CN210479454U - Petroleum drill pipe placing and transferring frame - Google Patents

Petroleum drill pipe placing and transferring frame Download PDF

Info

Publication number
CN210479454U
CN210479454U CN201921162077.3U CN201921162077U CN210479454U CN 210479454 U CN210479454 U CN 210479454U CN 201921162077 U CN201921162077 U CN 201921162077U CN 210479454 U CN210479454 U CN 210479454U
Authority
CN
China
Prior art keywords
frame
rack
semicircular groove
placing
crossbeam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201921162077.3U
Other languages
Chinese (zh)
Inventor
孔祥峰
郜向东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiyuan Dongfang Heavy Industry Co Ltd
Original Assignee
Jiyuan Dongfang Heavy Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiyuan Dongfang Heavy Industry Co Ltd filed Critical Jiyuan Dongfang Heavy Industry Co Ltd
Priority to CN201921162077.3U priority Critical patent/CN210479454U/en
Application granted granted Critical
Publication of CN210479454U publication Critical patent/CN210479454U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Earth Drilling (AREA)

Abstract

The utility model relates to a petroleum drilling rod places transport frame, including bottom frame, intermediate frame, top frame, bottom crossbeam, top beam, connecting bolt, lug, semicircular groove and liner, bottom frame, intermediate frame and top frame are the multiunit, pass through between bottom frame, intermediate frame and the top frame connecting bolt connect fixedly, the bottom crossbeam is connected each bottom frame as an organic whole, the top beam is connected each top frame as an organic whole, be provided with two lugs on the top frame, all there is semicircular groove on bottom frame, intermediate frame, the top frame, there is the liner in the semicircular groove. The utility model discloses simple structure, the placing, hoist and mount and the transportation of the oil drill pipe of being convenient for.

Description

Petroleum drill pipe placing and transferring frame
Technical Field
The utility model relates to an oil drilling tool technical field, concretely relates to oil drill pipe places transport frame.
Background
The drilling rod is the equipment of wide application in oil development, and the current storage mode at transportation and job site is mostly stack each other superposes, and the drilling rod is long and thin hollow column structure, and under this kind of mode of stacking, because inertia and other internal force external force's combined action, take place the extrusion easily each other, make the drilling rod tubular column take place to warp, the top coat lacquer drops, drilling rod both ends screw thread bumps bad scheduling problem to influence the in service behavior of drilling rod, a plurality of drilling rod pile together also do not make things convenient for the shipment of drilling rod in addition.
SUMMERY OF THE UTILITY MODEL
The utility model provides a petroleum drilling rod places transport frame, simple structure, the petroleum drilling rod of being convenient for place, hoist and mount and transportation.
In order to solve the technical problem, the utility model discloses a technical scheme as follows:
the utility model provides a petroleum drilling rod places transport frame, includes bottom frame, middle frame, top frame, bottom crossbeam, top crossbeam, connecting bolt, lug, semicircular groove and liner, bottom frame, middle frame and top frame are the multiunit, pass through between bottom frame, middle frame and the top frame connecting bolt connect fixedly, the bottom crossbeam is connected each bottom frame as an organic whole, the top crossbeam is connected each top frame as an organic whole, be provided with two lugs on the top frame, all there is semicircular groove on bottom frame, middle frame, the top frame, there is the liner in the semicircular groove.
The combination of the bottom layer frame, the middle frame and the top layer frame is at least three groups.
The semicircular groove of the bottom layer frame is positioned above the bottom layer frame.
The semicircular groove of the top layer frame is positioned below the top layer frame.
The semicircular grooves of the middle frame are provided with two rows which are respectively positioned above and below the middle frame.
The semicircular grooves below the bottom layer frame and the middle frame can be in one-to-one correspondence to form circular holes.
The semicircular grooves on the upper parts of the top layer frame and the middle frame can be in one-to-one correspondence to form circular holes.
The intermediate frame may be one or more layers.
The diameter of the semicircular groove is the same as that of the oil drill rod.
The beneficial effects of the utility model reside in that: the utility model provides a pair of oil drill pipe places transport frame, simple structure can effectively solve the oil drill pipe stack and cause shortcomings such as drilling rod deformation easily, guarantees that the drilling rod does not receive the damage placing, hoist and mount and transportation.
Drawings
FIG. 1 is a schematic end view of an oil drill pipe placing and transferring rack of the present invention,
fig. 2 is the utility model relates to a side schematic view of oil drill pipe places transport frame.
The device comprises a base, a middle frame, a top frame, a bottom beam, a top beam, a connecting bolt, a lifting lug, a semicircular groove and a gasket, wherein the base is 1-the bottom frame, the middle frame is 2-the top frame, the bottom beam is 4-the top beam is 5-the connecting bolt is 6-the lifting lug is 7-the semicircular groove is 8-the gasket is 9-the gasket.
Detailed Description
The technical solution of the present invention will be further explained with reference to the accompanying drawings and the detailed description.
As shown in fig. 1, the oil drill pipe placing and transporting frame comprises a bottom frame 1, a middle frame 2, a top frame 3, a bottom cross beam 4, a top cross beam 5, connecting bolts 6, lifting lugs 7, semicircular grooves 8 and gaskets 9, wherein the bottom frame 1, the middle frame 2 and the top frame 3 are in multiple groups, the bottom frame 1, the middle frame 2 and the top frame 3 are fixedly connected through the connecting bolts 6, the bottom cross beam 4 connects the bottom frames 1 into a whole, the top cross beam 5 connects the top frames 3 into a whole, the top frame 3 is provided with two lifting lugs 7, the bottom frame 1, the middle frame 2 and the top frame 3 are respectively provided with the semicircular grooves 8, and the gaskets 9 are arranged in the semicircular grooves 8.
The combination of the bottom layer frame 1, the middle frame 2 and the top layer frame 3 is at least three groups.
The semicircular groove 8 of the bottom layer frame 1 is positioned above the bottom layer frame 1.
The semicircular groove 8 of the top shelf 3 is located below the top shelf 3.
The semicircular grooves 8 of the middle frame 2 are provided with two rows which are respectively positioned above and below the middle frame 2.
The bottom layer frame 1 and the semicircular grooves 8 below the middle frame 2 can form round holes in a one-to-one correspondence mode.
The semicircular grooves 8 on the top layer frame 3 and the middle frame 2 can form round holes in a one-to-one correspondence mode.
The intermediate frame 2 may be one or more layers.
The diameter of the semicircular groove 8 is the same as that of the oil drill rod.
The above is the preferred embodiment of the present invention, and it should be noted that, for those skilled in the art, the present invention is not limited by the above embodiments, and a plurality of changes and improvements can be made without departing from the overall concept of the present invention, and these should also be regarded as the protection scope of the present invention.

Claims (9)

1. The utility model provides a petroleum drilling rod places transport frame, includes bottom frame, middle frame, top frame, bottom crossbeam, top crossbeam, connecting bolt, lug, semicircular groove and liner, bottom frame, middle frame and top frame are the multiunit, pass through between bottom frame, middle frame and the top frame connecting bolt connect fixedly, the bottom crossbeam is connected each bottom frame as an organic whole, the top crossbeam is connected each top frame as an organic whole, be provided with two lugs on the top frame, all there is semicircular groove on bottom frame, middle frame, the top frame, there is the liner in the semicircular groove.
2. The rack for placing and transporting the petroleum drilling rod as claimed in claim 1, wherein the combination of the bottom layer rack, the middle rack and the top layer rack is at least three groups.
3. The rack of claim 1, wherein the semicircular groove of the sub-rack is located above the sub-rack.
4. The rack of claim 1, wherein the semicircular groove of the top rack is located below the top rack.
5. The rack for placing and transporting the petroleum drilling rods as claimed in claim 1, wherein the semicircular grooves of the middle rack are arranged in two rows respectively above and below the middle rack.
6. The rack for placing and transporting the oil drill pipes as claimed in claim 1, wherein the semicircular grooves below the bottom rack and the middle rack are formed with circular holes in a one-to-one correspondence manner.
7. The rack for placing and transporting the oil drill pipes as claimed in claim 1, wherein the semicircular grooves on the top rack and the middle rack form round holes in a one-to-one correspondence manner.
8. The rack for placing and transporting the petroleum drilling rod as claimed in claim 1, wherein the middle rack can be one or more layers.
9. The rack of claim 1, wherein the semicircular groove has the same diameter as the diameter of the oil drill pipe.
CN201921162077.3U 2019-07-23 2019-07-23 Petroleum drill pipe placing and transferring frame Expired - Fee Related CN210479454U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921162077.3U CN210479454U (en) 2019-07-23 2019-07-23 Petroleum drill pipe placing and transferring frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921162077.3U CN210479454U (en) 2019-07-23 2019-07-23 Petroleum drill pipe placing and transferring frame

Publications (1)

Publication Number Publication Date
CN210479454U true CN210479454U (en) 2020-05-08

Family

ID=70532261

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921162077.3U Expired - Fee Related CN210479454U (en) 2019-07-23 2019-07-23 Petroleum drill pipe placing and transferring frame

Country Status (1)

Country Link
CN (1) CN210479454U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113086380A (en) * 2021-04-16 2021-07-09 新疆农业大学 Fixing device is used in transport of assembly type building structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113086380A (en) * 2021-04-16 2021-07-09 新疆农业大学 Fixing device is used in transport of assembly type building structure

Similar Documents

Publication Publication Date Title
CN210479454U (en) Petroleum drill pipe placing and transferring frame
CN103774861B (en) A kind of reinforcement means of grid structure bar
CN203332580U (en) Sealing gasket storage box with sealing gaskets fixed through penetration rods and supporting plates
CN210438271U (en) Large-scale steel construction modularization hoist device
CN210192286U (en) Damage-proof placing device for anticorrosive steel pipe
CN103896158A (en) Friction energy dissipation and seismic mitigation device
CN202510473U (en) Connection steel tube of spherical net rack without beam-column
CN104192441A (en) Assembly capable of fixing multiple steel pipes
CN210815285U (en) Combined hump supporting structure
CN210858187U (en) Multistage yielding double-pipe constraint type self-resetting buckling-restrained brace device
CN210653503U (en) Motorcycle frame and vehicle
CN101989487B (en) Novel transformer heat radiator fixing structure
CN209277320U (en) A kind of novel buckling restrained brace stage by stage
CN203727824U (en) Stacking-type storage shelf
CN210793984U (en) A stromatolite tool equipment for transporting roller
CN208034019U (en) Pipe docks balancer
CN201812632U (en) Novel transformer radiator fixing structure
CN202807411U (en) Supporting and transporting bracket of derricks of skid-mounted drilling rigs
CN210259257U (en) Stock device convenient to it is range upon range of
CN102079435B (en) Fixing device for short pipe
CN214030060U (en) A auxiliary structure that is used for power station water delivery tubular product to pile up and deposits
CN204148810U (en) The oil-well rig boring tower assembling bearing of variable aperture
CN207353367U (en) A kind of storage battery reinforced aluminium connector
CN212338547U (en) Armored large pull rod corrugated compensator
CN219860077U (en) Triangular hoisting ear piece structure of prefabricated house

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200508

Termination date: 20210723