CN209854981U - A prefabricated recycled concrete buckling-resistant steel plate shear wall - Google Patents

A prefabricated recycled concrete buckling-resistant steel plate shear wall Download PDF

Info

Publication number
CN209854981U
CN209854981U CN201920540877.8U CN201920540877U CN209854981U CN 209854981 U CN209854981 U CN 209854981U CN 201920540877 U CN201920540877 U CN 201920540877U CN 209854981 U CN209854981 U CN 209854981U
Authority
CN
China
Prior art keywords
steel
steel plate
recycled concrete
angle
shear wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920540877.8U
Other languages
Chinese (zh)
Inventor
魏木旺
刘伟才
谢建和
黄颖韬
朱景陶
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong University of Technology
Original Assignee
Guangdong University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong University of Technology filed Critical Guangdong University of Technology
Priority to CN201920540877.8U priority Critical patent/CN209854981U/en
Application granted granted Critical
Publication of CN209854981U publication Critical patent/CN209854981U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Rod-Shaped Construction Members (AREA)

Abstract

本实用新型涉及装配式建筑技术领域,尤其涉及一种装配式再生混凝土防屈曲钢板剪力墙。本实用新型公开了一种装配式再生混凝土防屈曲钢板剪力墙,包括:钢框架、钢板、螺栓、角钢和再生混凝土盖板;钢板和再生混凝土盖板均设置在钢框架内侧,其中,钢板的边缘各处均通过角钢与钢框架连接,再生混凝土盖板固定在钢板的两侧;钢板与角钢通过螺栓连接,钢框架与角钢通过螺栓连接。其中,角钢设置在钢板的边缘各处且使用足够的螺栓,确保在钢板达到其极限抗拉承载能力之前,角钢与螺栓不发生剪切破坏,从而能够充分利用钢板的性能。另外,螺栓连接也方便更换与维修,解决了现有的防屈曲钢板剪力墙的焊缝处容易因为焊缝缺陷导致节点破坏的问题。

The utility model relates to the technical field of assembled buildings, in particular to an assembled recycled concrete anti-buckling steel plate shear wall. The utility model discloses an assembled recycled concrete anti-buckling steel plate shear wall, comprising: a steel frame, steel plates, bolts, angle steel and recycled concrete cover plates; both the steel plates and the recycled concrete cover plates are arranged inside the steel frame, wherein the steel plates Every edge of the building is connected to the steel frame through angle steel, and the recycled concrete cover plate is fixed on both sides of the steel plate; the steel plate and angle steel are connected by bolts, and the steel frame and angle steel are connected by bolts. Among them, the angle steels are arranged around the edge of the steel plate and sufficient bolts are used to ensure that the angle steel and bolts do not undergo shear failure before the steel plate reaches its ultimate tensile bearing capacity, so that the performance of the steel plate can be fully utilized. In addition, the bolt connection is also convenient for replacement and maintenance, which solves the problem that the welds of the existing buckling-resistant steel plate shear walls are easily damaged due to weld defects.

Description

一种装配式再生混凝土防屈曲钢板剪力墙A prefabricated recycled concrete buckling-resistant steel plate shear wall

技术领域technical field

本实用新型涉及装配式建筑技术领域,尤其涉及一种装配式再生混凝土防屈曲钢板剪力墙。The utility model relates to the technical field of assembled buildings, in particular to an assembled recycled concrete anti-buckling steel plate shear wall.

背景技术Background technique

装配式建筑是用预制部件在工地装配而成的建筑,主要包括装配式混凝土结构建筑、钢结构建筑、现代木结构建筑等。装配式建筑采用标准化设计、工厂化生产、装配化施工、信息化管理和智能化应用,把传统建造方式中的大量现场作业工作转移到工厂进行,是现代工业化生产方式。Prefabricated buildings are buildings assembled on site with prefabricated components, mainly including prefabricated concrete structure buildings, steel structure buildings, modern wood structure buildings, etc. The prefabricated building adopts standardized design, factory production, assembly construction, information management and intelligent application, and transfers a large number of on-site operations in the traditional construction method to the factory. It is a modern industrial production method.

钢结构具有结构自重轻、工业化程度高、可回收利用、绿色节能和良好抗震性能等优点,是天然的装配建筑材料。近年,钢板剪力墙作为优异的抗侧构件已开始应用于实际工程项目。钢板剪力墙钢板在水平荷载作用下易发生面外屈曲,为了抑制钢板面外位移,出现了防屈曲钢板剪力墙,其主要特点是,鱼尾板将钢板与钢框架连接在一起,鱼尾板主要是通过焊缝与钢框架相连接。然而,焊缝处会存在焊接残余应力,在钢板剪力墙发生破坏时,焊缝连接处往往由于焊缝缺陷而成为一个薄弱环节,进而发生节点破坏,且破坏模式为脆性破坏。Steel structure has the advantages of light weight, high degree of industrialization, recyclability, green energy saving and good seismic performance, and is a natural assembly building material. In recent years, steel plate shear walls have been used in practical engineering projects as excellent lateral members. Steel plate shear wall is prone to out-of-plane buckling under the action of horizontal load. In order to restrain the out-of-plane displacement of the steel plate, a buckling-resistant steel plate shear wall has appeared. The main feature is that the fish plate connects the steel plate and the steel frame together. The tail plate is mainly connected to the steel frame through welds. However, there will be welding residual stress at the weld. When the steel plate shear wall is damaged, the weld joint often becomes a weak link due to weld defects, and then node failure occurs, and the failure mode is brittle failure.

实用新型内容Utility model content

本实用新型提供了一种装配式再生混凝土防屈曲钢板剪力墙,解决了现有的防屈曲钢板剪力墙的焊缝处容易因为焊缝缺陷导致节点破坏的问题。The utility model provides an assembled recycled concrete anti-buckling steel plate shear wall, which solves the problem that the welds of the existing anti-buckling steel plate shear walls are easily damaged due to weld defects.

其具体技术方案如下:Its specific technical scheme is as follows:

本实用新型提供了一种装配式再生混凝土防屈曲钢板剪力墙,包括:钢框架、钢板、螺栓、角钢和再生混凝土盖板;The utility model provides an assembled recycled concrete anti-buckling steel plate shear wall, comprising: a steel frame, a steel plate, bolts, angle steel and a recycled concrete cover plate;

所述钢板和所述再生混凝土盖板均设置在所述钢框架内侧,其中,所述钢板的边缘各处均通过所述角钢与所述钢框架连接,所述再生混凝土盖板固定在所述钢板的两侧;Both the steel plate and the recycled concrete cover plate are arranged inside the steel frame, wherein the edges of the steel plate are connected to the steel frame through the angle steel, and the recycled concrete cover plate is fixed on the both sides of the steel plate;

所述钢板与所述角钢通过所述螺栓连接,所述钢框架与所述角钢通过所述螺栓连接。The steel plate is connected to the angle steel by the bolt, and the steel frame is connected to the angle steel by the bolt.

优选地,所述角钢的数量为8个;Preferably, the number of angle steels is 8;

所述钢板的两侧分别固定有4个角钢。Four angle steels are respectively fixed on both sides of the steel plate.

优选地,所述钢框架和所述钢板均为矩形,所述钢板与所述钢框架相匹配。Preferably, both the steel frame and the steel plate are rectangular, and the steel plate matches the steel frame.

优选地,所述角钢包括第一面板和第二面板;Preferably, said steel angle comprises a first panel and a second panel;

所述第一面板为矩形,所述第二面板为等腰梯形,所述第一面板与所述钢框架连接,所述第二面板与所述钢板连接。The first panel is rectangular, the second panel is isosceles trapezoidal, the first panel is connected to the steel frame, and the second panel is connected to the steel plate.

优选地,所述钢框架包括第一H型钢梁、第一H型钢柱、第二H型钢梁和第二H型钢柱。Preferably, the steel frame includes a first H-shaped steel beam, a first H-shaped steel column, a second H-shaped steel beam and a second H-shaped steel column.

优选地,所述角钢的钢材为Q345钢材。Preferably, the steel of the angle steel is Q345 steel.

优选地,所述钢板的钢材为Q235钢材。Preferably, the steel material of the steel plate is Q235 steel material.

从以上技术方案可以看出,本实用新型具有以下优点:As can be seen from the above technical solutions, the utility model has the following advantages:

本实用新型提供了一种装配式再生混凝土防屈曲钢板剪力墙,包括:再生混凝土盖板、钢框架、螺栓、钢板和角钢;钢板设置在钢框架内侧,其中钢板的边缘各处均通过角钢与钢框架连接,再生混凝土盖板固定在钢板的两侧;钢板与角钢通过螺栓连接,钢框架与角钢通过螺栓连接。其中,角钢设置在钢板的边缘各处且使用足够的螺栓,确保在钢板达到其极限抗拉承载能力之前,角钢与螺栓不发生剪切破坏,从而能够充分利用钢板的性能。另外,螺栓连接也方便更换与维修。在钢结构工厂生产完构件后,再在现场进行螺栓拼接,减少了现场的施工工序,提高施工效率。The utility model provides an assembled recycled concrete anti-buckling steel plate shear wall, comprising: recycled concrete cover plate, steel frame, bolts, steel plate and angle steel; Connected with the steel frame, the recycled concrete cover plate is fixed on both sides of the steel plate; the steel plate and the angle steel are connected by bolts, and the steel frame and the angle steel are connected by bolts. Among them, the angle steels are arranged around the edge of the steel plate and sufficient bolts are used to ensure that the angle steel and bolts do not undergo shear failure before the steel plate reaches its ultimate tensile bearing capacity, so that the performance of the steel plate can be fully utilized. In addition, the bolt connection is also convenient for replacement and maintenance. After the components are produced in the steel structure factory, the bolts are spliced on site, which reduces the construction process on site and improves construction efficiency.

附图说明Description of drawings

为了更清楚地说明本实用新型实施例或现有技术中的技术方案,下面将对实施例或现有技术描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本实用新型的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动性的前提下,还可以根据这些附图获得其它的附图。In order to more clearly illustrate the technical solutions in the embodiments of the present invention or the prior art, the following will briefly introduce the accompanying drawings that need to be used in the description of the embodiments or the prior art. Obviously, the accompanying drawings in the following description These are only some embodiments of the present utility model, and those skilled in the art can also obtain other drawings according to these drawings without any creative effort.

图1为本实用新型实施例提供的一种装配式再生混凝土防屈曲钢板剪力墙的结构示意图;Fig. 1 is a structural schematic diagram of a prefabricated recycled concrete anti-buckling steel plate shear wall provided by the embodiment of the present invention;

图2为本实用新型实施例提供的一种装配式再生混凝土防屈曲钢板剪力墙的侧视图;Fig. 2 is a side view of an assembled recycled concrete anti-buckling steel plate shear wall provided by the embodiment of the present invention;

图3为本实用新型实施例提供的角钢的侧视图;Fig. 3 is the side view of the angle steel that the utility model embodiment provides;

图4为本实用新型实施例提供的角钢的后视图;Fig. 4 is the back view of the angle steel that the utility model embodiment provides;

图5为本实用新型实施例提供的一种装配式再生混凝土防屈曲钢板剪力墙的制备方法的流程示意图;Fig. 5 is a schematic flow chart of a method for preparing a prefabricated recycled concrete anti-buckling steel plate shear wall provided by an embodiment of the utility model;

其中,图示说明如下:1、角钢;2、钢板;3、第一H型钢梁;4、第一H型钢柱;5、第二H型钢梁;6、第二H型钢柱;7、再生混凝土盖板。Among them, the illustrations are as follows: 1. Angle steel; 2. Steel plate; 3. The first H-shaped steel beam; 4. The first H-shaped steel column; 5. The second H-shaped steel beam; 6. The second H-shaped steel column; 7 , recycled concrete cover.

具体实施方式Detailed ways

本实用新型实施例提供了一种装配式再生混凝土防屈曲钢板剪力墙,用于解决现有的防屈曲钢板剪力墙的焊缝处容易因为焊缝缺陷导致节点破坏的问题。The embodiment of the utility model provides an assembled recycled concrete anti-buckling steel plate shear wall, which is used to solve the problem that the welding seam of the existing anti-buckling steel plate shear wall is easily damaged due to weld defects.

为使得本实用新型的实用新型目的、特征、优点能够更加的明显和易懂,下面将对本实用新型实施例中的技术方案进行清楚、完整地描述,显然,下面所描述的实施例仅仅是本实用新型一部分实施例,而非全部的实施例。基于本实用新型中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其它实施例,都属于本实用新型保护的范围。In order to make the purpose, features and advantages of the utility model more obvious and understandable, the technical solutions in the embodiments of the utility model will be clearly and completely described below. Obviously, the embodiments described below are only the present invention. Some embodiments of the utility model, but not all embodiments. Based on the embodiments of the present utility model, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the scope of protection of the present utility model.

请参阅图1,本实用新型实施例提供的一种装配式防屈曲钢板剪力墙的结构示意图。Please refer to FIG. 1 , which is a schematic structural diagram of a prefabricated anti-buckling steel plate shear wall provided by an embodiment of the present invention.

请参阅图2,本实用新型实施例提供的一种装配式再生混凝土防屈曲钢板剪力墙的侧视图。Please refer to FIG. 2 , which is a side view of a prefabricated recycled concrete anti-buckling steel plate shear wall provided by an embodiment of the present invention.

请参阅图3,本实用新型实施例提供的角钢1的侧视图。Please refer to FIG. 3 , which is a side view of the angle steel 1 provided by the embodiment of the present invention.

请参阅图4,本实用新型实施例提供的角钢1的剖视图。Please refer to FIG. 4 , which is a cross-sectional view of the angle steel 1 provided by the embodiment of the present invention.

本实用新型提供的一种装配式防屈曲钢板剪力墙的一个实施例包括:An embodiment of an assembled anti-buckling steel plate shear wall provided by the utility model includes:

钢框架、螺栓、钢板2、角钢1和再生混凝土盖板7。Steel frame, bolts, steel plate 2, angle steel 1 and recycled concrete cover 7.

钢板2和再生混凝土盖板7均设置在钢框架内侧,其中,钢板2的边缘各处均通过角钢1与钢框架连接,再生混凝土盖板7通过螺栓固定在钢板2的两侧。Both the steel plate 2 and the recycled concrete cover 7 are arranged inside the steel frame, wherein the edges of the steel plate 2 are connected to the steel frame through angle steel 1 everywhere, and the recycled concrete cover 7 is fixed on both sides of the steel plate 2 by bolts.

如图1所示,钢板2的四边均通过角钢1与钢框架连接,使得角钢1围成一个矩形框架。As shown in FIG. 1 , the four sides of the steel plate 2 are connected to the steel frame through the angle steel 1 , so that the angle steel 1 forms a rectangular frame.

钢板2与角钢1通过螺栓连接,钢框架与角钢1通过螺栓连接。The steel plate 2 and the angle steel 1 are connected by bolts, and the steel frame and the angle steel 1 are connected by bolts.

本实用新型实施例中,混凝土盖板与钢框架间留有缝隙,混凝土盖板不参与抵抗结构的水平和竖向荷载,仅提供面外约束刚度,约束钢板发生面外变形。从混凝土盖板不参与抵抗结构水平和竖向荷载的受力特点可知,混凝土盖板不是结构的主要受力构件,对其力学性能要求并不高。因而,将建筑废弃混凝土加工成的再生骨料代替天然骨料制成的再生混凝土应用于防屈曲钢板剪力墙结构中,不仅可实现混凝土盖板的在结构中的功能,而且可达成建筑废弃物资源化原则,符合绿色、环保、节能和减排的可持续发展思路,具有重要的社会经济意义。In the embodiment of the utility model, there is a gap between the concrete cover slab and the steel frame, and the concrete cover slab does not participate in resisting the horizontal and vertical loads of the structure, but only provides out-of-plane restraint stiffness, and restrains out-of-plane deformation of the steel plate. It can be seen from the mechanical characteristics that the concrete cover slab does not participate in resisting the horizontal and vertical loads of the structure. The concrete cover slab is not the main force-bearing member of the structure, and the requirements for its mechanical properties are not high. Therefore, the use of recycled aggregate processed from construction waste concrete instead of recycled concrete made from natural aggregates in the buckling-resistant steel plate shear wall structure can not only realize the function of the concrete cover plate in the structure, but also achieve the goal of building waste. The principle of material resources is in line with the sustainable development ideas of green, environmental protection, energy saving and emission reduction, and has important social and economic significance.

现有技术中,钢板2与钢框架通过鱼尾板连接在一起,而鱼尾板通过焊缝与钢框架连接,焊接工序多,工作量大,而且容易破坏钢框架和鱼尾板的防锈涂料,焊接质量也得不到保证。另外,鱼尾板与钢框架的焊缝处会存在焊接残余应力,在钢板2剪力墙发生破坏时,焊缝连接处会由于焊缝缺陷发生节点破坏,且破坏模式为脆性破坏。In the prior art, the steel plate 2 and the steel frame are connected together through a fishplate, and the fishplate is connected to the steel frame through a weld seam. There are many welding procedures and a large workload, and it is easy to damage the rust prevention of the steel frame and the fishplate. Paint, welding quality can not be guaranteed. In addition, there will be welding residual stress at the weld between the fishplate and the steel frame. When the steel plate 2 shear wall is damaged, the joint of the weld will be damaged due to weld defects, and the failure mode is brittle failure.

本实用新型实施例中,角钢1设置在钢板2的边缘各处且使用足够的螺栓,确保在钢板2达到其极限抗拉承载能力之前,角钢1与螺栓不发生剪切破坏,从而能够充分利用钢板2的性能。另外,螺栓连接也方便更换与维修。在钢结构工厂生产完构件后,再在现场进行螺栓拼接,减少了现场的施工工序,提高施工效率。In the embodiment of the utility model, the angle steel 1 is arranged on the edges of the steel plate 2 and enough bolts are used to ensure that the angle steel 1 and the bolts do not undergo shear failure before the steel plate 2 reaches its ultimate tensile bearing capacity, so that the steel plate 2 can be fully utilized. Properties of Plate 2. In addition, the bolt connection is also convenient for replacement and maintenance. After the components are produced in the steel structure factory, the bolts are spliced on site, which reduces the construction process on site and improves construction efficiency.

需要说明的是,本实用新型实施例中使用的螺栓均为高强摩擦型螺栓。It should be noted that the bolts used in the embodiments of the present utility model are all high-strength friction bolts.

进一步地,钢框架和钢板2均为矩形,钢板2与钢框架相匹配。Further, both the steel frame and the steel plate 2 are rectangular, and the steel plate 2 matches the steel frame.

本实用新型实施例中,钢板2为内嵌钢板。In the embodiment of the utility model, the steel plate 2 is an embedded steel plate.

进一步地,角钢1的数量为8个,钢板2的两侧分别固定有4个角钢1。Further, the number of angle steels 1 is eight, and four angle steels 1 are respectively fixed on both sides of the steel plate 2 .

如图1所示,钢板2的一侧分布有四个角钢1,四个角钢1相互配合,沿钢框架内壁形成矩形框架结构,且布满钢板2的四边。As shown in FIG. 1 , four angle steels 1 are distributed on one side of the steel plate 2 , and the four angle steels 1 cooperate with each other to form a rectangular frame structure along the inner wall of the steel frame and cover the four sides of the steel plate 2 .

进一步地,角钢1包括第一面板和第二面板。Further, the angle steel 1 includes a first panel and a second panel.

本实用新型实施例中,第一面板为矩形,第二面板为等腰梯形,第一面板与第二面板的宽度相同,第一面板与钢框架连接,第二面板与钢板2连接,从而无缝连接形成矩形框架结构。In the embodiment of the utility model, the first panel is rectangular, the second panel is isosceles trapezoidal, the width of the first panel and the second panel are the same, the first panel is connected with the steel frame, and the second panel is connected with the steel plate 2, so that there is no Seam connections form a rectangular frame structure.

进一步地,钢框架包括第一H型钢梁3、第一H型钢柱4、第二H型钢梁5和第二H型钢柱6焊接。Further, the steel frame includes a first H-shaped steel beam 3 , a first H-shaped steel column 4 , a second H-shaped steel beam 5 and a second H-shaped steel column 6 welded together.

进一步地,角钢1的钢材为Q345钢材。Further, the steel material of the angle steel 1 is Q345 steel material.

进一步地,钢板2的钢材为Q235钢材。Further, the steel material of the steel plate 2 is Q235 steel material.

以上是本实用新型实施例提供的一种装配式防屈曲钢板剪力墙的一个实施例进行详细的描述,以下将对本实用新型实施例提供的一种装配式防屈曲钢板剪力墙的制备方法进行详细的描述。The above is a detailed description of an embodiment of a prefabricated buckling-resistant steel plate shear wall provided by the embodiment of the present utility model. The preparation method of a prefabricated buckling-resistant steel plate shear wall provided by the embodiment of the present utility model will be described below Give a detailed description.

本实用新型提供的一种装配式防屈曲钢板剪力墙的制备方法的一个实施例包括以下步骤:An embodiment of the preparation method of an assembled anti-buckling steel plate shear wall provided by the utility model includes the following steps:

使用螺栓依次将钢板2的各边与钢框架进行固定。Use bolts to fix each side of the steel plate 2 to the steel frame in sequence.

请参阅图5,本实用新型实施例提供的一种装配式防屈曲钢板剪力墙的制备方法的流程示意图。Please refer to FIG. 5 , which is a schematic flowchart of a method for preparing an assembled anti-buckling steel plate shear wall provided by an embodiment of the present invention.

本实用新型实施例中,上述制备方法具体为:In the embodiment of the utility model, the above-mentioned preparation method is specifically:

步骤1:使用第一个角钢1的第一面板通过第一螺栓与钢框架的翼缘进行固定;Step 1: Use the first panel of the first angle steel 1 to fix the flange of the steel frame with the first bolt;

步骤2:将角钢1的第二面板与钢板2的一侧通过第二螺栓进行固定;Step 2: Fix the second panel of the angle steel 1 and one side of the steel plate 2 with the second bolt;

步骤3:使用第二个角钢1的第二面板通过第二螺栓与钢板2的另一侧进行固定;Step 3: Fix the second panel of the second angle steel 1 to the other side of the steel plate 2 through the second bolt;

步骤4:再使用第三螺栓将第二个角钢1的第一面板与钢框架的翼缘进行固定;Step 4: Use the third bolt to fix the first panel of the second angle steel 1 to the flange of the steel frame;

步骤5:采用上述方法依次固定钢板2的另外三个边。Step 5: Use the above method to fix the other three sides of the steel plate 2 in sequence.

需要说明的是,钢框架的翼缘为第一H型钢梁3、第一H型钢柱4、第二H型钢梁5或第二H型钢柱6的翼缘。It should be noted that the flange of the steel frame is the flange of the first H-shaped steel beam 3 , the first H-shaped steel column 4 , the second H-shaped steel beam 5 or the second H-shaped steel column 6 .

进一步地,钢框架包括第一H型钢梁3、第一H型钢柱4、第二H型钢梁5和第二H型钢柱6。Further, the steel frame includes a first H-shaped steel beam 3 , a first H-shaped steel column 4 , a second H-shaped steel beam 5 and a second H-shaped steel column 6 .

进一步地,使用螺栓依次将钢板2的各边与钢框架进行固定前,还包括:Further, before using bolts to sequentially fix each side of the steel plate 2 with the steel frame, it also includes:

将第一H型钢梁3、第一H型钢柱4、第二H型钢梁5和第二H型钢柱6依次焊接形成钢框架。The first H-shaped steel beam 3, the first H-shaped steel column 4, the second H-shaped steel beam 5 and the second H-shaped steel column 6 are sequentially welded to form a steel frame.

本实用新型实施例中,采用上述制备方法得到的装配式防屈曲钢板2剪力墙,使得钢板2在达到极限抗拉承载能力之前,不会发生剪切破坏,从而能够充分利用钢板2的性能。In the embodiment of the present utility model, the assembled anti-buckling steel plate 2 shear wall obtained by the above preparation method makes the steel plate 2 not be sheared before reaching the ultimate tensile bearing capacity, so that the performance of the steel plate 2 can be fully utilized .

以上,以上实施例仅用以说明本实用新型的技术方案,而非对其限制;尽管参照前述实施例对本实用新型进行了详细的说明,本领域的普通技术人员应当理解:其依然可以对前述各实施例所记载的技术方案进行修改,或者对其中部分技术特征进行等同替换;而这些修改或者替换,并不使相应技术方案的本质脱离本实用新型各实施例技术方案的精神和范围。Above, the above embodiments are only used to illustrate the technical solutions of the present utility model, and are not intended to limit it; although the utility model has been described in detail with reference to the foregoing embodiments, those of ordinary skill in the art should understand that: it can still understand the foregoing The technical solutions recorded in each embodiment are modified, or some of the technical features are replaced equivalently; and these modifications or replacements do not make the essence of the corresponding technical solutions deviate from the spirit and scope of the technical solutions of the various embodiments of the present invention.

Claims (8)

1.一种装配式再生混凝土防屈曲钢板剪力墙,其特征在于,包括:钢框架、钢板、螺栓、角钢和再生混凝土盖板;1. An assembled recycled concrete buckling-resistant steel plate shear wall is characterized in that, comprising: steel frame, steel plate, bolt, angle steel and recycled concrete cover plate; 所述钢板和所述再生混凝土盖板均设置在所述钢框架内侧,其中,所述钢板的边缘各处均通过所述角钢与所述钢框架连接,所述再生混凝土盖板固定在所述钢板的两侧;Both the steel plate and the recycled concrete cover plate are arranged inside the steel frame, wherein the edges of the steel plate are connected to the steel frame through the angle steel, and the recycled concrete cover plate is fixed on the both sides of the steel plate; 所述钢板与所述角钢通过所述螺栓连接,所述钢框架与所述角钢通过所述螺栓连接。The steel plate is connected to the angle steel by the bolt, and the steel frame is connected to the angle steel by the bolt. 2.根据权利要求1所述的装配式再生混凝土防屈曲钢板剪力墙,其特征在于,所述角钢的数量为8个;2. The assembled recycled concrete buckling-resistant steel plate shear wall according to claim 1, wherein the number of said angle steels is 8; 所述钢板的两侧分别固定有4个角钢。Four angle steels are respectively fixed on both sides of the steel plate. 3.根据权利要求1所述的装配式再生混凝土防屈曲钢板剪力墙,其特征在于,所述钢框架和所述钢板均为矩形,所述钢板与所述钢框架相匹配。3. The fabricated recycled concrete buckling-resistant steel plate shear wall according to claim 1, wherein the steel frame and the steel plate are both rectangular, and the steel plate matches the steel frame. 4.根据权利要求1所述的装配式再生混凝土防屈曲钢板剪力墙,其特征在于,所述角钢包括第一面板和第二面板;4. The assembled recycled concrete buckling-resistant steel plate shear wall according to claim 1, wherein the angle steel comprises a first panel and a second panel; 所述第一面板为矩形,所述第二面板为等腰梯形,所述第一面板与所述钢框架连接,所述第二面板与所述钢板连接。The first panel is rectangular, the second panel is isosceles trapezoidal, the first panel is connected to the steel frame, and the second panel is connected to the steel plate. 5.根据权利要求3所述的装配式再生混凝土防屈曲钢板剪力墙,其特征在于,所述钢框架包括第一H型钢梁、第一H型钢柱、第二H型钢梁和第二H型钢柱。5. The assembled recycled concrete buckling-resistant steel plate shear wall according to claim 3, wherein the steel frame includes a first H-shaped steel beam, a first H-shaped steel column, a second H-shaped steel beam and a first H-shaped steel beam. Two H-shaped steel columns. 6.根据权利要求1所述的装配式再生混凝土防屈曲钢板剪力墙,其特征在于,所述角钢的钢材为Q345钢材。6. The assembled recycled concrete buckling-resistant steel plate shear wall according to claim 1, characterized in that, the steel of the angle steel is Q345 steel. 7.根据权利要求1所述的装配式再生混凝土防屈曲钢板剪力墙,其特征在于,所述钢板的钢材为Q235钢材。7. The prefabricated recycled concrete buckling-resistant steel plate shear wall according to claim 1, wherein the steel of the steel plate is Q235 steel. 8.根据权利要求5所述的装配式再生混凝土防屈曲钢板剪力墙,其特征在于,所述第一H型钢梁、所述第一H型钢柱、所述第二H型钢梁和所述第二H型钢柱依次焊接形成所述钢框架。8. The assembled recycled concrete buckling-resistant steel plate shear wall according to claim 5, wherein the first H-shaped steel beam, the first H-shaped steel column, the second H-shaped steel beam and The second H-shaped steel columns are sequentially welded to form the steel frame.
CN201920540877.8U 2019-04-19 2019-04-19 A prefabricated recycled concrete buckling-resistant steel plate shear wall Active CN209854981U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920540877.8U CN209854981U (en) 2019-04-19 2019-04-19 A prefabricated recycled concrete buckling-resistant steel plate shear wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920540877.8U CN209854981U (en) 2019-04-19 2019-04-19 A prefabricated recycled concrete buckling-resistant steel plate shear wall

Publications (1)

Publication Number Publication Date
CN209854981U true CN209854981U (en) 2019-12-27

Family

ID=68938337

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920540877.8U Active CN209854981U (en) 2019-04-19 2019-04-19 A prefabricated recycled concrete buckling-resistant steel plate shear wall

Country Status (1)

Country Link
CN (1) CN209854981U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109914653A (en) * 2019-04-19 2019-06-21 广东工业大学 A kind of assembled recycled concrete anti-buckling steel plate shear wall and preparation method thereof
CN116657791A (en) * 2023-05-31 2023-08-29 中建科工集团绿色科技有限公司 Anti-buckling steel plate shear wall and its manufacturing method and installation method
CN117627220A (en) * 2023-10-27 2024-03-01 中建科工集团绿色科技有限公司 Anti-buckling steel plate shear wall and its production method and installation method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109914653A (en) * 2019-04-19 2019-06-21 广东工业大学 A kind of assembled recycled concrete anti-buckling steel plate shear wall and preparation method thereof
CN116657791A (en) * 2023-05-31 2023-08-29 中建科工集团绿色科技有限公司 Anti-buckling steel plate shear wall and its manufacturing method and installation method
CN117627220A (en) * 2023-10-27 2024-03-01 中建科工集团绿色科技有限公司 Anti-buckling steel plate shear wall and its production method and installation method

Similar Documents

Publication Publication Date Title
CN107143034A (en) A kind of assembly concrete frame structure beam column rigid connection node
CN105863050A (en) Function-restorable assembly type wave web beam-column composite joint connection device
CN105863052A (en) Function-restorable assembly type beam column-column flange connection joint device
CN204826308U (en) Structure assembly type structure is pieced together in advance to prefabricated shaped steel concrete shear force wall
CN209854981U (en) A prefabricated recycled concrete buckling-resistant steel plate shear wall
CN105133731B (en) A kind of assembled steel performance
CN110359556A (en) Beam-to-column joints connected by end-plate connections of square steel pipe columns with inner inserts in prefabricated steel structures
CN110080418A (en) A kind of detachable assembling type shear wall structure of bolt splicing
CN107083807A (en) A kind of endplate connections node
CN106759858A (en) The connecting node and preparation method of a kind of H profile steel beam and rectangular steel-tube concrete column
CN209854935U (en) Compound concrete-filled steel tube corner post-steel beam joint
CN209603378U (en) A Multi-Cavity Rectangular Steel Tube Concrete Special-shaped Column Structure
CN209585270U (en) Rectangle steel tubing string-H girder steel is bolted structures with semi-rigid joints entirely
CN209779860U (en) An assembled steel frame structure node
CN209339326U (en) A steel-concrete composite node
CN207919737U (en) A kind of assembled steel-Combined concrete frame structure
CN206800712U (en) A kind of power consumption assembled combined steel plate shearing force wall of strip connecting plate
CN110005055A (en) A kind of assembling frame system for the recoverable function being made of drum combination beam
CN219431008U (en) Assembled special-shaped column steel frame-supporting structure system capable of recovering functions
CN209443654U (en) Assembled large span T plate building prefabricated components
CN109537724B (en) Unilateral bolt connection beam column continuous collapse resistant reinforcing node and construction method thereof
CN104032861A (en) Joint structure and construction method of hybrid connected-wall steel column and non-energy-dissipating beam
CN218597373U (en) Assembled top and bottom L-shaped piece H-shaped steel beam column strong shaft connecting device
CN108951848A (en) Assembled steel frame joint can be repaired
CN216892932U (en) Assembled composite wall perps power consumption connection structure