CN210194603U - Empty pile steel pipe column positioning device - Google Patents

Empty pile steel pipe column positioning device Download PDF

Info

Publication number
CN210194603U
CN210194603U CN201920593619.6U CN201920593619U CN210194603U CN 210194603 U CN210194603 U CN 210194603U CN 201920593619 U CN201920593619 U CN 201920593619U CN 210194603 U CN210194603 U CN 210194603U
Authority
CN
China
Prior art keywords
positioning
pipe column
cross rod
hoop
steel pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920593619.6U
Other languages
Chinese (zh)
Inventor
Weixing Yao
姚伟兴
Guangle Ni
倪光乐
Chenhui Duan
段晨辉
Jiepeng Li
李杰鹏
Chunxiang Lin
林春香
Jiawang Chen
陈佳望
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GUANGZHOU TAIJI ENGINEERING TECHNOLOGY Co Ltd
Original Assignee
GUANGZHOU TAIJI ENGINEERING TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUANGZHOU TAIJI ENGINEERING TECHNOLOGY Co Ltd filed Critical GUANGZHOU TAIJI ENGINEERING TECHNOLOGY Co Ltd
Priority to CN201920593619.6U priority Critical patent/CN210194603U/en
Application granted granted Critical
Publication of CN210194603U publication Critical patent/CN210194603U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a positioning device for an empty pile steel pipe column, which relates to the technical field of building construction and comprises a positioning base frame, this location bed frame is provided with a plurality of locating platform, each locating platform is parallel arrangement from top to bottom in proper order, each locating platform all installs adjustment mechanism, each adjustment mechanism includes horizontal pole subassembly and installs the staple bolt subassembly on this horizontal pole subassembly, each horizontal pole subassembly all includes first horizontal pole and the second horizontal pole that is parallel to each other, each staple bolt subassembly all includes two location hoops that set up relatively, have the locating hole that supplies the steel-pipe column to pass between two relative location hoops, each location hoop middle part has the locating surface that is used for laminating the steel-pipe column, each location hoop's one end is installed on corresponding first horizontal pole and can be followed this first horizontal pole length direction and remove, each location hoop's the other end is installed on corresponding second horizontal pole and can be followed this second horizontal pole length direction and remove. The utility model discloses ensure the straightness and the coordinate location that hang down of steel-pipe column.

Description

Empty pile steel pipe column positioning device
Technical Field
The utility model relates to a construction technical field, in particular to empty stake steel-pipe column positioner.
Background
Underground construction is complicated to be forced, and the requirement to the pile foundation is higher and higher, and what adopted at present is that the mode that steel-pipe column and bored concrete pile combine is under construction. The steel pipe column is connected with the cast-in-place pile, the steel pipe column and the cast-in-place pile are required to be constructed simultaneously, the end portion of the steel pipe column is anchored in concrete of the cast-in-place pile during construction of the cast-in-place pile, and integrity and strength of connection of the steel pipe column and the cast-in-place pile are improved.
Because the bored concrete pile is in ground pore-forming construction, pile bolck elevation is longer apart from ground, about 15 meters, do not pour concrete part we call empty pile, and empty pile length is longer, go down the steel-pipe column to the top of bored concrete pile anchor before the bored concrete pile is pour, the steel-pipe column is difficult to guarantee at the straightness that hangs down of empty pile part, also be the control main points of construction, because the mobility of concrete when pouring the concrete, lead to the steel-pipe column to appear the phenomenon of off normal out easily, or by the concrete up jack-up lead to steel-pipe column come-up scheduling problem.
Disclosure of Invention
An object of the utility model is to provide a vacant pile steel-pipe column positioner can fix a position the steel-pipe column when the construction of the vacant stake of overlength, ensures the straightness and the coordinate location that hang down of steel-pipe column, also avoids the steel-pipe column come-up when later stage concrete placement.
The technical scheme adopted for solving the technical problems is as follows:
the utility model provides an empty pile steel-pipe column positioner, including the location bed frame, this location bed frame is provided with a plurality of locating platform, each locating platform is parallel arrangement from top to bottom in proper order, each locating platform all installs adjustment mechanism, each adjustment mechanism includes the horizontal pole subassembly and installs the staple bolt subassembly on this horizontal pole subassembly, each horizontal pole subassembly all includes first horizontal pole and the second horizontal pole that is parallel to each other, each staple bolt subassembly all includes two location hoops that set up relatively, have the locating hole that supplies the steel-pipe column to pass between two relative location hoops, each location hoop middle part has the locating surface that is used for laminating the steel-pipe column, each the one end of location hoop is installed on corresponding first horizontal pole and can be followed this first horizontal pole length direction and removed, each the other end of location hoop is installed on corresponding second horizontal pole and can be followed this second horizontal pole length direction and removed.
As a further improvement of the above technical solution, there are two positioning platforms, the upper layer of the positioning platform has a first cross bar perpendicular to the lower layer of the positioning platform, and the upper layer of the positioning platform has a second cross bar perpendicular to the lower layer of the positioning platform.
As a further improvement of the above technical solution, each positioning hoop includes an arc-shaped hoop arm and adjustment seats disposed at two ends of the hoop arm, each adjustment seat includes a connecting plate connected to the corresponding hoop arm and a level adjustment plate connected to the connecting plate, and each positioning surface is disposed on an inner side surface of the corresponding hoop arm.
As a further improvement of the above technical solution, each of the leveling plates is bolted to the corresponding first crossbar, each of the leveling plates is bolted to the corresponding second crossbar, each of the leveling plates is provided with at least one first connecting through hole, and each of the first crossbar and each of the second crossbar is provided with a first oblong hole matched with the corresponding first connecting through hole.
As a further improvement of the above technical solution, two ends of each positioning hoop are provided with hydraulic cylinders, end portions of piston rods of the hydraulic cylinders are pressed against the outer sides of the corresponding adjusting seats, and cylinder barrels of the hydraulic cylinders are fixed on the corresponding first cross bars or the corresponding second cross bars.
As a further improvement of the above technical solution, each of the positioning platforms is a square frame structure, and each of the positioning platforms includes a first beam, a second beam perpendicular to the first beam, a third beam perpendicular to the second beam, and a fourth beam perpendicular to the third beam;
in the positioning platform on the upper layer, two ends of the first cross rod and two ends of the second cross rod are respectively erected on the second beam and the fourth beam;
in the lower layer of the positioning platform, the two ends of the first cross rod and the two ends of the second cross rod are erected on the first beam and the third beam respectively.
As a further improvement of the above technical scheme, two ends of each first cross rod and two ends of each second cross rod are respectively connected with the corresponding positioning platform through bolts, at least one second connecting through hole is respectively arranged at two ends of each first cross rod and two ends of each second cross rod, a second long round hole matched with each second connecting through hole is respectively arranged on each positioning platform, and the length direction of each second long round hole on the same positioning platform is perpendicular to the length direction of each first long round hole on the positioning platform.
As a further improvement of the technical scheme, the positioning base frame comprises four upright posts, four corner positions of each positioning platform are fixedly connected with the upright posts respectively, and the bottoms of the upright posts are provided with anchoring plates.
The utility model has the advantages that: the utility model discloses a design a plurality of positioning platform, install adjustment mechanism on each positioning platform, put down after the top of bored concrete pile under the steel-pipe column, through adjusting the position of the location hoop on every positioning platform, realize fixing a position and fixing steel-pipe column top position, two upper and lower staple bolt subassemblies can cooperate the straightness that hangs down at adjustment steel-pipe column top to guarantee the holistic straightness that hangs down of steel-pipe column, each staple bolt subassembly cramps behind the steel-pipe column, avoid the steel-pipe column come-up when later stage concrete placement. The utility model discloses simple structure can ensure the straightness and the coordinate location of hanging down of steel-pipe column.
Drawings
In order to more clearly illustrate the technical solution in the embodiments of the present invention, the drawings used in the description of the embodiments will be briefly described below. It is clear that the described figures represent only some embodiments of the invention, not all embodiments, and that a person skilled in the art can also derive other designs and figures from these figures without inventive effort.
Fig. 1 is a perspective view of an embodiment of the present invention;
fig. 2 is a plan view of an embodiment of the present invention, wherein a steel pipe column is also shown;
fig. 3 is a schematic structural diagram of a positioning hoop in an embodiment of the present invention.
Detailed Description
The conception, the specific structure, and the technical effects produced by the present invention will be clearly and completely described below in conjunction with the embodiments and the accompanying drawings to fully understand the objects, the features, and the effects of the present invention. Obviously, the described embodiments are only a part of the embodiments of the present invention, and not all embodiments, and other embodiments obtained by those skilled in the art without inventive labor based on the embodiments of the present invention all belong to the protection scope of the present invention. In addition, all the coupling/connection relationships mentioned herein do not mean that the components are directly connected, but mean that a better coupling structure can be formed by adding or reducing coupling accessories according to specific implementation conditions.
Referring to fig. 1 and 2, an empty pile steel pipe column positioner, including the location bed frame, this location bed frame is provided with a plurality of locating platform 20, and each locating platform 20 is parallel arrangement from top to bottom in proper order, specifically speaking, in this embodiment, the location bed frame includes four stands 11, and locating platform 20 is total two, and four angular position of each locating platform 20 respectively with each stand 11 rigid coupling, anchor plate 12 is installed to each stand 11 bottom, when using empty pile steel pipe column positioner, each anchor plate 12 of accessible fixed is fixed.
Each positioning platform 20 is provided with an adjusting mechanism, and each adjusting mechanism comprises a cross rod assembly and a hoop assembly arranged on the cross rod assembly.
Each cross bar assembly comprises a first cross bar 31 and a second cross bar 32 parallel to each other. Each hoop component comprises two opposite positioning hoops 40, a positioning hole 61 for the steel pipe column 62 to pass through is arranged between the two opposite positioning hoops 40, a positioning surface for fitting the steel pipe column 62 is arranged in the middle of each positioning hoop 40, one end of each positioning hoop 40 is installed on the corresponding first cross rod 31 and can move along the length direction of the first cross rod 31, and the other end of each positioning hoop 40 is installed on the corresponding second cross rod 32 and can move along the length direction of the second cross rod 32. As shown in fig. 1, the first cross bar 31 of the upper positioning platform 20 is perpendicular to the first cross bar 31 of the lower positioning platform 20, and the second cross bar 32 of the upper positioning platform 20 is perpendicular to the second cross bar 32 of the lower positioning platform 20, that is, the hoop component movement adjusting direction of the upper positioning platform 20 is perpendicular to the hoop component movement adjusting direction of the lower positioning platform 20. Specifically, each positioning platform 20 is a square frame structure, and each positioning platform 20 includes a first beam 21, a second beam 22 perpendicular to the first beam 21, a third beam 23 perpendicular to the second beam 22, and a fourth beam 24 perpendicular to the third beam 23; in the upper positioning platform 20, two ends of the first cross bar 31 and two ends of the second cross bar 32 are respectively erected on the second beam 22 and the fourth beam 24; in the lower positioning platform 20, both ends of the first cross bar 31 and both ends of the second cross bar 32 are erected on the first beam 21 and the third beam 23, respectively.
Specifically, referring to fig. 3, each positioning hoop 40 includes an arc-shaped hoop arm 41 and adjusting seats disposed at two ends of the hoop arm 41, each adjusting seat includes a connecting plate 42 connected to the corresponding hoop arm 41 and a leveling plate 43 connected to the connecting plate 42, and each positioning surface is disposed on an inner side surface of the corresponding hoop arm. When using empty pile steel-pipe column positioner, transfer the back with steel-pipe column 62 along locating hole 61, through two staple bolt subassemblies adjustment steel-pipe column 62's position and straightness that hangs down, if only set up a staple bolt subassembly, need highly increasing staple bolt arm 41, otherwise be difficult to guarantee steel-pipe column 62's straightness that hangs down, still need be unanimous with the radian of the locating surface of staple bolt arm 41 and steel-pipe column 62 outer peripheral face simultaneously, otherwise the condition that the power of holding tightly is not enough appears easily. However, in this embodiment, the upper and lower positioning platforms 20 are two meters apart, that is, the upper and lower hoop assemblies are two meters apart, the two positioning hoops 40 of the upper positioning platform 20 tightly hold the steel pipe column 62, the clamping force direction is along the x-axis direction shown in fig. 1, the two positioning hoops 40 of the lower positioning platform 20 tightly hold the steel pipe column 62, and the clamping force direction is along the y-axis direction shown in fig. 1, even if the positioning surface of the hoop arm 41 is not consistent with the radian of the outer circumferential surface of the steel pipe column 62, the steel pipe column 62 can be positioned by the two positioning points of the upper positioning platform 20 and the two positioning points of the lower positioning platform 20, and the perpendicularity of the steel pipe column 62 can be adjusted.
Specifically, each level adjustment plate 43 is bolted to a corresponding first crossbar 31, each level adjustment plate 43 is bolted to a corresponding second crossbar 32, each level adjustment plate 43 is provided with at least one first connection through hole 51, and each first crossbar 31 and each second crossbar 32 are provided with a first oblong hole 52 that is matched with the corresponding first connection through hole 51.
And hydraulic cylinders 71 are arranged at two ends of each positioning hoop 40, the end part of a piston rod of each hydraulic cylinder 71 is pressed against the outer side of the corresponding adjusting seat, and a cylinder barrel of each hydraulic cylinder 71 is fixed on the corresponding first cross rod 31 or the corresponding second cross rod 32. Because the gravity of steel-pipe column is heavier, remove the steel-pipe column and move by the removal location hoop 40, it is comparatively difficult through manual operation, but set up each pneumatic cylinder 71 after, can adjust very conveniently.
In addition, the position of the cross bar assembly can be adjusted on the positioning platform 20, specifically, two ends of each first cross bar 31 and two ends of each second cross bar 32 are both connected with the corresponding positioning platform through bolts, at least one second connecting through hole 53 is respectively arranged at two ends of each first cross bar 31 and two ends of each second cross bar 32, second long round holes 54 matched with the second connecting through holes 53 are respectively arranged on each positioning platform 20, and the length direction of each second long round hole 54 on the same positioning platform is perpendicular to the length direction of each first long round hole 52 on the positioning platform. So, when can prevent that empty pile steel-pipe column from fixing a position, the dislocation is great, so also can adjust the horizontal pole subassembly, cooperates the staple bolt subassembly again, the position of adjustable locating hole. Of course, the adjustment can be performed by this method for steel pipe columns of different sizes. Of course, each first connecting through hole 51 may be disposed in an oblong manner, and in this case, the length direction of the first connecting through hole 51 is perpendicular to the length direction of the first oblong hole 52. Similarly, each second connecting through hole 53 may also be disposed in an oblong manner, and in this case, the length direction of the second connecting through hole 53 is perpendicular to the length direction of the second oblong hole 54.
When the empty pile steel pipe column positioning device is used, the concrete operation steps are as follows:
s1, fixing the empty pile steel pipe column positioning device;
s2, the steel pipe column 62 is lowered into the cast-in-place pile from the positioning hole 61 through a crane, and meanwhile, a plurality of lug plates are welded to the top of the steel pipe column 62, so that the steel pipe column 62 can be prevented from falling before adjustment;
s3, vertically releasing four dotted line marks on the steel pipe column 62 by using a measuring instrument (such as a total station) in advance, wherein the positions of the four dotted line marks are consistent with the positions of the positioning hoops 40 of the two positioning platforms 20, and the steel pipe column 62 is lowered to a set position, and at the moment, the steel pipe column 62 is still hoisted by a crane, and the position of the steel pipe column 62 is adjusted to enable the four dotted line marks to be overlapped with the positioning hoops 40;
and S4, moving each holding hoop 40, gradually holding the steel pipe column 62, paying attention to the positions marked by the four dotted lines and the verticality of the steel pipe column 62 in the process of adjustment, and finally holding the steel pipe column 62 by each holding hoop 40.
The embodiments of the present invention have been described in detail with reference to the accompanying drawings, but the present invention is not limited to the above embodiments, and various changes can be made without departing from the gist of the present invention within the scope of knowledge possessed by those skilled in the art.

Claims (8)

1. The utility model provides a blank pile steel-pipe column positioner which characterized in that: the steel pipe column positioning device comprises a positioning base frame, wherein the positioning base frame is provided with a plurality of positioning platforms (20), each positioning platform (20) is sequentially arranged in an up-and-down parallel manner, each positioning platform (20) is provided with an adjusting mechanism, each adjusting mechanism comprises a cross rod assembly and a hoop assembly arranged on the cross rod assembly, each cross rod assembly comprises a first cross rod (31) and a second cross rod (32) which are parallel to each other, each hoop assembly comprises two positioning hoops (40) which are oppositely arranged, a positioning hole (61) for a steel pipe column (62) to pass through is formed between the two opposite positioning hoops (40), the middle part of each positioning hoop (40) is provided with a positioning surface for attaching the steel pipe column (62), one end of each positioning hoop (40) is arranged on the corresponding first cross rod (31) and can move along the length direction of the first cross rod (31), and the other end of each positioning hoop (40) is arranged on the corresponding second cross rod (32) and can move along the second cross rod (32) 32) And moving in the length direction.
2. The empty pile steel pipe column positioning device according to claim 1, characterized in that: the number of the positioning platforms (20) is two, the upper layer is the first cross rod (31) of the positioning platform (20) is perpendicular to the lower layer, the second cross rod (32) of the positioning platform (20) is perpendicular to the lower layer, and the upper layer is the second cross rod (32) of the positioning platform (20).
3. The empty pile steel pipe column positioning device according to claim 2, characterized in that: each positioning hoop (40) comprises an arc-shaped hoop arm (41) and adjusting seats arranged at two ends of the hoop arm (41), each adjusting seat comprises a connecting plate (42) connected with the corresponding hoop arm (41) and a horizontal adjusting plate (43) connected with the connecting plate (42), and each positioning surface is arranged on the inner side surface of the corresponding hoop arm.
4. The empty pile steel pipe column positioning device according to claim 3, characterized in that: each level adjusting plate (43) is in bolted connection with the corresponding first cross rod (31), each level adjusting plate (43) is in bolted connection with the corresponding second cross rod (32), each level adjusting plate (43) is provided with at least one first connecting through hole (51), and each first cross rod (31) and each second cross rod (32) are respectively provided with a first long round hole (52) matched with the corresponding first connecting through hole (51).
5. The empty pile steel pipe column positioning device according to claim 4, characterized in that: and hydraulic cylinders (71) are arranged at two ends of each positioning hoop (40), the end parts of piston rods of the hydraulic cylinders (71) are pressed against the outer sides of the corresponding adjusting seats, and cylinder barrels of the hydraulic cylinders (71) are fixed on the corresponding first cross rods (31) or the corresponding second cross rods (32).
6. The empty pile steel pipe column positioning device according to claim 5, characterized in that: each positioning platform (20) is of a square frame structure, and each positioning platform (20) comprises a first beam (21), a second beam (22) perpendicular to the first beam (21), a third beam (23) perpendicular to the second beam (22) and a fourth beam (24) perpendicular to the third beam (23);
in the positioning platform (20) on the upper layer, two ends of the first cross rod (31) and two ends of the second cross rod (32) are respectively erected on the second beam (22) and the fourth beam (24);
in the lower layer of the positioning platform (20), two ends of the first cross rod (31) and two ends of the second cross rod (32) are erected on the first beam (21) and the third beam (23) respectively.
7. The empty pile steel pipe column positioning device according to claim 6, characterized in that: the two ends of each first transverse rod (31) and the two ends of each second transverse rod (32) are respectively in bolted connection with the corresponding positioning platforms, at least one second connecting through hole (53) is respectively arranged at the two ends of each first transverse rod (31) and the two ends of each second transverse rod (32), second long round holes (54) matched with the second connecting through holes (53) are respectively arranged on each positioning platform (20), and the length direction of each second long round hole (54) on the same positioning platform is perpendicular to the length direction of each first long round hole (52) on the positioning platform.
8. The empty pile steel pipe column positioning device according to claim 3, characterized in that: the positioning base frame comprises four upright posts (11), four corner positions of each positioning platform (20) are fixedly connected with the upright posts (11) respectively, and the bottom of each upright post (11) is provided with an anchoring plate (12).
CN201920593619.6U 2019-04-26 2019-04-26 Empty pile steel pipe column positioning device Active CN210194603U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920593619.6U CN210194603U (en) 2019-04-26 2019-04-26 Empty pile steel pipe column positioning device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920593619.6U CN210194603U (en) 2019-04-26 2019-04-26 Empty pile steel pipe column positioning device

Publications (1)

Publication Number Publication Date
CN210194603U true CN210194603U (en) 2020-03-27

Family

ID=69882060

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920593619.6U Active CN210194603U (en) 2019-04-26 2019-04-26 Empty pile steel pipe column positioning device

Country Status (1)

Country Link
CN (1) CN210194603U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111502307A (en) * 2020-05-01 2020-08-07 重庆交通大学 Multidirectional positioning device and positioning method for underground embedded steel pipe column
CN112681316A (en) * 2020-12-25 2021-04-20 中铁天丰建筑工程有限公司 Deep basal pit underground structure reverse construction method steel pipe column positioner

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111502307A (en) * 2020-05-01 2020-08-07 重庆交通大学 Multidirectional positioning device and positioning method for underground embedded steel pipe column
CN112681316A (en) * 2020-12-25 2021-04-20 中铁天丰建筑工程有限公司 Deep basal pit underground structure reverse construction method steel pipe column positioner

Similar Documents

Publication Publication Date Title
KR101614253B1 (en) Cantilever construction method of temporary bridge
CN111851565B (en) Steel structure stand column alignment structure with cup-mouth type foundation and construction method thereof
CN210194603U (en) Empty pile steel pipe column positioning device
JP6493939B2 (en) Ground reinforcing bar construction method
CN111877345B (en) Steel pipe pile positioning device for steel trestle construction in water area and construction method
CN106013206A (en) Steel pipe column positioning device and steel pipe concrete column and pile foundation connecting structure
CN202117074U (en) Foundation bed steel structure for positioning and mounting base of tower crane
CN205894490U (en) Steel core concrete column and pile foundation connection structure
CN216586578U (en) Supporting structure in foundation
CN212742614U (en) Foundation inner stand column positioning and mounting structure
JP4070748B2 (en) Bridge erection device and bridge erection method
CN210238492U (en) Crown beam type miniature pile construction formwork capable of being circulated
US6748717B2 (en) Method and system for emplacing prefabricated buildings
CN214301300U (en) Adjustable bracket system for mounting steel box girder
CN210366740U (en) Tower crane landing leg fixing device
CN109252536B (en) System and method for accurately positioning long and thin steel pull rod group
CN209779626U (en) Upright pile positioning and lowering auxiliary device
KR20130117171A (en) Cone mounting method of top side deck
CN213836527U (en) Auxiliary installation device for high-pile wharf berthing component
CN206512611U (en) A kind of empty rail bridge pier of suspension type, which is installed, uses ground frock
CN113006288B (en) Integral positioning device for embedded counter-force ground anchor and construction method
CN112304651A (en) Track beam static load test bed and construction method thereof
CN103276725A (en) Construction structure and construction method of anchor pile for large-tonnage test pile
CN116971355A (en) Water steel platform structure with tower crane foundation and installation method thereof
CN212926067U (en) Adjustable positioning device of steel pipe pile in water area suitable for vibratory hammer construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant