CN210829393U - Subway secretly digs station and prevents drainage structure - Google Patents
Subway secretly digs station and prevents drainage structure Download PDFInfo
- Publication number
- CN210829393U CN210829393U CN201921874081.2U CN201921874081U CN210829393U CN 210829393 U CN210829393 U CN 210829393U CN 201921874081 U CN201921874081 U CN 201921874081U CN 210829393 U CN210829393 U CN 210829393U
- Authority
- CN
- China
- Prior art keywords
- concrete layer
- base
- layer
- subway
- water
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Revetment (AREA)
Abstract
The utility model discloses a subway subsurface excavated station waterproof and drainage structure, which comprises a concrete layer, wherein the concrete layer is provided with a water seepage hole, and the concrete layer is provided with a water baffle plate, and is characterized in that the water seepage hole on the concrete layer extends into the interior of a rock base layer, the water seepage hole is uniformly distributed at the middle lower side of the concrete layer, the concrete layer is uniformly provided with a connecting bolt, the water baffle plate is connected with the concrete layer through the connecting bolt, the connecting bolt is respectively provided with a first gasket and a second gasket at the two sides of the water baffle plate, the water baffle plate is hermetically connected with a base, the base is arranged on a main supporting column and an auxiliary supporting column, and a drainage pipe is arranged below the base, has the advantages of obvious waterproof effect and rapid drainage.
Description
Technical Field
The utility model relates to a tunnel drainage engineering field specifically is a subway secretly digs station and prevents drainage structure.
Background
In recent years, some cities develop rapidly, the population increases explosively, the ground traffic pressure of the cities is increased rapidly, and most cities begin to build subway rail traffic to relieve the ground traffic pressure, but the problems of traffic jam are caused by greenbelt migration, underground pipelines are rearranged, a basement stratum is deeper and the construction, so that the subway construction needs to basically place the main structure of a subway station in a hard rock stratum and adopt a subsurface excavation method for construction.
The construction of the underground excavation method needs to consider the water seepage problem of a tunnel structure, but underground water in a rock stratum is generally bedrock fracture water, although the water quantity is not large, the water head is higher, the existing method mostly adopts a full-package waterproof mode, namely a secondary lining and an inverted arch structure, and the seepage is easily caused at construction joints and deformation joints when the underground excavation method bears high water pressure for a long time.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a subway secretly digs station and prevents drainage structure to solve the problem that proposes among the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme:
the utility model provides a subway secretly digs station drainage structures, is including installing in the concrete layer of rock base layer, be provided with the infiltration hole on the concrete layer, install the breakwater on the concrete layer, its characterized in that, the infiltration hole on the concrete layer is deepened the inside of rock base layer, infiltration hole evenly distributed is at the well downside of concrete layer, evenly install connecting bolt on the concrete layer, the breakwater passes through connecting bolt and links to each other with the breakwater, breakwater and base sealing connection, the pedestal mounting is on main tributary dagger and vice support column.
Concrete layer laminating rock-based layer, with the firm contact of rock-based layer, and play effective support and fixed action, the infiltration hole is arranged in leading a small amount of infiltration in the rock-based layer, because the rock structure of rock-based layer makes the infiltration volume less, and the infiltration is easy to be collected toward crack and breach department under the extrusion of rock, the infiltration hole only need in the ground layer the downside evenly lay can, can effectively water conservancy diversion whole concrete layer's infiltration.
Further, connecting bolt is stud, stud one end links to each other with concrete layer, the stud other end is equipped with connecting thread, stud one end links to each other with the breakwater, connecting bolt's middle part is provided with the flange.
Specifically, one end of the stud bolt is of a screw structure, the stud bolt is installed in a mode of knocking and nailing into a concrete layer, and the other end of the stud bolt is provided with connecting threads, so that the stud bolt is convenient to install a water baffle in combination with a nut.
Furthermore, the flange is connected with the water baffle through a nut, a first gasket is arranged between the flange and the water baffle, and a second gasket is arranged between the nut and the water baffle.
Specifically, first gasket and second gasket are used for plugging up the bolt hole of cooperation connecting bolt on the baffle, further avoid the possibility of infiltration.
Furthermore, a drain pipe is arranged below the base and connected with a city pipe network.
Specifically, the drain pipe can in time discharge into city pipe network with the water of base below, avoids overstock volume too much to lead to the infiltration backward flow, and the general management water in the station also can be regarded as to the infiltration simultaneously.
Optionally, a waterproof layer is arranged on the inner side of the water baffle.
The waterproof layer can cover the water baffle plate while further preventing water, and simultaneously covers the connecting bolt and the nut, so that the inner wall is more attractive.
Compared with the prior art, the beneficial effects of the utility model are that: the utility model discloses a drain pipe of infiltration hole, connecting bolt, breakwater and base below on the concrete layer realizes the subway and secretly digs the waterproof and drainage water of station, has effectively solved the infiltration problem between rock-based layer and the concrete layer.
Drawings
Fig. 1 is a schematic structural view of a waterproof and drainage structure of a subway underground excavation station.
Fig. 2 is an enlarged view of a structure at a point a in a waterproof and drainage structure of a subway underground excavated station.
Fig. 3 is a schematic structural view of a connecting bolt in a waterproof and drainage structure of a subway underground excavation station.
In the figure: 1-rock base layer, 2-concrete layer, 3-water seepage hole, 4-connecting bolt, 40-flange, 41-first gasket, 42-second gasket, 420-connecting thread, 43-nut, 5-water baffle, 6-waterproof layer, 7-base, 8-main supporting column, 9-drain pipe and 10-auxiliary supporting column.
Detailed Description
In the description of the present invention, it is to be understood that the terms "upper", "lower", "front", "rear", "left", "right", "top", "bottom", "inner" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplicity of description, and do not indicate or imply that the device or element being referred to must have a particular orientation, be constructed and operated in a particular orientation, and therefore, should not be construed as limiting the present invention.
In the present invention, unless otherwise expressly stated or limited, the terms "mounted," "connected," and "fixed" are to be construed broadly and may, for example, be fixedly connected, detachably connected, or integrally formed; can be mechanically or electrically connected; either directly or indirectly through intervening media, either internally or in any other relationship. The specific meaning of the above terms in the present invention can be understood according to specific situations by those skilled in the art.
Furthermore, the terms "first", "second" and "first" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of that feature. In the description of the present invention, "a plurality" means two or more unless specifically limited otherwise.
The technical solution of the present patent will be described in further detail with reference to the following embodiments.
Example 1:
with reference to fig. 1-3, a subway secretly digs station waterproof drainage structure, including installing in the concrete layer 2 of rock base layer 1, be provided with infiltration hole 3 on the concrete layer 2, install breakwater 5 on the concrete layer 2, its characterized in that, infiltration hole 3 on the concrete layer 2 gos deep into the inside of rock base layer 1, infiltration hole 3 evenly distributed is at the well downside of concrete layer 2, evenly install connecting bolt 4 on the concrete layer 2, breakwater 5 passes through connecting bolt 4 and links to each other with breakwater 5, breakwater 5 and base 7 sealing connection, base 7 is installed on main tributary strut 8 and vice support column 10.
Connecting bolt 4 is stud, stud one end links to each other with concrete layer 2, the stud other end is equipped with connecting thread 420, stud one end links to each other with breakwater 5, connecting bolt 4's middle part is provided with flange 40.
The flange 40 is connected with the water baffle 5 through a nut 43, a first gasket 41 is arranged between the flange 40 and the water baffle 5, and a second gasket 42 is arranged between the nut 43 and the water baffle 5.
Further, a drain pipe 9 is arranged below the base 7, and the drain pipe 9 is connected with a city pipe network.
Specifically, the accumulated water in the rock base layer 1 enters between the concrete layer 2 and the water baffle 5 through the seepage holes 3 under the extrusion of the rock and the concrete layer 2 and then flows into the space below the base 7, the drainage pipe 9 is arranged in the base 7, and the water in the base 7 can be pumped into the drainage pipe 9 network by a water pump because the depth of a station is generally deeper than that of the urban drainage pipe 9 network.
Another way to deal with the overstocked water seepage is to primarily treat the water seepage and use the water seepage as water for management in stations, such as cleaning and sanitation.
Example 2: the embodiment is further improved and optimized on the basis of the embodiment 1.
Optionally, a waterproof layer 6 is arranged on the inner side of the water baffle 5.
The waterproof layer 6 is used for further waterproofing, and meanwhile, the waterproof layer 6 covering the water baffle 5 can cover the connecting bolt 4 and the nut 43, so that the inner wall is neater and more attractive.
When needing to be noticed: the utility model discloses an evenly lay infiltration hole 3, the infiltration of connecting bolt 4 water conservancy diversion infiltration on concrete layer 2, the infiltration of overstock is stored through the space that forms in the middle of base 7 and concrete layer 2, and through the drainage of drain pipe 9, the above-mentioned structure cooperation realizes that the subway secretly digs the waterproof and drainage at station is the utility model discloses an innovation point, the utility model discloses the infiltration problem between rock basement 1 and the concrete layer 2 has effectively been solved.
The above description is only a preferred embodiment of the present invention, and should not be taken as limiting the invention, and any modifications, equivalent replacements, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention. Any reference sign in a claim should not be construed as limiting the claim concerned.
Furthermore, it should be understood that although the present description refers to embodiments, not every embodiment may contain only a single embodiment, and such description is for clarity only, and those skilled in the art should integrate the description, and the embodiments may be combined as appropriate to form other embodiments understood by those skilled in the art.
Claims (5)
1. The utility model provides a subway secretly digs station waterproof and drainage structure, is including installing concrete layer (2) on rock base layer (1), be provided with infiltration hole (3) on concrete layer (2), be connected with breakwater (5) on concrete layer (2), its characterized in that, infiltration hole (3) on concrete layer (2) are deepened the inside of rock base layer (1), infiltration hole (3) evenly distributed is at the well downside of concrete layer (2), evenly install connecting bolt (4) on concrete layer (2), breakwater (5) link to each other with breakwater (5) through connecting bolt (4), breakwater (5) and base (7) sealing connection, base (7) are installed on main tributary dagger (8) and vice support column (10).
2. The underground excavation station waterproof and drainage structure of claim 1, characterized in that the connecting bolt (4) is a stud bolt, one end of the stud bolt is connected with the concrete layer (2), the other end of the stud bolt is provided with a connecting thread (420), the other end of the stud bolt is connected with the water baffle (5), and a flange (40) is arranged in the middle of the connecting bolt (4).
3. The underground excavation station waterproof and drainage structure of claim 2, characterized in that the flange (40) is connected with the water baffle (5) through a nut (43), a first gasket (41) is arranged between the flange (40) and the water baffle (5), and a second gasket (42) is arranged between the nut (43) and the water baffle (5).
4. The underground excavation station water-proof and drainage structure of the subway according to claim 1, characterized in that a drain pipe (9) is arranged below the base (7), and the drain pipe (9) is connected with a city pipe network.
5. The waterproof and drainage structure for the underground excavated station of the subway as claimed in claim 1, wherein a waterproof layer (6) is provided on an inner side of the breakwater (5).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921874081.2U CN210829393U (en) | 2019-10-31 | 2019-10-31 | Subway secretly digs station and prevents drainage structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921874081.2U CN210829393U (en) | 2019-10-31 | 2019-10-31 | Subway secretly digs station and prevents drainage structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN210829393U true CN210829393U (en) | 2020-06-23 |
Family
ID=71264320
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201921874081.2U Expired - Fee Related CN210829393U (en) | 2019-10-31 | 2019-10-31 | Subway secretly digs station and prevents drainage structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN210829393U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112227496A (en) * | 2020-09-29 | 2021-01-15 | 何滔 | Multifunctional comprehensive subway drainage ditch structure |
-
2019
- 2019-10-31 CN CN201921874081.2U patent/CN210829393U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112227496A (en) * | 2020-09-29 | 2021-01-15 | 何滔 | Multifunctional comprehensive subway drainage ditch structure |
CN112227496B (en) * | 2020-09-29 | 2022-02-01 | 何滔 | Multifunctional comprehensive subway drainage ditch structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205895312U (en) | Be used for rich irrigated land section tunnel water handling system | |
CN100410492C (en) | Centralized water discharge apparatus and method for tunnelling | |
CN203655307U (en) | Waste water pump room in metro tunnel | |
CN105240024B (en) | A kind of method of parallel shield method enlarging construction subway station | |
CN103510528A (en) | Blind trench water discharging structure used for underground structure up-floating prevention | |
CN211446958U (en) | Do benefit to underground structure of drainage | |
CN210829393U (en) | Subway secretly digs station and prevents drainage structure | |
CN108533317A (en) | A kind of tunnel bottom discharge structure | |
CN108361065B (en) | Tunnel inverted arch filling drainage structure | |
CN205501983U (en) | Decompression drainage tubular pile | |
CN208168937U (en) | A kind of tunnel bottom discharge structure | |
CN110985007A (en) | Construction process of subway communication channel | |
CN213116339U (en) | Wall-penetrating water stop structure for mechanical pipe-jacking circular working well opening | |
CN202610946U (en) | Tooth-shaped meshed hard permeable hose | |
CN111827345B (en) | Combined shock insulation protection system for preventing landslide | |
CN210049221U (en) | Foundation treatment structure for deep silt | |
CN211819412U (en) | Seabed wastewater pump house structure | |
CN210917390U (en) | Anti-collapse enclosure device | |
CN210917428U (en) | Deep basal pit relief well | |
CN211143096U (en) | Deep foundation pit drainage structure | |
CN112814735A (en) | Waterproof and drainage construction method for suspension bridge tunnel type anchorage cavern | |
CN214784090U (en) | Deep foundation pit drainage structure | |
CN217298989U (en) | Stainless steel is from pressure release equipment | |
CN217299969U (en) | Basement water seepage seam treatment facility | |
CN109252543A (en) | The retaining wall structure of ground is built on slope |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20200623 Termination date: 20201031 |
|
CF01 | Termination of patent right due to non-payment of annual fee |