CN209874455U - Scaffold G-shaped quick lock - Google Patents

Scaffold G-shaped quick lock Download PDF

Info

Publication number
CN209874455U
CN209874455U CN201920593595.4U CN201920593595U CN209874455U CN 209874455 U CN209874455 U CN 209874455U CN 201920593595 U CN201920593595 U CN 201920593595U CN 209874455 U CN209874455 U CN 209874455U
Authority
CN
China
Prior art keywords
frame
locking
scaffold
locking mechanism
fixedly connected
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920593595.4U
Other languages
Chinese (zh)
Inventor
黄国庆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuxi Anjie Scaffold Co Ltd
Original Assignee
Wuxi Anjie Scaffold Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuxi Anjie Scaffold Co Ltd filed Critical Wuxi Anjie Scaffold Co Ltd
Priority to CN201920593595.4U priority Critical patent/CN209874455U/en
Application granted granted Critical
Publication of CN209874455U publication Critical patent/CN209874455U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Movable Scaffolding (AREA)

Abstract

The utility model discloses a quick tool to lock of scaffold frame G type, including the pole setting, one side of pole setting outer wall is equipped with first locking mechanism, first locking mechanism is including the first link of locating pole setting one side outer wall, the rigid coupling is in the bending frame at first link top, the rigid coupling is in the first spacing frame of first link bottom and the catch of rigid coupling in the bending frame bottom, the bottom of catch does not seal, the inside rigid coupling of catch has convex locking block, catch and locking block form the embedding space, the inside embedding in embedding space has the embedding frame that agrees with the embedding space, the bottom rigid coupling of embedding frame has the lock ring cover, the both sides rigid coupling of lock ring cover has the second link of symmetry, one side rigid coupling that lock ring cover was kept away from to the second link has the crossbeam, first locking mechanism presents the shape of class "G" letter.

Description

Scaffold G-shaped quick lock
Technical Field
The utility model relates to a scaffold frame tool to lock field, in particular to quick tool to lock of scaffold frame G type.
Background
The scaffold is a working platform which is erected for ensuring that each construction process is smoothly carried out, and is divided into an outer scaffold and an inner scaffold according to the erected position; the scaffold can be divided into a wood scaffold, a bamboo scaffold and a steel pipe scaffold according to different materials; the scaffold is divided into a vertical rod type scaffold, a bridge type scaffold, a door type scaffold, a suspension type scaffold, a hanging type scaffold, a lifting type scaffold and a climbing type scaffold according to the structural form.
The scaffold is built and still needs the manpower to realize at present, and the scaffold of building in earlier stage need drop into certain human cost, if the engineering volume is great, then need spend a large amount of time to assemble, and the process of building is also very hard, and the workman can't easily assemble the scaffold, and the whole process of building is wasted time and energy.
At present, chinese patent with publication number CN208363549U discloses a scaffold, it includes platen and a plurality of stabilizer blades that are used for supporting the platen, the opening has been seted up to the platen, the opening vertically runs through the platen, be provided with material hoisting device on the platen, material hoisting device includes supporting component, connect in supporting component's wiring subassembly and be used for driving the power component of wiring subassembly, the wiring subassembly includes pivot and winding roller, the winding roller is located the opening top, and be connected with the stay cord, stay cord one end is connected in winding roller, the other end passes the opening and is connected with year thing board.
Although this kind of scaffold can assist the staff to transport the material to the scaffold to make things convenient for the staff to use, nevertheless: the scaffold also does not solve the problem that the scaffold cannot be assembled quickly, and a large amount of manpower and time are needed to assemble the scaffold when the similar scaffold is installed, so that the project period is prolonged, the economic loss of an enterprise is increased, and workers who operate on the spot can not finish the process.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing a quick tool to lock of scaffold frame G type, it has the advantage of being convenient for build the scaffold frame fast.
The above technical purpose of the present invention can be achieved by the following technical solutions:
the utility model provides a quick tool to lock of scaffold frame G type, includes the pole setting, one side of pole setting outer wall is equipped with first locking mechanism, first locking mechanism is including the first link of locating pole setting one side outer wall, rigid coupling in the bending frame at first link top, rigid coupling in the first spacing frame of first link bottom and rigid coupling in the catch of bending frame bottom, the bottom of catch is not sealed, the inside rigid coupling of catch has convex locking block, catch and locking block form the embedding space, the inside embedding in embedding space has the embedding frame that agrees with the embedding space, the bottom rigid coupling of embedding frame has the lock ring cover, the both sides rigid coupling of lock ring cover has symmetrical second link, the one side rigid coupling that the lock ring cover was kept away from to the second link has the crossbeam, first locking mechanism presents the shape of class "G" letter.
Through adopting above-mentioned technical scheme, the pole setting is the state of putting vertically, be used as the major structure who constitutes the scaffold, first locking mechanism can be fixed detachable installation's scaffold structure, when the tool to lock is realized being connected fixedly through first link and pole setting, weld first link in the pole setting during fixed, guarantee that the tool to lock can not drop from the pole setting, first link and catch are connected to the bending frame, catch and catch cover cooperate and realize the installation between pole setting and the crossbeam, the inside at the catch is fixed to the locking block, the locking block forms the embedding space with the catch, the embedding frame is fixed in stretching into the embedding space during installation, first spacing is realized tentatively fixing crossbeam and catch cover, the crossbeam passes through the second link and realizes fixedly with the catch cover, install the crossbeam in the pole setting with this.
Further setting: one side of the locking ring, which is far away from the first connecting frame, is provided with a second limiting frame, the second limiting frame is rotatably connected inside the locking ring, one side of the locking ring, which is close to the second limiting frame, outside the locking ring is provided with an adjusting bolt, and one side of the locking ring sleeve, which is close to the second limiting frame, is provided with a movable opening.
Through adopting above-mentioned technical scheme, the spacing frame of second passes through adjusting bolt and realizes not hard up and the switching of stationary state, is convenient for stretch into the movable opening with the spacing frame of second when not hard up, and the spacing frame of second withstands the movable opening after fixed, makes the catch cover can't break away from the catch easily, realizes the fixed of catch cover, stability when having strengthened the scaffold installation.
Further setting: and a second locking mechanism with the same structure as the first locking mechanism is arranged on the other side of the outer wall of the upright rod, and a fixing mechanism is arranged between the second locking mechanism and the first locking mechanism.
Through adopting above-mentioned technical scheme, second locking mechanism is the same with first locking mechanism structure, can adopt the same mode to install fixedly at the angle of difference to the crossbeam, and fixed establishment can strengthen the stability between first locking mechanism and the second locking mechanism.
Further setting: the fixing mechanism comprises a third connecting frame fixedly connected to the first locking mechanism, a fourth connecting frame fixedly connected to the second locking mechanism and a fastener fixedly connected between the third connecting frame and the fourth connecting frame, and the fastener is arranged on the outer wall of the vertical rod.
Through adopting above-mentioned technical scheme, the fastener passes through the third link to be fixed with first locking mechanical system, and is fixed with second locking mechanical system through the fourth link, and the fastener tightly detains at the outer wall of pole setting, and first locking mechanical system of help is fixed with second locking mechanical system realization simultaneously.
Further setting: the bottom rigid coupling of bending frame has first mount, the lateral wall fixedly connected with second mount of lock ring cover, the one end that first mount is far away from bending frame is arranged in the one side that the lock ring cover one end was kept away from to the second mount, be equipped with the first stop bolt that runs through both between first mount and the second mount.
Through adopting above-mentioned technical scheme, first spacing bolt is used for fixed first mount and second mount, and first mount and second mount can help the catch cover to realize fixedly.
Further setting: and a second limiting bolt is arranged on the side wall of the first fixing frame, and the embedded frame and the locking ring are fixed by the second limiting bolt.
Through adopting above-mentioned technical scheme, run through first mount, catch and embedding frame simultaneously after the second stop bolt sets up, with the inside of the position locking in embedding space of embedding frame, further strengthen the stability behind the scaffold frame erection joint.
To sum up, the utility model discloses following beneficial effect has: the utility model discloses can be convenient for the installation of scaffold frame is built, realize the installation between crossbeam and the pole setting in the equidirectional through first locking mechanism and second locking mechanism, first spacing bolt, first mount has strengthened the stability of tool to lock when the pole setting with the cooperation of second mount formation, the second spacing bolt has strengthened the fixed ability of lock ring cover, whole tool to lock can be convenient for the work of building between the scaffold frame, it is laborsaving for the staff, and build the back stability can be better, each part all has good fixed ability.
Drawings
Fig. 1 is a schematic structural view of a first lock mechanism in embodiment 1;
FIG. 2 is a front view of embodiment 1;
fig. 3 is a schematic structural view of an embedding space in embodiment 1.
In the figure, 1, a vertical rod; 2. a first locking mechanism; 21. a first connecting frame; 22. a bending frame; 23. a first limit bracket; 24. a locking ring; 3. a locking block; 4. an embedding space; 5. an embedding frame; 6. a lock ring sleeve; 7. a second link frame; 8. a cross beam; 9. a second limiting frame; 10. adjusting the bolt; 11. a movable opening; 12. a second locking mechanism; 13. a fixing mechanism; 131. a third connecting frame; 132. a fourth link frame; 133. a fastener; 14. a first fixing frame; 15. a second fixing frame; 16. a first limit bolt; 17. and a second limit bolt.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings.
Example 1: a G-type quick lock for scaffold is disclosed, as shown in FIG. 1, FIG. 2 and FIG. 3, a vertical rod 1 is vertically arranged, a beam 8 is arranged on one side of the vertical rod 1, a detachable structure is arranged between the beam 8 and the vertical rod 1, a first locking mechanism 2 is arranged on one side of the outer wall of the vertical rod 1, a second locking mechanism 12 is arranged on the other side of the outer wall of the vertical rod 1, a fixing mechanism 13 is arranged between the first locking mechanism 2 and the second locking mechanism 12, the fixing mechanism 13 is composed of a third connecting frame 131, a fourth connecting frame 132 and a fastener 133, the structural components in the first locking mechanism 2 are the same as those in the second locking mechanism 12, the third connecting frame 131 is fixedly connected to the bottom of the first locking mechanism 2, the fourth connecting frame 132 is fixedly connected to the top of the second locking mechanism 12, the fastener 133 is arranged between the third connecting frame 131 and the fourth connecting frame 132, the fastener 133 is fastened to the outer wall of the, and the fastener 133 is fixedly connected to the third connecting frame 131 and the fourth connecting frame 132.
As shown in fig. 1, 2 and 3, the first locking mechanism 2 is composed of a first connecting frame 21, a bending frame 22, a first limit frame 23 and a locking ring 24, the first locking mechanism 2 is shaped like a letter "G", the third connecting frame 131 is fixedly connected to the bottom of the first connecting frame 21, the first connecting frame 21 is welded to the side wall of the vertical rod 1, the bending frame 22 is fixedly connected to the top of the first connecting frame 21, the bent first limit frame 23 is fixedly connected to the bottom of the first connecting frame 21, the locking ring 24 is fixedly connected to the bottom of the bending frame 22, the bottom of the locking ring 24 is not sealed, the locking block 3 is fixedly connected to the inside of the locking ring 24, the locking block 3 is arranged inside the locking ring 24 to form an embedding space 4 with the locking ring 24, a locking ring sleeve 6 is sleeved on the outside of the locking ring 24, an embedding frame 5 is fixedly connected to the top of the locking ring 6, the embedding frame 5 can be arranged inside the embedding space 4 when being, the shape of the insertion shelf 5 and the shape of the insertion space 4 are adapted to each other.
As shown in fig. 1, 2 and 3, the surface of the lock ring sleeve 6 is provided with a movable opening 11, one side of the lock ring 24 away from the first connecting frame 21 is provided with a second limiting frame 9 capable of rotating inside the lock ring 24, and one side of the outside of the lock ring 24 close to the second limiting frame 9 is provided with an adjusting bolt 10.
As shown in fig. 1, 2 and 3, a first fixing frame 14 is fixedly connected to the bottom of the bending frame 22, two second limiting bolts 17 are arranged on the side wall of the first fixing frame 14 close to the top, the second limiting bolts 17 are used for fixing the relative position between the embedded frame 5 and a locking ring 24, three first limiting bolts 16 are arranged on the side wall of the first fixing frame 14 close to the bottom, a second fixing frame 15 is fixedly connected to one side of the locking ring sleeve 6 close to the first connecting frame 21, the first fixing frame 14 is attached to the second fixing frame 15, and the first limiting bolts 16 are used for fixing the relative position between the first fixing frame 14 and the second fixing frame 15.
As shown in fig. 1, 2 and 3, two second connecting frames 7 are fixedly connected to two sides of the lock ring sleeve 6, and a cross beam 8 is fixedly connected to one side of the second connecting frame 7 away from the lock ring sleeve 6.
In the embodiment of the present invention, the fastener 133 is fastened to the outside of the vertical rod 1, the first connecting frame 21 of the first locking mechanism 2 and the second locking mechanism 12 is welded to the vertical rod 1, the first locking mechanism 2 and the vertical rod 1 are fixed to the vertical rod 1, the embedded frame 5 is inserted into the embedding space 4, the second position-limiting frame 9 is received in the opening 11, the lock ring sleeve 6 is disposed outside the lock ring 24, the second position-limiting frame 9 is screwed out and the adjusting bolt 10 is screwed, the second position-limiting bolt 17 is screwed, the lock ring 24 and the embedded frame 5 are inserted, the lock ring sleeve 6 is disposed outside the lock ring 24, the second fixing frame 15 is attached to the first fixing frame 14, the first position-limiting bolt 16 is screwed, the first fixing frame 14 and the second fixing frame 15 are fixed together, i.e. the installation is completed, the installed beam 8 and the vertical rod 1 are protected by multiple times, the stability is strong, and the installation is convenient.
The above-mentioned embodiments are merely illustrative of the present invention, and are not intended to limit the present invention, and those skilled in the art can make modifications of the present embodiments without inventive contribution as required after reading the present specification, but all the embodiments are protected by patent law within the scope of the present invention.

Claims (6)

1. The utility model provides a quick tool to lock of scaffold G type, includes pole setting (1), its characterized in that: a first locking mechanism (2) is arranged on one side of the outer wall of the upright rod (1), the first locking mechanism (2) comprises a first connecting frame (21) arranged on the outer wall of one side of the upright rod (1), a bending frame (22) fixedly connected to the top of the first connecting frame (21), a first limiting frame (23) fixedly connected to the bottom of the first connecting frame (21) and a locking ring (24) fixedly connected to the bottom of the bending frame (22), the bottom of the locking ring (24) is not sealed, a convex locking block (3) is fixedly connected to the inside of the locking ring (24), an embedding space (4) is formed by the locking ring (24) and the locking block (3), an embedding frame (5) matched with the embedding space (4) is embedded into the embedding space (4), a locking ring sleeve (6) is fixedly connected to the bottom of the embedding frame (5), and symmetrical second connecting frames (7) are fixedly connected to two sides of the locking ring sleeve (6), and a cross beam (8) is fixedly connected to one side, far away from the lock ring sleeve (6), of the second connecting frame (7), and the first locking mechanism (2) is in a shape similar to a 'G' letter.
2. The scaffold G-type quick lock according to claim 1, characterized in that: one side of the locking ring (24) far away from the first connecting frame (21) is provided with a second limiting frame (9), the second limiting frame (9) is rotatably connected to the inside of the locking ring (24), one side of the outside of the locking ring (24) close to the second limiting frame (9) is provided with an adjusting bolt (10), and one side of the locking ring sleeve (6) close to the second limiting frame (9) is provided with a movable opening (11).
3. A scaffold G-type quick lock according to claim 2, characterized in that: the other side of pole setting (1) outer wall is equipped with second locking mechanism (12) the same with first locking mechanism (2) structure, be equipped with fixed establishment (13) between second locking mechanism (12) and first locking mechanism (2).
4. A scaffold G-type quick lock according to claim 3, characterized in that: fixing mechanism (13) include third link (131) of rigid coupling on first locking mechanism (2), fourth link (132) and rigid coupling in third link (131), fastener (133) between fourth link (132) on second locking mechanism (12), pole setting (1) is arranged in fastener (133).
5. A scaffold G-type quick lock according to claim 4, characterized in that: the bottom rigid coupling of bending frame (22) has first mount (14), the lateral wall fixedly connected with second mount (15) of lock ring cover (6), the one end that first mount (14) kept away from bending frame (22) is arranged in one side that second mount (15) kept away from lock ring cover (6) one end, be equipped with between first mount (14) and second mount (15) and run through first stop bolt (16) between them.
6. A scaffold G-type quick lock according to claim 5, characterized in that: and a second limiting bolt (17) is arranged on the side wall of the first fixing frame (14), and the embedded frame (5) and the locking ring (24) are fixed by the second limiting bolt (17).
CN201920593595.4U 2019-04-26 2019-04-26 Scaffold G-shaped quick lock Active CN209874455U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920593595.4U CN209874455U (en) 2019-04-26 2019-04-26 Scaffold G-shaped quick lock

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920593595.4U CN209874455U (en) 2019-04-26 2019-04-26 Scaffold G-shaped quick lock

Publications (1)

Publication Number Publication Date
CN209874455U true CN209874455U (en) 2019-12-31

Family

ID=68962629

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920593595.4U Active CN209874455U (en) 2019-04-26 2019-04-26 Scaffold G-shaped quick lock

Country Status (1)

Country Link
CN (1) CN209874455U (en)

Similar Documents

Publication Publication Date Title
CN204040435U (en) High-altitude steel structure welding Hanging Basket
CN209874455U (en) Scaffold G-shaped quick lock
CN102454292A (en) Supporting steel frame of high altitude large-span cantilever structure mold frame
CN201486120U (en) Detachable steel column connecting construction operation platform
CN211499182U (en) Reinforced steel structure at joint of steel structure
CN209990179U (en) Construction safety protection support frame
CN206646836U (en) A kind of exterior wall, inner partition plate movement lifting frame
CN215212255U (en) Suspension type frame combined high-altitude operation platform
CN215803166U (en) A wooden template for civil engineering construction easy to assemble and disassemble
CN201943350U (en) Supporting steel frame for die holder of high-altitude large span overhanging structure
CN213329975U (en) Steel pull rod hanging and pulling overhanging bearing steel beam structure
CN213448902U (en) Pre-buried box steel bracket structure
CN204703542U (en) The assembled passage of a kind of Construction of Steel Structure regularization
CN207974502U (en) Operation platform in a kind of combined electrical stair shaft
CN209874185U (en) A piece together formula angle steel lattice keel bearing structure for stone material curtain
CN112211384A (en) Scaffold for building site
CN207032027U (en) Packaged type hanging basket for cement decorative plate reparation on the outside of Bridge guardrail and construction
CN211850788U (en) House building engineering is with reinforcement type supporting template
CN214144828U (en) Fixing device for building safety
CN218934031U (en) Safety protection fence
CN213509561U (en) Scaffold fixing calipers for building construction
CN214935831U (en) High-bearing-performance safety hanging basket
CN211007951U (en) Protector is used in municipal works construction
CN212507009U (en) Anti-seismic support conversion layer structure of large-space ceiling
CN215252869U (en) Steel pipe group pile positioning tool

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of utility model: Scaffold G-type quick lock

Effective date of registration: 20220210

Granted publication date: 20191231

Pledgee: Bank of Jiangsu Limited by Share Ltd. Wuxi New District sub branch

Pledgor: WUXI SAFETY-SCAFFOLDING Co.,Ltd.

Registration number: Y2022320010061