CN210396246U - Spliced integral toilet - Google Patents
Spliced integral toilet Download PDFInfo
- Publication number
- CN210396246U CN210396246U CN201920877983.5U CN201920877983U CN210396246U CN 210396246 U CN210396246 U CN 210396246U CN 201920877983 U CN201920877983 U CN 201920877983U CN 210396246 U CN210396246 U CN 210396246U
- Authority
- CN
- China
- Prior art keywords
- precast concrete
- fixing piece
- frame
- corner post
- column
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Residential Or Office Buildings (AREA)
Abstract
The utility model provides a spliced integral toilet, which comprises a precast concrete bottom plate, a precast concrete top plate, a precast concrete wall plate and a plurality of groups of corner post components, wherein each corner post component comprises a corner post, a first fixing part and a second fixing part, the precast concrete bottom plate is inserted into the bottom of the corner post in a splicing mode, and the precast concrete top plate is inserted into the top of the corner post in a splicing mode; the first fixing piece and the second fixing piece are inserted into the side face of the corner column in an inserting mode, and the precast concrete wall is fixed with the first fixing piece or the second fixing piece through bolts. The utility model discloses can realize assembling fast at the job site, effectively solve the loaded down with trivial details problem that wastes time of work progress, improve the efficiency of whole bathroom site Assembly.
Description
Technical Field
The utility model relates to a building engineering technical field, in particular to whole bathroom of concatenation formula.
Background
The integral toilet is characterized in that all parts of the toilet and all facilities in the toilet are prefabricated and installed in a factory, the toilet is integrally transported to a construction site, the toilet is directly and integrally installed, and after the toilet is installed in place, water and lines are connected in a butt joint mode, and the toilet can be used. The integrated toilet is convenient for on-site assembly as opposed to all toilet components, as well as facilities within the toilet, being shipped as discrete parts to the site.
The existing integral toilet is prefabricated in a factory, the integral toilet is transported to a construction site, and the integral toilet is directly installed in a reserved space of a building. The existing installation process of the whole toilet is inevitably influenced by the existing building wall, so that the installation of the whole toilet is difficult. For prefabricated toilet parts, the toilet is assembled on a construction site, the construction process is very complicated, the construction process is time-consuming and labor-consuming, and the rapid assembly of the whole toilet is difficult to realize.
Therefore, in order to solve the problems that in the prior art, the assembly efficiency of the whole toilet is low, and the construction process is complicated and time-consuming, a spliced whole toilet is needed.
SUMMERY OF THE UTILITY MODEL
The utility model aims to provide a spliced integral toilet which comprises a precast concrete bottom plate, a precast concrete top plate, a precast concrete wall and a plurality of groups of corner post components, wherein,
the angle column assembly comprises an angle column, a first fixing piece and a second fixing piece, the precast concrete bottom plate is inserted into the bottom of the angle column in an inserting mode, and the precast concrete top plate is inserted into the top of the angle column in an inserting mode;
the first fixing piece and the second fixing piece are inserted into the side face of the corner column in an inserting mode, and the precast concrete wall is fixed with the first fixing piece or the second fixing piece through bolts.
Preferably, the corner post comprises a column body, and a first connecting part and a second connecting part;
the first connecting part and the second connecting part are provided with at least one slot, and the first fixing part and the second fixing part are provided with lugs for being inserted into the slots;
the top of the column body is provided with a first jack, the bottom of the column body is provided with a second jack, the precast concrete top plate is provided with a first frame, and the first frame is provided with a first jack post for inserting the first jack; the precast concrete bottom plate is provided with a second frame, and a second inserting column used for being inserted into the second inserting hole is arranged on the second frame.
Preferably, a sealing strip is arranged in the slot.
Preferably, a plurality of light steel keels are arranged in the first frame of the precast concrete top plate in a crossed mode.
Preferably, the precast concrete top plate is integrally formed with the first frame, and the precast concrete bottom plate is integrally formed with the second frame.
Preferably, the whole toilet further comprises a precast concrete door pocket plate, wherein a door opening is formed in the precast concrete door pocket plate, and the precast concrete door pocket plate is fixed with the first fixing piece or the second fixing piece through bolts.
The utility model provides a pair of whole bathroom of concatenation formula, bottom plate, roof, wallboard to and the mode that the corner post passes through grafting is fixed, can realize assembling fast at the job site, effectively solves the loaded down with trivial details problem of wasting time of work progress, improves the efficiency of whole bathroom field assembly.
It is to be understood that both the foregoing general description and the following detailed description are exemplary and explanatory and are not restrictive of the invention, as claimed.
Drawings
Further objects, functions and advantages of the present invention will become apparent from the following description of embodiments of the present invention, with reference to the accompanying drawings, in which:
fig. 1 schematically shows each part schematic diagram of the utility model discloses a whole bathroom of concatenation formula.
Fig. 2 shows the utility model discloses an enlarged schematic view of the whole bathroom corner post subassembly of concatenation formula.
Fig. 3 shows the utility model relates to a fixed schematic diagram of whole bathroom precast concrete roof of concatenation formula, precast concrete bottom plate and corner post.
Fig. 4 shows a top view of fig. 2.
Fig. 5 shows the utility model discloses a fixed schematic diagram of whole bathroom precast concrete wall of concatenation formula and corner post subassembly.
Detailed Description
The objects and functions of the present invention and methods for accomplishing the same will be apparent by reference to the exemplary embodiments. However, the present invention is not limited to the exemplary embodiments disclosed below; it can be implemented in different forms. The nature of the description is merely to assist those skilled in the relevant art in a comprehensive understanding of the specific details of the invention.
Hereinafter, embodiments of the present invention will be described with reference to the accompanying drawings. In the drawings, the same reference numerals denote the same or similar parts, or the same or similar steps.
It is right below through specific embodiment the utility model provides a pair of splice type integral toilet carries out detailed description, as shown in fig. 1 the utility model relates to an each part schematic diagram of splice type integral toilet, according to the embodiment of the utility model, a splice type integral toilet includes precast concrete top 1, precast concrete bottom plate 2, polylith precast concrete wall 3, a precast concrete door pocket board 4 to and multiunit unit subassembly 5.
In this embodiment, precast concrete roof 1, precast concrete bottom plate 2, polylith precast concrete wall 3, a precast concrete door pocket board 4 are made by 12mm cement board and rock wool mixture, directly use as building wall.
Referring to fig. 2, an enlarged view of a spliced integral toilet corner post assembly (an enlarged view of a region a in fig. 1) according to an embodiment of the present invention, a corner post assembly 5 includes a corner post 501, a first fixing member 502 and a second fixing member 503.
The corner post 501 includes a post 5011, and the post 5011 is a 75 × 75 × 6 square steel in this embodiment. The top of the column 5011 is provided with a first insertion hole 5014, and the bottom of the column is provided with a second insertion hole (not shown, and symmetrically arranged at the bottom of the column 5011 with respect to the first insertion hole 5014). The corner post 501 includes also a first connection 5012 and a second connection 5013.
As shown in fig. 3 the utility model relates to a fixed schematic diagram of whole bathroom precast concrete roof of concatenation formula, precast concrete bottom plate and corner post, according to the utility model discloses an embodiment, precast concrete roof 1 has first frame 101, sets up the first post 1011 of inserting that is used for inserting first jack 5014 on the first frame 101. The precast concrete floor 2 has a second frame 201 on which a second post 2011 for inserting a second jack is provided. As shown in fig. 3, the precast concrete floor 2 is inserted into the bottom of the corner post 501 by plugging, and the precast concrete roof 1 is inserted into the top of the corner post 501 by plugging.
According to the present invention, in some preferred embodiments, a plurality of light steel keels 1012 are arranged crosswise within the first frame 101 of the precast concrete roof panel 1 to improve the rigidity of the ceiling structure. In other preferred embodiments, the precast concrete upper deck 1 is integrally formed with the first frame 101, and the precast concrete lower deck 2 is integrally formed with the second frame 201.
Fig. 4 is a top view of fig. 2, and fig. 5 is a schematic view illustrating the fixing of the precast concrete wall and the corner post assembly of the splicing type integrated toilet of the present invention. According to the utility model discloses an embodiment, corner post 501 includes cylinder 5011, first connecting portion 5012 and second connecting portion 5013.
The first connecting portion 5012 and the second connecting portion 5013 have at least one slot, and the first fixing member 502 and the second fixing member 503 have protrusions for inserting into the slots. In this embodiment, the first connection portion 5012 has two slots, namely a first slot 5015 and a second slot 5015 ', and the second connection portion has two slots, namely a third slot 5016 and a fourth slot 5016'. The first fixing member 502 has two protrusions, namely a first protrusion 5021 and a second protrusion 5021 ', and the second fixing member 503 has two protrusions, namely a third protrusion 5031 and a fourth protrusion 5031'.
The first fixing member 502 and the second fixing member 503 are inserted into the side of the corner post by inserting, specifically, in this embodiment, the first protrusion 5021 is inserted into the first slot 5015, the second protrusion 5021 'is inserted into the second slot 5015', the third protrusion 5031 is inserted into the third slot 5016, and the fourth protrusion 5031 'is inserted into the fourth slot 5016'.
According to the present invention, in some preferred embodiments, a sealing strip is provided within the slot. In this embodiment, a sealing strip is disposed in one of the two slots. As shown in fig. 4 and 5, a first sealing strip 5017 is disposed in the first slot 5015, and a second sealing strip 5018 is disposed in the third slot 5016, so that when the first fixing member 502 and the second fixing member 503 are inserted into the first connecting portion 5012 and the second connecting portion 5013 on both sides of the corner post 501 in an inserting manner, the first sealing strip 5017 and the second sealing strip 5018 seal the inserted joint.
According to the embodiment of the present invention, the precast concrete wall 3 is fixed to the first fixing member 502 or the second fixing member 503 by bolts. In this embodiment, taking two adjacent precast concrete walls as an example, the first precast concrete wall 3a and the first fixing member 502 are fixed by bolts, and the second precast concrete wall 3b and the second fixing member 503 are fixed by bolts. Specifically, nuts are embedded in the first fixing member 502 and the second fixing member 503, the first bolt 5019 penetrates through the first precast concrete wall 3a and then is screwed into the nuts embedded in the first fixing member 502, and the second bolt 5020 penetrates through the second precast concrete wall 3b and then is screwed into the nuts embedded in the second fixing member 503.
According to the utility model discloses an embodiment, the door opening is seted up to precast concrete door pocket board 4, and precast concrete door pocket board 4 passes through the bolt fastening with first mounting 502 or second mounting 503. Specifically, the connection process is the same as the connection method of the precast concrete wall 3 and the first fixing member 502 or the second fixing member 503, and will not be described again.
The utility model provides a pair of whole bathroom of concatenation formula, the form concatenation of angle post subassembly with pegging graft to it is fixed with angle post subassembly to pass through the bolt with the precast concrete wall, and the angle post that makes can effectively bear the structure atress of whole bathroom.
The utility model provides a pair of whole bathroom of concatenation formula, bottom plate, roof, wallboard to and the mode that the corner post passes through grafting is fixed, can realize assembling fast at the job site, effectively solves the loaded down with trivial details problem of wasting time of work progress, improves the efficiency of whole bathroom field assembly.
Other embodiments of the invention will be apparent to those skilled in the art from consideration of the specification and practice of the invention disclosed herein. It is intended that the specification and examples be considered as exemplary only, with a true scope and spirit of the invention being indicated by the following claims.
Claims (6)
1. A spliced integral toilet is characterized by comprising a precast concrete bottom plate, a precast concrete top plate, a precast concrete wall plate and a plurality of groups of corner post assemblies,
the angle column assembly comprises an angle column, a first fixing piece and a second fixing piece, the precast concrete bottom plate is inserted into the bottom of the angle column in an inserting mode, and the precast concrete top plate is inserted into the top of the angle column in an inserting mode;
the first fixing piece and the second fixing piece are inserted into the side face of the corner column in an inserting mode, and the precast concrete wall is fixed with the first fixing piece or the second fixing piece through bolts.
2. The integrated lavatory according to claim 1, wherein the corner post comprises a post body, and first and second connection portions;
the first connecting part and the second connecting part are provided with at least one slot, and the first fixing part and the second fixing part are provided with lugs for being inserted into the slots;
the top of the column body is provided with a first jack, the bottom of the column body is provided with a second jack, the precast concrete top plate is provided with a first frame, and the first frame is provided with a first jack post for inserting the first jack; the precast concrete bottom plate is provided with a second frame, and a second inserting column used for being inserted into the second inserting hole is arranged on the second frame.
3. The integrated lavatory according to claim 2, wherein a sealing strip is provided in the slot.
4. The integrated lavatory according to claim 2, wherein a plurality of lightgage steel joists are arranged crosswise within the first frame of the precast concrete roof panel.
5. The integrated lavatory according to claim 2, wherein the precast concrete top panel is integrally formed with the first frame and the precast concrete bottom panel is integrally formed with the second frame.
6. The integrated toilet according to claim 1, further comprising a precast concrete door pocket plate, wherein the precast concrete door pocket plate is provided with a door opening and fixed with the first fixing member or the second fixing member through bolts.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920877983.5U CN210396246U (en) | 2019-06-12 | 2019-06-12 | Spliced integral toilet |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920877983.5U CN210396246U (en) | 2019-06-12 | 2019-06-12 | Spliced integral toilet |
Publications (1)
Publication Number | Publication Date |
---|---|
CN210396246U true CN210396246U (en) | 2020-04-24 |
Family
ID=70348820
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201920877983.5U Active CN210396246U (en) | 2019-06-12 | 2019-06-12 | Spliced integral toilet |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN210396246U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114215394A (en) * | 2021-12-10 | 2022-03-22 | 中建海龙科技有限公司 | Prefabricated toilet and construction method thereof |
CN114215393A (en) * | 2021-12-10 | 2022-03-22 | 中建海龙科技有限公司 | Prefabricated toilet with rear-mounted top plate and construction method thereof |
CN114809304A (en) * | 2022-05-11 | 2022-07-29 | 中建八局第二建设有限公司 | High-rigidity dust-free assembled laboratory |
-
2019
- 2019-06-12 CN CN201920877983.5U patent/CN210396246U/en active Active
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114215394A (en) * | 2021-12-10 | 2022-03-22 | 中建海龙科技有限公司 | Prefabricated toilet and construction method thereof |
CN114215393A (en) * | 2021-12-10 | 2022-03-22 | 中建海龙科技有限公司 | Prefabricated toilet with rear-mounted top plate and construction method thereof |
CN114215393B (en) * | 2021-12-10 | 2023-09-12 | 中建海龙科技有限公司 | Prefabricated toilet with rear top plate and construction method thereof |
CN114215394B (en) * | 2021-12-10 | 2023-09-12 | 中建海龙科技有限公司 | Prefabricated toilet and construction method thereof |
CN114809304A (en) * | 2022-05-11 | 2022-07-29 | 中建八局第二建设有限公司 | High-rigidity dust-free assembled laboratory |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN210396246U (en) | Spliced integral toilet | |
US4918897A (en) | Construction system for detention structures and multiple story buildings | |
CN115126079B (en) | Cylindrical tower type building and construction method thereof | |
CN106836469B (en) | Assembly type building | |
KR100956974B1 (en) | Building remodeling construction method using precast concrete panel, and remodeled building thereof | |
CN111456222B (en) | Assembly type steel structure integrated green building and design and installation process thereof | |
CN112282047B (en) | Connecting structure and connecting method for assembled composite floor slab and composite wallboard | |
CN214246220U (en) | Prefabricated slot-in-groove type shear wall vertical joint connecting structure | |
WO2006095266A1 (en) | Method of constructing structures using prefabricated materials | |
KR101671894B1 (en) | Stud-Anchor Connection Method for Seismic Resistant with Precast Wall Panels in an Old Reinforced Concrete Beam Column Building | |
CN113530028A (en) | Structural system design of assembled fireproof sound insulation wall | |
CN212506801U (en) | T-shaped connecting structure of top plate and wall plate of prefabricated building | |
CN109577511B (en) | Vertical seam connecting structure and connecting method for prefabricated wall panel | |
US20240011276A1 (en) | Modular building structure | |
KR100628537B1 (en) | Pc structure wall system with high earthquake resistance capacity | |
KR101143553B1 (en) | Construction method for building remodeling by using pc panel for building remodeling, and connecting structure for remodeling pc panel | |
CN112523545A (en) | Basic module for building and low and multi-storey modular building structure system | |
KR101115016B1 (en) | Construction method for building remodeling by using precast panel, and connecting structure for remodeling precast panel | |
KR20100133637A (en) | Building remodeling construction method using precast concrete panel, and remodeled building thereof | |
CN115404992B (en) | Modularized building | |
CN218405818U (en) | Upper and lower connected node of modularization concrete structure | |
CN220058324U (en) | Modular structure adopting mixed nodes | |
CN215055686U (en) | Basic module for building and low and multi-storey modular building structure system | |
CN213143405U (en) | Connecting box for prefabricated building and upper and lower prefabricated part connecting structure | |
CN212836243U (en) | Outer hanging prefabricated outer window containing auxiliary frame wallboard module, external wall panel and housing construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |