CN211123125U - High-voltage test device for lightning arrester of power transmission line - Google Patents
High-voltage test device for lightning arrester of power transmission line Download PDFInfo
- Publication number
- CN211123125U CN211123125U CN201921719794.1U CN201921719794U CN211123125U CN 211123125 U CN211123125 U CN 211123125U CN 201921719794 U CN201921719794 U CN 201921719794U CN 211123125 U CN211123125 U CN 211123125U
- Authority
- CN
- China
- Prior art keywords
- insulator spindle
- arrester
- transmission line
- wire
- fastener
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000012360 testing method Methods 0.000 title claims abstract description 37
- 230000005540 biological transmission Effects 0.000 title claims abstract description 10
- 239000012212 insulator Substances 0.000 claims abstract description 23
- WABPQHHGFIMREM-UHFFFAOYSA-N lead(0) Chemical compound [Pb] WABPQHHGFIMREM-UHFFFAOYSA-N 0.000 claims abstract description 14
- 238000009413 insulation Methods 0.000 claims abstract description 12
- 210000001503 joint Anatomy 0.000 claims abstract description 4
- 229910052573 porcelain Inorganic materials 0.000 claims description 5
- 239000004677 Nylon Substances 0.000 claims description 4
- 229920001778 nylon Polymers 0.000 claims description 4
- 238000000034 method Methods 0.000 abstract description 6
- 239000002184 metal Substances 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 239000002390 adhesive tape Substances 0.000 description 1
- 238000003745 diagnosis Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000009421 internal insulation Methods 0.000 description 1
- 238000005728 strengthening Methods 0.000 description 1
- 238000010998 test method Methods 0.000 description 1
- 238000004804 winding Methods 0.000 description 1
Images
Landscapes
- Testing Relating To Insulation (AREA)
Abstract
The utility model relates to a transmission line arrester high-voltage testing device, including scalable insulator spindle, fastener, penetrate low-insulation direct current shielding high-voltage lead in scalable insulator spindle, public, female butt joint plug are made respectively to low-insulation direct current shielding high-voltage lead both ends, and public plug end is fixed in the one end of scalable insulator spindle, and female plug end is connected to the arrester of being tried with the public plug of fastener through the flexible lead in the insulator spindle, the fastener includes big, little two clamps, and big clamp connects the sinle silk of shielded wire, and little clamp connects the shielding of shielded wire. The device has both increased the commonality that same equipment is applicable to multiple scene and has reduced testing personnel's work load, improves work efficiency, has avoided testing personnel to take place the risk that the high altitude falls when carrying out the work at the platform edge above the shaft tower repeatedly simultaneously, and the most important can avoid droing of high voltage lead wire among the testing process to guarantee testing personnel's personal safety and avoid damaging test equipment.
Description
Technical Field
The utility model belongs to the technical field of the high voltage test, a arrester is related to, especially a transmission line arrester high voltage test device.
Background
The direct current reference voltage and leakage current test of the lightning arrester is the most important handover, routine and diagnosis test item of the lightning arrester, and has important significance for finding that the internal insulation of the lightning arrester is affected with damp and aged, and serious partial discharge exists.
Because the direct current reference voltage of the lightning arrester is generally higher, for example, the direct current reference voltage of each section of the 220kV lightning arrester is generally about 150kV, and the direct current reference voltage of each section of the 500kV lightning arrester can be generally about 200 kV. However, the insulation of the high-voltage lead wire of the current lightning arrester direct-current reference voltage and leakage current test is generally low, so that how to arrange the high-voltage lead wire in the test project is very important work, and the work sometimes takes a lot of time, especially for occasions where field devices are installed highly and are close to the ground, and the high-voltage lead wire is not easy to arrange. For example, the direct current reference voltage and leakage current test are carried out after the lightning arrester on the tower is installed, and because the structure is more complicated on the tower, the number of grounded metal parts is more, and equipment such as an insulating support porcelain insulator and a cable head also exist simultaneously, so the following problems exist when the direct current reference voltage and leakage current test of the lightning arrester on the tower is carried out:
1. in order to keep enough safe distance between the high-voltage lead and the grounding part, the insulating support porcelain insulator, the cable head and the like of the tower, the position and the wiring mode of the high-voltage lead need to be repeatedly adjusted, and each phase of lightning arrester test needs to carry out the work, so that the workload of test personnel is greatly increased, the working efficiency is reduced, and the timely operation of equipment is not facilitated;
2. at present, when a direct-current high-voltage lead is arranged, an insulating adhesive tape is usually used for suspending the high-voltage lead on a grounding metal part or winding the high-voltage lead on an insulating porcelain insulator, and then the trend of the high-voltage lead is adjusted;
3. when carrying out the hoist and mount of high voltage lead wire or twine high voltage lead wire on the insulator with the insulating tape, the testing personnel often need stand and carry out work at the most marginal of platform above the shaft tower, and this has increased the risk that testing personnel takes place the high altitude and fall undoubtedly, and the test work of arrester is gone on at night in the shaft tower very many times especially, and consequently testing personnel's sight can be very fuzzy, and energy is also more easily dispersed, so arrange the work time taking place the high altitude accident of falling more easily carrying out high voltage lead wire.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to overcome prior art's weak point, provide a transmission line arrester high voltage test device, the device has avoided the tester to carry out the risk that the during operation takes place the high altitude and falls repeatedly at the platform edge above the shaft tower, and the most important can avoid droing of high voltage lead wire in the test process to guarantee tester's personal safety and avoid damaging test equipment.
The utility model provides a technical scheme that technical problem adopted is:
the utility model provides a transmission line arrester high voltage test device, includes scalable insulator spindle, fastener, penetrates low-insulation direct current shielding high voltage lead wire in scalable insulator spindle, and public, female butt joint plug are made respectively to low-insulation direct current shielding high voltage lead wire both ends, and public plug end is fixed in the one end of scalable insulator spindle, and female plug end is connected to the arrester of being tried with the public plug of fastener through the flexible lead wire in the insulator spindle, the fastener includes big, two little clips, and big clip connects the sinle silk of shielded wire, and little clip connects the shielding of shielded wire.
And two openable hooks are fixedly arranged at two ends of the outer wall of the telescopic insulating rod.
And when in use, the telescopic insulating rod is fixed on the insulating porcelain insulator through the insulating nylon pull wire.
The utility model has the advantages that:
(1) the device can greatly reduce the workload of testers, save wiring time, improve working efficiency and ensure timely operation of the tested equipment;
(2) the device can avoid the falling of the high-voltage lead in the test process, thereby ensuring the personal safety of the test personnel and avoiding damaging the test equipment;
(3) the device can prevent the tester from repeatedly working on the edge of the platform on the tower, thereby preventing the tester from falling from high altitude.
Drawings
Fig. 1 is a structural view of the present apparatus.
Detailed Description
The present invention will be described in further detail with reference to the following embodiments, which are illustrative, not restrictive, and the scope of the invention should not be limited thereto.
A high-voltage test device for a lightning arrester of a power transmission line comprises a telescopic insulating rod 6, a wire clamp and a low-insulation direct-current shielding high-voltage lead 5, wherein a male butt plug and a female butt plug are respectively manufactured at two ends of the low-insulation direct-current shielding high-voltage lead, and a male plug end 8 is fixed at the front end of the telescopic insulating rod so as to be convenient for connecting a butt joint lower lead with a high-voltage output end of a hair straightener; the female plug end 4 is connected with the male plug 3 of the wire clamp through a telescopic lead in the insulating rod to the tested lightning arrester. The fastener includes big, two little clips, and 2 connecing wire cores of shielded wire of big clip, little clip 1 connects the shielding of shielded wire, and the shielded wire of 15 meters length is reserved to this end, is convenient for extend the wiring to each looks arrester behind the fixed insulator spindle of well phase insulation support vase department on the shaft tower. When a non-line arrester test is carried out, the telescopic insulating rod can be thrown open to directly connect the wire clamp with an external shielding wire, the wire clamp is connected with the tested arrester, and the other end of the external shielding wire is connected with the output end of the direct current generator, which is consistent with the traditional test method; the universality that the same equipment is suitable for various fields is increased.
Two openable hooks 7 are fixedly arranged at two ends of the outer wall of the telescopic insulating rod, so that redundant low-insulation direct-current shielding high-voltage lead discs at the rear end of the wire clamp are locked after being looped in a test process, and the low-insulation direct-current shielding high-voltage lead is prevented from falling off in the test process; the safety of pressurization is guaranteed.
Adopt the insulating nylon of strengthening to act as go-between to fix scalable insulator spindle on insulating vase, insulating nylon acts as go-between installation and dismantlement are all very convenient, can guarantee that the insulator spindle can not drop in the testing process, have improved work efficiency.
The foregoing is only a preferred embodiment of the present invention, and it should be noted that, for those skilled in the art, many modifications and improvements can be made without departing from the spirit of the present invention, and these modifications and improvements are all within the protection scope of the present invention.
Claims (3)
1. The utility model provides a transmission line arrester high voltage test device which characterized in that: including scalable insulator spindle, fastener, penetrate low-insulation direct current shielding high voltage lead wire in scalable insulator spindle, public, female butt joint plug are made respectively to low-insulation direct current shielding high voltage lead wire both ends, and the one end at scalable insulator spindle is fixed to the public plug, and female plug end is connected to the arrester of being tried with the public plug of fastener through the flexible lead wire in the insulator spindle, the fastener includes big, two little clamps, and big clamp connects the sinle silk of shielded wire, and little clamp connects the shielding of shielded wire.
2. The high-voltage test device for the lightning arrester of the power transmission line according to claim 1, characterized in that: two openable hooks are fixedly arranged at two ends of the outer wall of the telescopic insulating rod.
3. The high-voltage test device for the lightning arrester of the power transmission line according to claim 1, characterized in that: when the telescopic insulator is used, the telescopic insulator rod is fixed on the insulator porcelain bottle through the insulating nylon stay wire.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921719794.1U CN211123125U (en) | 2019-10-15 | 2019-10-15 | High-voltage test device for lightning arrester of power transmission line |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921719794.1U CN211123125U (en) | 2019-10-15 | 2019-10-15 | High-voltage test device for lightning arrester of power transmission line |
Publications (1)
Publication Number | Publication Date |
---|---|
CN211123125U true CN211123125U (en) | 2020-07-28 |
Family
ID=71690371
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201921719794.1U Active CN211123125U (en) | 2019-10-15 | 2019-10-15 | High-voltage test device for lightning arrester of power transmission line |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN211123125U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110618362A (en) * | 2019-10-15 | 2019-12-27 | 国网天津市电力公司 | High-voltage test device for lightning arrester of power transmission line |
CN112327077A (en) * | 2020-10-27 | 2021-02-05 | 广东电网有限责任公司广州供电局 | Electric power test auxiliary tool |
-
2019
- 2019-10-15 CN CN201921719794.1U patent/CN211123125U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110618362A (en) * | 2019-10-15 | 2019-12-27 | 国网天津市电力公司 | High-voltage test device for lightning arrester of power transmission line |
CN112327077A (en) * | 2020-10-27 | 2021-02-05 | 广东电网有限责任公司广州供电局 | Electric power test auxiliary tool |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN211123125U (en) | High-voltage test device for lightning arrester of power transmission line | |
CN109462053A (en) | A kind of novel grounded line apparatus for aerial insulated wire | |
CN110618362A (en) | High-voltage test device for lightning arrester of power transmission line | |
CN205646216U (en) | Insulation is tested denso and is established earth connection auxiliary rod | |
CN207459219U (en) | A kind of cable elbow-shaped head convenient for experiment | |
CN209607932U (en) | A kind of ground line electroscopic device | |
CN211295399U (en) | Line side shielding formula ground terminal structure and insulating bar of installation usefulness thereof | |
CN109061358B (en) | Method and system for testing single-phase instantaneous grounding short circuit of power transmission line | |
CN204190261U (en) | For preventing the removable instrument that electrical verification rod falls and earth rod swings | |
CN117117748A (en) | Wind power generation and transmission system | |
CN110702952A (en) | Portable 10kV handcart switch loop resistance test auxiliary device | |
CN105610052B (en) | A kind of Lightning Warning lifts linked system | |
CN213366836U (en) | Hand throwing formula earth connection connecting device | |
CN104362485A (en) | Special lead for test on lightning arrester of power transmission cable tower | |
CN107589280A (en) | A kind of testing wire clamp and complexes for relay protection small bus transition | |
CN211179934U (en) | A terminal rod for arrester high-voltage test more than 220kV | |
CN211122944U (en) | Special adapter for GIS cable terminal test | |
CN208157665U (en) | A kind of pipe bus inductance earthing or grounding means being exclusively used in line maintenance | |
CN207994582U (en) | A kind of buried protection pipe of power cable | |
CN208220987U (en) | Protective device is pulled in a kind of torsion of wind-driven generator | |
CN207301122U (en) | A kind of testing wire clamp and complexes for relay protection small bus transition | |
CN201247839Y (en) | Pull type uphill-free ground grounding wire capable of being picked and hanged | |
CN201436754U (en) | Ground wire ice-thawing device capable of being used combinedly | |
CN217215138U (en) | Safe and undamaged grounding electricity testing hanging ring device for wire cores | |
CN210982698U (en) | 500kV zinc oxide arrester leakage current exempts from to ascend a height testing arrangement |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |