Anti water impact blasting structure of high-pressure water-rich section of tunnel engineering Download PDF

Info

Publication number
CN211012690U
CN211012690U CN201921677180.1U CN201921677180U CN211012690U CN 211012690 U CN211012690 U CN 211012690U CN 201921677180 U CN201921677180 U CN 201921677180U CN 211012690 U CN211012690 U CN 211012690U
Authority
CN
China
Prior art keywords
blasting
charge tube
big gun
gun hole
big
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201921677180.1U
Other languages
Chinese (zh)
Inventor
赵春杰
赵宇
高明成
沈家君
全斐
李翔翔
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 10 Engineering Group Co Ltd
Original Assignee
China Railway No 10 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 10 Engineering Group Co Ltd filed Critical China Railway No 10 Engineering Group Co Ltd
Priority to CN201921677180.1U priority Critical patent/CN211012690U/en
Application granted granted Critical
Publication of CN211012690U publication Critical patent/CN211012690U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Drilling And Exploitation, And Mining Machines And Methods (AREA)

Abstract

The utility model discloses an anti water impact blasting structure of rich water section of tunnel engineering high pressure belongs to tunnel construction technical field. It includes the big gun hole of boring at the position of waiting to explode, characterized by: be provided with charging means in the big gun hole, charging means includes the charge tube of PVC material, the tail end of charge tube is sealed, the head end of charge tube is open structure, the head end front end of charge tube is connected with the device that blocks up, the device that blocks up is big-mouth outwards horn mouth form, the device that blocks up with the big gun hole mouth inner wall in big gun hole hugs closely together, the charge tube is filled with a plurality of cartridges for the blasting, and the millisecond detonator for the blasting is drawn forth outside the tubes from the charge tube. The utility model discloses fine solution tunnel engineering high pressure rich water section bore that exists explode the degree of difficulty big, the big gun hole interior volume of a powder receives the water impact easily to appear the off normal, rush out the big gun hole scheduling problem, can fine reach the blasting effect, and its construction easy operation, the efficiency of construction is high.

Description

Anti water impact blasting structure of high-pressure water-rich section of tunnel engineering
Technical Field
The utility model relates to a blasting structure, especially a blasting structure that is used for anti water impact of rich water section of tunnel engineering high pressure belongs to tunnel construction technical field.
Background
In recent years, with the large-scale construction of public facilities, the construction of underground tunnel engineering is required in many fields, and the underground tunnel engineering construction often encounters an area with abnormally complicated geology. The most common excavation method of the tunnel engineering is still a drilling and blasting method at present, and has the obvious advantages of simple construction process, flexible application and reasonable manufacturing cost.
The construction of tunnel engineering is closely related to geological conditions, particularly the construction of high-pressure water-rich section tunnel engineering with development of underground water and great burial depth and high pressure, the underground water has great softening influence on surrounding rocks and structural surfaces, the loading difficulty of drilling and blasting construction is great, the explosive rolls in blast holes are easy to deviate and punch out of the holes under the impact of high-pressure water flow, the explosive rolls in the blast holes are not completely positioned at the bottoms of the holes, the undermining effect is influenced, the peripheral holes are not loaded at intervals, the overbreak is obvious, and the like, so that the blasting effect is not ideal.
Disclosure of Invention
To the above-mentioned defect that exists among the prior art, the utility model provides a tunnel engineering high pressure rich water section anti water impact blasting structure that the construction is simple, not shift is strikeed by the rivers.
The utility model discloses a realize through following technical scheme: the utility model provides an anti water impact blasting structure of rich water section of tunnel engineering high pressure, includes and drills the big gun hole of establishing, characterized by in treating the blasting position: be provided with charging means in the big gun hole, charging means includes the charge tube of PVC material, the tail end of charge tube is sealed, the head end of charge tube is open structure, the head end front end of charge tube is connected with the device that blocks up, the device that blocks up is big-mouth outwards horn mouth form, the device that blocks up with the big gun hole mouth inner wall in big gun hole hugs closely together, the charge tube is filled with a plurality of cartridges for the blasting, and the millisecond detonator for the blasting is drawn forth outside the tubes from the charge tube.
The utility model discloses in, the cartridge is packed into the intraductal corresponding position of powder charge, and the tight device of stopper through powder charge tube head end makes it fixed firm with the big gun hole mouth, can avoid the downthehole rivers of big gun to dash out the powder charge, and the cartridge in the powder charge pipe does not receive the rivers impact influence, and the skew can not take place for the cartridge position, can reach anticipated blasting effect.
Furthermore, the charging tube and the plugging device are integrated into a whole.
The utility model has the advantages that: the utility model discloses simple structure, the preparation is convenient, low cost. The utility model discloses an adopt the charge tube of special structural design as charge structure, its stopper tight device can be fixed firm with big gun hole mouth when installing in big gun hole, can avoid the downthehole rivers of big gun to go out the charge device, and the interior cartridge of charge tube does not receive the rivers impact influence, and the skew can not take place for the cartridge position, can reach anticipated blasting effect. The utility model discloses construction operation is simple, utilizes the utility model discloses during the construction, but the greatly reduced construction degree of difficulty can improve the efficiency of construction greatly.
Drawings
FIG. 1 is a schematic front view of the present invention in an embodiment;
FIG. 2 is a schematic structural view of a charge of the present invention;
in the figure, 1, a blast hole, 2, a charge tube, 3, a plugging device, 4, a millisecond detonator, 5 and a cartridge.
Detailed Description
The invention will now be further described by way of non-limiting examples with reference to the accompanying drawings:
as shown in the attached drawing, the anti-water impact blasting structure for the high-pressure water-rich section in tunnel engineering comprises a blast hole 1 drilled at a position to be blasted, wherein a charging device is arranged in the blast hole 1 and comprises a charging tube 2 made of PVC materials, the tail end of the charging tube 2 is sealed, the head end of the charging tube 2 is of an open structure, the front end of the head end of the charging tube 2 is connected with a plugging device 3, the plugging device 3 is in a horn mouth shape with a large opening facing outwards, the plugging device 3 is tightly attached to the inner wall of the blast hole 1, a plurality of blasting cartridges 5 are filled in the charging tube 2, and a blasting millisecond 4 is led out of the charging tube 2 to the outside.
The utility model provides a tight device 3 of stopper and charge pipe 2 can adopt the split type structure of linking together, for the processing preparation, preferably, charge pipe 2 with tight device 3 of stopper makes the structure as an organic whole.
Utilize the utility model discloses when boring the construction of exploding:
② measuring the drilling and hole distribution by accurately locating the positions of excavation contour line, peripheral eyes, auxiliary eyes and cut-out eyes on the working face with a total station;
③ explosive is installed, the explosive charging device of the utility model can be adopted wholly or partially according to the distribution of the high-pressure water-rich blast holes on the tunnel face, and the explosive charging device of the utility model is used for charging the underwater blast holes at the bottom of the tunnel;
according to blast hole types such as undercut hole, auxiliary hole, all edges of the hole, pack into explosive, millisecond detonator according to the explosive charging structure who bores and explodes the design the utility model provides a charging device, millisecond detonator or detonating cord "take a seat in opposite sign";
after confirming that the depth of the blast hole meets the drilling and blasting requirements, directly loading explosive loading devices loaded with explosives, detonators or detonating cords into the corresponding blast hole, and tightly attaching the explosive loading devices to the blast hole by using the plugging device 3 of the explosive loading tube 2 to prevent water flow in the blast hole from rushing out the explosive loading devices;
④, detonating and effect checking, wherein a blasting operator uses a blasting machine to detonate at a safe explosion avoiding point, the blasting effect is checked after blasting, the blasting effects such as over-short excavation, footage and the like are mainly checked, and the drilling and blasting design is continuously optimized.
The utility model discloses every circulation charging time of more conventional blasting shortens 20 minutes, and reducible blind big gun is handled simultaneously, the owe digs mends the influence of big gun time to the work efficiency, can improve the efficiency of construction greatly.
The utility model discloses fine solution tunnel engineering high pressure rich water section bore that exists explode the degree of difficulty big, the big gun hole interior volume of a powder receives the water impact and easily appears the off normal, rush out the big gun hole scheduling problem, can fine reach the blasting effect, and its construction easy operation, the efficiency of construction is high, is favorable to the reduction of erection time.
Other parts in this embodiment are the prior art, and are not described herein again.

Claims (2)

1. The utility model provides an anti water impact blasting structure of rich water section of tunnel engineering high pressure, includes and drills the big gun hole of establishing, characterized by in treating the blasting position: be provided with charging means in the big gun hole, charging means includes charge tube (2) of PVC material, the tail end of charge tube (2) is sealed, the head end of charge tube (2) is open structure, the head end front end of charge tube (2) is connected with and is filled tight device (3), it is big mouthful of horn mouth form outwards to fill tight device (3), fill tight device (3) with the big gun hole mouth inner wall in big gun hole is hugged closely together, be filled with a plurality of explosive rolls for the blasting in charge tube (2), the millisecond detonator that the blasting was used is drawn forth to the outside of tubes in charge tube (2).
2. The anti-water flow impact blasting structure of the high-pressure water-rich section in the tunnel engineering according to claim 1, which is characterized in that: the medicine loading pipe (2) and the plugging device (3) are of an integrated structure.
CN201921677180.1U 2019-10-09 2019-10-09 Anti water impact blasting structure of high-pressure water-rich section of tunnel engineering Expired - Fee Related CN211012690U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921677180.1U CN211012690U (en) 2019-10-09 2019-10-09 Anti water impact blasting structure of high-pressure water-rich section of tunnel engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921677180.1U CN211012690U (en) 2019-10-09 2019-10-09 Anti water impact blasting structure of high-pressure water-rich section of tunnel engineering

Publications (1)

Publication Number Publication Date
CN211012690U true CN211012690U (en) 2020-07-14

Family

ID=71480463

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921677180.1U Expired - Fee Related CN211012690U (en) 2019-10-09 2019-10-09 Anti water impact blasting structure of high-pressure water-rich section of tunnel engineering

Country Status (1)

Country Link
CN (1) CN211012690U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114777593A (en) * 2022-05-16 2022-07-22 中铁二十局集团有限公司 Tunnel blast hole charging device and method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114777593A (en) * 2022-05-16 2022-07-22 中铁二十局集团有限公司 Tunnel blast hole charging device and method
CN114777593B (en) * 2022-05-16 2023-04-28 中铁二十局集团有限公司 Tunnel blast hole charging device and method

Similar Documents

Publication Publication Date Title
CN101614134B (en) Drilling-explosion-pumping triadic pressure-relief outburst-prevention method
CN104819670B (en) Pre-drilling mesopore shaft excavation blasting method
CN102878876A (en) Mine roadway advancing and undermining method and main blasting parameters
CN102997766B (en) Deep-hole pressure-relief blasting method
CN101338999A (en) Method for blasting seepage enhancement for low infiltration sandrock -type uranium deposit
CN103206903A (en) Hard roof directional pressure-bearing blasting control method
CN103148748A (en) Pressure-adjustable expansion plastic pipe deep hole blasting control method
CN108798669B (en) Deep hole loosening hydraulic pressure relief integrated blasting method and device
CN203362135U (en) Perforating device improving gas permeability of coal beds
CN104405434A (en) Hypotonic coal seam region mineshaft gas phase fracturing and rapid coal uncovering method and hypotonic coal seam region mineshaft gas phase fracturing and rapid coal uncovering device
CN111456801B (en) Method for permeability-increasing coal seam in drilling holes in top plate and bottom plate of coal seam
CN111521069A (en) Carbon dioxide phase change directional pressure relief fracturing device for tunneling and use method thereof
CN211012690U (en) Anti water impact blasting structure of high-pressure water-rich section of tunnel engineering
CN102817633A (en) Device for draining gas by deep hole crack control blasting and precracking method
CN201074990Y (en) Shooting blast hole sleeve
CN108801086A (en) Deep hole loosens stress pre-released hydraulically blasting method and device
CN106121644B (en) The water-filling pressure-bearing unloading pressure by blasting of cellular structure and supporting reinforcement are crosslinked based on drilling in coal and rock plane
CN103743304B (en) Demolition set
US3063373A (en) Method of blasting
CN102927863B (en) A kind of new method of total rock tunnel blasting construction
CN110243244A (en) It is a kind of based on Detonation waveform modulation circumferential slit without cavity liner air gap CUMULATIVE BLASTING loading method
CN204754894U (en) Module perforation for rifle efflux energization pass and to explode device
CN108731560B (en) Blasting structure of high-efficient blasting unit
CN112611276A (en) Deep hole sectional blasting method
CN104806210A (en) Jet flow energization explosion-propagating device for module perforating gun and application method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200714

Termination date: 20211009

CF01 Termination of patent right due to non-payment of annual fee