CN210459214U - Device for accurately positioning hole-forming pile points of pedal steel drill - Google Patents
Device for accurately positioning hole-forming pile points of pedal steel drill Download PDFInfo
- Publication number
- CN210459214U CN210459214U CN201921103642.9U CN201921103642U CN210459214U CN 210459214 U CN210459214 U CN 210459214U CN 201921103642 U CN201921103642 U CN 201921103642U CN 210459214 U CN210459214 U CN 210459214U
- Authority
- CN
- China
- Prior art keywords
- drill rod
- drill
- pedal
- cylinder
- ash
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
The utility model provides a pedal device for accurately positioning a drill rod hole-forming pile point, which comprises a drill rod, an ash pouring cylinder and a funnel, wherein the drill rod comprises a drill rod body, a drill bit, a pedal and a level gauge, the drill bit is positioned at the lower end of the drill rod body and is conical, the pedal is positioned at the lower part of the drill rod body, and the level gauge is positioned at the top of the drill rod body; the ash filling cylinder comprises a hollow cylinder body and an ash filling cylinder handle positioned above the cylinder body, the cylinder body is sleeved on the drill rod body, the inner wall of the cylinder body is attached to the outer wall of the drill rod body, and the length of the cylinder body is smaller than the distance from the drill rod head to the pedal; funnel lower extreme external diameter is less than the stack shell internal diameter can irritate lime 20cm to 50cm in the soil, rather than only spilling at the soil surface, will close on the setpoint overlay of mark when operation on every side, can eradicate the covering soil, eradicates a bit soil a little more and can expose the mark position, and the eyelet is little, irritates the ash few, and the location is accurate, and difficult off tracking easily looks for original setpoint, labour saving and time saving, convenient and fast.
Description
Technical Field
The utility model belongs to the technical field of the construction, especially, relate to a step on device of drill rod pore-forming stake point accurate positioning.
Background
Pile foundation engineering has now been widely applied to construction technical field in the construction, and pile point location beats in the first step of pile foundation engineering construction, and pile core position deviation whether will directly influence the construction quality of pile foundation engineering. In the traditional method for positioning the pile point, after a total station or other instruments, steel rulers and the like are matched to find the position of the pile core, lime is directly scattered on the position, or objects such as reinforcing steel bars, wooden piles, iron nails with red cloth and the like are inserted into the position, so that the position of the pile core is marked. The method has the defects that the position of a pile core is easy to deviate, or slurry or soil coverage is close to a marked point position during drilling operation, so that a lot of inconvenience is brought to construction:
the lime spreading range is large, the marking position deviation is large, and the pile position deviation is easy to exceed the standard range.
Objects such as reinforcing steel bars are inserted, the reinforcing steel bars are easy to deflect when surrounding soil is extruded, and people and machinery are inconvenient to walk and easy to trip pedestrians, so that the people are injured. When the machine is positioned to prepare for drilling, the steel bar needs to be pulled out, and the pile position deviation is easy to cause.
The timber pile is adopted for positioning, because the strength of the timber pile is low, a construction site is easily damaged by vehicles and the like, and an obvious mark cannot be started on the site by adopting the timber pile. The method of attaching red cloth to the iron nails is adopted, and although the red cloth can play an obvious marking role, the iron nails are not firm and are easy to deviate, and the iron nails are low in buried depth and easy to damage.
When the adjacent distance of the two piles is close, the piles formed by holes are firstly formed, soil or slurry flows out and then easily covers the marked pile points around, so that repeated positioning is caused, and manpower and material resources are consumed.
Disclosure of Invention
The utility model discloses make the improvement to the problem that above-mentioned prior art exists, promptly the utility model provides a pedal drill rod pore-forming stake point accurate positioning's device, this device easy operation, preparation, easy dismounting improve the efficiency of construction, practice thrift the cost of labor, and the device commonality is strong, and the stake point is difficult for being destroyed.
In order to solve the technical problem, the utility model provides a device for accurately positioning the hole-forming pile point of a pedal drill rod, which comprises a drill rod, an ash pouring cylinder and a funnel, wherein,
the drill rod comprises a drill rod body, a drill bit, a pedal and a level gauge, wherein the drill bit is positioned at the lower end of the drill rod body and is conical, the pedal is positioned at the lower part of the drill rod body, and the level gauge is positioned at the top of the drill rod body;
the ash filling cylinder comprises a hollow cylinder body and an ash filling cylinder handle positioned above the cylinder body, the cylinder body is sleeved on the drill rod body, the inner wall of the cylinder body is attached to the outer wall of the drill rod body, and the length of the cylinder body is smaller than the distance from the drill rod head to the pedal;
the outer diameter of the lower end of the funnel is smaller than the inner diameter of the cylinder body.
Preferably, a handle is arranged at the upper part of the drill shank.
Preferably, the length of the barrel body is 20cm to 50 cm.
Through the technical scheme, lime can be poured into the soil by 20cm to 50cm instead of being only scattered on the surface of the soil, the covering soil can be removed in a covering mode of the positioning points close to the marks in the surrounding operation, and the marking points can be exposed by removing a little more soil. The hole is small, the ash is filled less, the positioning is accurate, and the deviation is not easy to occur. The original positioning points are easy to find, and the direct pile driver is time-saving, labor-saving, convenient and quick to drill in place or to check the point.
Drawings
FIG. 1 is a schematic structural view of an ash pouring cylinder of a device for accurately positioning hole-forming pile points of pedal steel chisels in an embodiment of the present invention;
FIG. 2 is a schematic view of a drill steel structure of a device for accurately positioning a hole-forming pile point of a pedal drill steel according to an embodiment of the present invention;
FIG. 3 is a schematic structural view of a funnel of a device for accurately positioning hole-forming pile points of a pedal drill rod according to an embodiment of the present invention;
FIG. 4 is a combined view of a drill steel and a mortar pouring cylinder of the device for accurately positioning the hole-forming pile point of the pedal drill steel of the embodiment of the present invention;
FIG. 5 is a combined view of a funnel and an ash pouring cylinder of a device for accurately positioning hole-forming pile points of a pedal drill rod according to an embodiment of the present invention;
in the figure:
1. barrel body 2, ash filling barrel handle 3 and level gauge
4. Drill shank 5, handle 6 and pedal
7. Drill bit 8, funnel
Detailed Description
The technical solution in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention. It is to be understood that the embodiments described are only some embodiments of the invention, and not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplification of description, but do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and thus, should not be construed as limiting the present invention.
As shown in fig. 1 to 5, the utility model provides a device for accurately positioning hole-forming pile points of pedal steel drills, which comprises the steel drills, an ash pouring cylinder and a funnel, wherein,
the drill rod comprises a drill rod body 4, a drill bit 7, a pedal 6 and a level 3, wherein the drill bit 7 is positioned at the lower end of the drill rod body 4 and is conical, the pedal 6 is positioned at the lower part of the drill rod body 4, and the level 3 is positioned at the top of the drill rod body 4;
the ash filling cylinder comprises a hollow cylinder body 1 and an ash filling cylinder handle 2 positioned above the cylinder body 1, the cylinder body 1 is sleeved on the drill shank 4, the inner wall of the cylinder body 1 is attached to the outer wall of the drill shank 4, and the length of the cylinder body 1 is smaller than the distance from the drill bit 7 to the pedal 6;
the outer diameter of the lower end of the funnel 8 is smaller than the inner diameter of the cylinder body 1.
Preferably, the upper part of the drill shank 4 is provided with a handle 5.
Preferably, the length of the barrel 1 is 20cm to 50 cm.
The utility model provides a manufacturing method of pedal drill rod pore-forming stake point accurate positioning's device, including the step:
step one, round steel with the diameter of 12mm is used as the lower half part of a drill shank 4, the lower end of the drill shank is polished into a cone shape to be used as a drill bit 7, round steel with the diameter of 14mm or larger is used for manufacturing the upper half part of the drill shank 4, the middle of the drill shank is welded, the top of the drill shank 4 is pasted with a leveling instrument 3 by building glue, 30cm-50cm of deformed steel bar with the diameter of 20mm or larger is cut out to be used as a handle 5 and a pedal 6 on the drill shank, and the handle 5 and the pedal 6 are parallel and are vertically welded on the drill shank 4;
and step two, adopting a phi 14mm steel pipe as a cylinder body 1 of the ash filling cylinder, cutting out 30-50 cm deformed steel with the diameter of phi 1mm as an ash filling cylinder handle 2, and vertically welding the ash filling cylinder handle 2 on the cylinder body 1.
In a preferable scheme, the length of the barrel body 1 is 40 cm.
The utility model provides a pedal drill rod pore-forming stake point accurate positioning's device application method, including the step:
step one, determining a center line point of an engineering pile through measurement and setting-out;
secondly, sleeving the ash filling cylinder at the lower end of the drill body 4 until the handle 2 of the ash filling cylinder is propped against the lower part of the pedal 6;
aligning a drill bit 7 to a central line point of an engineering pile, adjusting a drill body 4 to be kept vertical through a level 3 at the upper end of the drill body 4, holding a handle 5 by hand, stepping on a pedal 6 by feet, and pressing the lower part of the drill body 4 and an ash filling cylinder sleeved on the lower part of the drill body 4 into the ground until a handle 2 of the ash filling cylinder is close to the ground;
and step four, vertically pulling out the drill shank 4, enabling the lower end of the funnel 8 to penetrate into the ash filling cylinder, filling the ash filling cylinder with lime through the funnel 8, and vertically pulling out the ash filling cylinder.
In a preferred scheme, in the fourth step, when the hopper 8 is used for filling lime into the lime pouring cylinder, the drill shank 4 is used for tamping the lime pouring cylinder, so that the lime is filled compactly.
In the fourth step, when the ash pouring cylinder is vertically pulled out, soil layers on two sides of the ash pouring cylinder are temporarily fixed, the ash pouring cylinder is slowly and stably lifted, and pile point holes are prevented from being damaged when the ash pouring cylinder is pulled out of the soil layers; preferably, a heavy object can be pressed above the soil layers on the two sides of the ash filling cylinder to temporarily fix the soil layers; it is further preferred that the hopper is rotated synchronously during the lifting of the hopper.
Through the technical scheme, lime can be poured into the soil by 20cm to 50cm instead of being only scattered on the surface of the soil, the covering soil can be removed in a covering mode of the positioning points close to the marks in the surrounding operation, and the marking points can be exposed by removing a little more soil. The hole is small, the ash is filled less, the positioning is accurate, and the deviation is not easy to occur. The original positioning points are easy to find, and the direct pile driver is time-saving, labor-saving, convenient and quick to drill in place or to check the point.
The device can deepen the buried depth of the pile point according to the local soil condition, the pile point retention time is long, the device is simple to operate, the manufacturing and the dismounting are convenient, the construction efficiency is improved, and the labor cost is saved. The device is strong in universality, and the device can be applied to related pile point projects.
The embodiments of the present invention have been described in detail, but the description is only for the preferred embodiments of the present invention and should not be construed as limiting the scope of the present invention. All the equivalent changes and improvements made according to the application scope of the present invention should still fall within the patent coverage of the present invention.
Claims (3)
1. A pedal device for accurately positioning a steel chisel hole-forming pile point is characterized by comprising a steel chisel, an ash pouring cylinder and a funnel, wherein,
the drill rod comprises a drill rod body, a drill bit, a pedal and a level gauge, wherein the drill bit is positioned at the lower end of the drill rod body and is conical, the pedal is positioned at the lower part of the drill rod body, and the level gauge is positioned at the top of the drill rod body;
the ash filling cylinder comprises a hollow cylinder body and an ash filling cylinder handle positioned above the cylinder body, the cylinder body is sleeved on the drill rod body, the inner wall of the cylinder body is attached to the outer wall of the drill rod body, and the length of the cylinder body is smaller than the distance from the drill rod head to the pedal;
the outer diameter of the lower end of the funnel is smaller than the inner diameter of the cylinder body.
2. The device for accurately positioning the hole-forming point of the pedal drill steel according to claim 1, wherein a handle is arranged at the upper part of the drill body.
3. The apparatus of claim 2, wherein the length of the shaft is 20cm to 50 cm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921103642.9U CN210459214U (en) | 2019-07-15 | 2019-07-15 | Device for accurately positioning hole-forming pile points of pedal steel drill |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921103642.9U CN210459214U (en) | 2019-07-15 | 2019-07-15 | Device for accurately positioning hole-forming pile points of pedal steel drill |
Publications (1)
Publication Number | Publication Date |
---|---|
CN210459214U true CN210459214U (en) | 2020-05-05 |
Family
ID=70445372
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201921103642.9U Active CN210459214U (en) | 2019-07-15 | 2019-07-15 | Device for accurately positioning hole-forming pile points of pedal steel drill |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN210459214U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110258563A (en) * | 2019-07-15 | 2019-09-20 | 中冶天工集团有限公司 | A kind of pinpoint device of foot-operated drill rod drilling pile point, production method and application method |
-
2019
- 2019-07-15 CN CN201921103642.9U patent/CN210459214U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110258563A (en) * | 2019-07-15 | 2019-09-20 | 中冶天工集团有限公司 | A kind of pinpoint device of foot-operated drill rod drilling pile point, production method and application method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103266599B (en) | The dry construction method of digging drilling pile of soil skerry ground churning driven | |
CN210459214U (en) | Device for accurately positioning hole-forming pile points of pedal steel drill | |
CN108589707A (en) | A kind of full-sleeve long screw auger and churning driven combined type construction | |
CN109457694A (en) | A kind of variable diameters steel reinforcement cage enlarged footing anti-floating or pressure bearing pile and construction in conjunction with mixing pile or rotary churning pile | |
CN210090077U (en) | Portable ground detects sampling device | |
CN110258563A (en) | A kind of pinpoint device of foot-operated drill rod drilling pile point, production method and application method | |
EP0937825B1 (en) | Method and apparatus for forming enlarged pile heads | |
CN106638600A (en) | Construction method for breaking bored pile head | |
CN211922605U (en) | Equal-core flexible-rigid composite pile | |
CN217174760U (en) | Mounting device for steel pipe pile | |
CN212175732U (en) | Soil material collecting device for soil test | |
CN206205012U (en) | A kind of SMW engineering methods stake inclinometer pipe installation aiding device | |
CN213742217U (en) | Embedded detachable overhanging scaffold positioning and fastening system | |
CN212358328U (en) | Foundation pit support anchor rod | |
CN209230632U (en) | A kind of measurement and positioning and the fixed control stake of elevation | |
CN110485413B (en) | Combined type protection rapid hole forming method for pile foundation of viaduct adjacent to subway | |
CN114293556A (en) | Prefabricated screw pile construction drilling tool and pile forming method | |
CN207079587U (en) | CFG stakes site localization marks lime cylinder | |
CN208486266U (en) | Pile foundation telltale mark point tool | |
CN208505655U (en) | Simple sampler suitable for soil sampling | |
CN108708369B (en) | Positioning construction method and device for construction net measurement control pile | |
CN208309585U (en) | A kind of device for avoiding a machine from repeating measuring stake position | |
CN111719558B (en) | CFG pile composite foundation construction process | |
CN205857172U (en) | Compacted effect static pressure pile pipe | |
CN218027744U (en) | Slope body space cross submitting composite retaining structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |