CN209692229U - A kind of offshore boosting station intelligent management plateform system - Google Patents
A kind of offshore boosting station intelligent management plateform system Download PDFInfo
- Publication number
- CN209692229U CN209692229U CN201920608255.4U CN201920608255U CN209692229U CN 209692229 U CN209692229 U CN 209692229U CN 201920608255 U CN201920608255 U CN 201920608255U CN 209692229 U CN209692229 U CN 209692229U
- Authority
- CN
- China
- Prior art keywords
- module
- cabin
- control module
- control
- sensor
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Alarm Systems (AREA)
Abstract
The utility model discloses a kind of offshore boosting station intelligent management plateform systems, more particularly to booster stations technical field, including cabin, the cabin includes control cabin and secondary cabin, the control cabin interior is provided with control module, the control module connecting pin is provided with system alarm module and fire protection warning module, the system alarm module and fire protection warning module are arranged in secondary cabin, the pair cabin interior is provided with power equipment, and the control module output end is provided with display module.The utility model is by being equipped with system alarm module, intelligent it can cool down to power equipment, and temperature data can be stored in storage module by control module, so that maintenance personnel checks, the data that control module can acquire system alarm module are analyzed, when the data parameters of acquisition are not in setting range value, control module can be reminded operator by display module, to remind operator to safeguard.
Description
Technical field
The utility model relates to booster stations technical fields, more specifically, originally practical to be related to a kind of offshore boosting station intelligence
Change management platform system.
Background technique
China's offshore wind energy resource is abundant, makes a breakthrough as the realization technology of offshore wind power development is constantly progressive, marine
Wind-powered electricity generation gradually becomes the emphasis of China's future development of clean energy.Since marine wind electric field booster stations are distributed wide, sea climate
The operation inspection work of bad environments, marine wind electric field booster stations is complicated more than the inspection operational difficulties of land wind power plant, tradition
Wind power plant operational management scheme primarily directed to land environmental quality design, be unable to satisfy marine wind electric field booster stations
Operational management.Booster stations switchgear house in marine wind electric field booster stations carries transmission and the distribution weight of entire wind park electric energy
Appoint, is a ring important in wind power plant operational management.
The utility model patent of patent application publication CN204090020U discloses a kind of marine wind electric field booster stations view
Frequency monitoring system, it is by power module, video camera, infrared thermometer, optical-fibre communications equipment, data collector and industry control
Machine composition;Video camera and infrared thermometer be it is multiple, every two is one group and passes through optical fiber and optical-fibre communications equipment phase
Connection;Optical-fibre communications equipment is connected on data collector;Data collector is connected with industrial personal computer by RS485 bus.Number
According to setting on collector, there are two RS232 and RS485 serial communication interfaces.Video camera, infrared thermometer, optical fiber are logical
News equipment, data collector pass through power supply line with industrial personal computer and are connected with power module.The utility model, which realizes, to be monitored
Remote real-time video monitoring, remote failure and fortuitous event, which are accused, to be realized to affiliated substation by existing power telecom network in center
Alert reception processing, ensure that the safety and reliability of substation operation and maintenance.
But it is in actual use, cannot effectively acquire equipment operating data, it cannot the timely discovering device course of work
The anomalous variation of middle generation, intelligence degree are low.
Utility model content
In order to overcome the drawbacks described above of the prior art, it is intelligent that the embodiments of the present invention provide a kind of offshore boosting station
Management platform system, the utility model intelligent can cool down to power equipment by being equipped with system alarm module, and control
Temperature data can be stored in storage module by molding block, and so that maintenance personnel checks, control module can be to system alarm
The data of module acquisition are analyzed, and when the data parameters of acquisition are not in setting range value, control module can pass through display
Module reminds operator, to remind operator to safeguard.
To achieve the above object, the utility model provides the following technical solutions: a kind of offshore boosting station intelligent management is flat
Platform system, including cabin, the cabin include control cabin and secondary cabin, and the control cabin interior is provided with control mould
Block, the control module connecting pin are provided with system alarm module and fire protection warning module, the system alarm module and fire-fighting
Alarm module is arranged in secondary cabin, and the pair cabin interior is provided with power equipment, the control module output end setting
There is display module, the control module is internally provided with storage module;
System alarm module includes temperature sensor, humidity sensor, monitoring camera, Partial discharge detector and shake
Dynamic sensor, the temperature sensor, humidity sensor, monitoring camera, Partial discharge detector and shock sensor output
End is connect by conducting wire with control module, the fixed electricity of the temperature sensor, Partial discharge detector and shock sensor
In power equipment, the monitoring camera and humidity sensor are fixed on secondary compartment roof;
Fire protection warning module includes smoke sensor device and gas sensor, and the smoke sensor device and gas sensor are defeated
Outlet passes through conducting wire and connect with control module, and the smoke sensor device and gas sensor are each attached to secondary compartment roof.
In a preferred embodiment, the control module is set as single-chip microcontroller, and the storage module is set as storing up
Storage, the single-chip microcontroller and reservoir are to be electrically connected.
In a preferred embodiment, the display module is set as touch display screen.
In a preferred embodiment, the smoke sensor device is linked by control module and monitoring camera.
In a preferred embodiment, the secondary compartment roof is provided with electromagnetic valve for fire control, the electromagnetic valve for fire control
Input terminal is connect with control module.
In a preferred embodiment, the cabin interior is provided with air-conditioner set and dehumidifier, the air-conditioning
Unit and dehumidifier input terminal are connect with control module.
In a preferred embodiment, the control module can be connect by seabed fiber with server.
The technical effect and advantage of the utility model:
1, the utility model can monitor the indoor electric power in secondary cabin and set by being equipped with system alarm module, system alarm module
It is standby, when a certain secondary cabin power equipment when the temperature is excessively high, control module can increase the pair cabin air-conditioner set and run power, thus
Intelligence cools down to power equipment, and temperature data can be stored in storage module by control module, for safeguarding people
Member is checked that when humidity is excessively high, control module will start dehumidifier, to avoid the excessive influence power equipment of air humidity
It operates normally, the data that control module can acquire system alarm module are analyzed, when the data parameters of acquisition are not being set
When in value range, control module can be reminded operator by display module, to remind operator to safeguard,
And control module meeting control system alarm module shows global image, the local detail image of equipment is then shown, to obtain
Target more information, facilitates operator quickly to grasp field condition, and control module can pass through seabed fiber and foreign teacher's server
Connection makes operator that can remotely monitor the operating condition of secondary cabin power equipment inside booster stations, the management to operator
It brings great convenience, intelligence degree is high;
2, the utility model is floatd by being equipped with smoke sensor device and gas sensor when smoke sensor device collects in air
When scattered smoke signal, the signal data of acquisition can pass to control module, and control module can control monitoring camera shooting should
The secondary indoor power equipment in cabin, operator carry out judging whether to start electromagnetic valve for fire control, gas sensing according to the picture of transmission
Device can analyze aerosol gases, thus judge whether contain toxic gas in smog, it can be to the operator of forward fire extinguishing
It is reminded, in case unexpected occur.
Detailed description of the invention
Fig. 1 is the utility model overall structure diagram.
Fig. 2 is Tthe utility model system structural schematic diagram.
Fig. 3 is the utility model electrical block diagram.
Appended drawing reference are as follows: 1 cabin, 11 control cabins, 101 secondary cabins, 2 control modules, 3 system alarm modules, 33 temperature
Sensor, 34 humidity sensors, 35 monitoring cameras, 36 Partial discharge detectors, 37 shock sensors, 4 fire protection warning modules,
44 smoke sensor devices, 45 gas sensors, 5 power equipments, 6 display modules, 7 storage modules, 8 electromagnetic valve for fire control, 9 air conditioners
Group, 10 dehumidifiers.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model
Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole
Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work
Every other embodiment obtained, fall within the protection scope of the utility model.
The utility model provides a kind of offshore boosting station intelligent management plateform system, including cabin 1, and feature exists
In: the cabin 1 includes control cabin 11 and secondary cabin 101, and the control cabin 11 is internally provided with control module 2, institute
It states 2 connecting pin of control module and is provided with system alarm module 3 and fire protection warning module 4, the system alarm module 3 and fire-fighting report
Alert module 4 is arranged in secondary cabin 101, and the pair cabin 101 is internally provided with power equipment 5, and the control module 2 exports
End is provided with display module 6, and the control module 2 is internally provided with storage module 7;System alarm module 3 includes that temperature passes
Sensor 33, humidity sensor 34, monitoring camera 35, Partial discharge detector 36 and shock sensor 37, the temperature sensing
Device 33, humidity sensor 34, monitoring camera 35, Partial discharge detector 36 and 37 output end of shock sensor pass through conducting wire
It is connect with control module 2, the fixed power equipment of the temperature sensor 33, Partial discharge detector 36 and shock sensor 37
On 5, the monitoring camera 35 and humidity sensor 34 are fixed on secondary 101 top of cabin;Fire protection warning module 4 includes smog
Sensor 44 and gas sensor 45, the smoke sensor device 44 and 45 output end of gas sensor pass through conducting wire and control mould
Block 2 connects, and the smoke sensor device 44 and gas sensor 45 are each attached to secondary 101 top of cabin.
The 33 model DS18B20 temperature sensor of temperature sensor, 34 model of humidity sensor
SENSIRION humidity sensor, the 35 model DS-2CD3232D-I5 monitoring camera of monitoring camera, the part is put
36 model st-2020 Partial discharge detector of electro-detection instrument, 37 model HOLTHAUSEN of the shock sensor vibration pass
Sensor, the 44 model d4240 smoke sensor device of smoke sensor device, the 45 model SGXMICS-VZ- of gas sensor
89TE gas sensor, the single-chip microcontroller model AVR single chip, the 10 model MOH-7156BC dehumidifier of dehumidifier.
As shown in Figure 1-3, embodiment specifically: the temperature regime of the meeting real-time monitoring power equipment 5 of temperature sensor 33,
And the temperature data of acquisition is passed into control module 2, control module 2 can analyze temperature data, when a certain secondary cabin
When the temperature is excessively high, control module 2 can increase 101 air-conditioner set 9 of pair cabin operation power to 101 power equipments 5, thus intelligent
Cool down to power equipment 5, and control module 2 temperature data can be stored in storage module 7, for maintenance personnel into
Capable to check, in the meeting of humidity sensor 34 real-time monitoring pair cabin 101 humidity, and the humidity data of acquisition is passed into control mould
Block 2, control module 2 can analyze the humidity data of detection, and when humidity is excessively high, control module 2 will start dehumidifier 10,
Dehumidifier 10 can reduce the air humidity in secondary cabin 101, to avoid the excessive influence power equipment 5 of air humidity normally fortune
Row, Partial discharge detector 36 and shock sensor 37 can detect the discharged condition and vibration amplitude of power equipment 5 respectively, and will
The data of acquisition pass to control module 2, and control module 2 can analyze the data of acquisition, when acquisition data parameters not
When in setting range value, control module 2 can be reminded operator by display module 6, to remind operator
Safeguarded, power equipment 5 includes switchgear, current transformer, voltage transformer, transformer etc., when temperature sensor 33,
When Partial discharge detector 36 and shock sensor 37 detect that a certain power equipment 5 breaks down, signal can be passed to control
Molding block 2, control module 2 will start monitoring camera 35, make monitoring camera 35 that can show faulty equipment region in time, and control
Molding block 2 can control monitoring camera 35 and show global image, the local detail image of equipment then be shown, to obtain target
More information, facilitates operator quickly to grasp field condition, and control module 2 can be connected by seabed fiber and foreign teacher's server
It connects, makes operator that can remotely monitor the operating condition of 101 power equipment 5 of secondary cabin inside booster stations, to the pipe of operator
Reason brings great convenience.
The control module 2 is set as single-chip microcontroller, and the storage module 7 is set as reservoir, the single-chip microcontroller and storage
Device is to be electrically connected, and the display module 6 is set as touch display screen, and the smoke sensor device 44 passes through control module 2 and prison
It controls camera 35 to link, is provided with electromagnetic valve for fire control 8,8 input terminal of electromagnetic valve for fire control and control at the top of the pair cabin 101
Module 2 connects, and is provided with air-conditioner set 9 and dehumidifier 10 inside the cabin 1, the air-conditioner set 9 and dehumidifier 10 are defeated
Enter end to connect with control module 2, the control module 2 can be connect by seabed fiber with server.
As shown in Figs. 1-2, embodiment specifically: the electric power in the meeting of smoke sensor device 44 real-time monitoring pair cabin 101 is set
Whether standby 5 occur fire, and when smoke sensor device 44 collects the smoke signal drifted in air, the signal data of acquisition can be passed
Control module 2 is passed, since smoke sensor device 44 and monitoring camera 35 link, control module 2 can control monitoring camera 35
The power equipment 5 in the pair cabin 101 is shot, operator carries out judging whether to start electromagnetic valve for fire control according to the picture of transmission
8, gas sensor 45 can analyze aerosol gases, and the data after analysis can pass to control module 2 and compare, thus
Judge whether contain toxic gas in smog, the operator of forward fire extinguishing can be reminded.
Utility model works principle:
Referring to Figure of description 1-3, the temperature regime of the meeting real-time monitoring power equipment 5 of temperature sensor 33, and will acquire
Temperature data pass to control module 2, control module 2 can analyze the temperature data of detection, and control module 2 is by adopting
The intelligent adjusting air conditioning group 9 of the data meeting of collection runs power, wet in the meeting of humidity sensor 34 real-time monitoring pair cabin 101
Degree, and the humidity data of acquisition is passed into control module 2, control module 2 can be reduced in secondary cabin 101 by dehumidifier 10
Air humidity, Partial discharge detector 36 and shock sensor 37 can detect the discharged condition and vibration width of power equipment 5 respectively
Degree, and the data of acquisition are passed into control module 2, control module 2 can analyze the data of acquisition, when the data of acquisition
When parameter is not in setting range value, control module 2 can be reminded operator by display module 6, monitoring camera
35 can show faulty equipment region in time;
Referring to Figure of description 1-2, when smoke sensor device 44 collects the smoke signal drifted in air, the letter of acquisition
Number can pass to control module 2, and since smoke sensor device 44 and monitoring camera 35 link, control module 2 can control prison
The power equipment 5 in the shooting of the camera 35 pair cabin 101 is controlled, gas sensor 45 can analyze aerosol gases, analyze
Data afterwards can pass to control module 2 and compare, to judge whether contain toxic gas in smog.
The several points that should finally illustrate are: firstly, in the description of the present application, it should be noted that unless otherwise prescribed and
It limits, term " installation ", " connected ", " connection " shall be understood in a broad sense, can be mechanical connection or electrical connection, be also possible to two
Connection inside element, can be directly connected, and "upper", "lower", "left", "right" etc. are only used for indicating relative positional relationship, when
The absolute position for being described object changes, then relative positional relationship may change;
Secondly: the utility model discloses in embodiment attached drawing, relates only to the structure being related to the embodiment of the present disclosure,
His structure, which can refer to, to be commonly designed, and under not conflict situations, the utility model the same embodiment and different embodiments can be mutual
Combination;
Last: the above descriptions are merely preferred embodiments of the present invention, is not intended to limit the utility model, all
Within the spirit and principles of the present invention, any modification, equivalent replacement, improvement and so on should be included in practical
Within novel protection scope.
Claims (7)
1. a kind of offshore boosting station intelligent management plateform system, including cabin (1), it is characterised in that: the cabin (1) includes
There are control cabin (11) and secondary cabin (101), the control cabin (11) is internally provided with control module (2), the control mould
Block (2) connecting pin is provided with system alarm module (3) and fire protection warning module (4), the system alarm module (3) and fire-fighting report
Alert module (4) are arranged in secondary cabin (101), and the pair cabin (101) is internally provided with power equipment (5), the control
Module (2) output end is provided with display module (6), and the control module (2) is internally provided with storage module (7);
System alarm module (3) includes temperature sensor (33), humidity sensor (34), monitoring camera (35), locally puts
Electro-detection instrument (36) and shock sensor (37), the temperature sensor (33), humidity sensor (34), monitoring camera
(35), Partial discharge detector (36) and shock sensor (37) output end pass through conducting wire and connect with control module (2), described
On temperature sensor (33), Partial discharge detector (36) and shock sensor (37) fixed power equipment (5), the monitoring
Camera (35) and humidity sensor (34) are fixed at the top of secondary cabin (101);
Fire protection warning module (4) includes smoke sensor device (44) and gas sensor (45), the smoke sensor device (44) and
Gas sensor (45) output end passes through conducting wire and connect with control module (2), the smoke sensor device (44) and gas sensing
Device (45) is each attached at the top of secondary cabin (101).
2. a kind of offshore boosting station intelligent management plateform system according to claim 1, it is characterised in that: the control
Module (2) is set as single-chip microcontroller, and the storage module (7) is set as reservoir, and the single-chip microcontroller and reservoir are to be electrically connected.
3. a kind of offshore boosting station intelligent management plateform system according to claim 1, it is characterised in that: the display
Module (6) is set as touch display screen.
4. a kind of offshore boosting station intelligent management plateform system according to claim 1, it is characterised in that: the smog
Sensor (44) is linked by control module (2) and monitoring camera (35).
5. a kind of offshore boosting station intelligent management plateform system according to claim 1, it is characterised in that: the pair cabin
It is provided with electromagnetic valve for fire control (8) at the top of room (101), electromagnetic valve for fire control (8) input terminal is connect with control module (2).
6. a kind of offshore boosting station intelligent management plateform system according to claim 1, it is characterised in that: the cabin
(1) internal to be provided with air-conditioner set (9) and dehumidifier (10), the air-conditioner set (9) and dehumidifier (10) input terminal with
Control module (2) connection.
7. a kind of offshore boosting station intelligent management plateform system according to claim 1, it is characterised in that: the control
Module (2) can be connect by seabed fiber with server.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920608255.4U CN209692229U (en) | 2019-04-29 | 2019-04-29 | A kind of offshore boosting station intelligent management plateform system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920608255.4U CN209692229U (en) | 2019-04-29 | 2019-04-29 | A kind of offshore boosting station intelligent management plateform system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209692229U true CN209692229U (en) | 2019-11-26 |
Family
ID=68608465
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201920608255.4U Expired - Fee Related CN209692229U (en) | 2019-04-29 | 2019-04-29 | A kind of offshore boosting station intelligent management plateform system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209692229U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114715360A (en) * | 2021-01-05 | 2022-07-08 | 中国电建集团华东勘测设计研究院有限公司 | Seabed big data center attached to large offshore substation and installation and maintenance process |
-
2019
- 2019-04-29 CN CN201920608255.4U patent/CN209692229U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114715360A (en) * | 2021-01-05 | 2022-07-08 | 中国电建集团华东勘测设计研究院有限公司 | Seabed big data center attached to large offshore substation and installation and maintenance process |
CN114715360B (en) * | 2021-01-05 | 2023-02-24 | 中国电建集团华东勘测设计研究院有限公司 | Seabed big data center attached to large offshore transformer substation and installation and maintenance process |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102122844B (en) | Communication network based on sensor and smart substation of expert system | |
CN205910570U (en) | Need not people intelligent monitoring system of transformer substation that always falls on duty | |
CN204009556U (en) | For the watch-dog of intelligent substation | |
CN208820537U (en) | A kind of box-type substation integrated information monitoring system based on Internet of Things | |
CN103941784A (en) | System and method for monitoring and acquiring power distribution station environment | |
CN110136391A (en) | A kind of energy-accumulating power station fire early-warning system and method | |
CN103207616A (en) | Environmental information monitoring method for transformer substation | |
CN108375962A (en) | Offshore boosting station patrols control system | |
CN106340962A (en) | Monitoring and alarming system for DC power supply in transformer substation | |
CN107065980B (en) | Power distribution room on-line monitoring and accident pre-alarming system based on HT-iBS Virtual Intelligent bus | |
CN103134554A (en) | Operation environment monitoring device for relay protection device and monitoring method thereof | |
CN112634579A (en) | Transformer substation security early warning linkage system | |
CN203759160U (en) | Integrated intelligent monitoring system of transformer station | |
CN211878460U (en) | Intelligent comprehensive monitoring system for distribution transformer environment | |
CN209692229U (en) | A kind of offshore boosting station intelligent management plateform system | |
CN206653397U (en) | The towed electricity of hanger rail leads to integrated piping lane environmental monitoring intelligent miniature robot | |
CN214202124U (en) | Intelligent monitoring screen cabinet of power distribution room | |
CN103941785A (en) | Method for controlling intelligent control device for power distribution station environment | |
CN112202241A (en) | Distribution network equipment state monitoring and fault judgment system | |
CN206742968U (en) | A kind of switchgear house intelligence attended computer device people's system | |
CN107807583A (en) | The internal environment detection method of electric power cabinet | |
CN204143280U (en) | Distribution substation environmental monitoring acquisition system | |
CN211321021U (en) | On-line monitoring system for intelligent power distribution room | |
CN202649804U (en) | Centralized control system for communication base station | |
CN108270293A (en) | Offshore boosting station switchgear house patrols control system and booster stations switchgear house |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20191126 Termination date: 20210429 |
|