacing or changing the technical solution and the improvement concept of the present invention with equivalents and modifications within the technical scope of the present invention.