CN210508408U CN201920621726.5U CN201920621726U CN210508408U CN 210508408 U CN210508408 U CN 210508408U CN 201920621726 U CN201920621726 U CN 201920621726U CN 210508408 U CN210508408 U CN 210508408U
Authority
CN
China
Prior art keywords
panel
concrete
block
supporting component
clamping
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920621726.5U
Other languages
Chinese (zh)
Inventor
张旭
陈静
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201920621726.5U priority Critical patent/CN210508408U/en
Application granted granted Critical
Publication of CN210508408U publication Critical patent/CN210508408U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a concrete placement workstation is built in room, including panel, supporting component and clamping unit, supporting component's top fixed connection panel, supporting component include bottom plate, pneumatic cylinder, fore-set and tray, and the upper surface center department of panel installs clamping unit, and clamping unit includes (holding) chuck, plectane, main shaft, slider, fixed block, screw rod and kicking block: this concrete placement workstation is built in room, supporting component's whole length can be adjusted through the pneumatic cylinder, can make the adaptability adjustment according to the job site demand like this, satisfy different operating modes, the upper surface center department of panel installs the clamping component who is the symmetric distribution, clamping component presss from both sides tight concrete feed cylinder and prevents that concrete feed cylinder from taking place to rock when carrying out concrete placement, just can drive the removal slider through rotating the screw rod and remove, make the (holding) chuck press from both sides tight concrete feed cylinder in order to satisfy the installation demand, height-adjustable about the whole device, the operation process is simple, it is also very convenient to press from both sides the dress to the concrete feed cylinder.

Description

Concrete pouring workbench for house construction
Technical Field
The utility model relates to a construction equipment technical field specifically is a concrete placement workstation is built in room.
Background
The concrete pouring refers to a process of pouring concrete into a mold until the concrete is plasticized, in the civil engineering and building engineering, materials such as concrete are put into the mold to form a preset shape, the free height of the concrete is not more than 2m when the concrete is poured, and corresponding measures are taken when the free height of the concrete exceeds 3 m.
When carrying out long distance or higher concrete transport, need specific pump truck, the concrete that the pump truck will adjust passes through the concrete feed cylinder and carries template department, but because the quality and the kinetic energy of concrete feed cylinder are big, rocking of certain degree can take place for the concrete feed cylinder, if not in time fix the concrete feed cylinder can cause some unnecessary losses, current room building concrete placement workstation does not all have fine accomplishing to maintain the steady of concrete feed cylinder, it adjusts inconveniently simultaneously, adaptability is not good.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a concrete placement workstation is built in room possesses adaptability well, and convenient operation's advantage can solve the problem among the prior art.
In order to achieve the above object, the utility model provides a following technical scheme: a concrete pouring workbench for a house building comprises a panel, a supporting assembly and a clamping assembly, wherein the top end of the supporting assembly is fixedly connected with the panel, the supporting assembly comprises a bottom plate, a hydraulic cylinder, a top column and a tray, the bottom end of the hydraulic cylinder is fixedly connected with the bottom plate, the top end of the hydraulic cylinder is provided with the top column, the top end of the top column is fixedly connected with the tray, the tray is connected with the lower surface of the panel, the clamping assembly is arranged at the center of the upper surface of the panel and comprises a clamping disc, a circular plate, a main shaft, a sliding block, a fixing block, a screw rod and a top block, the main shaft is movably connected with the center of the panel, the top end of the main shaft is fixedly connected with the circular plate, the clamping disc and the sliding block are movably connected with the upper surface of the circular plate, one end of the sliding block is, the fixed block is fixedly connected with the circular plate and is parallel to the sliding block.
Preferably, the side wall of the chuck is provided with a curved groove.
Preferably, the cross section of the sliding block is in an isosceles trapezoid shape, and one end of the sliding block is in contact connection with the fixed block.
Preferably, the upper surface of the circular plate is provided with a sliding groove matched with the sliding block.
Preferably, the clamping components mounted on the upper surface of the panel are symmetrically distributed.
Compared with the prior art, the beneficial effects of the utility model are as follows:
this concrete placement workstation is built in room, supporting component's whole length can be adjusted through the pneumatic cylinder, can make the adaptability adjustment according to the job site demand like this, satisfy different operating modes, the upper surface center department of panel installs the clamping component who is the symmetric distribution, clamping component presss from both sides tight concrete feed cylinder and prevents that concrete feed cylinder from taking place to rock when carrying out concrete placement, just can drive the removal slider through rotating the screw rod and remove, make the (holding) chuck press from both sides tight concrete feed cylinder in order to satisfy the installation demand, height-adjustable about the whole device, the operation process is simple, it is also very convenient to press from both sides the dress to the concrete feed cylinder.
Drawings
Fig. 1 is a schematic view of the overall structure of the present invention;
fig. 2 is a schematic top view of the clamping assembly of the present invention;
fig. 3 is a schematic cross-sectional view of the clamping assembly of the present invention.
In the figure: 1. a panel; 2. a support assembly; 21. a base plate; 22. a hydraulic cylinder; 23. a top pillar; 24. a tray; 3. a clamping assembly; 31. a chuck; 32. a circular plate; 33. a main shaft; 34. a slider; 35. a fixed block; 36. a screw; 37. and (7) a top block.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-3, a concrete pouring workbench for a building comprises a panel 1, a supporting component 2 and a clamping component 3, wherein the top end of the supporting component 2 is fixedly connected with the panel 1, the supporting component 2 is used for supporting and fixing, the supporting component 2 comprises a bottom plate 21, a hydraulic cylinder 22, a top post 23 and a tray 24, the bottom end of the hydraulic cylinder 22 is fixedly connected with the bottom plate 21, the top end of the hydraulic cylinder 22 is provided with the top post 23, the top end of the top post 23 is fixedly connected with the tray 24, the tray 24 is connected with the lower surface of the panel 1, namely, the whole length of the supporting component 2 can be adjusted through the hydraulic cylinder 22, the clamping component 3 is arranged at the center of the upper surface of the panel 1, the clamping components 3 arranged on the upper surface of the panel 1 are symmetrically distributed, the symmetrically distributed clamping components 3 just clamp concrete cylinders, and prevent the concrete cylinders from shaking during concrete pouring, The concrete charging barrel comprises a circular plate 32, a main shaft 33, a sliding block 34, a fixing block 35, a screw rod 36 and a top block 37, wherein the main shaft 33 is movably connected with the center of the panel 1, the top end of the main shaft 33 is fixedly connected with the circular plate 32, the upper surface of the circular plate 32 is provided with a sliding groove matched with the sliding block 34, so that the sliding block 34 can freely slide on the upper surface of the circular plate 32, the upper surface of the circular plate 32 is movably connected with a clamping disc 31 and the sliding block 34, the cross section of the sliding block 34 is isosceles trapezoid, so that the sliding block 34 cannot slide out, one end of the sliding block 34 is in contact connection with the fixing block 35, the sliding block 34 can drive the clamping disc 31 to move together, one end of the sliding block 34 is fixedly connected with the clamping disc 31, the side wall of the clamping disc 31 is provided with a curved groove, the curved groove is designed to ensure perfect matching with the outer wall of the, the fixing block 35 is fixedly connected with the circular plate 32, the fixing block 35 is parallel to the sliding block 34, and the screw 36 is rotated to drive the sliding block 34 to move, so that the installation requirement is met.
The building concrete pouring workbench comprises a panel 1, a supporting component 2 and a clamping component 3, wherein the top end of the supporting component 2 is fixedly connected with the panel 1, the whole length of the supporting component 2 can be adjusted through a hydraulic cylinder 22, so that adaptability adjustment can be made according to construction site requirements, different working condition requirements are met, the clamping component 3 is installed at the center of the upper surface of the panel 1, the clamping components 3 which are symmetrically distributed just clamp a concrete charging barrel, the concrete charging barrel is prevented from shaking during concrete pouring, the clamping component 3 comprises a chuck plate 31, a circular plate 32, a main shaft 33, a sliding block 34, a fixed block 35, a screw rod 36 and a top block 37, the upper surface of the circular plate 32 is provided with a sliding groove matched with the sliding block 34, so that the sliding block 34 can freely slide on the upper surface of the circular plate 32, the cross section of the sliding block 34 is in an isosceles trapezoid shape, slider 34 can drive (holding) chuck 31 and move together, and the curved surface groove of seting up on the (holding) chuck 31 lateral wall guarantees with the outer wall perfect adaptation of concrete feed cylinder, and screw rod 36 passes through screw-thread fit's mode swing joint fixed block 35, rotates screw rod 36 and just can drive and remove slider 34 and remove to satisfy the installation demand.
In summary, the following steps: this house building concrete placement workstation, the whole length of supporting component 2 can be adjusted through pneumatic cylinder 22, can make the adaptability adjustment according to the job site demand like this, satisfy different operating modes, the upper surface center department of panel 1 installs the clamping component 3 that is the symmetric distribution, clamping component 3 presss from both sides tight concrete feed cylinder and prevents that concrete feed cylinder from taking place to rock when carrying out concrete placement, just can drive removal slider 34 through rotating screw rod 36 and remove, make chuck 31 press from both sides tight concrete feed cylinder in order to satisfy the installation demand, height-adjustable about the whole device, the operation process is simple, it is also very convenient to press from both sides the dress to the concrete feed cylinder.
It is noted that, herein, relational terms such as first and second, and the like may be used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (5)

1. The utility model provides a room building concrete placement workstation, includes panel (1), supporting component (2) and clamping component (3), its characterized in that: the top end of the supporting component (2) is fixedly connected with the panel (1), the supporting component (2) comprises a bottom plate (21), a hydraulic cylinder (22), a top column (23) and a tray (24), the bottom end of the hydraulic cylinder (22) is fixedly connected with the bottom plate (21), the top end of the hydraulic cylinder (22) is provided with the top column (23), the top end of the top column (23) is fixedly connected with the tray (24), the tray (24) is connected with the lower surface of the panel (1), the center of the upper surface of the panel (1) is provided with a clamping component (3), the clamping component (3) comprises a chuck (31), a circular plate (32), a main shaft (33), a sliding block (34), a fixed block (35), a screw rod (36) and a top block (37), the main shaft (33) is movably connected with the center of the panel (1), the top end of the main shaft (33) is fixedly connected with the circular plate (32), the upper surface of the, one end fixed connection (31) of slider (34), the other end and kicking block (37) swing joint of slider (34), kicking block (37) fixed connection screw rod (36) one end, screw rod (36) pass through screw-thread fit's mode swing joint fixed block (35), fixed block (35) fixed connection plectane (32), fixed block (35) and slider (34) keep parallel.
2. A concrete casting work bench for building construction according to claim 1, wherein: the side wall of the chuck (31) is provided with a curved groove.
3. A concrete casting work bench for building construction according to claim 1, wherein: the cross section of the sliding block (34) is isosceles trapezoid, and one end of the sliding block (34) is in contact connection with the fixing block (35).
4. A concrete casting work bench for building construction according to claim 1, wherein: the upper surface of the circular plate (32) is provided with a sliding groove matched with the sliding block (34).
5. A concrete casting work bench for building construction according to claim 1, wherein: the clamping components (3) arranged on the upper surface of the panel (1) are symmetrically distributed.
CN201920621726.5U 2019-04-30 2019-04-30 Concrete pouring workbench for house construction Active CN210508408U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920621726.5U CN210508408U (en) 2019-04-30 2019-04-30 Concrete pouring workbench for house construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920621726.5U CN210508408U (en) 2019-04-30 2019-04-30 Concrete pouring workbench for house construction

Publications (1)

Publication Number Publication Date
CN210508408U true CN210508408U (en) 2020-05-12

Family

ID=70542417

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920621726.5U Active CN210508408U (en) 2019-04-30 2019-04-30 Concrete pouring workbench for house construction

Country Status (1)

Country Link
CN (1) CN210508408U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112343055A (en) * 2020-11-18 2021-02-09 杨玉庆 Concrete pouring device for hydraulic engineering building and use method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112343055A (en) * 2020-11-18 2021-02-09 杨玉庆 Concrete pouring device for hydraulic engineering building and use method thereof

Similar Documents

Publication Publication Date Title
CN109304574B (en) Slotting device for H-shaped steel flange plate
CN210508408U (en) Concrete pouring workbench for house construction
CN211735532U (en) Steel-edged rubber waterstop reinforcing clamp
CN217702126U (en) High-efficient steel welding set
CN210938549U (en) Electric discharge machine polishing equipment for annular workpiece
CN209799368U (en) Frame post template structure
CN209620596U (en) Device preventing tilting is used in a kind of support of building template
CN216641408U (en) Novel wall post template location device
CN214834656U (en) Pre-buried connecting device of concrete building scaffold
CN213174809U (en) Strutting arrangement is used in building engineering construction
CN213672141U (en) Adjustable steel structure cutting device
CN211163624U (en) Aluminum alloy template processingequipment
CN210195271U (en) Concrete placement equipment for construction
CN210164277U (en) Safety device used during inclined surface concrete pouring
CN214089495U (en) Chamfer template is used in road bridge construction
CN218715190U (en) Novel pouring tool for building construction
CN220741399U (en) Pipe cutting fixing device
CN216577537U (en) Auxiliary supporting and positioning device for disassembling old coil of motor
CN217530603U (en) Supporting device for multi-degree-of-freedom adjustment for auxiliary installation of water heating pipeline
CN219691079U (en) Square column steel moulding plate capable of positioning
CN218169228U (en) Positioner is used in steel construction processing
CN215617144U (en) Building material equipment of polishing
CN216840611U (en) Stair template device for house construction
CN219094915U (en) Turnover fixture for machining automobile parts
CN214418078U (en) Multifunctional welding equipment

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant