CN210002827U - Climbing frame gap bridge of connection tower cranes - Google Patents
Climbing frame gap bridge of connection tower cranes Download PDFInfo
- Publication number
- CN210002827U CN210002827U CN201920658307.9U CN201920658307U CN210002827U CN 210002827 U CN210002827 U CN 210002827U CN 201920658307 U CN201920658307 U CN 201920658307U CN 210002827 U CN210002827 U CN 210002827U
- Authority
- CN
- China
- Prior art keywords
- climbing frame
- building
- gap bridge
- tower crane
- frame
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Jib Cranes (AREA)
Abstract
The utility model relates to a building climbs the passageway field between frame and tower crane, more specifically says, it relates to kinds of climbing frame gap bridges of connecting the tower crane, and its technical scheme main points are including being used for fixed connection to climb the horizontal guidance tape of walking of frame, keep away from the building and climb the frame walk guidance tape end and be close to the tower crane and climb the frame, walk the guidance tape and keep away from the both sides that building climbed end and the building and climb the frame and be located all fixed being provided with the link on walking the guidance tape top, be located the link between guidance tape and the building climbing frame and hang and be equipped with wire rope, the utility model discloses a kind of climbing frame gap bridges of connecting the tower crane have the advantage of tower crane about the staff of convenience.
Description
Technical Field
The utility model relates to a building climbs the passageway field between frame and tower crane, more specifically says, and it relates to the climbing frame gap bridge of connection tower cranes.
Background
Along with the development of the society, the tower crane is visible everywhere in the city, simultaneously the tower crane is also the most commonly used kinds of hoisting equipment on the building site and is also named as a tower crane, with sections sections of extension, is used for hanging construction raw materials such as reinforcing steel bars, wooden ridges, concrete, steel pipes and the like, the tower crane is indispensable equipment on the building site, however, when staff climb and lower the tower crane, there is very big potential safety hazard, to climbing and lower the tower crane, also unnecessary safety measure.
Aiming at the problems, at present, chinese patent with publication number CN208726656U discloses , which has the technical scheme that the device comprises a vertical rod and arc-shaped guard rails, wherein the inner surfaces of the arc-shaped guard rails are welded with guard rail fixing plates, sliding grooves are formed in sides of the guard rail fixing plates far away from the arc-shaped guard rails, sliding blocks are connected to the inner walls of the sliding grooves in a sliding mode, 0 sides of the sliding blocks are fixedly connected with ends of steel wire ropes, fixing blocks are fixedly connected with other ends of steel wire ropes, sides of the fixing blocks are fixedly connected with strap fixing plates, straps are fixedly connected to two sides of the strap fixing plates, sides of the fixing blocks are fixedly connected with ends of second steel wire ropes, and other ends of the.
Above-mentioned scheme is equipped with anti-skidding line through climbing the pole, can prevent that the condition such as hand is smooth and the foot from taking place, and the staff wears the braces, can prevent unexpected emergence when the climbing. However, as the tower crane is higher, the time and labor of the staff are wasted when the tower crane is lifted up and down in a climbing mode.
SUMMERY OF THE UTILITY MODEL
Not enough to prior art exists, the utility model aims to provide a climbing frame gap bridge of kinds of connection tower cranes has the advantage of making things convenient for the upper and lower tower cranes of staff.
kinds of climbing frame of connecting the tower crane cross the bridge, including being used for fixed connection to climb the frame upgradable guidance tape in the building, keep away from the building and climb the frame walk guidance tape end and be close to the tower crane and climb the frame, walk the guidance tape and keep away from the both sides that the building climbed held and the building climbs the frame and be located and all fix on walking guidance tape top and be provided with the link, lie in and walk the guidance tape and build the link between the frame and hang and be equipped with wire rope.
Through adopting above-mentioned technical scheme, the tower crane staff rises to the high floor that the building is good through the goods ladder earlier on, then the rethread is connected and is climbed and tower crane and climb the guidance tape between the frame and enter into the tower crane control chamber and carry out work at the building, slowly climb up through the cat ladder among the prior art and enter into the tower crane control chamber and compare, very big tower crane about having made things convenient for the staff.
The utility model discloses step sets up to walk the board both sides and all be provided with the rail guard.
By adopting the technical scheme, the safety factor of workers passing through the walkway plate is improved by arranging the guard railings on the two sides of the walkway plate.
The utility model discloses step sets up to building climbing frame department installs protection , protection is fixed with building climbing frame through the tool to lock.
Through adopting above-mentioned technical scheme, through protection and install the tool to lock on protection to avoid non-staff to pass through walkways board business turn over tower crane.
The utility model discloses step sets up to be that the support rod is obliquely arranged between the both sides of the lower surface of the walkway plate and the building climbing frame.
Through adopting above-mentioned technical scheme, climb the bracing piece between the frame through setting up at guidance tape and building to it improves the stability of guidance tape installation to advance steps.
The utility model discloses advance step and set up as the bracing piece includes mount pad, screw rod and threaded sleeve threaded connection, the mount pad sets up two, two the mount pad is articulated with screw rod and threaded sleeve's tip respectively, and two mount pads are installed respectively on pavement board lower surface and building climb the frame, threaded sleeve is including rotation portion and connecting portion, rotation portion and connecting portion rotate to be connected, rotation portion end and screw rod threaded connection in addition, connecting portion end articulates on the mount pad.
Through adopting above-mentioned technical scheme, through rotating the threaded sleeve to adjust the length of screw rod, and then adjust and support intensity.
The utility model is characterized in that steps are that the side wall of the rotating part is symmetrically provided with a rotating handle.
Through adopting above-mentioned technical scheme, through rotating the handle, make things convenient for threaded sleeve's rotation.
The utility model discloses advance step and set up as walk the curb plate lower surface and the lateral wall of building climbing frame and all set up the caulking groove that supplies the mount pad to put into, the caulking groove lateral wall is seted up and is supplied mount pad male mounting groove, walk and offer the hole of stepping down that communicates with the mounting groove on curb plate and the building climbing frame.
Through adopting above-mentioned technical scheme, the mount pad is installed in inserting the mounting groove through the caulking groove to, thereby, improve the stability of mount pad installation.
The utility model discloses step sets up to be that the caulking groove is pegged graft with the abaculus, the abaculus passes through bolt fixed connection in the caulking groove.
Through adopting above-mentioned technical scheme, when the mount pad was installed in the mounting groove, install the abaculus in the caulking groove through the bolt to it further step improves the stability of mount pad installation.
To sum up, the utility model discloses following beneficial effect has:
, tower crane workers firstly ascend to a high building floor through a goods elevator and then enter a tower crane operation room through a walkway plate connected between a building climbing frame and a tower crane climbing frame to work, and compared with the prior art that the workers slowly climb up to enter the tower crane operation room through a crawling ladder, the tower crane operation room greatly facilitates the workers to get on and off the tower crane;
secondly, through the bracing piece that sets up between the guidance tape and the building climbs the frame to it improves the stability of guidance tape installation to advance steps.
Drawings
FIG. 1 is a schematic view of the installation structure of the gap bridge and the building climbing frame in the embodiment;
fig. 2 is a schematic view of a part of the installation structure of the walkway plate, the building climbing frame and the installation base in the embodiment after being cut open.
In the drawing, the building climbing frame comprises 1, 2, a walkway plate, 3, a high-rise floor slab, 4, a lifting ring, 5, a steel wire rope, 6, a protective guard, 7, a protective , 8, a lock, 9, a supporting rod, 10, an installation seat, 11, a screw rod, 12, a threaded sleeve, 13, a rotating part, 14, a connecting part, 15, a limiting ring, 16, a rotating handle, 17, an embedded groove, 18, an installation groove, 19, an abdicating hole, 20 and an embedded block.
Detailed Description
The present invention will be described in detail with reference to the accompanying drawings and examples.
climbing frame gap bridge connecting tower cranes, as shown in figure 1, including the walkway plate 2 used for fixed connection on the building climbing frame 1, walkway plate 2 is fixed on the building climbing frame 1 through bolts, the walkway plate 2 end far away from the building climbing frame 1 is close to the tower crane climbing frame, walkway plate 2 is parallel and level with the built high-rise floor 3, the two sides of walkway plate 2 far away from the building climbing frame 1 end and the building climbing frame 1 are both fixed with a hanging ring above the walkway plate 2, the hanging ring between the walkway plate 2 and the building climbing frame 1 is hung with a steel wire rope 5. the building climbing frame 1 is mainly applied to high-rise shear wall type building discs and can climb up along with the building.
As shown in figure 1, steps are taken, protective guards 6 are vertically arranged on two sides of a walkway plate 2, and safety factors of workers passing through the walkway plate 2 are improved through the protective guards 6 arranged on the two sides of the walkway plate, and a protection 7 is arranged on a building climbing frame 1 located at the walkway plate 2, a protection 7 is fixed with the building climbing frame 1 through a lock 8, and the non-workers are prevented from entering and exiting the tower crane through the walkway plate 2 through the protection 7 and the lock 8 arranged on the protection 7.
As shown in fig. 1 and 2, a support rod 9 is obliquely arranged between two sides of the lower surface of the walkway plate 2 and the building climbing frame 1, specifically, the support rod 9 includes two installation bases 10, a screw 11 and a threaded sleeve 12, the screw 11 is in threaded connection with the threaded sleeve 12, the installation bases 10 are provided with two ends, the two installation bases 10 are respectively hinged to the ends of the screw 11 and the threaded sleeve 12, the two installation bases 10 are respectively installed on the lower surface of the walkway plate 2 and the building climbing frame 1, the threaded sleeve 12 includes a rotating portion 13 and a connecting portion 14, the rotating portion 13 and the connecting portion 14 are rotatably connected through a limit ring 15 fixedly arranged on the connecting portion 14, another end of the rotating portion 13 is in threaded connection with the screw 11, a rotating handle 16 is symmetrically arranged on the side wall of the rotating portion 13, an end of the connecting portion 14 is hinged to the installation bases 10, and the threaded sleeve 12 is rotated, so.
As shown in fig. 2, the lower surface of the walkway plate 2 and the side wall of the building creeper 1 are both provided with an embedded groove 17 for the installation seat 10 to be placed in, the side wall of the embedded groove 17 is provided with an installation groove 18 for the installation seat 10 to be inserted in, and the walkway plate 2 and the building creeper 1 are provided with a abdicating hole 19 communicated with the installation groove 18. the installation seat 10 is installed by inserting the embedded groove 17 into the installation groove 18, so as to improve the installation stability of the installation seat 10. the embedded block 20 is inserted in the embedded groove 17, the embedded block 20 is fixedly connected in the embedded groove 17 through a bolt, when the installation seat 10 is installed in the installation groove 18, the embedded block 20 is installed in the embedded groove 17 through a bolt, so as to further improve the installation stability of the installation seat.
The embodiment of this specific implementation mode is the preferred embodiment of the present invention, not limit according to this the utility model discloses a protection scope, so: all equivalent changes made according to the structure, shape and principle of the utility model are covered within the protection scope of the utility model.
Claims (8)
- The climbing frame gap bridge of the tower crane is connected to , and is characterized in that the climbing frame gap bridge comprises a track board (2) which is fixedly connected to the building climbing frame (1) and is horizontal, the track board (2) end is close to the tower crane climbing frame, the track board (2) is far away from the two sides of the building climbing frame (1) end, the building climbing frame (1) is located above the track board (2) and is fixedly provided with a hanging ring, and a steel wire rope (5) is hung on the hanging ring between the track board (2) and the building climbing frame (1).
- 2. The climbing frame gap bridge of kinds of connection tower cranes of claim 1, characterized in that both sides of the walkway plate (2) are provided with guard rails (6).
- 3. The climbing frame gap bridge of kinds of connection tower cranes of claim 1, characterized in that the building climbing frame (1) is installed with a protection (7), the protection (7) is fixed with the building climbing frame (1) through a lock (8).
- 4. The climbing frame gap bridge of kinds of connection tower cranes of claim 1, characterized in that a support bar (9) is obliquely arranged between the two sides of the lower surface of the walkway plate (2) and the building climbing frame (1).
- 5. The climbing frame gap bridge of connection towers according to claim 4, wherein the bracing piece (9) includes mount pad (10), screw rod (11) and threaded sleeve (12) threaded connection, mount pad (10) set up two, two mount pad (10) are articulated with the tip of screw rod (11) and threaded sleeve (12) respectively, install respectively on pavement board (2) lower surface and building climbing frame (1) two mount pads (10), threaded sleeve (12) are including rotating portion (13) and connecting portion (14), it rotates to be connected to rotate portion (13) and connecting portion (14), it connects with screw rod (11) threaded connection to rotate portion (13) in addition end, connecting portion (14) end articulates on mount pad (10).
- 6. The climbing frame gap bridge of kinds of connection tower cranes of claim 5, characterized in that the side wall of the rotating part (13) is symmetrically provided with rotating handles (16).
- 7. The climbing frame gap bridges of connecting tower cranes of claim 5, wherein the lower surface of the walkway plate (2) and the side wall of the building climbing frame (1) are both provided with caulking grooves (17) for the installation seats (10) to be put in, the side wall of the caulking grooves (17) is provided with installation grooves (18) for the installation seats (10) to be inserted, and the walkway plate (2) and the building climbing frame (1) are provided with abdicating holes (19) communicated with the installation grooves (18).
- 8. The climbing frame gap bridge of kinds of connection tower cranes of claim 7, characterized in that an insert block (20) is inserted in the insert groove (17), and the insert block (20) is fixedly connected in the insert groove (17) through a bolt.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920658307.9U CN210002827U (en) | 2019-05-08 | 2019-05-08 | Climbing frame gap bridge of connection tower cranes |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920658307.9U CN210002827U (en) | 2019-05-08 | 2019-05-08 | Climbing frame gap bridge of connection tower cranes |
Publications (1)
Publication Number | Publication Date |
---|---|
CN210002827U true CN210002827U (en) | 2020-01-31 |
Family
ID=69306235
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201920658307.9U Active CN210002827U (en) | 2019-05-08 | 2019-05-08 | Climbing frame gap bridge of connection tower cranes |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN210002827U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113174808A (en) * | 2021-04-16 | 2021-07-27 | 江苏宏基铝业科技股份有限公司 | Pavement slab splicing ultrathin aluminum profile |
-
2019
- 2019-05-08 CN CN201920658307.9U patent/CN210002827U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113174808A (en) * | 2021-04-16 | 2021-07-27 | 江苏宏基铝业科技股份有限公司 | Pavement slab splicing ultrathin aluminum profile |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US8511039B2 (en) | Safety barrier for multi-storey buildings | |
US5159993A (en) | Self-raising work platform assembly | |
US20100293875A1 (en) | Stairway for Use on Building Sites | |
NZ556204A (en) | Integral safety system which can be used for construction | |
KR100989111B1 (en) | Tilting access stairway structure for approaching bridge inspection passage | |
CN210002827U (en) | Climbing frame gap bridge of connection tower cranes | |
US6340070B1 (en) | Adjustable cantilever scaffolding | |
CN110886488A (en) | Intelligent integrated high-rise building machine | |
CN210857952U (en) | Novel attached lifting scaffold | |
CN210976461U (en) | Integrated integral construction platform in elevator shaft | |
JP3950800B2 (en) | Suspension scaffold | |
CN211776076U (en) | Steel construction retractable cat ladder of going to people for elevator well | |
CN207079889U (en) | A kind of working assembling type mobile construction platform of ceiling | |
NZ242874A (en) | Cantilevered and adjustably suspended worker's staging or platform with jack devices exteriorly of structure's wall | |
CN212802412U (en) | Tower type scaffold for artificial passage | |
CN215670884U (en) | Assembly type building staircase operation platform | |
US20070267249A1 (en) | Roof safety system | |
CN114427304A (en) | Assembled type edge-facing protection device for cast-in-place concrete stairs | |
CN209874468U (en) | Construction hydraulic pressure template climbing device | |
CN216276806U (en) | Novel integral lifting type operation platform for elevator shaft construction | |
JP4011722B2 (en) | Hanging stairs | |
JPH0755777B2 (en) | Elevator installation method and installation work floor equipment | |
CN217840841U (en) | High-altitude movable ladder-hanging type auxiliary construction system | |
CN214169873U (en) | Hanging basket for mounting loading platform | |
CN220036073U (en) | Assembled stairwell construction is with operation steel platform |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |