CN210164332U - Convenient bridge construction who adjusts is with isolation barrier - Google Patents

Convenient bridge construction who adjusts is with isolation barrier Download PDF

Info

Publication number
CN210164332U
CN210164332U CN201920702360.4U CN201920702360U CN210164332U CN 210164332 U CN210164332 U CN 210164332U CN 201920702360 U CN201920702360 U CN 201920702360U CN 210164332 U CN210164332 U CN 210164332U
Authority
CN
China
Prior art keywords
fixedly connected
inboard
spliced pole
hole
isolation barrier
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201920702360.4U
Other languages
Chinese (zh)
Inventor
吴应天
黄城伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201920702360.4U priority Critical patent/CN210164332U/en
Application granted granted Critical
Publication of CN210164332U publication Critical patent/CN210164332U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a convenient bridge construction of adjusting is with isolation barrier, including first spliced pole and second spliced pole, the top on first spliced pole right side and the equal fixedly connected with connecting pipe in bottom, the second through-hole has been seted up to the inboard of connecting pipe, the left top of second spliced pole and the equal fixedly connected with connecting rod in bottom, first through-hole has been seted up on the surface of connecting rod. The utility model discloses a first spliced pole, fixed stop gear, coupling mechanism, the second chassis, the second spliced pole, the connecting rod, first through-hole, the cooperation of second through-hole and connecting pipe, can effectually adjust its length, it is comparatively convenient when using to make things convenient for people, reduce a large amount of operating time simultaneously, it is not convenient for adjust to have solved current isolation barrier, not only its length all is fixed connection, and the connection position is all welded and is formed, because its whole length is too long again, in order to lead to people comparatively loaded down with trivial details problem when using.

Description

Convenient bridge construction who adjusts is with isolation barrier
Technical Field
The utility model relates to an isolation barrier technical field specifically is a convenient bridge construction of adjusting is with isolation barrier.
Background
The bridge is a building constructed for a road to cross natural or artificial barriers, is erected on rivers, lakes and seas to enable vehicles, pedestrians and the like to smoothly pass through, and generally consists of an upper structure, a lower structure and an auxiliary structure, wherein the upper structure mainly refers to a bridge span structure and a support system, the lower structure comprises a bridge abutment, a bridge pier and a foundation, the auxiliary structure refers to a bridge head butt strap, a conical protection slope, a protection bank, a diversion project and the like, the bridge is divided according to a structural system and comprises four basic systems of a beam bridge, an arch bridge, a rigid frame bridge and a suspension cable bearing, the bridge construction refers to a process of constructing the bridge according to design contents, mainly refers to contents of bridge construction technology, construction organization, construction management, construction quality and the like, and in the construction process, non-workers are prohibited to enter due to danger, an isolation guardrail is required at the moment, and has the effect of isolating a construction site from the outside, but current isolation barrier is not convenient for adjust, and not only its length all is fixed connection, and the connection part all welds moreover and forms, and because its whole length is too long again to lead to people comparatively loaded down with trivial details when using, for this reason, we provide a bridge construction that conveniently adjusts and use isolation barrier.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a convenient bridge construction of adjusting is with isolation barrier possesses adjustable advantage, has solved current isolation barrier and is not convenient for adjust, and not only its length all is fixed connection, connects the position moreover and all welds and form, because its whole length is too long again to lead to the comparatively loaded down with trivial details problem of people when using.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a convenient bridge construction of adjusting is with isolation barrier, includes first spliced pole and second spliced pole, the top on first spliced pole right side and the equal fixedly connected with connecting pipe in bottom, the second through-hole has been seted up to the inboard of connecting pipe, the left top of second spliced pole and the equal fixedly connected with connecting rod in bottom, first through-hole has been seted up on the surface of connecting rod, the connecting pipe all is provided with fixed stop gear with the inboard of connecting rod, fixed stop gear's inboard is provided with coupling mechanism.
Preferably, fixed stop gear is including card strip and montant, card strip joint in the inner chamber of first through-hole and second through-hole, the inboard fixedly connected with connecting plate of card strip, the inboard fixedly connected with telescopic link of connecting plate, the inboard of connecting plate and the outside fixedly connected with spring that is located the telescopic link, the top and the bottom of montant all set up flutedly, the equal fixed connection in the inner chamber of recess of inboard of spring and telescopic link.
Preferably, coupling mechanism includes the connecting block, connecting block fixed connection is in the inboard upper end and the lower extreme of montant, the inboard fixedly connected with go-between of connecting block, the inboard fixedly connected with iron chain of go-between.
Preferably, the bottoms of the first connecting column and the second connecting column are fixedly connected with a first chassis and a second chassis respectively.
Compared with the prior art, the beneficial effects of the utility model are as follows:
the utility model discloses a first spliced pole, fixed stop gear, coupling mechanism, the second chassis, the second spliced pole, the connecting rod, first through-hole, the cooperation of second through-hole and connecting pipe, can effectually adjust its length, it is comparatively convenient when using to make things convenient for people, reduce a large amount of operating time simultaneously, it is not convenient for adjust to have solved current isolation barrier, not only its length all is fixed connection, and the connection position is all welded and is formed, because its whole length is too long again, in order to lead to people comparatively loaded down with trivial details problem when using.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic structural view of the fixing and limiting mechanism of the present invention;
fig. 3 is a schematic view of the structure of the connection mechanism of the present invention.
In the figure: the device comprises a first connecting column 1, a fixed limiting mechanism 2, a vertical rod 21, a telescopic rod 22, a spring 23, a clamping strip 24, a connecting plate 25, a groove 26, a first chassis 3, a connecting mechanism 4, a connecting block 41, a connecting ring 42, an iron chain 43, a second chassis 5, a second connecting column 6, a connecting rod 7, a first through hole 8, a second through hole 9 and a connecting pipe 10.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-3, an isolation barrier for bridge construction convenient to adjust comprises a first connection column 1 and a second connection column 6, wherein the bottoms of the first connection column 1 and the second connection column 6 are respectively and fixedly connected with a first chassis 3 and a second chassis 5, the top and the bottom of the right side of the first connection column 1 are respectively and fixedly connected with a connection pipe 10, the length of the isolation barrier can be effectively adjusted, so that people can use the isolation barrier conveniently, and a large amount of working time is reduced, thereby solving the problems that the existing isolation barrier is not convenient to adjust, not only the length of the isolation barrier is fixedly connected, but also the connection parts are welded, the overall length of the isolation barrier is too long, so that people use the isolation barrier is complicated, a second through hole 9 is formed in the inner side of the connection pipe 10, a connection rod 7 is fixedly connected with the top and the bottom of the left side of the second connection column 6, and a first through hole 8 is, connecting pipe 10 all is provided with fixed stop gear 2 with the inboard of connecting rod 7, fixed stop gear 2 is including card strip 24 and montant 21, card strip 24 joint in the inner chamber of first through-hole 8 and second through-hole 9, the inboard fixedly connected with connecting plate 25 of card strip 24, the inboard fixedly connected with telescopic link 22 of connecting plate 25, the inboard outside fixedly connected with spring 23 that just is located telescopic link 22 of connecting plate 25, recess 26 has all been seted up with the bottom at the top of montant 21, the equal fixed connection in the inner chamber of recess 26 in the inboard of spring 23 and telescopic link 22, the inboard of fixed stop gear 2 is provided with coupling mechanism 4, coupling mechanism 4 includes connecting block 41, connecting block 41 fixed connection is in the inboard upper end and the lower extreme of montant 21, the inboard fixedly connected with go-between 42 of connecting block 41, the inboard fixedly connected with iron chain.
When in use, the connecting rod 7 and the connecting pipe 10 are in a sleeved connection, the distance between the first connecting post 1 and the second connecting post 6 can be adjusted, the clamping strip 24 penetrates through the second through hole 9 and the first through hole 8 and can be used for limiting and fixing the vertical rod 21, the plurality of first through holes 8 and the plurality of second through holes 9 are formed so as to adjust the position of the vertical rod 21 along with the adjustment of the distance between the connecting rod 7 and the connecting pipe 10, the connecting ring 42 connected with the connecting block 41 and the iron chain 43 connected with the inner side of the connecting ring 42 are used for isolating and connecting the vertical rod, when the adjustment is needed, the connecting plate 25 is manually squeezed inwards to squeeze the telescopic rod 22 and the spring 23 by the connecting plate 25 so as to enable the clamping strip 24 to leave the original first through hole 8 and the original second through hole 9, after the disassembly is completed, the clamping strip 24 can be inserted into the new first through hole 8 and the new second through hole 9 along with the requirements of a user, at this moment, the installation can be completed, the length of the isolation guardrail can be effectively adjusted, so that the isolation guardrail is convenient and fast to use, a large amount of working time is reduced, the problem that the existing isolation guardrail is inconvenient to adjust, the length of the isolation guardrail is not only fixedly connected, but also the connecting part is welded, and the problem that the whole length of the isolation guardrail is too long so as to cause people to be more fussy in use is solved.
In summary, the following steps: this convenient bridge construction of adjusting is with isolation barrier, through first spliced pole 1, fixed stop gear 2, coupling mechanism 4, second chassis 5, second spliced pole 6, connecting rod 7, first through-hole 8, the cooperation of second through-hole 9 and connecting pipe 10, can effectually adjust its length, it is comparatively convenient when using to make things convenient for people, reduce a large amount of operating time simultaneously, it is not convenient for adjust to have solved current isolation barrier, not only its length all is fixed connection, and the equal welding in connection position forms, because its whole length is too long again, in order to lead to people comparatively loaded down with trivial details problem when using.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (4)

1. The utility model provides a convenient bridge construction who adjusts is with isolation barrier, includes first spliced pole (1) and second spliced pole (6), its characterized in that: the top and the equal fixedly connected with connecting pipe (10) in bottom on first spliced pole (1) right side, second through-hole (9) have been seted up to the inboard of connecting pipe (10), the left top of second spliced pole (6) and the equal fixedly connected with connecting rod (7) in bottom, first through-hole (8) have been seted up on the surface of connecting rod (7), connecting pipe (10) all are provided with fixed stop gear (2) with the inboard of connecting rod (7), the inboard of fixed stop gear (2) is provided with coupling mechanism (4).
2. The conveniently adjusted isolation barrier for bridge construction according to claim 1, wherein: fixed stop gear (2) are including card strip (24) and montant (21), card strip (24) joint in the inner chamber of first through-hole (8) and second through-hole (9), the inboard fixedly connected with connecting plate (25) of card strip (24), the inboard fixedly connected with telescopic link (22) of connecting plate (25), the inboard of connecting plate (25) just is located outside fixedly connected with spring (23) of telescopic link (22), recess (26) are all seted up with the bottom at the top of montant (21), the inner chamber of recess (26) is all fixedly connected with in the inboard of spring (23) and telescopic link (22).
3. The conveniently-adjusted isolation fence for bridge construction according to claim 1 or 2, wherein: coupling mechanism (4) are including connecting block (41), connecting block (41) fixed connection is in the inboard upper end and the lower extreme of montant (21), the inboard fixedly connected with go-between (42) of connecting block (41), the inboard fixedly connected with iron chain (43) of go-between (42).
4. The conveniently adjusted isolation barrier for bridge construction according to claim 1, wherein: the bottom of the first connecting column (1) and the bottom of the second connecting column (6) are respectively and fixedly connected with a first chassis (3) and a second chassis (5).
CN201920702360.4U 2019-05-16 2019-05-16 Convenient bridge construction who adjusts is with isolation barrier Expired - Fee Related CN210164332U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920702360.4U CN210164332U (en) 2019-05-16 2019-05-16 Convenient bridge construction who adjusts is with isolation barrier

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920702360.4U CN210164332U (en) 2019-05-16 2019-05-16 Convenient bridge construction who adjusts is with isolation barrier

Publications (1)

Publication Number Publication Date
CN210164332U true CN210164332U (en) 2020-03-20

Family

ID=69793076

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920702360.4U Expired - Fee Related CN210164332U (en) 2019-05-16 2019-05-16 Convenient bridge construction who adjusts is with isolation barrier

Country Status (1)

Country Link
CN (1) CN210164332U (en)

Similar Documents

Publication Publication Date Title
CN204753354U (en) Cover worker's board landing stage
CN206346118U (en) A kind of large-span steel pipe truss beam falsework
CN210164332U (en) Convenient bridge construction who adjusts is with isolation barrier
CN211368438U (en) Reinforcing apparatus that bridge concatenation was used
CN210134699U (en) Fender is enclosed in construction of height-adjusting of being convenient for building
CN209024976U (en) A kind of more hoop brackets of Bridge High-pier Coping Construction
CN110485258A (en) A kind of full assembling type steel structure access bridge and its construction method
CN215758594U (en) Widened pier column steel column tie beam device
CN213389686U (en) Vase pier capping beam structure
CN211420912U (en) Support frame for supporting bridge
CN206091416U (en) Multi -functional assembled suspension fretwork platform of ecological environment -friendly
CN216275683U (en) Manual hole digging pile filling platform convenient to use
CN208486165U (en) A kind of concrete circular stub and girder steel consolidate connecting structure
CN211897788U (en) Assembled steel and concrete combined bridge
CN106320175A (en) Simple device for connecting steel pipe support piers
CN206090194U (en) Multi -functional suspension platform of ecological environment -friendly
CN214996608U (en) Safety protection net is used in highway construction
CN212335795U (en) Liftable bridge maintenance device
CN215052225U (en) Drag construction reaction frame device
CN215482279U (en) Bridge steel structure for stably connecting bridge expansion joints
CN217231491U (en) Two-way support system of pre-buried formula in operation pier position on water
CN212953863U (en) Municipal administration bridge construction is with supplementary hoisting structure
CN214657999U (en) Connecting structure for quickly assembling shear wall
CN220579925U (en) Combined template for construction of overflow surface hole downstream inverted suspension body
CN210341627U (en) Municipal administration bridge hinge joint reinforcing apparatus

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200320

Termination date: 20210516