CN209669794U - A kind of leakage piping dykes and dams of speedily carrying out rescue work build structure - Google Patents

A kind of leakage piping dykes and dams of speedily carrying out rescue work build structure Download PDF

Info

Publication number
CN209669794U
CN209669794U CN201920036417.1U CN201920036417U CN209669794U CN 209669794 U CN209669794 U CN 209669794U CN 201920036417 U CN201920036417 U CN 201920036417U CN 209669794 U CN209669794 U CN 209669794U
Authority
CN
China
Prior art keywords
cloth
curtain
rescue work
out rescue
curtain face
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920036417.1U
Other languages
Chinese (zh)
Inventor
吴永松
翟高勇
任玉彬
甄峰
左保静
曹善宇
沈颖
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Water Conservancy Engineering Science And Technology Consulting Ltd By Share Ltd
Original Assignee
Jiangsu Water Conservancy Engineering Science And Technology Consulting Ltd By Share Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Water Conservancy Engineering Science And Technology Consulting Ltd By Share Ltd filed Critical Jiangsu Water Conservancy Engineering Science And Technology Consulting Ltd By Share Ltd
Priority to CN201920036417.1U priority Critical patent/CN209669794U/en
Application granted granted Critical
Publication of CN209669794U publication Critical patent/CN209669794U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/11Hard structures, e.g. dams, dykes or breakwaters

Landscapes

  • Revetment (AREA)

Abstract

The utility model relates to a kind of leakage piping dykes and dams of speedily carrying out rescue work to build structure, including curtain face cloth, steel label and woven belt, wherein woven belt is several, along curtain face, cloth axis is evenly arranged on the cloth of curtain face, and 0.8-1.5 meters of spacing between adjacent two woven belts, and woven belt is connected with each other and constitutes the casing of closed hoop structure, steel label are column structure, quantity is identical as casing quantity, and each casing coats a bar steel label, steel signs end face beyond at least 5 centimetres of curtain face cloth upper surface, and lower end surface exceeds at least 10 centimetres of curtain face cloth lower end surface.It includes that preparation leakage piping dykes and dams of speedily carrying out rescue work such as build structure and contain leakproof at two steps that it, which builds method,.The utility model water blocking is good compared with fruit, and equipment is installed simply, and installation speed is fast, and material utilization amount of speedily carrying out rescue work is few, and equipment is simple, low cost, can be reserved for time limit length, preservation occupies little space, is reusable.Generally reach the features such as faster, efficient, economic of speedily carrying out rescue work.

Description

A kind of leakage piping dykes and dams of speedily carrying out rescue work build structure
Technical field
The utility model relates to a kind of leakage piping dykes and dams of speedily carrying out rescue work to build structure, belong to water conservancy construction technical field.
Background technique
When river high water level, because of a variety of causes, dyke downstream slope will appear the dangerous situations such as infiltration, piping, loophole, infiltration, pipe Gush, three kinds of situations of loophole are several stages that dangerous situation gradually develops from light to heavy, increase inspection dynamics when seeping clear water, seep muddy water When, emergency measure is taken, strives for properly protecting before dangerous situation is further aggravated;When directly there is leakage piping situation, Ying Cai Take urgent emergency measure, it is necessary to protection of speedily carrying out rescue work is carried out within the shortest time.Guarantee to speedily carry out rescue work is the important category of equipment of speedily carrying out rescue work rapidly Property.
Infiltration piping emergency control method has at present: earth bag anti-filter encloses well, earth-bag cofferdam hooping, drainage pressure leaching these three modes of platform And corresponding construction technology, but found in actual construction, it is larger to there is the cofferdam earth bag scale of construction, implementation speedily carry out rescue work the used time compared with It is long, it cannot preferably realize fast reaction of speedily carrying out rescue work;Cofferdam leakproof is poor compared with fruit, and hooping inner product water speed is relatively unrestrained;Dangerous situation is gone with crossing The biggish defect of cleaning workload afterwards.
Utility model content
The utility model aim, which is that, overcomes above-mentioned deficiency, provides a kind of leakage piping dykes and dams of speedily carrying out rescue work and builds structure, pacifies Dress is simple and speed is fast, avoids the generation of dangerous situation.
To achieve the above object, the utility model is to be achieved through the following technical solutions:
A kind of leakage piping dykes and dams of speedily carrying out rescue work build structure, including curtain face cloth, drill rod and woven belt, and wherein curtain face cloth is long Spending length is 8-10 meters, and breadth length ratio range is 0.17 ~ 0.24;Woven belt is several, arranges along curtain face cloth axis direction, adjacent two It is sewn on the cloth of curtain face for 1.0 meters of spacing between woven belt, constitutes the casing of closed hoop structure, direct 5 centimetres of casing, sail Strap remains 30 centimetres of ribbons above the cloth of curtain face, and the reservation of curtain face cloth lower section is 60 centimetres wide not to sew casing;Drill rod is column Shape structure, diameter are 0.6 ~ 0.7 times of casing diameter, and quantity is identical as casing quantity, and drill rod length is that curtain cloth width adds 10 centimetres.
Further, the drill rod lower end surface is pyramidal structure.
Further, the drill rod is prism, any one in cylindrical structure, and drill rod diameter is casing diameter 0.6-0.7 times.
The utility model has the advantage that compared with traditional equipment and mounting process
1, installation is simple and speed is fast: under more people's performances, only needing a few minutes that can complete curtain installation.3-7 Everyone penetrates a drill rod to people, and erect-position buttresses drill rod, and in addition 1-3 people sets drill rod with hammer, then arranges 1-2 people along flat Ground shovels out one 30 centimeters wide 5-8 centimeters deep soil box at paving canvas.
2, can storage time it is short: after curtain is installed, shovel soil pressure face paving curtain just on the spot at once can be with water storage, this When quickly build after curtain again after earth bag in an opposite direction.
3, water blocking effect is good: screen sinking hooping is from when starting water blocking, cofferdam, that is, waterproof, and earth-bag cofferdam waits for that it is filled It needs to implement again when height to cover waterproof geotextiles, just completely waterproof at this time, water storage speed is relatively slow.
4, material utilization amount is few: comparing with earth bag hooping.The permeable geotextiles and pressure bleed being laid in hooping are identical, no longer Calculate comparison.Earth bag bearing height after curtain earth bag embankment curtain need to only fill the 2/3 of curtain height.Screen sinking embankment is disconnected Face, earth-bag cofferdam hooping section See Figure.Curtain embankment section M1=0.8 square metre, earth-bag cofferdam hooping section M2=2.16 are flat Square rice is about 2:5 with material ratio.
5, cleaning project amount is few
Cleaning project amount is corresponding with reclamation work amount later for dangerous situation, and screen sinking earth bag clearing amount is traditional earth-bag cofferdam hooping The 2/5 of clearing amount.
6, curtain can overlap use: when seepage from dykes section is longer, a curtain length is unsatisfactory in use, curtain can overlap It sets, to reach the length of speedily carrying out rescue work of needs.The drill rod of adjacent curtain end two, which sets spacing, to guarantee two no more than 0.5 meter It holds reserved canvas to be superimposed together no less than 0.5 meter, effectively blocks water.
7, curtain is reusable: it is faster for the dangerous situation exclusion time, it is reused after curtain is capable of washing;Drill rod is to making It is not had much affect with the time, it is reusable.
Detailed description of the invention
FIG. 1 is a schematic structural view of the utility model;
Fig. 2 is that the utility model builds construction process figure.
Specific embodiment
As shown in Fig. 1-2, including curtain face cloth 1, drill rod 2 and woven belt 3, wherein curtain face cloth length is 8-10 meters, wide Length is 0.17 ~ 0.24 than range;Woven belt 3 is several, arranges along 1 cloth axis direction of curtain face, between adjacent two woven belts 3 between It is sewn on curtain face cloth 1 away from 1.0 meters, constitutes the casing of closed hoop structure, direct 5 centimetres of casing, woven belt 3 is in curtain face 30 centimetres of ribbons are remained above cloth 1, are retained below curtain face cloth 1 and 60 centimetres wide are not sewed casing;Drill rod 2 is column structure, directly Diameter is 0.6-0.7 times of casing diameter, and quantity is identical as casing quantity, and 2 length of drill rod is that curtain cloth width adds 10 centimetres.
Wherein, 2 lower end surface of drill rod is pyramidal structure, and the drill rod 2 is prism, any one in cylindrical structure Kind, and 2 diameter of drill rod is 0.6-0.7 times of casing diameter.
The utility model leakage piping speedily carry out rescue work dykes and dams build structure when building the following steps are included:
The first step, preparation leakage piping dykes and dams of speedily carrying out rescue work build structure, according to the structure feature of dam leakage piping positions 4, Selection meets the quantity and distributing position using 1 length and width of curtain face cloth and drill rod 2 and woven belt 3 that need, then curtain Curtain face cloth 1 and woven belt 3 are attached positioning;
Second step contains leakproof, the structure feature of the dam leakage piping positions 4 determined first according to the first step, in dike Dam leaks on rear side of piping positions, and apart from dam leakage piping positions side surface at least 100 centimeters, each drill rod jack is entered curtain In the casing that curtain face cloth 1 and woven belt 3 are formed, and it is driven into foundation structure around dam leakage piping positions, embedded depth At least 60 centimetres, then ribbon above the cloth of curtain face is bound to 5-8 centimetres of 2 top of drill rod position, by 1 lower section nothing of curtain face cloth Sleeve portion (60 centimeter length) is directly laid on the foundation surface at drill rod rear, and curtain face cloth is made to constitute cross section " L " shape Structure, tiling curtain face plant ground and dig out the groove that depth is 5-8 centimetres, width is 30 centimetres, and face cloth is laid on groove, so Earth bag is directly placed in afterwards on the curtain face cloth of tiling, and tamped, construction can be completed.
Wherein, curtain face cloth 1 surrounds circular arc at a distance of at least 100 centimetres of piping positions around dam leakage piping positions Shape.
In addition, curtain face cloth surrounds circular arc at a distance of at least 100 centimetres of piping positions around dam leakage piping positions Shape, and ground upper surface corresponding to the tiling of curtain face cloth sets depth as 5-8 centimetres of grooves 6, curtain face cloth 1 is embedded in groove 6 It is interior.
At the same time, in the second step, structure building in an opposite direction after earth bag 5 uses, and 5 height of earth bag is that curtain face cloth 1 is high The 3/2 of degree.
The utility model has the advantage that compared with traditional equipment and mounting process
1, installation is simple and speed is fast: under more people's performances, only needing a few minutes that can complete curtain installation.3-7 Everyone penetrates a drill rod to people, and erect-position buttresses drill rod, and in addition 2-3 people sets drill rod with hammer, then arranges 1-2 people along flat Ground shovels out one 30 centimeters wide 5-8 centimeters deep soil box at paving canvas.
2, can storage time it is short: after curtain is installed, shovel soil pressure face paving curtain just on the spot at once can be with water storage, this When quickly build after curtain again after earth bag in an opposite direction.
3, water blocking effect is good: screen sinking hooping is from when starting water blocking, cofferdam, that is, waterproof, and earth-bag cofferdam waits for that it is filled It needs to implement again when height to cover waterproof geotextiles, just completely waterproof at this time, water storage speed is relatively slow.
4, material utilization amount is few: comparing with earth bag hooping.The permeable geotextiles and pressure bleed being laid in hooping are identical, no longer Calculate comparison.Earth bag bearing height after curtain earth bag embankment curtain need to only fill the 2/3 of curtain height.Screen sinking embankment is disconnected Face, earth-bag cofferdam hooping section See Figure.Curtain embankment section M1=0.8 square metre, earth-bag cofferdam hooping section M2=2.16 are flat Square rice is about 2:5 with material ratio.
5, cleaning project amount is few
Cleaning project amount is corresponding with reclamation work amount later for dangerous situation, and screen sinking earth bag clearing amount is traditional earth-bag cofferdam hooping The 2/5 of clearing amount.
6, curtain can overlap use: when seepage from dykes section is longer, a curtain length is unsatisfactory in use, curtain can overlap It sets, to reach the length of speedily carrying out rescue work of needs.The drill rod of adjacent curtain end two, which sets spacing, to guarantee two no more than 0.5 meter It holds reserved canvas to be superimposed together no less than 0.5 meter, effectively blocks water.
7, curtain is reusable: it is faster for the dangerous situation exclusion time, it is reused after curtain is capable of washing;Drill rod is to making It is not had much affect with the time, it is reusable.The basic principles and main features of the utility model have been shown and described above And the advantages of the utility model.It should be understood by those skilled in the art that the present utility model is not limited to the above embodiments, on It states and only illustrates the principles of the present invention described in embodiment and specification, do not departing from the spirit and scope of the utility model Under the premise of, the utility model also has various changes and improvements, these changes and improvements both fall within claimed it is practical In novel range.The protection scope of the present invention is defined by the appended claims and their equivalents.

Claims (4)

1. a kind of leakage piping is speedily carried out rescue work, dykes and dams build structure, it is characterised in that: leakage piping dykes and dams of speedily carrying out rescue work build structure Including curtain face cloth, drill rod and woven belt, wherein curtain face cloth length is 8-10 meter, breadth length ratio range for 0.175 ~ 0.225;The woven belt is several, arranges along curtain face cloth axis direction, and 1.0 meter ampere of spacing is attached between adjacent two woven belts On the cloth of curtain face, the casing of closed hoop structure is constituted, direct 5 centimetres of casing, woven belt remains 30 lis above the cloth of curtain face Rice ribbon, the reservation of curtain face cloth lower section is 60 centimetres wide not to sew casing;The drill rod is column structure, and diameter is casing diameter 0.6 ~ 0.7 times, quantity is identical as casing quantity, and drill rod length is that curtain cloth width adds 10 centimetres.
2. a kind of leakage piping according to claim 1 is speedily carried out rescue work, dykes and dams build structure, it is characterised in that: curtain face cloth both ends Respectively retain 50 centimetres of face cloth and 7 casings are installed in outside of sleeve, i.e. 8 meters of long curtain face cloth.
3. a kind of leakage piping according to claim 1 is speedily carried out rescue work, dykes and dams build structure, it is characterised in that: the drill rod lower end Face is pyramidal structure.
4. a kind of leakage piping according to claim 1 is speedily carried out rescue work, dykes and dams build structure, it is characterised in that: the drill rod is rib Any one in column, cylindrical structure, and drill rod diameter is 0.6-0.7 times of casing diameter.
CN201920036417.1U 2019-01-09 2019-01-09 A kind of leakage piping dykes and dams of speedily carrying out rescue work build structure Active CN209669794U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920036417.1U CN209669794U (en) 2019-01-09 2019-01-09 A kind of leakage piping dykes and dams of speedily carrying out rescue work build structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920036417.1U CN209669794U (en) 2019-01-09 2019-01-09 A kind of leakage piping dykes and dams of speedily carrying out rescue work build structure

Publications (1)

Publication Number Publication Date
CN209669794U true CN209669794U (en) 2019-11-22

Family

ID=68565185

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920036417.1U Active CN209669794U (en) 2019-01-09 2019-01-09 A kind of leakage piping dykes and dams of speedily carrying out rescue work build structure

Country Status (1)

Country Link
CN (1) CN209669794U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109469005A (en) * 2019-01-09 2019-03-15 江苏省水利工程科技咨询股份有限公司 A kind of leakage piping dykes and dams of speedily carrying out rescue work build structure and application method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109469005A (en) * 2019-01-09 2019-03-15 江苏省水利工程科技咨询股份有限公司 A kind of leakage piping dykes and dams of speedily carrying out rescue work build structure and application method

Similar Documents

Publication Publication Date Title
CN107859145A (en) A kind of drainpipe is plugged into construction method under water
CN106284081B (en) A kind of blast cofferdam is as cast-in-place box beam bracket foundation construction method
CN203668885U (en) Novel hydraulic reclamation mould bag
CN112681350A (en) River cofferdam diversion construction method
CN109024458A (en) A kind of coal mine subsidence land landscape revetment and the construction method of water-bed antiseepage
CN104947680A (en) Method for overwater bearing platform foundation pit excavation construction of quick sand stratum
CN209669794U (en) A kind of leakage piping dykes and dams of speedily carrying out rescue work build structure
CN107761668B (en) Coastal shore reservoir land-building type revetment structure and construction method thereof
CN109083100B (en) River channel excavation construction process after mud blowing and landing
CN114855846A (en) Underground seepage-proofing pressure-reducing anti-floating blind pipe structure and construction method thereof
CN102493810B (en) Grouting construction process of pipeline inclined shaft engineering
CN104612128A (en) Vacuum preloading reinforcement construction method applicable to underwater silt environment
CN210482339U (en) Embankment side slope protection system
CN111778922A (en) Construction method of river basin flood control dam
CN201580547U (en) Pontoon applicable to excavation operation on water surface
CN109469005A (en) A kind of leakage piping dykes and dams of speedily carrying out rescue work build structure and application method
CN113123358B (en) Ship pool deformation prevention and control structure under action of uneven settlement of coal mining and construction method
CN103422467A (en) Method for damming by mucky soil filling bags
CN103938581B (en) Batch production manufactures the method for dykes and dams component and fast construction dykes and dams
CN113863335A (en) Method for treating quicksand stratum drainage channel slope collapse and purifying and recycling drainage water
CN107130644A (en) Coffering composite geo-membrane and gravelly clay combination against seepage construction method
CN205188909U (en) Lake prevention of seepage spacer body
Liu et al. Research on Deformation Characteristics of New Type of Cofferdams Structure
Al Siaede A Practical Geotechnical Analysis of in situ Stress Variations and Hydraulic Stability of Small Weirs Using SEEP/W and SIGMA/W Simulation
CN218643098U (en) Mountain area is filled out and is dug interface connection structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant