CN210316401U - Assembled putty scraping tool free of climbing operation - Google Patents

Assembled putty scraping tool free of climbing operation Download PDF

Info

Publication number
CN210316401U
CN210316401U CN201920746678.2U CN201920746678U CN210316401U CN 210316401 U CN210316401 U CN 210316401U CN 201920746678 U CN201920746678 U CN 201920746678U CN 210316401 U CN210316401 U CN 210316401U
Authority
CN
China
Prior art keywords
putty
box
extrusion baffle
assembled
climbing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920746678.2U
Other languages
Chinese (zh)
Inventor
宋立康
马清杰
蒋磊
陈浩
杲晓
蒋鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd
Original Assignee
Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd filed Critical Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd
Priority to CN201920746678.2U priority Critical patent/CN210316401U/en
Application granted granted Critical
Publication of CN210316401U publication Critical patent/CN210316401U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses an exempt from to ascend a height operation assembled puttying instrument, including strutting arrangement, putty box and extrusion baffle, the putty box is the triangular prism form, and one side is open setting in three sides, and this side swing joint has the extrusion baffle, the upside of putty box is provided with the discharge gate, the downside swing joint of extrusion baffle has the bracing piece, and in the engineering work progress, the operation ceiling putty of ascending a height construction exists certain potential safety hazard, and because of midway add putty needs handling frame from top to bottom, and the time-consuming that takes a lot of work, equally also can meet the unable condition of being under construction of putty in narrow and small space, adopts the operation assembled puttying instrument of exempting from to ascend a height, and the workman need not handling frame from top to bottom, need not to ascend a height the operation, and the work efficiency is high, and the potential safety hazard is low, and narrow and small space.

Description

Assembled putty scraping tool free of climbing operation
Technical Field
The utility model relates to an exempt from to ascend a height operation assembled putty instrument mainly is the putty that is used for the decoration in-process to scrape ceiling, the narrow and small position in space, belongs to the operation tool of construction operation.
Background
In the engineering decoration construction process, the putty construction of the ceiling and the narrow space has potential safety hazards or can not be carried out on the site. In the past, tools such as movable scaffolds, herringbone ladders and the like are generally erected and stand on the tools for long-term construction, potential safety hazards such as high falling exist, and meanwhile, a worker looks up for a long time, hands and shoulders of the worker feel sore and the working radius is small. The process of adding putty and setting up a climbing tool is labor-consuming and time-consuming. Under the condition that workers are difficult to enter the narrow space, putty scraping construction cannot be carried out.
Disclosure of Invention
The purpose of the invention is as follows: the utility model aims to provide an exempt from to ascend a height operation assembled puttying instrument to prior art not enough, in order to solve all kinds of problems that exist in the narrow and small position puttying work progress in ceiling, space. The invention has simple operation, convenient carrying, assembly, large operation radius and no need of ascending by labor staff. The potential safety hazard can be solved, and the working hours are reduced in the putty adding process. Meanwhile, muscle soreness in the operation process is reduced, and convenience is brought to engineering construction
The technical scheme is as follows: an exempt from to ascend a height operation assembled puttying instrument, including strutting arrangement, putty box and extrusion baffle, the putty box is the triangular prism form, and just one side in three sides is open setting, and this side swing joint has extrusion baffle, the upside of putty box is provided with the discharge gate, extrusion baffle's downside swing joint has the bracing piece.
Preferably, the discharge port is located opposite to the inner side of the extrusion baffle.
Preferably, the upper side of the extrusion baffle is movably connected with the upper side of the putty box through at least two groups of hinges.
Preferably, one side of the putty box opposite to the hinge is an arc-shaped plate with the hinge as a circle center and the length of the extrusion baffle as a radius.
Preferably, the middle part of the outer side of the extrusion baffle is provided with a bayonet, and the upper end of the support rod is movably connected in the bayonet.
Preferably, the support rods are two groups and are connected through a plastic sleeve.
Preferably, one side opposite to the hinge in the putty box is provided with at least two sets of buckles, be provided with at least two sets of springs on the bayonet socket, the one end of spring is provided with movable hook, and every movable hook of group respectively with the buckle swing joint that corresponds.
Has the advantages that: in the engineering construction process, the ceiling putty for the climbing operation construction has certain potential safety hazards, and the operation frame needs to be lifted up and down due to midway addition of the putty, so that labor and time are wasted. The situation that putty in a narrow space cannot be constructed can be met. The assembled putty scraping tool free of ascending operation is adopted, workers do not need to go up and down the operation frame, ascending operation is not needed, work efficiency is high, potential safety hazards are low, meanwhile, construction can be carried out in a narrow space, and assembly is convenient.
Drawings
Fig. 1 is a schematic structural diagram of an embodiment of the present invention.
In the drawings: 1 putty box, 2 extrusion baffles, 3 hinges, 4 ceilings, 5 buckles, 6 springs, 7 buckles, 8 discharge ports, 9 support rods and 10 plastic sleeves.
Detailed Description
The technical solution of the present invention is described in detail below with reference to the accompanying drawings, but the scope of the present invention is not limited to the embodiments.
Example 1: the utility model provides an exempt from to ascend a height operation assembled puttying instrument, including bracing piece 9, putty box 1 and extrusion baffle 2, putty box 1 is the triangular prism form, and one side is open setting in three sides, this side swing joint has extrusion baffle 2, the upside of putty box 1 is provided with discharge gate 8, the downside swing joint of extrusion baffle 2 has bracing piece 9, putty box 1 and extrusion baffle 2 constitute the triangular prism form, when bracing piece 9 up hard, bracing piece 9 promotes extrusion baffle 2 and uses hinge 3 to be circular motion as the center, upwards extrude putty in the putty box 1, make putty emerge from discharge gate 8.
As shown in fig. 1, the discharge port 8 is located opposite to the inner side of the extrusion baffle 2, and is farthest from the extrusion baffle 2, so that the putty in the putty box 1 can be completely extruded out.
As shown in fig. 1, the upper side of the pressing baffle 2 is movably connected with the upper side of the putty box 1 through at least two groups of hinges 3, so that the pressing baffle 2 is prevented from falling off due to the damage of one group of hinges 3.
As shown in fig. 1, the side opposite to the hinge 3 in the putty box 1 is with the hinge 3 as the centre of a circle, and the length of the extrusion baffle 2 is the radial arc, and the arc sets up, and the length of the easy extrusion baffle 2 is the radius, so that when the extrusion baffle 2 moves upwards, the arc is hugged closely to one side close to the arc all the time, and the putty is prevented from leaking.
As shown in fig. 1, a bayonet is arranged in the middle of the outer side of the extrusion baffle 2, and the upper end of the support rod 9 is movably connected in the bayonet, so that the support rod 9 and the extrusion baffle 2 can rotate mutually.
As shown in fig. 1, the two sets of support rods 9 are connected by a plastic sleeve 10, the two sets of support rods 9 have different diameters, the support rod 9 with a large diameter is hollow, and the support rod 9 with a small diameter can extend into the support rod 9 with a large diameter, and the support rod 9 with a small diameter can be retracted into the support rod 9 with a large diameter by screwing the plastic sleeve 10, so as to adjust the length of the support rod 9.
As shown in fig. 1, one side opposite to hinge 3 in the putty box 1 is provided with at least two sets of buckles 75, is provided with at least two sets of springs 6 on the bayonet socket, and the one end of spring 6 is provided with movable hook, and every movable hook of group makes with the setting of the 75 swing joint spring 6 of buckle that corresponds respectively, and when this instrument did not use, spring 6 can pull extrusion baffle 2 downwards for in the putty resorption that just emerged in the discharge gate 8 entered putty box 1, prevented that putty from spilling.
Before the utility model is used, the support rod 9 is taken down, the extrusion baffle 2 is opened, the adjusted putty is loaded into the putty box 1, the extrusion baffle 2 is installed, partial putty is extruded, and the putty at the discharge port 8 is ensured to be full; the installation direction and the length of the supporting rod 9 are adjusted according to the height, the construction direction and the construction position of the ceiling 4; lifting the putty box 1 to the position of the ceiling 4 by using a support rod 9, and keeping a discharge hole 8 of the putty box 1 close to the part of the ceiling 4 to be coated; the supporting rod 9 is used for pushing the extrusion baffle 2 to extrude putty from the discharge hole 8, the supporting rod 9 is pushed to be pulled towards the coating direction at the moment, and the putty baffle is extruded while being pulled, so that the discharge hole 8 of the putty box 1 is ensured.
As mentioned above, although the present invention has been shown and described with reference to certain preferred embodiments, it should not be construed as limiting the invention itself. Various changes in form and detail may be made therein without departing from the spirit and scope of the invention as defined by the appended claims.

Claims (7)

1. The utility model provides an exempt from to ascend a height operation assembled puttying instrument, a serial communication port, including strutting arrangement, putty box and extrusion baffle, the putty box is the triangular prism form, and one side is open setting in three sides, and this side swing joint has extrusion baffle, the upside of putty box is provided with the discharge gate, extrusion baffle's downside swing joint has the bracing piece.
2. The modular no-climb puttying tool of claim 1, wherein said spout is located opposite the inside of the squeeze fence.
3. The climbing-free operation assembled putty tool according to claim 1 is characterized in that the upper side of the pressing baffle is movably connected with the upper side of the putty box through at least two groups of hinges.
4. The climbing-free operation assembled putty tool according to claim 1, characterized in that one side of the putty box opposite to the hinge is an arc plate with the center of the hinge as a circle center and the length of the extrusion baffle as a radius.
5. The climbing-free operation assembled putty tool according to claim 1, characterized in that a bayonet is arranged in the middle of the outer side of the extrusion baffle, and the upper end of the support rod is movably connected in the bayonet.
6. The climbing-free assembled putty tool according to claim 1 or 5 is characterized in that the support rods are two groups and are connected through a plastic sleeve.
7. The climbing-free operation assembled putty tool according to claim 5, characterized in that at least two sets of buckles are arranged on one side of the putty box opposite to the hinge, at least two sets of springs are arranged on the bayonet, one ends of the springs are provided with movable hooks, and each set of movable hooks are movably connected with the corresponding buckles respectively.
CN201920746678.2U 2019-05-23 2019-05-23 Assembled putty scraping tool free of climbing operation Active CN210316401U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920746678.2U CN210316401U (en) 2019-05-23 2019-05-23 Assembled putty scraping tool free of climbing operation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920746678.2U CN210316401U (en) 2019-05-23 2019-05-23 Assembled putty scraping tool free of climbing operation

Publications (1)

Publication Number Publication Date
CN210316401U true CN210316401U (en) 2020-04-14

Family

ID=70140059

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920746678.2U Active CN210316401U (en) 2019-05-23 2019-05-23 Assembled putty scraping tool free of climbing operation

Country Status (1)

Country Link
CN (1) CN210316401U (en)

Similar Documents

Publication Publication Date Title
CN204001647U (en) Demountable combined-type Mobile operating platform
CN210316401U (en) Assembled putty scraping tool free of climbing operation
CN206360316U (en) A kind of high lift Architectural Equipment of stability
CN211473327U (en) Building external climbing type building construction operation platform
CN112681700A (en) Movable frame for construction of building interior wall
CN103485522A (en) Novel easily-connected scaffold
CN214169856U (en) Safety platform for building scaffold
CN206737800U (en) A kind of double ladder for building for being easy to regulation
CN206189872U (en) Aluminum alloy template hoist
CN206352387U (en) A kind of deformable hoistway operation steel platform of automatic climbing formula
CN215331330U (en) Scaffold frame for municipal works that protecting effect is good
CN208456101U (en) A kind of housing construction scaffold
CN212689494U (en) Construction platform for building construction
CN217998841U (en) Concrete pouring workbench for house construction
CN209352424U (en) A kind of hoisting prefabricated part of embedded small hoisting ring group
CN103643790A (en) Self-crawling type operating platform applicable to colossal column
CN207177339U (en) A kind of easy-disassembling-assembling Construction of Civil Engineering Support bracket
CN207144444U (en) A kind of Super High scaffold used for outwall construction
CN214006578U (en) Reinforcing bar guiding device for construction of reinforced block masonry wall
CN207063503U (en) A kind of scaffold
CN219528369U (en) Scaffold with protection extension ladder
CN106238250B (en) A kind of anchor chain hanger bracket
CN220521910U (en) Building construction frame
CN205637537U (en) A auto -lock draw bridge frame for climbing frame
CN205558227U (en) Last people scaffold frame of dismouting can relapse

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant