CN210918893U - Drill bit for rapidly repairing wall of pile hole - Google Patents

Drill bit for rapidly repairing wall of pile hole Download PDF

Info

Publication number
CN210918893U
CN210918893U CN201922117639.9U CN201922117639U CN210918893U CN 210918893 U CN210918893 U CN 210918893U CN 201922117639 U CN201922117639 U CN 201922117639U CN 210918893 U CN210918893 U CN 210918893U
Authority
CN
China
Prior art keywords
hole
drill
drill bit
pile hole
drill body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201922117639.9U
Other languages
Chinese (zh)
Inventor
张云健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201922117639.9U priority Critical patent/CN210918893U/en
Application granted granted Critical
Publication of CN210918893U publication Critical patent/CN210918893U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Earth Drilling (AREA)

Abstract

The utility model belongs to the technical field of the civil engineering, specifically provide a be used for quick prosthetic drill bit of stake hole pore wall, it is including boring the body, it is the cylinder to bore the body, hold including first end and second, it is connected with an interface end to bore the first end of the body, the second end of boring the body is a cone, the shape of interface end is a square cylinder, be equipped with a plurality of pinholes on the square cylinder. Through the utility model provides a drill body comes to extrude the filler material of the hole pore wall that collapses in current stake hole to realize the rapid processing at the hole position that collapses in the hole body, improved site operation efficiency greatly, simultaneously owing to do not need whole pouring concrete, also reduced the cost of the hole measures of collapsing.

Description

Drill bit for rapidly repairing wall of pile hole
Technical Field
The utility model relates to a civil engineering pile foundation engineering construction equipment technical field especially relates to a drill bit that is used for quick restoration of stake hole pore wall.
Background
When the rotary drilling bit is used for operation, due to different construction geological conditions, the cave body is often collapsed. For example, as shown in fig. 1, after a mechanical rotary drilling construction hole is dug to a certain depth, the hole wall collapses. The existing solution is to pour concrete or treat the steel casing wall protection into the hole, and when the concrete is filled, the rotary drilling bit is used to dig the drill again after the concrete reaches a certain strength. The method not only increases the working hours of construction, but also wastes a large amount of concrete. The method of adopting the steel casing to protect the wall also greatly increases the construction cost. Therefore, it is desirable for those skilled in the art to improve the efficiency of the pile hole collapse construction process and reduce the process cost.
SUMMERY OF THE UTILITY MODEL
Technical purpose
The method is used for solving the problems of low treatment efficiency and high cost of the cave collapse part when the cave collapse occurs in the construction process of the conventional rotary excavating construction process.
Technical scheme
The drill bit comprises a drill body, wherein the drill body is a cylinder and comprises a first end and a second end, the first end of the drill body is connected with an interface end, the second end of the drill body is a cone, the interface end is in a square cylinder shape, and a plurality of pin holes are formed in the square cylinder.
The stake hole that appears the cavern body collapse generally divide into the dry hole that the hole water content is less and the great wet hole of hole water content, and above-mentioned technical scheme carries out quick prosthetic technological principle to the stake hole and does: when the body of the hole collapses, the first condition is when the construction hole is dry hole, only need through filling 5 to the hole: 5's soil stone mixture later bores the body rotation operation downwards that this technical scheme provided to it is closely knit to extrude the space that soil stone mixture extruded to collapse fast, later can continue to use to dig soon and bore a section of thick bamboo and carry out the operation, has greatly improved the efficiency of construction. The second condition is that when the water content of the construction hole is larger, only concrete exceeding the collapse position needs to be poured into the hole body, and then 5 parts of 2.5 meters are filled into the hole body: 5, then carry out the operation in the hole through the brill body that this technical scheme provided to utilize the earth-rock mixture that later fills to extrude the concrete to the space that collapses fast in, the earth-rock mixture extrudees down to the position that collapses and stops the operation (at this moment the earth-rock mixture is downthehole, the concrete is extruded to the pore wall), makes the concrete fill to pore wall and the position that collapses all around, furthest utilizes the concrete to pore wall and position that collapses, after the concrete reaches certain intensity, can continue to use and dig a drill section of thick bamboo and carry out the operation soon, because the downthehole concrete mixture that is filled, the pore wall that is filled is the concrete, the measure cost of construction treatment has been reduced.
Technical effects
As described above, through the utility model provides a drilling tool comes to extrude the material of current pore wall to realize the pore wall processing of the body in a cave, improved site operation efficiency greatly, simultaneously because downthehole packing be the soil stone mixture, the concrete is crowded to the pore wall by the soil stone mixture, has also reduced the cost of handling.
Drawings
Fig. 1 is a schematic diagram illustrating collapse of a hole dug by a conventional rotary drill bit.
Fig. 2 shows a schematic structural diagram of a drill bit for rapidly repairing a pile hole wall according to the present invention.
Fig. 3 shows a cross-sectional view of the drill bit for rapidly repairing the wall of the pile hole.
Detailed Description
Example 1
Referring to fig. 2, a drill 3 for quickly repairing a wall of a pile hole is provided, which includes a drill body 31, wherein the drill body 31 is a cylinder and includes a first end and a second end, the first end of the drill body 31 is connected with a joint end 32, the second end of the drill body is a cone, the joint end 32 is a square cylinder, and a plurality of pin holes are formed in the square cylinder.
Specifically, referring to fig. 3, two pairs of pin holes are vertically arranged in parallel on a first diagonal surface of the square column on which the interface end 32 is located, and a pair of pin holes are vertically arranged in parallel on a second diagonal surface of the square column on which the interface end 32 is located.
Specifically, the peripheries of the square columns are respectively connected with a reinforcing plate 33 connected with the first end of the drill body 31, wherein the reinforcing plate is a triangular steel plate. The reinforcing plate 33 may increase the rigidity of the connection between the drill body 31 and the interface end 32 during rotation.
Specifically, referring to fig. 3, a cone on the first end of the drill body 31 and a cylinder on which the drill body is located are integrally connected, and the drill body 31 and the cone are both hollow structures.
Specifically, the drill body 31 and the interface end 32 are both made of steel.

Claims (7)

1. The utility model provides a drill bit for quick restoration of stake hole pore wall which includes the brill body, its characterized in that:
the drill body is a cylinder and comprises a first end and a second end, the first end of the drill body is connected with an interface end, the second end of the drill body is a cone, the interface end is in a square column shape, and a plurality of pin holes are formed in the square column.
2. The drill bit for the rapid repair of a pile hole wall according to claim 1, wherein: the periphery of the square column body is respectively connected with a reinforcing plate connected with the first end of the drill body.
3. The drill bit for the rapid repair of a pile hole wall according to claim 2, wherein: the reinforcing plate is a triangular steel plate.
4. The drill bit for the rapid repair of a pile hole wall according to claim 1, wherein: two pairs of pin holes are vertically arranged in parallel on a first diagonal surface of the square column body where the interface end is located, and a pair of pin holes are vertically arranged in parallel on a second diagonal surface of the square column body where the interface end is located.
5. The drill bit for the rapid repair of a pile hole wall according to claim 1, wherein: the cone on the first end of the drill body is integrally connected with the cylinder on which the drill body is arranged.
6. The drill bit for the rapid repair of a pile hole wall according to claim 5, wherein: the drill body and the cone are both of hollow structures.
7. The drill bit for the rapid repair of a pile hole wall according to claim 1, wherein: the drill body and the interface end are both made of steel.
CN201922117639.9U 2019-12-02 2019-12-02 Drill bit for rapidly repairing wall of pile hole Expired - Fee Related CN210918893U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201922117639.9U CN210918893U (en) 2019-12-02 2019-12-02 Drill bit for rapidly repairing wall of pile hole

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201922117639.9U CN210918893U (en) 2019-12-02 2019-12-02 Drill bit for rapidly repairing wall of pile hole

Publications (1)

Publication Number Publication Date
CN210918893U true CN210918893U (en) 2020-07-03

Family

ID=71346634

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201922117639.9U Expired - Fee Related CN210918893U (en) 2019-12-02 2019-12-02 Drill bit for rapidly repairing wall of pile hole

Country Status (1)

Country Link
CN (1) CN210918893U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111962507A (en) * 2020-08-20 2020-11-20 中交一公局集团有限公司 Pile foundation hole forming method
CN114233178A (en) * 2021-12-15 2022-03-25 山东方大工程有限责任公司 Rotary excavating machine drill bit for coal mine ground engineering construction

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111962507A (en) * 2020-08-20 2020-11-20 中交一公局集团有限公司 Pile foundation hole forming method
CN114233178A (en) * 2021-12-15 2022-03-25 山东方大工程有限责任公司 Rotary excavating machine drill bit for coal mine ground engineering construction

Similar Documents

Publication Publication Date Title
CN110206493B (en) Construction process of full-sleeve full-rotation bored pile
CN101812976B (en) Adjustable multiple coil extruding and expanding drilling tool
CN204370414U (en) Steel casing for drilling concrete cast-in-place pile and drilling device
CN104988907A (en) Construction method of concrete pile
CN106351585A (en) Hole collapse and shrinkage prevention bidirectional spiral extrusion and expansion drilling tool and construction technology thereof
CN103556628B (en) Spiral conical soil compaction pile construction method
CN210918893U (en) Drill bit for rapidly repairing wall of pile hole
CN104196044A (en) Cofferdam construction method combining impact drilling limiting hole forming and groove milling with steel sheet piles
CN105133641A (en) Thin-wall continuous-wall-type foundation reinforcing structure and method
CN104563104A (en) Linkage type wall protecting device for pile driving drilling machine and construction method for using linkage type wall protecting device for pile driving drilling machine
CN108643166B (en) Construction method for weakening soil layer vibration of driven and pulled steel sheet pile
CN203129151U (en) Grouting head capable of drilling and grouting synchronously
CN214245694U (en) Pile forming system for large-diameter cast-in-situ bored pile in karst area
CN204608773U (en) Pile work drilling machine coordinated type breast wall apparatus
CN113668564A (en) Construction method for supporting and reinforcing open-cut underground passage adjacent to subway station
CN206752454U (en) One kind perfusion embedded pile
CN212052725U (en) Karst cave area stake construction structures
CN111962507A (en) Pile foundation hole forming method
CN204418167U (en) A kind of novel slurry filling pile body structure
CN207878472U (en) Solid matter step type rotary digging pile supporting system
CN110792077A (en) Supporting disc pile device suitable for muddy soft soil and construction process thereof
CN105887842A (en) Arc-locking crossed retaining pile manufacturing equipment
CN111485616B (en) Construction method for newly adding municipal inspection well to water-rich sand-pressed pebble layer
CN105625435B (en) Sea product island multi-section, multi-level special-shaped equipment deep basal pit quick molding method
CN111778969A (en) Double-sleeve type full-rotation super-long pile construction tool and construction method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200703

Termination date: 20201202