CN209779867U - Connecting structure of high-altitude steel structure frame beam - Google Patents
Connecting structure of high-altitude steel structure frame beam Download PDFInfo
- Publication number
- CN209779867U CN209779867U CN201920252094.XU CN201920252094U CN209779867U CN 209779867 U CN209779867 U CN 209779867U CN 201920252094 U CN201920252094 U CN 201920252094U CN 209779867 U CN209779867 U CN 209779867U
- Authority
- CN
- China
- Prior art keywords
- plate
- frame beams
- flange plate
- fixed
- lower flange
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Joining Of Building Structures In Genera (AREA)
Abstract
本实用新型公开一种高空钢结构框架梁的连接结构,包括两框架梁,两框架梁均包括上翼缘板和下翼缘板,上翼缘板、下翼缘板之间连接有腹板;还包括对位板,对位板的一端部为固定端部,固定端部固定于两框架梁中一者的上翼缘板或下翼缘板,另一端部为自由端部,设有第一连接孔,两框架梁中的另一者对应的上翼缘板或下翼缘板设有连接件;对接状态下,连接件能够穿过第一连接孔,以通过对位板连接两框架梁,且两框架梁的上翼缘板相抵、下翼缘板相抵。本实用新型所提供高空钢结构框架梁的连接结构,其两框架梁通过对位板进行对接定位,可以大幅减少对吊装设备的占用时间,以节省成本,且能够简化焊接操作,以提高作业效率。
The utility model discloses a connection structure of high-altitude steel structure frame beams, which comprises two frame beams, both of which include an upper flange plate and a lower flange plate, and a web is connected between the upper flange plate and the lower flange plate ; It also includes the alignment plate, one end of the alignment plate is a fixed end, the fixed end is fixed on the upper flange plate or the lower flange plate of one of the two frame beams, and the other end is a free end, with In the first connection hole, the upper or lower flange corresponding to the other of the two frame beams is provided with a connecting piece; in the docked state, the connecting piece can pass through the first connecting hole to connect the two frame beams through the alignment plate. frame beams, and the upper flange plates of the two frame beams are against each other, and the lower flange plates are against each other. The connection structure of the high-altitude steel frame beam provided by the utility model, the two frame beams are docked and positioned through the alignment plate, which can greatly reduce the time occupied by the hoisting equipment to save costs, and can simplify the welding operation to improve work efficiency .
Description
技术领域technical field
本实用新型涉及钢结构技术领域,具体涉及一种高空钢结构框架梁的连接结构。The utility model relates to the technical field of steel structures, in particular to a connection structure of high-altitude steel structure frame beams.
背景技术Background technique
现有技术中,对于钢结构框架梁在高空中的对接安装通常需要采用吊装设备进行吊装对位,然后采用焊接方式进行固定。然而,高空对接并不容易,需要吊装设备对两根框架梁的上下位置进行反复调整,对于吊装设备的占用时间较长,且在进行焊接时,由于两根框架梁的位置也并未固定,焊接作业的难度也较大。In the prior art, for the butt joint installation of steel structure frame beams in high altitude, hoisting equipment is usually used for hoisting alignment, and then welding is used for fixing. However, high-altitude docking is not easy, and hoisting equipment is required to repeatedly adjust the upper and lower positions of the two frame beams, which takes a long time for the hoisting equipment, and the position of the two frame beams is not fixed during welding. Welding work is also more difficult.
因此,如何提供一种方案,以克服上述缺陷,仍是本领域技术人员亟待解决的技术问题。Therefore, how to provide a solution to overcome the above defects is still a technical problem to be solved urgently by those skilled in the art.
实用新型内容Utility model content
本实用新型的目的是提供一种高空钢结构框架梁的连接结构,其中,两框架梁可以通过对位板进行对接定位,可以大幅减少对吊装设备的占用时间,以节省成本,且能够简化焊接操作,以提高作业效率。The purpose of this utility model is to provide a connection structure of high-altitude steel structure frame beams, in which two frame beams can be docked and positioned through alignment plates, which can greatly reduce the time occupied by hoisting equipment to save costs and simplify welding operation to improve work efficiency.
为解决上述技术问题,本实用新型提供一种高空钢结构框架梁的连接结构,包括两框架梁,两所述框架梁均包括上翼缘板和下翼缘板,所述上翼缘板、所述下翼缘板之间连接有腹板;还包括对位板,所述对位板的一端部为固定端部,所述固定端部固定于两所述框架梁中一者的所述上翼缘板或所述下翼缘板,另一端部为自由端部,设有第一连接孔,两所述框架梁中的另一者对应的所述上翼缘板或所述下翼缘板设有连接件;对接状态下,所述连接件能够穿过所述第一连接孔,以通过所述对位板连接两所述框架梁,且两所述框架梁的所述上翼缘板能够相抵、所述下翼缘板能够相抵。In order to solve the above-mentioned technical problems, the utility model provides a connection structure of high-altitude steel structure frame beams, including two frame beams, and the two frame beams both include an upper flange plate and a lower flange plate, and the upper flange plate, A web is connected between the lower flange plates; an alignment plate is also included, one end of the alignment plate is a fixed end, and the fixed end is fixed to the one of the two frame beams. The upper flange plate or the lower flange plate, the other end is a free end, provided with a first connecting hole, the other of the two frame beams corresponds to the upper flange plate or the lower wing The edge plate is provided with a connecting piece; in the docked state, the connecting piece can pass through the first connecting hole to connect the two frame beams through the alignment plate, and the upper wings of the two frame beams The flange plates can be butted against each other, and the lower flange plates can be butted against each other.
采用上述结构,在对接状态下,连接件能够穿过第一连接孔,以通过对位板来连接两框架梁,且此时,两框架梁的上翼缘板可以相抵、下翼缘板可以相抵,两框架梁已经完成初步的对接定位,也就可以解除对吊装设备的占用,相比于现有技术,每一根框架梁的安装至少可以减少调整对位时间20分钟,从而可以大幅减少机械台班和费用投入。With the above structure, in the docked state, the connecting piece can pass through the first connecting hole to connect the two frame beams through the alignment plate, and at this time, the upper flange plates of the two frame beams can be offset, and the lower flange plates can be In contrast, the initial docking positioning of the two frame beams has been completed, and the occupancy of the hoisting equipment can be released. Compared with the existing technology, the installation of each frame beam can reduce the adjustment and alignment time by at least 20 minutes, which can greatly reduce Mechanical shift and cost input.
而且,由于两框架梁已经完成初步的对接定位,两框架梁的上翼缘板和下翼缘板已经相抵,二者的位置相对固定,此时,再进行焊接作业,难度相对较低,且由于作业环境较好,焊接的效率也可以提高,还可以节省作业时间,以提高整个钢结构工程的作业效率。Moreover, since the initial docking positioning of the two frame beams has been completed, the upper flange plate and the lower flange plate of the two frame beams have been offset, and the positions of the two are relatively fixed. At this time, the difficulty of welding is relatively low, and Due to the better working environment, the efficiency of welding can also be improved, and the working time can also be saved to improve the working efficiency of the entire steel structure project.
可选地,相抵接的两所述上翼缘板通过焊接固定,相抵接的两所述下翼缘板通过焊接固定。Optionally, the two abutting upper flange plates are fixed by welding, and the two abutting lower flange plates are fixed by welding.
可选地,还包括加强板,以连接两所述框架梁的所述腹板。Optionally, a reinforcing plate is also included to connect the webs of the two frame beams.
可选地,所述加强板通过高强螺栓与所述腹板相连。Optionally, the reinforcing plate is connected to the web through high-strength bolts.
可选地,所述对位板包括贴合板部和加强板部,所述贴合板部的一板面与所述上翼缘板或所述下翼缘板相贴合,另一板面设置有所述加强板部。Optionally, the alignment plate includes a fitting board part and a reinforcing board part, one board surface of the fitting board part is fitted to the upper flange board or the lower flange board, and the other board surface is set There is the reinforcing plate portion.
可选地,所述对位板的数量为两个,两所述对位板的所述固定端部分别固定在同一所述框架梁的所述上翼缘板、所述下翼缘板。Optionally, there are two alignment plates, and the fixed ends of the two alignment plates are respectively fixed to the upper flange plate and the lower flange plate of the same frame beam.
可选地,所述对位板的数量为两个,其中,一个所述对位板的所述固定端部固定于两所述框架梁中一者的所述上翼缘板,另一个所述对位板的所述固定端部固定于两所述框架梁中另一者的所述下翼缘板。Optionally, there are two alignment plates, wherein, the fixed end of one alignment plate is fixed to the upper flange plate of one of the two frame beams, and the other is fixed to the upper flange plate of one of the two frame beams. The fixed end of the alignment plate is fixed to the lower flange plate of the other of the two frame beams.
可选地,所述连接件包括螺栓和螺母。Optionally, the connectors include bolts and nuts.
可选地,所述固定端部也通过所述连接件固定于所述框架梁。Optionally, the fixed end is also fixed to the frame beam through the connecting piece.
附图说明Description of drawings
图1为本实用新型所提供高空钢结构框架梁的连接结构的一种具体实施方式的结构示意图;Fig. 1 is the structural schematic diagram of a kind of embodiment of the connection structure of high-altitude steel structure frame beam provided by the utility model;
图2为对位板的结构示意图。Fig. 2 is a structural schematic diagram of the alignment plate.
图1-2中的附图标记说明如下:The reference signs in Figure 1-2 are explained as follows:
1框架梁、11上翼缘板、12下翼缘板、13腹板、131第二连接孔、14连接件、141螺栓、142螺母;1 frame beam, 11 upper flange plate, 12 lower flange plate, 13 web plate, 131 second connection hole, 14 connector, 141 bolt, 142 nut;
2对位板、2a固定端部、2b自由端部、21贴合板部、211第一连接孔、22加强板部;2 alignment plate, 2a fixed end, 2b free end, 21 laminating plate, 211 first connecting hole, 22 reinforcing plate;
3加强板、31高强螺栓。3 reinforcement plates, 31 high-strength bolts.
具体实施方式Detailed ways
为了使本领域的技术人员更好地理解本实用新型的技术方案,下面结合附图和具体实施例对本实用新型作进一步的详细说明。In order to make those skilled in the art better understand the technical solution of the utility model, the utility model will be further described in detail below in conjunction with the accompanying drawings and specific embodiments.
本文中所述“第一”、“第二”等词,仅是为了便于描述结构相同或相类似的两个以上的结构或部件,并不表示对顺序的某种特殊限定。Words such as "first" and "second" mentioned herein are only used to describe two or more structures or components with the same or similar structures, and do not represent any special limitation on the order.
请参考图1、图2,图1为本实用新型所提供高空钢结构框架梁的连接结构的一种具体实施方式的结构示意图,图2为对位板的结构示意图。Please refer to Fig. 1 and Fig. 2. Fig. 1 is a structural schematic diagram of a specific embodiment of the connection structure of the high-altitude steel structure frame beam provided by the utility model, and Fig. 2 is a structural schematic diagram of the alignment plate.
如图1、图2所示,本实用新型提供一种高空钢结构框架梁的连接结构,包括两框架梁1,两框架梁1均包括上翼缘板11和下翼缘板12,上翼缘板11、下翼缘板12之间连接有腹板13。可以理解,在两框架梁1中,一者已经固定在高空中,为固定梁,反映于附图为左侧的框架梁1,另一者需要吊装并与固定梁相对接,为对接梁,反映于附图为右侧的框架梁1。As shown in Figure 1 and Figure 2, the utility model provides a connection structure of high-altitude steel structure frame beams, including two frame beams 1, both frame beams 1 include an upper flange plate 11 and a lower flange plate 12, and the upper flange plate A web 13 is connected between the edge plate 11 and the lower flange plate 12 . It can be understood that among the two frame beams 1, one has been fixed high in the air and is a fixed beam, which is reflected in the attached figure as the frame beam 1 on the left, and the other needs to be hoisted and connected to the fixed beam, which is a butt joint beam. Reflected in the accompanying drawings is the frame beam 1 on the right.
区别于现有技术中,上述连接结构还可以包括对位板2,对位板2的一端部为固定端部2a,固定端部2a固定于两框架梁1中一者的上翼缘板11或下翼缘板12,另一端部为自由端部2b,设有第一连接孔211,两框架梁1中的另一者对应的上翼缘板11或下翼缘板12设有连接件14。Different from the prior art, the above connection structure may also include an alignment plate 2, one end of the alignment plate 2 is a fixed end portion 2a, and the fixed end portion 2a is fixed to the upper flange plate 11 of one of the two frame beams 1 Or the lower flange plate 12, the other end is a free end 2b, and a first connection hole 211 is provided, and the upper flange plate 11 or the lower flange plate 12 corresponding to the other of the two frame beams 1 is provided with a connecting piece 14.
需要说明,上述的“对应”是与对位板2的安装位置相对应;以存在一个对位板2为例,若该对位板2的固定端部2a固定于一个框架梁1的上翼缘板11,则另一个框架梁1也应该是上翼缘板11设置前述连接件14,若该对位板2的固定端部2a固定于一个框架梁1的下翼缘板12,则另一个框架梁1也应该是下翼缘板12设置前述连接件14。It should be noted that the above-mentioned "correspondence" corresponds to the installation position of the alignment plate 2; taking the existence of an alignment plate 2 as an example, if the fixed end 2a of the alignment plate 2 is fixed to the upper wing of a frame beam 1 flange 11, the other frame beam 1 should also be the upper flange 11 provided with the aforementioned connector 14, if the fixed end 2a of the alignment plate 2 is fixed to the lower flange 12 of a frame beam 1, then another A frame beam 1 should also be provided with the aforementioned connecting piece 14 on the lower flange plate 12 .
在对接状态下,连接件14能够穿过第一连接孔211,以通过对位板2来连接两框架梁1,且此时,两框架梁1的上翼缘板11可以相抵、下翼缘板12可以相抵,两框架梁1已经完成初步的对接定位,也就可以解除对吊装设备的占用,相比于现有技术,每一根框架梁1的安装至少可以减少调整对位时间20分钟,从而可以大幅减少机械台班和费用投入。In the docked state, the connecting piece 14 can pass through the first connecting hole 211 to connect the two frame beams 1 through the alignment plate 2, and at this time, the upper flange plates 11 of the two frame beams 1 can abut against each other, and the lower flange The plates 12 can offset each other, and the initial docking positioning of the two frame beams 1 has been completed, so that the occupancy of the hoisting equipment can be released. Compared with the existing technology, the installation of each frame beam 1 can reduce the adjustment and alignment time by at least 20 minutes , so that the mechanical shift and cost input can be greatly reduced.
而且,由于两框架梁1已经完成初步的对接定位,两框架梁1的上翼缘板11和下翼缘板12已经相抵,二者的位置相对固定,此时,再进行焊接作业,难度相对较低,且由于作业环境较好,焊接的效率也可以提高,还可以节省作业时间,以提高整个钢结构工程的作业效率。Moreover, since the initial butt joint positioning of the two frame beams 1 has been completed, the upper flange plate 11 and the lower flange plate 12 of the two frame beams 1 have been offset, and the positions of the two are relatively fixed. At this time, the welding operation is relatively difficult. It is lower, and due to the better working environment, the efficiency of welding can also be improved, and it can also save working time to improve the working efficiency of the entire steel structure project.
在具体的方案中,相抵接的两上翼缘板11、两下翼缘板12均可以通过焊接进行固定,可形成全熔透的对接焊缝,配合对位板2可以保证两框架梁1之间的可靠连接。In a specific scheme, the two upper flange plates 11 and the two lower flange plates 12 that are in contact with each other can be fixed by welding to form a fully penetrated butt weld, and the alignment plate 2 can ensure that the two frame beams 1 reliable connection between.
需要指出,通过对位板2相连接的两上翼板11或两下翼板12之间也可以不再采用焊接的方式进行二次固定,即也可以仅通过对位板2进行连接固定,此时,还可以减少焊接作业,以更大程度地减少作业时间、提高作业效率。It should be pointed out that the two upper wing plates 11 or the two lower wing plates 12 connected by the alignment plate 2 can no longer be welded for secondary fixing, that is, it can also be connected and fixed only by the alignment plate 2, At this time, welding operations can also be reduced to minimize operating time and improve operating efficiency.
上述连接件14可以包括螺栓141和螺母142,二者可以预先安装在框架梁1上,也可以由现场操作人员随身携带,以在使用时再进行安装。The above-mentioned connecting piece 14 may include bolts 141 and nuts 142, both of which may be pre-installed on the frame beam 1, and may also be carried by on-site operators for installation when in use.
对于固定端部2a,其需要提前与框架梁1进行连接,在一种方案中,固定端部2a可以采用焊接等方式与框架梁1相连,而在另一种方案中,固定端部2a则可以通过前述连接件14等来实现与框架梁1的可拆卸连接。具体到本实用新型实施例,优选采用可拆卸连接的方案,如此,在两框架梁1对接安装完毕后,该对位板2还可以拆除,以方便进行反复使用,还能够节省物料的消耗。For the fixed end part 2a, it needs to be connected with the frame beam 1 in advance. In one scheme, the fixed end part 2a can be connected with the frame beam 1 by means of welding, etc., while in another scheme, the fixed end part 2a is then The detachable connection with the frame beam 1 can be realized through the aforementioned connecting piece 14 and the like. Concretely to the embodiment of the present utility model, it is preferable to adopt a detachable connection scheme. In this way, after the two frame beams 1 are docked and installed, the alignment plate 2 can be removed to facilitate repeated use and save material consumption.
进一步地,还可以包括加强板3,用于连接两框架梁1的腹板13。详细而言,腹板13可以设有第二连接孔131,加强板3可以设有第三连接孔(图中未示出),高强螺栓31可以穿过两连接孔,以固连加强板3和腹板13,由于高强螺栓31的强度较高,承载能力较强,能够更大程度地提高两框架梁1的连接强度。Further, a reinforcing plate 3 may also be included for connecting the webs 13 of the two frame beams 1 . In detail, the web 13 can be provided with a second connecting hole 131, the reinforcing plate 3 can be provided with a third connecting hole (not shown in the figure), and high-strength bolts 31 can pass through the two connecting holes to securely connect the reinforcing plate 3 and the web 13, because the high-strength bolts 31 have higher strength and stronger load-bearing capacity, the connection strength between the two frame beams 1 can be improved to a greater extent.
应当知晓,高强螺栓31需要较高的连接精度和穿孔率,采用现有技术中的方案对两框架梁1进行安装时,需要吊钩反复调整框架梁1的高度,才能够使得第三连接孔与第二连接孔131完全对正,这也是现有技术对吊装设备占用时间较长的一个重要原因。而在本实用新型实施例中,由于对位板2可以对两框架梁1进行连接对位,可以很好地控制两框架梁1垂向中心线的偏差,两框架梁1的腹板13上的第二连接孔131基本可以维持在同一高度上,能够较大程度地保证高强螺栓31的一次穿孔率,以确保安装效率。It should be known that high-strength bolts 31 require high connection accuracy and perforation rate. When using the scheme in the prior art to install the two frame beams 1, it is necessary to repeatedly adjust the height of the frame beam 1 with the hook to make the third connection hole It is completely aligned with the second connection hole 131, which is also an important reason why the prior art takes a long time for the hoisting equipment. In the embodiment of the present invention, since the alignment plate 2 can connect and align the two frame beams 1, the deviation of the vertical centerline of the two frame beams 1 can be well controlled, and the webs 13 of the two frame beams 1 The second connecting holes 131 can basically be maintained at the same height, which can ensure the primary penetration rate of the high-strength bolts 31 to a large extent, so as to ensure installation efficiency.
前述对位板2可以包括贴合板部21和加强板部22,贴合板部21的一板面可以与上翼缘板11或下翼缘板12相贴合,另一板面可以设置有加强板部22。贴合板部21与加强板部22可以呈夹角设置,以形成类似角钢的结构,加强板部22可以对贴合板部21进行加强,且有利于保证贴合板部21的板面平整,以便在贴合板部21与两框架梁1的上翼缘板11或下翼缘板12相贴合时能够更好地控制两框架梁1垂向中心线的偏差。结合图2,该对位板2的截面形状可以呈T形,当然也可以为L形等。The above-mentioned alignment plate 2 can include a fitting plate portion 21 and a reinforcing plate portion 22, one plate surface of the fitting plate portion 21 can be fitted with the upper flange plate 11 or the lower flange plate 12, and the other plate surface can be provided with a reinforcement plate. plate portion 22 . The fitting plate portion 21 and the reinforcing plate portion 22 can be arranged at an angle to form a structure similar to an angle steel. The reinforcing plate portion 22 can strengthen the fitting plate portion 21, and it is beneficial to ensure that the plate surface of the fitting plate portion 21 is smooth, so that the When the bonding plate portion 21 is bonded to the upper flange plate 11 or the lower flange plate 12 of the two frame beams 1 , the deviation of the vertical centerlines of the two frame beams 1 can be better controlled. Referring to FIG. 2 , the cross-sectional shape of the alignment plate 2 can be T-shaped, or L-shaped, etc. of course.
在以图1为视角的实施例中,对位板2的数量可以为一个,该对位板2可以连接在两框架梁1的上翼缘板11或下翼缘板12上。In the embodiment shown in FIG. 1 , there can be one alignment plate 2 , and the alignment plate 2 can be connected to the upper flange plate 11 or the lower flange plate 12 of the two frame beams 1 .
而在具体实施时,该对位板2的数量也可以为多个,当为多个时,各对位板2可以分为两组,一组用于连接两框架梁1的上翼缘板11,另一组用于连接两框架梁1的下翼缘板12,以在上下两个方向上均对两框架梁1进行连接对位。在存在两组对位板2的方案中,最简单的方案是存在两个对位板2,两对位板2可以分别连接两框架梁1的两上翼缘板11、两下翼缘板12,以下本实用新型实施例即以该方案为例对存在两组对位板2时、对位板2与两框架梁1的连接结构进行描述。And in concrete implementation, the quantity of this aligning plate 2 also can be multiple, when being multiple, each aligning plate 2 can be divided into two groups, one group is used to connect the upper flange plate of two frame beams 1 11. Another set of lower flange plates 12 for connecting the two frame beams 1, so as to connect and align the two frame beams 1 in both up and down directions. Among the solutions with two sets of alignment plates 2, the simplest solution is that there are two alignment plates 2, and the two alignment plates 2 can respectively connect the two upper flange plates 11 and the two lower flange plates of the two frame beams 1. 12. The following embodiments of the present invention will take this scheme as an example to describe the connection structure between the alignment plates 2 and the two frame beams 1 when there are two sets of alignment plates 2 .
在一种方案中,两对位板2的固定端部2a可以分别固定在同一框架梁1的上翼缘板11、下翼缘板12,此时,另一框架梁1的上翼缘板11、下翼缘板12上均可以设有连接件14。In one solution, the fixed ends 2a of the two alignment plates 2 can be respectively fixed on the upper flange plate 11 and the lower flange plate 12 of the same frame beam 1. At this time, the upper flange plate of the other frame beam 1 11. Connecting pieces 14 may be provided on the lower flange plates 12 .
在另一种方案中,为便于区分,可以将两框架梁1分别称之为第一框架梁、第二框架梁,两对位板2中的一者可以固定在第一框架梁的上翼缘板11,另一者可以固定在第二框架梁的下翼缘板12,相应地,连接件14可以设置在第一框架梁的下翼缘板12和第二框架梁的上翼缘板11上。In another solution, for the convenience of distinction, the two frame beams 1 can be called the first frame beam and the second frame beam respectively, and one of the two alignment plates 2 can be fixed on the upper wing of the first frame beam. Flange plate 11, the other can be fixed on the lower flange plate 12 of the second frame beam, correspondingly, the connecting piece 14 can be arranged on the lower flange plate 12 of the first frame beam and the upper flange plate of the second frame beam 11 on.
比较而言,上述的两种方案均可以实现两组对位板2与两框架梁1的连接,在实际应用中,本领域技术人员可以根据实际需要进行选取。In comparison, both of the above two solutions can realize the connection between the two sets of alignment plates 2 and the two frame beams 1 , and in practical applications, those skilled in the art can choose according to actual needs.
以上仅是本实用新型的优选实施方式,应当指出,对于本技术领域的普通技术人员来说,在不脱离本实用新型原理的前提下,还可以做出若干改进和润饰,这些改进和润饰也应视为本实用新型的保护范围。The above are only preferred embodiments of the present utility model, and it should be pointed out that for those of ordinary skill in the art, some improvements and modifications can also be made without departing from the principles of the present utility model. It should be regarded as the protection scope of the present utility model.
Claims (9)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920252094.XU CN209779867U (en) | 2019-02-27 | 2019-02-27 | Connecting structure of high-altitude steel structure frame beam |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920252094.XU CN209779867U (en) | 2019-02-27 | 2019-02-27 | Connecting structure of high-altitude steel structure frame beam |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209779867U true CN209779867U (en) | 2019-12-13 |
Family
ID=68795983
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201920252094.XU Expired - Fee Related CN209779867U (en) | 2019-02-27 | 2019-02-27 | Connecting structure of high-altitude steel structure frame beam |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209779867U (en) |
-
2019
- 2019-02-27 CN CN201920252094.XU patent/CN209779867U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110056088A (en) | It is a kind of can the connection structure of Fast Installation girder steel and the installation method of girder steel | |
CN106065664B (en) | Reusable connecting node and connecting method for movable roof truss and upright post | |
CN103132458A (en) | Overall installation method of double-body separable combined beam | |
CN106812214A (en) | A kind of assembling type steel structure beam column node connection device | |
CN218814634U (en) | Combined floor slab | |
CN209779867U (en) | Connecting structure of high-altitude steel structure frame beam | |
CN209854556U (en) | A bridge deck and its bolt hole sealing structure | |
CN204921558U (en) | A interim connecting device that is used for component and bracket to dock | |
CN214574703U (en) | Concrete column-steel beam connection node with web plate provided with hole | |
CN204850048U (en) | Overlap joint structure of quick hoist and mount of supplementary high -rise girder steel | |
CN210134525U (en) | Connecting structure capable of quickly mounting steel beam | |
CN202322015U (en) | Main end beam connecting system for bridge crane | |
CN114673191A (en) | Attached steel structure construction elevator foundation capable of rotating in week and using method thereof | |
CN209335009U (en) | Cantilever crane group body tooling | |
CN105019556A (en) | Lap-joint structure assisting quick hoisting of high-rise steel beam, and application of lap-joint structure | |
CN219732342U (en) | Semi-assembled tensile beam column node structure for steel structure | |
CN217896184U (en) | Steel construction bridge node connection structure | |
CN219058362U (en) | A standard section of tower crane | |
CN205804601U (en) | The Moveable roof truss of repeatable utilization and the connection node of column | |
CN220011827U (en) | TBM aircraft nose hoist and mount anchor clamps | |
CN218508240U (en) | Height adjusting device is assembled to steel longeron bridge panel | |
CN220036183U (en) | Clamp type code plate for steel beam installation | |
CN221972683U (en) | Node structure for connecting out-of-plane steel plate shear wall and profile steel column | |
CN219196262U (en) | Steel construction beam column assembled connection structure | |
CN214653055U (en) | A double-girder crane segmented structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20191213 |