CN209907369U - Building pile - Google Patents

Building pile Download PDF

Info

Publication number
CN209907369U
CN209907369U CN201920457691.6U CN201920457691U CN209907369U CN 209907369 U CN209907369 U CN 209907369U CN 201920457691 U CN201920457691 U CN 201920457691U CN 209907369 U CN209907369 U CN 209907369U
Authority
CN
China
Prior art keywords
pile
pile body
fastening
reinforcing
tighrening
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920457691.6U
Other languages
Chinese (zh)
Inventor
龙方
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Long Hao Building Survey Design Co Ltd
Original Assignee
Zhejiang Long Hao Building Survey Design Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Long Hao Building Survey Design Co Ltd filed Critical Zhejiang Long Hao Building Survey Design Co Ltd
Priority to CN201920457691.6U priority Critical patent/CN209907369U/en
Application granted granted Critical
Publication of CN209907369U publication Critical patent/CN209907369U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model relates to a building pile, including the pile body, pile body bottom set to coniform, the cover is equipped with the tighrening ring on the pile body, has seted up the sliding tray on the lateral wall of pile body, the sliding tray be parallel with the rotation axis of pile body, the fixed sliding block that is provided with on the inside wall of tighrening ring, the cross section of sliding block equals with the cross section of sliding tray, the sliding block inlay and establish and remove at the sliding tray and along the sliding tray, the fixed dead lever that is provided with the perpendicular to pile body on the tighrening ring, one of keeping away from the pile body at the dead lever is served and is provided with the reinforcement pile, the axis of rotation of reinforcement pile and pile body is parallel, and the position that the reinforcement pile is connected with the dead lever is located the bottom surface of dead lever. The position of the building pile can be conveniently fixed, so that the pile body is not easy to incline or move transversely.

Description

Building pile
Technical Field
The utility model relates to a building apparatus's technical field especially relates to a building pile.
Background
With the development of cities, high-rise buildings are more and more. The building pile is a building tool and is mainly used for a foundation device which is driven into soil to support a building at the upper part of the building pile, so that the building pile is widely applied to the field of building engineering; current building pile includes pile body and stake point, and the stake point setting is in the bottom of pile body, and when using, through strikeing the pile body, uses the stake point to go forward downwards in earth to finally fix. Building pile all is vertical ground of inserting under great pressure, like the nail goes into wood, leans on the extrusion of earth all around, only receives vertical direction's frictional resistance, and solid steadiness is not high. During construction, the ground is often vibrated, so that the pile body can incline to the side or move transversely, and the pile body is unstable during use.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing a can make the difficult building pile that appears slope and longitudinal movement of pile body.
The above object of the present invention can be achieved by the following technical solutions: the utility model provides a building pile, includes the pile body, pile body bottom set to coniform, the cover is equipped with the tighrening ring on the pile body, has seted up the sliding tray on the lateral wall of pile body, the sliding tray be parallel with the rotation axis of pile body, the fixed sliding block that is provided with on the inside wall of tighrening ring, the cross section of sliding block equals with the cross section of sliding tray, the sliding block inlay to establish and remove in the sliding tray and along the sliding tray, the fixed dead lever that is provided with the perpendicular to pile body on the tighrening ring, one of keeping away from the pile body at the dead lever serves and is provided with the reinforcement stake, the axis of rotation of reinforcement stake and pile body is parallel, and the position that reinforcement stake and dead lever are connected is located the bottom surface of dead lever.
Through adopting above-mentioned technical scheme, can be when installing this building pile, earlier at subaerial excavation ground groove, later squeeze into the bottom surface in ground groove with the pile body, then overlap the tighrening ring from pile body upside cover on the pile body to make the bottom surface in dead lever and tighrening ring laminating ground groove, in squeezing into the bottom surface in ground groove with the reinforcement stake after that, reuse soil backfills ground groove at last. The position of tighrening ring is fixed by the reinforced pile, makes the pile body of cover establishing in the tighrening ring only can remove along the direction of perpendicular to tighrening ring to fix the position of this building pile, make the difficult phenomenon that slopes or lateral shifting appear of pile body, comparatively stable during the use.
The utility model discloses further set up to: the end of the fixed rod far away from the pile body is provided with a reinforcing hole, and the reinforcing pile is arranged in the reinforcing hole in a penetrating mode.
Through adopting above-mentioned technical scheme, can be when installation tighrening ring and dead lever, place the position of tighrening ring and dead lever earlier, later wear to establish in the reinforcing pile with the reinforcing pile again, it is more convenient in the installation. And the building pile can be conveniently transported.
The utility model discloses further set up to: the fixed rods are provided with at least three fixed rods, and the distance between the joints of the two adjacent fixed rods and the fastening ring is equal.
Through adopting above-mentioned technical scheme, the dead lever of at least three can be stable with the position fixed column of tighrening ring, and when vibration appeared in the ground, the all directions of tighrening ring all had the supplementary structure that supports to make the pile body can be stable by the support.
The utility model discloses further set up to: the cross section of sliding block be the sector ring shape, and one side of laminating tighrening ring in this sector ring shape keeps away from one side of its place circle centre department for the sector ring shape, the sliding block is provided with two at least, the interval between two adjacent sliding blocks equals.
By adopting the technical scheme, when the fastening ring is sleeved on the pile body, the fastening ring can only move up and down along the pile body. The area of junction is bigger between sliding block and the tighrening ring, connects more firmly, receives external force at the tighrening ring and when having the pivoted trend, the phenomenon of fracture on the tighrening ring is more difficult to appear following to the sliding block.
The utility model discloses further set up to: the lateral surface of tighrening ring on fixed be provided with the fastening block, seted up the fastening blind hole on the side of tighrening block keeping away from tighrening ring centre of a circle department, the dead lever wear to establish in the fastening blind hole, wear to be equipped with the fastening axle on the side of tighrening block, the length of fastening axle be greater than the width of tighrening block, the fastening axle passes tighrening block and dead lever simultaneously.
Through adopting above-mentioned technical scheme, make the dead lever can follow convenient installation and the dismantlement on the fastening ring, simple structure assembles the convenience. When the detachable umbrella is detached, the detachable umbrella can be conveniently transported. By passing the fastening shaft through the side surface of the fastening block, when the pile body buried in the ground has position deviation, the fastening shaft and the fastening blind hole can limit the transverse movement of the fixing rod, so that the pile body can be fixed more stably.
The utility model discloses further set up to: the length of the fixing rod is not more than twice of the diameter of a circle where the cross section of the pile body is located.
Through adopting above-mentioned technical scheme, dead lever length is longer, and it is great to take up an area of the space to cracked phenomenon appears easily, lead to the dead lever can not be fine fix the position of this building pile, set the length of dead lever to the diameter that is not more than pile body cross section place circle twice, can make the structure of dead lever and tighrening ring comparatively firm, be difficult for appearing the cracked phenomenon of dead lever.
The utility model discloses further set up to: the inserting and embedding groove is formed in the conical body at the lower end of the pile body and the lower end of the reinforcing pile, the cross section of the bottom surface of the conical body of the inserting and embedding groove is in a fan shape, one end of the inserting and embedding groove is contracted at the top point of the conical body, and the other end of the inserting and embedding groove is contracted at the upper side of the bottom surface of the conical body; the inserting grooves are at least three, and the distance between every two adjacent inserting grooves is equal.
Through adopting above-mentioned technical scheme, can make the bottom of pile body and reinforcing pile form the structure of three burred forms, when driving into ground with the pile body and reinforcing pile, can be more laborsaving pierce ground, it is more convenient to install.
The utility model discloses further set up to: the reinforcing pile upper end be provided with the stopper, the cross section size of stopper is greater than the cross section size of reinforcing hole.
Through adopting above-mentioned technical scheme, can be when driving into ground with the reinforcement stake, the stopper can restrict the reinforcement stake, makes the difficult phenomenon that drops from strengthening the downthehole appearance of reinforcement stake to the stopper can restrict the position of reinforcement stake and tighrening ring, makes the reinforcement stake and the tighrening ring of driving into in the ground be difficult for dropping from the pile body.
To sum up, the utility model discloses a beneficial technological effect does:
1. the position of the building pile can be conveniently fixed, so that the pile body is not easy to incline or move transversely;
2. the structure is more stable, and the phenomenon of fracture and damage is not easy to occur.
Drawings
Fig. 1 is a schematic structural diagram of the present invention;
fig. 2 is a schematic view of the installation of a reinforcing pile.
Reference numerals: 1. a pile body; 11. a fastening ring; 12. a sliding groove; 13. a slider; 2. a fastening block; 21. fastening the blind hole; 22. fixing the rod; 23. fastening the shaft; 24. reinforcing holes; 25. reinforcing piles; 26. a limiting block; 3. and inserting the caulking groove.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings.
As shown in fig. 1 and 2, a building pile comprises a pile body 1 and a fastening ring 11 sleeved on the pile body 1, wherein a sliding groove 12 parallel to a rotation axis of the pile body 1 is formed in a side wall of the pile body 1, three sliding grooves 12 are formed in the sliding groove 12, and the distance between two adjacent sliding grooves 12 is equal. Three sliding blocks 13 are integrally formed on the inner side surface of the fastening ring 11, and the cross section of the sliding groove 12 is equal to that of the sliding blocks 13. The cross section of the sliding block 13 is in a sector ring shape, one side of the sector ring, which is attached to the pile body 1, is the side of the sector ring, which is close to the center of the circle where the sector ring is located, and the intervals between the three sliding blocks 13 are equal and embedded in the sliding groove 12. Through such setting, the area of junction is bigger between sliding block 13 and the tighrening ring 11, connects more firmly, receives external force when having the pivoted trend at tighrening ring 11, and sliding block 13 is more difficult to the fracture. Three fastening blocks 2 are formed on the outer side wall of the fastening ring 11 in a protruding mode, the distance between the three fastening blocks 2 is equal, a fastening blind hole 21 is formed in the side face, away from the pile body 1, of the sliding block 13, a fixing rod 22 is inserted into the fastening blind hole 21, and the length of the fixing rod 22 enables the diameter of the circle where the cross section of the pile body 1 is located to be twice as large as the diameter of the circle. A fastening shaft 23 having a length greater than the width of the fastening block 2 is perforated on the side of the fastening block 2, and the fastening shaft 23 penetrates both the fastening block 2 and the fixing lever 22. The upper surface of the fixing rod 22 is provided with a reinforcing hole 24 at one end far away from the pile body 1, a reinforcing pile 25 penetrates through the reinforcing hole 24, the upper end of the reinforcing pile 25 is integrally formed with a limiting block 26, and the cross section of the limiting block 26 is larger than that of the reinforcing hole 24. Through the arrangement, when the pile body 1 is driven into the ground, the pile body 1 can be fixed through the fastening ring 11 and the reinforcing piles 25 driven into the ground, so that the pile body 1 sleeved in the fastening ring 11 is not easy to incline or move transversely. The limiting block 26 can limit the reinforcing pile 25, so that the reinforcing pile 25 is not easy to fall off from the reinforcing hole 24, and the pile body 1 can be better fixed.
As shown in fig. 1 and 2, the lower ends of the pile body 1 and the reinforcing pile 25 are both set to be cones, the pile body 1 and the reinforcing pile 25 are both provided with inserting and embedding grooves 3, the cross sections of the inserting and embedding grooves 3 on the pile body 1 at the position of the bottom surface of the cone at the lower end of the pile body 1 are in a fan shape, one end of each inserting and embedding groove 3 is converged at the vertex of the cone on the pile body 1, and the other end of each inserting and embedding groove 3 is converged at the position of the upper side of the bottom surface of the cone on the pile body 1; the cross section of the inserting groove on the reinforcing pile 25 at the position of the conical bottom surface at the lower end of the reinforcing pile 25 is in a fan shape, one end of the inserting groove 3 is converged at the vertex of the cone on the reinforcing pile 25, and the other end is converged at the position of the upper side of the conical bottom surface on the reinforcing pile 25. Through the arrangement, the bottom ends of the pile body 1 and the reinforcing pile 25 form a structure of the three-edged barbed pile, so that labor can be saved and the pile body 1 and the reinforcing pile 25 can be installed more conveniently when being driven into the ground.
The embodiment of this specific implementation mode is the preferred embodiment of the present invention, not limit according to this the utility model discloses a protection scope, so: all equivalent changes made according to the structure, shape and principle of the utility model are covered within the protection scope of the utility model.

Claims (8)

1. The utility model provides a building pile, includes pile body (1), its characterized in that: the bottom end of the pile body (1) is set to be conical, a fastening ring (11) is sleeved on the pile body (1), a sliding groove (12) is formed in the side wall of the pile body (1), the sliding groove (12) is parallel to a rotating shaft of the pile body (1), a sliding block (13) is fixedly arranged on the inner side wall of the fastening ring (11), the cross section of the sliding block (13) is equal to that of the sliding groove (12), the sliding block (13) is embedded in the sliding groove (12) and moves along the sliding groove (12), a fixing rod (22) perpendicular to the pile body (1) is fixedly arranged on the fastening ring (11), a reinforcing pile (25) is arranged at one end of the fixing rod (22) far away from the pile body (1), the pile (25) is parallel to the rotating shaft of the pile body (1), and the connecting position of the reinforcing pile (25) and the fixing rod (22) is positioned on the bottom surface of the fixing rod (22), the bottom end of the reinforcing pile (25) is conical.
2. A building pile according to claim 1, characterised in that: and one end of the fixing rod (22) far away from the pile body (1) is provided with a reinforcing hole (24), and a reinforcing pile (25) penetrates through the reinforcing hole (24).
3. A building pile according to claim 2, characterised in that: the fixing rods (22) are at least three, and the distance between the joints of the two adjacent fixing rods (22) and the fastening ring (11) is equal.
4. A building pile according to claim 3, characterised in that: the cross section of sliding block (13) be fan ring shape, and laminate fastening ring (11) in this fan ring shape one side be fan ring shape keep away from one side of its place circle centre department, sliding block (13) are provided with two at least, the interval between two adjacent sliding blocks (13) equals.
5. A building pile according to claim 4, characterised in that: the lateral surface of tighrening ring (11) on the fixed fastening block (2) that is provided with, seted up fastening blind hole (21) on the side of tighrening block (2) far away from tighrening ring (11) centre of a circle department, dead lever (22) wear to establish in fastening blind hole (21), wear to be equipped with fastening shaft (23) on the side of tighrening block (2), the length of fastening shaft (23) be greater than the width of tighrening block (2), the tighrening shaft (23) passes tighrening block (2) and dead lever (22) simultaneously.
6. A building pile according to claim 5, characterised in that: the length of the fixing rod (22) is not more than twice of the diameter of a circle where the cross section of the pile body (1) is located.
7. A building pile according to claim 1, characterised in that: the lower end of the pile body (1) and the cone at the lower end of the reinforcing pile (25) are provided with inserting grooves, the cross section of the position of the bottom surface of the cone of the inserting groove (3) is in a fan shape, one end of the inserting groove (3) is converged at the top point of the cone, and the other end of the inserting groove is converged at the upper side of the bottom surface of the cone; the inserting grooves are at least three, and the distance between every two adjacent inserting grooves is equal.
8. A building pile according to claim 1, characterised in that: the upper end of the reinforcing pile (25) is provided with a limiting block (26), and the size of the cross section of the limiting block (26) is larger than that of the reinforcing hole (24).
CN201920457691.6U 2019-04-04 2019-04-04 Building pile Active CN209907369U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920457691.6U CN209907369U (en) 2019-04-04 2019-04-04 Building pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920457691.6U CN209907369U (en) 2019-04-04 2019-04-04 Building pile

Publications (1)

Publication Number Publication Date
CN209907369U true CN209907369U (en) 2020-01-07

Family

ID=69035752

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920457691.6U Active CN209907369U (en) 2019-04-04 2019-04-04 Building pile

Country Status (1)

Country Link
CN (1) CN209907369U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113529695A (en) * 2021-09-09 2021-10-22 石庆林 Positioning pile for hydraulic engineering with stable positioning and positioning method
CN116220016A (en) * 2023-05-06 2023-06-06 中铁建工集团第二建设有限公司 Anti-seismic building pile

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113529695A (en) * 2021-09-09 2021-10-22 石庆林 Positioning pile for hydraulic engineering with stable positioning and positioning method
CN116220016A (en) * 2023-05-06 2023-06-06 中铁建工集团第二建设有限公司 Anti-seismic building pile
CN116220016B (en) * 2023-05-06 2023-07-25 中铁建工集团第二建设有限公司 Anti-seismic building pile

Similar Documents

Publication Publication Date Title
US8845236B1 (en) Ground anchor
CN209907369U (en) Building pile
KR20060039017A (en) Pile for civil engineering work
KR101625192B1 (en) Driven concrete pile with open lower part and construction method thereof
CN110892114B (en) Pile and its making method
KR101403213B1 (en) Construction method of driven grout pile
WO1985001535A1 (en) Supporting member
CN207159983U (en) A kind of soft clay area building lot structure of cement mixing method combination Pulling-Resistant Anchor Rod
JPH0262648B2 (en)
KR101650426B1 (en) Bottom enhancing type small diameter pile for ground reinforcement
KR20120102480A (en) Phc pile with improved end bearing capacity and piling method of phc pile using the same
CN102535452A (en) Novel engineering pile
US844294A (en) Building construction.
JP3361879B2 (en) Construction method of pile with drain layer and construction device used for it
JP3182243U (en) Foundation pile for structure installation
JP5887193B2 (en) How to install underground diagonal materials
CN102220760B (en) Method for casting deep inverted T-shaped pile
CN201520973U (en) Precast pile with grouting hole
KR101791211B1 (en) Helix steel pipe pile construction method for reinforcement of buckling
RU72986U1 (en) PILE
KR101859152B1 (en) Auger-drilled pile assembly
CN208668416U (en) A kind of Two bors d's oeuveres channel steel auxiliary pile pulling device
CN207700198U (en) A kind of advanced support supporting construction
CN202055756U (en) Novel expansion pile head structure for mixing
KR101585539B1 (en) Pile for reinforcing end bearing capacity

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant