CN211114238U - Partition wall exempts from buried tub of wiring system in advance - Google Patents

Partition wall exempts from buried tub of wiring system in advance Download PDF

Info

Publication number
CN211114238U
CN211114238U CN201920616704.XU CN201920616704U CN211114238U CN 211114238 U CN211114238 U CN 211114238U CN 201920616704 U CN201920616704 U CN 201920616704U CN 211114238 U CN211114238 U CN 211114238U
Authority
CN
China
Prior art keywords
box body
wiring system
distance
partition wall
component
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920616704.XU
Other languages
Chinese (zh)
Inventor
周梁
张学兵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Lyucheng Yizhu Technology Co ltd
Original Assignee
Beijing Lyucheng Yizhu Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Lyucheng Yizhu Technology Co ltd filed Critical Beijing Lyucheng Yizhu Technology Co ltd
Priority to CN201920616704.XU priority Critical patent/CN211114238U/en
Application granted granted Critical
Publication of CN211114238U publication Critical patent/CN211114238U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Installation Of Indoor Wiring (AREA)

Abstract

The utility model relates to a partition wall exempts from buried tub of wiring system in advance, which comprises a wall body, box body and fossil fragments, the wall body includes interior template component and the layer of plastering, interior template component both sides all are equipped with the layer of plastering, interior template component is equipped with a plurality of passageways, the box body is installed on interior template component, be equipped with the line hole that link up mutually with the passageway on the box body, distance between two arbitrary adjacent passageways equals, the upper portion and the lower part of interior template component all are equipped with fossil fragments, fossil fragments include a rectangular cylinder, a plurality of holes are equipped with in a side that is close to interior template component to the rectangular cylinder, distance between two arbitrary adjacent holes equals with distance between two arbitrary adjacent passageways, the both edges perpendicular to side of side is. The utility model has the advantages that: the manufacture is simple, and the installation is convenient; the traditional construction method is changed, so that the construction efficiency is greatly improved, and the construction safety is ensured; the application is wide, and the construction cost is reduced.

Description

Partition wall exempts from buried tub of wiring system in advance
Technical Field
The utility model relates to a building engineering field particularly, relates to a pre-buried tub of wiring system is exempted from to partition wall.
Background
The existing majority of houses need to pre-embed pipelines in the process of installing a wiring system, and are usually laid on a blank house according to a construction drawing, so that the construction is troublesome, and the re-laying is quite troublesome when the second addition or the re-routing is carried out. The existing wiring system is inconvenient to install, high in construction price, long in construction period and very time-wasting; in the secondary decoration process, most lines are laid again, and the assembly and disassembly are time-consuming and labor-consuming, which inevitably causes huge waste; when the residential user refits the electrical system, the safety and the reliability of laying the electrical circuit can not be ensured, and simultaneously, higher requirements are provided for the influence of civil engineering.
An effective solution to the problems in the related art has not been proposed yet.
SUMMERY OF THE UTILITY MODEL
To the above-mentioned technical problem among the correlation technique, the utility model aims at providing a pre-buried tub of wiring system is exempted from to partition wall overcomes not enough among the prior art.
The utility model aims at realizing through the following technical scheme: the utility model provides a pre-buried tub of wiring system is exempted from to partition wall, includes wall body, box body and fossil fragments, the wall body includes interior template component and the surface course of plastering, interior template component both sides all are equipped with the surface course of plastering, interior template component is equipped with a plurality of passageways, the box body install in on the interior template component, be equipped with on the box body with the line hole that the passageway link up mutually, arbitrary adjacent two distance between the passageway equals, the upper portion and the lower part of interior template component all are equipped with fossil fragments, fossil fragments include a rectangular cylinder, rectangular cylinder is being close to a side of interior template component is equipped with a plurality of holes, arbitrary adjacent two distance between the hole and arbitrary adjacent two distance between the passageway equals, the both sides perpendicular to of side the side is provided with the fixed plate.
Furthermore, the inner formwork component and the plastering layer are directly provided with a galvanized net.
Furthermore, the inner formwork assembly comprises two layers of inner formworks, and the two layers of inner formworks are fixed through bolts.
Further, the box body includes the box body, the box body is equipped with an opening face, all be provided with the wing limit perpendicularly around the box body.
Further, the distance between the wing edge and the opening surface is 20 mm.
A construction method of a partition wall pre-buried pipe-free wiring system comprises the following steps:
s1, paying off: paying off after the structural wall and the ground base layer are cleaned, firstly finding the center line of the wall during paying off, then bouncing the wall line at the two sides of the center line, and leading the wall line to the ceiling;
s2, keel installation: fixing keels on the ceiling and the ground;
s3, mounting an inner template: the inner formworks are installed after the ceiling keel is installed and accepted, when the inner formworks in each block are assembled, the inner formworks are firmly inserted, a closed pipeline space is formed after the PVC inner formworks are formed, the fire resistance limit of the PVC inner formworks is more than or equal to 2 hours, the inner wall of the PVC inner formworks is basically smooth, the standard requirements of a wire pipe and a wire groove are completely met, and the PVC inner formworks can replace the functions of a wire pipe and a wire groove;
s4, connection of strip lines: when the inner template is installed, adjusting the module position of the inner template to enable the channel to correspond to the top plate and the ground keel hole, threading the strip line, and rolling and fixing the strip line;
s5, mounting of the box body: the inner template is provided with a line and is provided with a hole properly, the box body is fixed on the inner template by bolts, and the strip line is drawn out from the pipeline space of the wall body and is fixed in the box body;
s6, laying a steel net: after the internal mold and the box body are installed, a galvanized net is laid after the internal mold and the box body are qualified through inspection, a spring fastener is adopted, a pull rod is used for fixing, and a hole position is reserved in the box body;
and S7, finishing mortar plastering after the galvanized steel net is laid.
Further, the distance between the fixing points of the top keel and the bottom keel in the step S2 is not more than 500 mm.
Further, step S3 the door and window entrance to a cave both sides need to lead to long to set up U type metal tank and consolidate when the inner formword is installed to reliably be fixed with smallpox, ground.
The utility model has the advantages that: the manufacture is simple, and the installation is convenient; the traditional construction method is changed, so that the construction efficiency is greatly improved, and the construction safety is ensured; the application is wide, the construction cost is reduced, and the damage to the wall body caused by slotting is avoided; the pipe distribution is avoided, and the material is saved; the common quality fault of secondary masonry wall body repairing cracking is avoided, and the common quality fault of secondary masonry wall body repairing cracking is avoided; the construction speed is high, and the integrity is good; the space of the pipeline is small in wire section occupation ratio and large in space, so that heat dissipation is facilitated, and the probability of electrical fire is effectively reduced; the box body is specially designed to be pre-embedded, so that the common problems of irregular arrangement and irregular size caused by easy displacement of a common pre-embedded box are solved; the maintenance is simple and quick; the secondary transformation and displacement are simple, the wall body does not need to be damaged too much, and the groove does not need to be formed.
Drawings
The present invention will be described in further detail with reference to the accompanying drawings.
Fig. 1 is a schematic structural view of a partition wall pre-buried pipe-free wiring system according to an embodiment of the present invention;
fig. 2 is a cross-sectional view of a partition wall pre-buried pipe-free wiring system according to an embodiment of the present invention;
FIG. 3 is an enlarged view of A in FIG. 2;
fig. 4 is a schematic view of a keel structure of a partition wall pre-buried pipe-free wiring system according to an embodiment of the present invention;
fig. 5 is a schematic structural diagram of a box body of a partition wall pre-buried pipe-free wiring system according to an embodiment of the present invention.
In the figure: 1. a keel; 2. an inner template; 3. a box body; 4. a rectangular cylinder; 5. a hole; 6. a fixing plate; 7. a galvanized net; 8. coating a surface layer; 9. an open face; 10. and (4) wing edges.
Detailed Description
Example 1
As shown in fig. 1-5, a partition wall pre-buried pipe-free wiring system comprises a wall body, a box body 3 and a keel 1, the wall body comprises an inner formwork component and a rendering coat 8, the rendering coat 8 is arranged on both sides of the inner formwork component, the inner template component is provided with a plurality of channels, the box body 3 is arranged on the inner template component, the box body 3 is provided with a line hole communicated with the channels, the distance between any two adjacent channels is equal, keels 1 are arranged on the upper portion and the lower portion of the inner formwork component, each keel 1 comprises a rectangular column 4, a plurality of holes 5 are formed in one side face, close to the inner formwork component, of the rectangular cylinder 4, the distance between any two adjacent holes 5 is equal to the distance between any two adjacent channels, and two edges of the side face are perpendicular to the side face and provided with fixing plates 6.
In a specific embodiment, the inner formwork component and the rendering coat 8 are directly provided with a galvanized mesh 7.
In a specific embodiment, the inner formwork assembly comprises two layers of inner formworks 2, and the two layers of inner formworks 2 are fixed through bolts.
In one embodiment, the box 3 comprises a box body, the box body is provided with an opening surface 9, and the periphery of the box body is vertically provided with a wing edge 10.
In a specific embodiment, the distance between the wing edge 10 and the opening face 9 is 20 mm.
The embodiment of the utility model provides a partition wall exempt from buried tub of wiring system's construction method in advance, the operating procedure as follows:
1. paying off: paying off after the structural wall and the ground base layer are cleaned, firstly finding the center line of the wall during paying off, then bouncing the wall line at the two sides of the center line and leading to a ceiling, wherein the paying off allowable error is plus 2 mm;
2. installing a ceiling keel 1: fixing the ceiling keel and the ground keel on the ceiling and the ground, wherein the distance between fixing points is not more than 500 mm; the joint with other wall bodies is firstly treated by a base layer, and the treatment is preferably carried out in the range of 300mm on each side of the central line;
3. and (3) installing an inner template 2: installing an internal mold section after the installation of the top and bottom keels is finished and the installation is qualified, wherein the error of the internal mold section during cutting is not more than 8 mm; when each block of the model material is assembled, the model material is firmly inserted and fixed without loosening; the two sides of the door and window opening need to be reinforced by U-shaped metal grooves which are arranged throughout and are reliably fixed with the ceiling and the ground;
4. connecting the strip lines: when the inner template 2 is installed, the modulus position of the inner template 2 is properly adjusted, so that the inner hole of the inner template basically corresponds to the top plate and the ground pipe, the strip line is threaded, and the strip line is coiled and fixed in a wall surface wire box or a distribution box;
5. installation of the switch socket box body 3: the inner template 2 is provided with a line in a bouncing way and is provided with a hole properly, the customized line box is fixed on the inner template through the line box wing edge 10 by bolts, meanwhile, the belt line is drawn out from the pipeline space of the wall body and is fixed in the box body 3, and the steel wire mesh outside the wing edge 10 is covered with a layer of plastering convenience;
6. installation of distribution box body: the inner template 2 is provided with a line and a hole, and the distribution box is fixed on the inner template 2 by bolts and the like; simultaneously, all the strip lines are drawn out from the pipeline space of the wall body and fixed in the box; if the thickness of the switch box embedded in the wall is more than 100mm, the box body is leveled with the surface of the internal mold during installation;
7. laying a steel mesh: after the inner template and the pipeline are installed, the galvanized net 7 is fully paved after the inner template and the pipeline are tested to be qualified, a spring fastener is adopted, and a pull rod is used for fixing, so that the paving flatness and firmness are ensured; if a switch box and the like are met, reserving a hole position;
8. smearing: after the galvanized steel mesh is laid, plastering or spraying M10 ready-mixed mortar on the surface layer 8 with the thickness of 20 mm; and (5) smearing in layers to form a closed pipeline space passage.
In conclusion, with the adoption of the technical scheme of the utility model, the manufacture is simple, and the installation is convenient; the traditional construction method is changed, so that the construction efficiency is greatly improved, and the construction safety is ensured; the application is wide, the construction cost is reduced, and the damage to the wall body caused by slotting is avoided; the pipe distribution is avoided, and the material is saved; the common quality fault of secondary masonry wall body repairing cracking is avoided, and the common quality fault of secondary masonry wall body repairing cracking is avoided; the construction speed is high, and the integrity is good; the space of the pipeline is small in wire section occupation ratio and large in space, so that heat dissipation is facilitated, and the probability of electrical fire is effectively reduced; the box body is specially designed to be pre-embedded, so that the common problems of irregular arrangement and irregular size caused by easy displacement of a common pre-embedded box are solved; the maintenance is simple and quick; the secondary transformation and displacement are simple, the wall body does not need to be damaged too much, and the groove does not need to be formed.
The present invention is not limited to the above-mentioned preferred embodiments, and any other products in various forms can be obtained by the teaching of the present invention, but any changes in the shape or structure thereof, which have the same or similar technical solutions as the present invention, fall within the protection scope of the present invention.

Claims (5)

1. The utility model provides a pre-buried tub of wiring system is exempted from to partition wall which characterized in that: comprises a wall body, a box body (3) and a keel (1), wherein the wall body comprises an internal formwork component and a plastering layer (8), the two sides of the inner template component are both provided with the plastering layers (8), the inner template component is provided with a plurality of channels, the box body (3) is arranged on the inner die plate component, a wire hole communicated with the channel is arranged on the box body (3), the distance between any two adjacent channels is equal, keels (1) are arranged on the upper portion and the lower portion of the inner formwork component, each keel (1) comprises a rectangular cylinder (4), a plurality of holes (5) are formed in one side face, close to the inner formwork component, of the rectangular cylinder body (4), the distance between any two adjacent holes (5) is equal to the distance between any two adjacent channels, and two edges of the side face are perpendicular to the side face and provided with fixing plates (6).
2. The pre-buried pipe wiring system is exempted from to partition wall of claim 1, its characterized in that: the inner formwork component and the plastering layer (8) are directly provided with a galvanized net (7).
3. The pre-buried pipe wiring system is exempted from to partition wall of claim 1, its characterized in that: the inner formwork component comprises two layers of inner formworks (2), and the two layers of inner formworks (2) are fixed through bolts.
4. The pre-buried pipe wiring system is exempted from to partition wall of claim 1, its characterized in that: the box body (3) comprises a box body, the box body is provided with an opening face (9), and the periphery of the box body is vertically provided with wing edges (10).
5. The pre-buried pipe wiring system of claim 4, wherein: the distance between the wing edge (10) and the opening surface (9) is 20 mm.
CN201920616704.XU 2019-04-30 2019-04-30 Partition wall exempts from buried tub of wiring system in advance Active CN211114238U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920616704.XU CN211114238U (en) 2019-04-30 2019-04-30 Partition wall exempts from buried tub of wiring system in advance

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920616704.XU CN211114238U (en) 2019-04-30 2019-04-30 Partition wall exempts from buried tub of wiring system in advance

Publications (1)

Publication Number Publication Date
CN211114238U true CN211114238U (en) 2020-07-28

Family

ID=71701078

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920616704.XU Active CN211114238U (en) 2019-04-30 2019-04-30 Partition wall exempts from buried tub of wiring system in advance

Country Status (1)

Country Link
CN (1) CN211114238U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110016982A (en) * 2019-04-30 2019-07-16 北京绿城易筑科技有限公司 A kind of partition wall exempts from built-in pipe wiring system and its construction method
CN115450372A (en) * 2022-08-12 2022-12-09 中国电建集团贵阳勘测设计研究院有限公司 A wire casing for assembly type structure

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110016982A (en) * 2019-04-30 2019-07-16 北京绿城易筑科技有限公司 A kind of partition wall exempts from built-in pipe wiring system and its construction method
CN115450372A (en) * 2022-08-12 2022-12-09 中国电建集团贵阳勘测设计研究院有限公司 A wire casing for assembly type structure
CN115450372B (en) * 2022-08-12 2023-10-03 中国电建集团贵阳勘测设计研究院有限公司 Wire slot for assembled building

Similar Documents

Publication Publication Date Title
CN104032925B (en) CSI house wall ground Stilt layer construction method
CN211114238U (en) Partition wall exempts from buried tub of wiring system in advance
US20140000192A1 (en) Wall assembly for a building structure
CN110016982A (en) A kind of partition wall exempts from built-in pipe wiring system and its construction method
CN110612373A (en) Prefabricated pre-decorated volume construction of buildings
CN109469220B (en) Heat-insulation external wall and building construction process thereof
CN210486028U (en) Static pressure box structure below grandstand ladder
CN208803681U (en) Piping shaft and building structure
CN218374567U (en) Can fix a position ALC wallboard reinforced structure that can exempt from to plaster
CN110805185A (en) Installation method of large-span curved surface special-shaped stone curtain wall
CN116104224A (en) External wall heat insulation integrated gap spliced construction node and construction method
CN106939699B (en) Construction method for galvanized steel sheet waterproof layer on inner side of open type ceramic plate curtain wall
CN110645696A (en) Heating and ventilation static pressure box structure and construction method thereof
CN208330029U (en) A kind of fixed device of prefabricated aluminum window
CN110607874A (en) Large-area inclined plane perforation gypsum board suspended ceiling falling-level molding installation structure
CN216406197U (en) Steel sleeve for electrical trough box penetrating floor
CN206800635U (en) A kind of big plate prefabricated buildings
CN217379531U (en) Adjustable theme park complex tile-hanging sloping roof system based on BIM technology
CN217601782U (en) Anti structure of splitting of indoor large-scale abnormal shape light gauge steel wall body
CN103998694A (en) Insulated wall module
JP7366475B1 (en) How to form a heat insulation layer
CN216344297U (en) Pipeline node tee junction spare
CN216340576U (en) Pipeline node connecting piece apron
CN219386795U (en) Waterproof dry-hanging system of open curtain wall
CN115059218A (en) Indoor large-scale special-shaped light steel keel wall anti-cracking structure and construction method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant