CN211282977U - Three-machine supply PE production equipment - Google Patents

Three-machine supply PE production equipment Download PDF

Info

Publication number
CN211282977U
CN211282977U CN201921919652.XU CN201921919652U CN211282977U CN 211282977 U CN211282977 U CN 211282977U CN 201921919652 U CN201921919652 U CN 201921919652U CN 211282977 U CN211282977 U CN 211282977U
Authority
CN
China
Prior art keywords
feeding
mounting
feed
main body
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201921919652.XU
Other languages
Chinese (zh)
Inventor
李剑铭
李祚鑫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Puxin Technology Co ltd
Original Assignee
Sichuan Puxin Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Puxin Technology Co ltd filed Critical Sichuan Puxin Technology Co ltd
Priority to CN201921919652.XU priority Critical patent/CN211282977U/en
Application granted granted Critical
Publication of CN211282977U publication Critical patent/CN211282977U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a PE production facility is supplied with to three machines, including feed machine and extruding machine, the feed machine includes mounting bracket, feed blanking structure and blanking structure, the extruding machine includes main part and extrusion molding structure, the mounting bracket comprises two first mount pads and two side boards the bottom of side board is provided with the supporting leg, two the both ends fixed connection of first mount pad and two side boards, feed blanking structure installs in the outside and the inside of mounting bracket, blanking structure installs in feed blanking structure's top, the main part is located the below of mounting bracket, the one end top of main part is provided with the feed inlet, the feed inlet is located the intermediate position of mounting bracket, the inside of main part is provided with the installation cavity. The utility model discloses feed work efficiency is high, and links up going on with the multichannel production process combination of PE material to whole production efficiency when having improved PE material production greatly.

Description

Three-machine supply PE production equipment
Technical Field
The utility model relates to a PE material processing equipment field specifically is a three machines supply with PE production facility.
Background
The PE particles are high pressure polyethylene particles, polyethylene, PE for short, a thermoplastic resin made by polymerizing ethylene. The polyethylene is odorless, nontoxic, has wax-like hand feeling, has excellent low-temperature resistance, has the lowest use temperature of-100 to-70 ℃, has good chemical stability, can resist the corrosion of most of acid and alkali, and cannot resist acid with oxidation property. The PE material is insoluble in common solvents at normal temperature, has small water absorption and excellent electrical insulation, and production equipment is used for replacing manpower to carry out production work of the PE material in the production process of the PE particles.
However, the existing PE production equipment has the following disadvantages:
1. the efficiency is lower when the materials are conveyed.
2. A plurality of working procedures exist in the production process, so that the production work is not convenient to be carried out continuously, and the production efficiency is influenced.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a PE production facility is supplied with to three machines to solve traditional PE production facility and carry the efficiency ratio lower when carrying the material, and have a plurality of processes in process of production, be not convenient for link up it and carry out production work, influence production efficiency's problem.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a PE production facility is supplied with to three machines, includes feeder machine and extruding machine, the feeder machine includes mounting bracket and feed blanking structure, the extruding machine includes main part and extrusion molding structure, the mounting bracket comprises two first mount pads and two side boards the bottom of side board is provided with the supporting leg, two the both ends fixed connection of first mount pad and two side boards, feed blanking structure installs in the outside and the inside of mounting bracket, the main part is located the below of mounting bracket, the one end top of main part is provided with the feed inlet, the feed inlet is located the intermediate position of mounting bracket, the inside of main part is provided with the installation cavity, one side of main part is provided with the second mount pad, extrusion molding structure installs in the inside of main part, the bottom of main part is provided with the supporting seat.
Preferably, the feeding and blanking structure comprises two sets of first mounting plates, first motors, a screw rod, a feeding plate, a second mounting plate, a hydraulic cylinder and a push plate, the two sets of feeding and blanking structures are respectively arranged at one side, far away from each other, of the two first mounting plates, the two first motors are respectively arranged on the upper end surfaces of the first mounting plates, the screw rod is positioned at one side, far away from the first motors, of the first mounting plates, one end of the screw rod is connected with the first motors through a coupler, the feeding plate is movably connected with the screw rod through a sliding block, the lower parts of the front side and the rear side of the feeding plate are movably connected with the top of the side panel through a connecting piece, the second mounting plate is vertically arranged on the upper end surface of the feeding plate, the hydraulic cylinder is arranged on one side surface of the second mounting plate, and the push plate is fixedly connected with the telescopic end, the working efficiency of the feeding work is improved.
Preferably, the longitudinal length of two push plates is less than the inside diameter of the upper end of the feed inlet, so that the push plates are prevented from pushing the material to the outside of the feed inlet when blanking.
Preferably, the extrusion molding structure includes third mounting panel, second motor, carries feed cylinder, screw conveyer pole, feed cylinder heater and extrusion molding mould, the third mounting panel is installed in the one side that the main part was kept away from to the second mount pad, the second motor is installed in the upper end surface of third mounting panel, carry the feed cylinder to install in the inside of main part, and carry the feed cylinder and be connected with the feed inlet intercommunication at the one end top that is close to the feed inlet, the screw conveyer pole is located the inside of defeated feed cylinder, and the output fixed connection of the one end of screw conveyer pole and second motor, the feed cylinder heater is installed in the outside of carrying the feed cylinder, the extrusion molding mould is installed in the one end of carrying the feed cylinder to keep away from in the second motor, and is located the outside of main part for can carry out extrusion molding work to the.
Preferably, the size of auger delivery pole and the inside diameter phase-match of carrying the feed cylinder have improved auger delivery pole's transport effect, avoid omitting.
Preferably, the vertical clearance distance between the feeding hole and the feeding plate is 10-15cm, so that the materials are ensured to directly fall into the feeding hole.
The utility model provides a PE production facility is supplied with to three machines possesses following beneficial effect:
(1) the utility model discloses a be provided with feed blanking structure, including first mounting panel, first motor, the lead screw, the delivery sheet, the second mounting panel, pneumatic cylinder and push pedal, and feed blanking structure is provided with two sets, make when carrying the work to the PE material, can be through starting two first motors, make two first motor's rotation drive two sliders and move with two delivery sheets that two sliders are connected, until removing the top of feed inlet in the extruding machine, then start the hydraulic cylinder, make the extension of pneumatic cylinder drive the push pedal and remove, thereby say during the material is from delivery sheet propelling movement to the feeding, then make the feed work of carrying out the material from both sides two-way, material feed speed when having improved PE material production greatly.
(2) The utility model installs the plastic extruding machine under the feeding machine, which comprises a third mounting plate, a second motor, a conveying material cylinder, a spiral conveying rod, a material cylinder heater and a plastic extruding mould, so that during the production process of PE materials, the feeding blanking structure is combined with the plastic extruding structure, continuous feeding blanking work is carried out through the feeding blanking structure, the second motor is started simultaneously, the second motor is rotated to drive the spiral conveying rod to rotate, further conveying work is carried out on the PE materials falling from the feeding port to the conveying material cylinder, in the conveying process, the material cylinder heater is started to heat the conveying material cylinder, thereby heating the PE materials in the conveying material cylinder, when the conveying material cylinder conveys the materials to the plastic extruding mould, through the matching of the plastic extruding mould and the spiral conveying rod, carry out extrusion molding work to the material, reached on the whole that the multichannel process links up the purpose of going on, improved the efficiency of holistic PE material production then greatly.
Drawings
Fig. 1 is a schematic view of the overall structure of the present invention;
fig. 2 is a schematic top view of the present invention;
fig. 3 is an enlarged schematic view of the position a of the present invention.
In the figure: 1. a mounting frame; 2. a main body; 3. a first mounting seat; 4. a side panel; 5. a feed inlet; 6. installing a cavity; 7. a second mounting seat; 8. a supporting seat; 9. a first mounting plate; 10. a first motor; 11. a screw rod; 12. a feeding plate; 13. a second mounting plate; 14. a hydraulic cylinder; 15. pushing the plate; 16. a third mounting plate; 17. a second motor; 18. a conveying barrel; 19. a screw conveying rod; 20. a cartridge heater; 21. and (4) extruding the die.
Detailed Description
The technical solution in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention.
As shown in fig. 1-3, the utility model provides a technical solution: a three-machine supply PE production device comprises a supply machine and an extruding machine, wherein the supply machine comprises a mounting frame 1 and a supply and blanking structure, the plastic extruding machine comprises a main body 2 and an extruding structure, the mounting frame 1 consists of two first mounting seats 3 and two side panels 4, supporting legs are arranged at the bottoms of the two side panels 4, the two first mounting seats 3 are fixedly connected with the two ends of the two side panels 4, the feeding and blanking structure is arranged outside and inside the mounting frame 1, the main body 2 is positioned below the mounting frame 1, a feed inlet 5 is arranged at the top of one end of the main body 2, the feed inlet 5 is positioned in the middle of the mounting frame 1, the main body 2 is internally provided with an installation cavity 6, one side of the main body 2 is provided with a second installation seat 7, the extrusion molding structure is arranged in the main body 2, and a supporting seat 8 is arranged at the bottom of the main body 2.
The feeding and blanking structure comprises first mounting plates 9, first motors 10, a screw rod 11, a feeding plate 12, a second mounting plate 13, a hydraulic cylinder 14 and a push plate 15, wherein the feeding and blanking structure is provided with two sets, the two first mounting plates 9 are respectively mounted at one sides of two first mounting seats 3 which are far away from each other, the two first motors 10 are respectively mounted on the upper end surfaces of the first mounting plates 9, the screw rod 11 is positioned at one side of the first mounting seats 3 which is far away from the first motors 10, one end of the screw rod 11 is connected with the first motors 10 through a coupler, the feeding plate 12 is movably connected with the screw rod 11 through a slide block, the lower parts of the front side and the rear side of the feeding plate 12 are movably connected with the top of the side panel 4 through connecting pieces, the second mounting plate 13 is vertically mounted on the upper end surface of the feeding plate 12, the hydraulic cylinder 14 is mounted on one side surface of the second mounting plate 13, and, when the PE material is conveyed, the two first motors 10 can be started, so that the two first motors 10 rotate to drive the two sliding blocks and the two feeding plates 12 connected with the two sliding blocks to move until the two sliding blocks move to the position above the feeding hole 5 in the extruding machine, then the hydraulic cylinder 14 is started, the hydraulic cylinder 14 extends to drive the push plate 15 to move, so that the material is pushed to the feeding from the feeding plates 12, the material feeding operation is performed bidirectionally from two sides, and the material feeding speed during the production of the PE material is greatly improved; the longitudinal length of the two push plates 15 is smaller than the inner diameter of the upper end of the feed port 5, so that when the push plates 15 are used for blanking, materials are prevented from being pushed to the outer part of the feed port 5; the extrusion molding structure comprises a third mounting plate 16, a second motor 17, a conveying material cylinder 18, a spiral conveying rod 19, a material cylinder heater 20 and an extrusion molding die 21, wherein the third mounting plate 16 is mounted on one side of the second mounting seat 7 far away from the main body 2, the second motor 17 is mounted on the upper end surface of the third mounting plate 16, the conveying material cylinder 18 is mounted in the main body 2, the conveying material cylinder 18 is communicated and connected with the feeding hole 5 at the top of one end close to the feeding hole 5, the spiral conveying rod 19 is positioned in the conveying material cylinder 18, one end of the spiral conveying rod 19 is fixedly connected with the output end of the second motor 17, the material cylinder heater 20 is mounted outside the conveying material cylinder 18, the extrusion molding die 21 is mounted at one end of the conveying material cylinder 18 far away from the second motor 17 and positioned outside the main body 2, so that the rotation of the second motor 17 can drive the spiral conveying rod 19 to rotate by starting the second motor 17, the PE material falling from the feeding hole 5 into the conveying material barrel 18 is further conveyed, and in the conveying process, the material barrel heater 20 is started to heat the conveying material barrel 18, so that the PE material in the conveying material barrel 18 is heated, and when the conveying material barrel 18 conveys the material to the extrusion molding die 21, the extrusion molding die 21 is matched with the spiral conveying rod 19 to perform extrusion molding on the material; the size of the spiral conveying rod 19 is matched with the inner diameter of the conveying material barrel 18, so that the situation that conveying of the spiral conveying rod 19 is incomplete and missing is avoided; the vertical gap distance between the feeding hole 5 and the feeding plate 12 is 10-15cm, so that the phenomenon that the material blanking position is unexpected due to the fact that the gap between the feeding hole 5 and the feeding plate 12 is too large is avoided.
The working principle is as follows: when the production work of PE materials is carried out, the PE materials for producing the PE materials are placed on the upper end surfaces of two feeding plates 12 at two ends of a feeding and blanking structure in a staged manner through a machine or manpower, then two first motors 10 are started, so that the two first motors 10 rotate to drive two sliding blocks and two feeding plates 12 connected with the two sliding blocks to move until the two sliding blocks move to the position above a feeding hole 5 in an extruding machine, then a hydraulic cylinder 14 is started, the hydraulic cylinder 14 extends to drive a push plate 15 to move, so that the materials are pushed to the feeding from the feeding plates 12, the feeding work of the materials is carried out in two directions from two sides, the material feeding speed during the production of the PE materials is greatly improved, meanwhile, a second motor 17 is started, so that the rotation of the second motor 17 drives a spiral conveying rod 19 to rotate, and further conveying work is carried out on the PE materials falling from the feeding hole 5 to the conveying barrel 18, and at the in-process of carrying, start feed cylinder heater 20 and carry out the heating work to carrying feed cylinder 18 to carry the inside PE material of feed cylinder 18 to carry out the heating work, until carry feed cylinder 18 when carrying the material to extrusion molding mould 21 department, through extrusion molding mould 21 and screw conveyer 19's cooperation, carry out extrusion molding work to the material, reached on the whole that the going on is coherent with multichannel process, then improved the efficiency of holistic PE material production greatly.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. A three-machine feeding PE production equipment, which comprises a feeding machine and an extruding machine, and is characterized in that: the feeder comprises a mounting frame (1) and a feeding and blanking structure, the extruding machine comprises a main body (2) and an extruding structure, the mounting frame (1) is composed of two first mounting seats (3) and two side panels (4), supporting legs are arranged at the bottoms of the two side panels (4), the two first mounting seats (3) are fixedly connected with the two ends of the two side panels (4), the feeding and blanking structure is mounted outside and inside the mounting frame (1), the main body (2) is located below the mounting frame (1), a feeding hole (5) is formed in the top of one end of the main body (2), the feeding hole (5) is located in the middle of the mounting frame (1), a mounting cavity (6) is formed in the main body (2), a second mounting seat (7) is arranged on one side of the main body (2), and the extruding structure is mounted inside the main body (2), the bottom of the main body (2) is provided with a supporting seat (8).
2. A three-machine feed PE production plant according to claim 1, characterized in that: the feeding and blanking structure comprises first mounting plates (9), first motors (10), a screw rod (11), a feeding plate (12), second mounting plates (13), a hydraulic cylinder (14) and a push plate (15), wherein the feeding and blanking structure is provided with two sets, the two first mounting plates (9) are respectively mounted on one sides, far away from each other, of the two first mounting seats (3), the two first motors (10) are respectively mounted on the upper end surfaces of the first mounting plates (9), the screw rod (11) is positioned on one sides, far away from the first motors (10), of the first mounting seats (3), one end of the screw rod (11) is connected with the first motors (10) through a coupler, the feeding plate (12) is movably connected with the screw rod (11) through a sliding block, the lower parts of the front side and the rear side of the feeding plate (12) are movably connected with the tops of the side panels (4) through connecting pieces, the second mounting plates (13) are vertically mounted on the upper end surfaces of the feeding plate (, the hydraulic cylinder (14) is installed on the surface of one side of the second installation plate (13), and the push plate (15) is fixedly connected with the telescopic end of the hydraulic cylinder (14).
3. A three-machine feed PE production plant according to claim 2, characterized in that: the longitudinal length of the two push plates (15) is smaller than the inner diameter of the upper end of the feed port (5).
4. A three-machine feed PE production plant according to claim 1, characterized in that: the extrusion molding structure comprises a third mounting plate (16), a second motor (17), a conveying material cylinder (18), a spiral conveying rod (19), a material cylinder heater (20) and an extrusion molding die (21), wherein the third mounting plate (16) is mounted on one side, away from the main body (2), of the second mounting plate (7), the second motor (17) is mounted on the upper end surface of the third mounting plate (16), the conveying material cylinder (18) is mounted in the main body (2), the conveying material cylinder (18) is connected with the feeding hole (5) at the top of one end, close to the feeding hole (5), in a communicating manner, the spiral conveying rod (19) is located inside the conveying material cylinder (18), one end of the spiral conveying rod (19) is fixedly connected with the output end of the second motor (17), the material cylinder heater (20) is mounted outside the conveying material cylinder (18), the extrusion molding die (21) is mounted at one end, away from the second motor (17), of the conveying material cylinder (18), and is located outside the main body (2).
5. A three-machine feed PE production plant according to claim 4, characterized in that: the size of the screw conveying rod (19) is matched with the inner diameter of the conveying material barrel (18).
6. A three-machine feed PE production plant according to claim 1, characterized in that: the vertical gap distance between the feed inlet (5) and the feed plate (12) is 10-15 cm.
CN201921919652.XU 2019-11-08 2019-11-08 Three-machine supply PE production equipment Expired - Fee Related CN211282977U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921919652.XU CN211282977U (en) 2019-11-08 2019-11-08 Three-machine supply PE production equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921919652.XU CN211282977U (en) 2019-11-08 2019-11-08 Three-machine supply PE production equipment

Publications (1)

Publication Number Publication Date
CN211282977U true CN211282977U (en) 2020-08-18

Family

ID=72015018

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921919652.XU Expired - Fee Related CN211282977U (en) 2019-11-08 2019-11-08 Three-machine supply PE production equipment

Country Status (1)

Country Link
CN (1) CN211282977U (en)

Similar Documents

Publication Publication Date Title
CN103317709B (en) Full-automatic plate plastics sucking moulding machine
CN203156877U (en) Wood board butt joint machine
CN210498719U (en) Front combined guide vertical roller for pipe welding machine
CN211282977U (en) Three-machine supply PE production equipment
CN109763279B (en) Carbon fiber processing discharging device
CN206406441U (en) A kind of vacuum plastic-absorbing machine
CN215849563U (en) Rubber processing extrusion material forming device
CN214813101U (en) Automatic feeding device of punch press
CN110143043B (en) Heating slurry printing device
CN210617223U (en) Heated board production water line
CN209902222U (en) Vacuum pressure casting machine with automatic feeding function
CN109454721B (en) Glue-free compacting equipment based on high frequency
CN105922493A (en) Full-automatic secondary foam molding machine
CN207788706U (en) Abrasive wheel forming tablet press machine
CN208375939U (en) A kind of novel double-screw rubber filtering extruder
CN215150946U (en) Automatic conveying device of raw materials for PVC composite film production
CN207671165U (en) A kind of feeding module
CN111136845A (en) Shaping system for manufacturing plastic-wood boards
CN220373728U (en) Cooling device after hot pressing
CN218593446U (en) Plastic mold with automatic ejection function
CN212920216U (en) Automatic injection molding feeding machine
CN213321643U (en) Heating mechanism of extruder for powder coating processing
CN203092717U (en) Spreading system of raised table processing equipment
CN210256396U (en) Board recovery processing equipment is moulded to PVC wood
CN212400097U (en) Ultrahigh molecular polyethylene board production system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200818

Termination date: 20201108

CF01 Termination of patent right due to non-payment of annual fee