CN209624731U - One or two fusion panel switches integration transmission agency detection systems - Google Patents

One or two fusion panel switches integration transmission agency detection systems Download PDF

Info

Publication number
CN209624731U
CN209624731U CN201822243779.6U CN201822243779U CN209624731U CN 209624731 U CN209624731 U CN 209624731U CN 201822243779 U CN201822243779 U CN 201822243779U CN 209624731 U CN209624731 U CN 209624731U
Authority
CN
China
Prior art keywords
cut
circuit
breaker
panel switches
simulation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201822243779.6U
Other languages
Chinese (zh)
Inventor
徐铭铭
马建伟
贺翔
袁晓东
程显
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhengzhou University
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Henan Electric Power Co Ltd
Original Assignee
Zhengzhou University
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Henan Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhengzhou University, State Grid Corp of China SGCC, Electric Power Research Institute of State Grid Henan Electric Power Co Ltd filed Critical Zhengzhou University
Priority to CN201822243779.6U priority Critical patent/CN209624731U/en
Application granted granted Critical
Publication of CN209624731U publication Critical patent/CN209624731U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

The utility model discloses one or two fusion panel switches integration transmission agency detection systems, monitoring host computer, control circuit including sequential connection, simulation cut-off circuit and one or two fusion devices, can cut-off, be remotely controlled, remote signalling, telemetry function test to distribution switchgear progress capacity after one or two fusions.Control circuit cut-offs circuit with simulation and is connected, and controls simulation by cut-offfing for control divide-shut brake breaker and cut-offs the generation of high current and high voltage in circuit.The system is cut-off by the cooperation completion capacity of one or two fusion breakers and synthesis loop and three distant functional tests are tested, the control of breaker is issued by monitoring host computer, fusion device receives and executes to form linkage, and distribution power automation terminal detection circuit-breaker status simultaneously returns to monitoring host computer composition closed loop.It carries out capacity by the system to cut-off and three distant Function detections, it can be determined that the complete machine operational reliability and stability of one or two fusion panel switches.

Description

One or two fusion panel switches integration transmission agency detection systems
Technical field
The utility model relates to technical field of electricity more particularly to one or two fusion panel switches integration transmission agency inspections Examining system.
Background technique
All the time, one secondary device of panel switches is to separate design, processing and manufacture, this mode to not only result in It needs to carry out a large amount of Interface Matchings after the assembling of one secondary device and wiring works, and many functions are not due to carrying out integrated design The case where cannot achieve, or even interfering with each other greatly reduces panel switches reliability and operation stability.
Mainstream panel switches testing agency, the country only has at present carries out independently for single primary equipment or secondary device The ability of test, institute's inspection project can not embody the complete machine operational reliability and stability of one or two fusion panel switches, it is seen that Panel switches one or two times fusion integrated technologies are the developing direction of panel switches detection technique.
Summary of the invention
For overcome the deficiencies in the prior art, the purpose of this utility model is to provide one or two fusion panel switches one Change transmission agency detection system, it is intended to solve the prior art and only have for single primary equipment or the independent survey of secondary device progress The problem of ability of examination, institute's inspection project can not embody the complete machine operational reliability and stability of one or two fusion panel switches.
The purpose of this utility model is implemented with the following technical solutions:
A kind of one or two fusion panel switches integration transmission agency detection systems, the monitoring host computer including sequential connection (1), circuit (3) and one or two fusion devices are cut-off in control circuit (2), simulation.
On the basis of the above embodiments, it is preferred that one or two fusion devices include that breaker (4), distribution are automatic Change terminal (5), electromagnetic current transducer (6), electronic current sensor (7), electromagnetic potential transformer, electronic voltage sensing Device (8), high-voltage probe (9), signal transmission and one of conversion equipment (10) or a variety of.
On the basis of the above embodiments, it is preferred that control circuit (2) cut-offs circuit by breaker (4) control simulation (3) generation of high current and high voltage in.
On the basis of the above embodiments, it is preferred that control circuit (2) is also connect with signal converting transmission device (10), Control circuit (2) sends synchronization signal to one or two fusion devices by signal converting transmission device (10), while will monitor Information data transmission to monitoring host computer (1).
On the basis of the above embodiments, it is preferred that the current state of breaker (4) is also passed through letter by control circuit (2) Number converting transmission device (10) is transferred to monitoring host computer (1).
On the basis of above-mentioned any embodiment, it is preferred that distribution power automation terminal (5) is also transmitted and converted by signal Device (10) is connected to monitoring host computer (1).
On the basis of the above embodiments, it is preferred that high-voltage probe (9), electronic current sensor (7) are respectively used to acquire Voltage signal, current signal in capacity breaking test, and compared with the communication data of distribution power automation terminal (5).
On the basis of above-mentioned any embodiment, it is preferred that the input module switch of the control circuit (2) uses photoelectricity Isolation technology is designed, and external circuit and control circuit (2) is made to carry out electrical isolation by optocoupler.
On the basis of above-mentioned any embodiment, it is preferred that simulation cut-off circuit (3) for build capacity cut-off with it is three distant Function test platform;
The true interrupting process of breaker in circuit (3) simulating grid is cut-off in the simulation, and one or two fusions are set It is standby to be connected in test loop.
On the basis of the above embodiments, it is preferred that it is described simulation cut-off circuit (3) include CCB combined floodgate breaker (11), ACB auxiliary circuit breaker (12), R0 frequency modulation resistance (13), C0 frequency modulation capacitor (14), Rogows ki coil (15), RVDT resistance point Depressor (16), RCVDT RC divider (17);
Wherein, CCB combined floodgate breaker (11), ACB auxiliary circuit breaker (12), R0 frequency modulation resistance (13), C0 frequency modulation capacitor (14), Rogows ki coil (15), RVDT resitstance voltage divider (16) are linked in sequence;C0 frequency modulation capacitor (14) also with RCVDT capacitance-resistance Divider (17) connection;
RVDT resitstance voltage divider (16) participates in composition current source, and current source is for generating high current;RCVDT RC divider (17) composition voltage source is participated in, voltage source is for generating high voltage;Rogows ki coil is for measuring major loop drop-out current.
Compared with prior art, the utility model has the beneficial effects that:
The utility model discloses one or two fusion panel switches integration transmission agency detection systems, set for one or two times The standby fused transmission agency detection of panel switches can carry out capacity to distribution switchgear after one or two fusions and cut-off, be distant Control, remote signalling, telemetry function test.
Detectable three distant function (i.e. remote control, remote signalling, telemetry function) of the system includes: (1) remote control division brake test; (2) remote control operation record check;(3) remote signalling of divide-shut brake location status is tested;(4) power supply status remote signalling is tested;(5) energy storage state Remote signalling test;(6) telemetering three-phase current, zero-sequence current, line voltage, residual voltage, active power, reactive power.
Control circuit in the system is cut-off circuit with simulation and is connect, and cut-offs circuit by the simulation of divide-shut brake breaker control The generation of middle high current and high voltage, control circuit, which is that one or two fusion device transmissions are synchronous with signal converting transmission device, to be believed Number, while by the information data monitored and breaker current state, it is transferred to monitoring host computer.The switch of control circuit inputs mould Block can carry out innovative design using photoelectric isolation technology, make external circuit and control loop by optocoupler progress electrically every From, avoid external circuit electromagnetic interference introduce controller, improve control reliability.
It includes current source and voltage source that simulation, which cut-offs circuit mainly, and the two is respectively used to generate high current and high voltage.In Simulation is cut-off in circuit, and R0, C0 adjust the amplitude and frequency of transient recovery voltage TRV jointly.The both ends A, B in circuit are cut-off in simulation It is connected to breaker, before breaker actuation, investment current source generates power current, the practical electricity of the route for mimic-disconnecting switch Stream, cut-offs about 0.5ms before zero passage, and investment voltage source generates TRV and is applied to fracture both ends, route when analog switch cabinet cuts off electric current The TRV of generation, test process meet circuit-breaker synthesizing test equivalence principle.
The utility model is cut-off circuit and built capacity and cut-off by simulation cut-offs circuit with three distant function test platforms, simulation For the true interrupting process of breaker in simulating grid, one or two fusion devices are connected in test loop, distribution is automatic Change terminal and monitoring host computer is connected to by signal transmission and conversion equipment, control circuit cut-offs circuit and to one for controlling simulation Secondary fusion device sends synchronization signal, and the high-voltage probe, electronic current sensor in hookup are cut-off for acquiring capacity Voltage, current signal in test, and the communication data of the distribution power automation terminal carried with breaker compares.
The utility model by the cooperation completion capacity that one or two fusion breakers and simulation cut-off circuit cut-off with it is three distant Functional test test, the control of breaker are issued by monitoring host computer, and fusion device receives and executes to form transmission, power distribution automation Terminal detection circuit-breaker status simultaneously returns to monitoring host computer composition closed loop, ensure that control reliability and convenience.The system can be with System test is carried out to one or two fused power distribution network switchgears, circuit progress capacity is cut-off by high-potting simulation and is opened Disconnected and three distant Function detections, judge the complete machine operational reliability and stability of one or two fusion panel switches according to testing result.
Detailed description of the invention
The present invention will be further described with reference to the accompanying drawings and examples.
Fig. 1 shows a kind of one or two fusions panel switches integration transmission agency inspection provided by the embodiment of the utility model The structural schematic diagram of examining system;
Fig. 2 shows a kind of simulate provided by the embodiment of the utility model to cut-off the circuit diagram in circuit.
In figure, 1, monitoring host computer;2, control circuit;Circuit 3 is cut-off in simulation;4, breaker;5, distribution power automation terminal;6, Electromagnetic current transducer;7, electronic current sensor;8, electronic voltage sensor;9, high-voltage probe;10, signal transmits and turns Changing device;11, CCB combined floodgate breaker;12, ACB auxiliary circuit breaker;13, R0 frequency modulation resistance;14, C0 frequency modulation capacitor;15, Rogows ki coil;16, RVDT resitstance voltage divider;17, RCVDT RC divider.
Specific embodiment
In the following, being described further in conjunction with attached drawing and specific embodiment to the utility model, it should be noted that Under the premise of not colliding, it can be formed in any combination between various embodiments described below or between each technical characteristic new Embodiment.
As shown in Figure 1, the utility model embodiment provides a kind of one or two fusion panel switches integration transmission agencies Detection system, monitoring host computer 1, control circuit 2, simulation including sequential connection cut-off circuit 3 and one or two time fusion device.
Preferably, one or two fusion devices may include that breaker 4, distribution power automation terminal 5, electromagnetic type electric current are mutual Sensor 6, electronic current sensor 7, electromagnetic potential transformer, electronic voltage sensor 8, high-voltage probe 9, signal transmit and turn One of changing device 10 is a variety of.The advantage of doing so is that one two fusions of the utility model embodiment to can be detected Equipment without limitation, is widely used, and practicability is high.
Preferably, control circuit 2 cut-offs the generation of high current and high voltage in circuit 3 by the control simulation of breaker 4.
Preferably, control circuit 2 is also connect with signal converting transmission device 10, and control circuit 2 passes through signal converting transmission Device 10 sends synchronization signals to one or two fusion devices, while by the information data transmission monitored to monitoring host computer 1.In this way The benefit done is to realize the communication between control circuit 2 and one or two time fusion device, monitoring host computer 1.
Preferably, the current state of breaker 4 is also transferred to monitoring by signal converting transmission device 10 by control circuit 2 Host 1.
Preferably, distribution power automation terminal 5 is also connected to monitoring host computer 1 with conversion equipment 10 by signal transmission.In this way The benefit done is to realize the communication between distribution power automation terminal 5 and monitoring host computer 1.
Preferably, high-voltage probe 9, electronic current sensor 7 be respectively used to acquisition capacity breaking test in voltage signal, Current signal, and compared with the communication data of distribution power automation terminal 5.The advantage of doing so is that one or two fusions can be set The signal of standby acquisition and the communication data of distribution power automation terminal 5 compare.
Preferably, the input module switch of the control circuit 2 is designed using photoelectric isolation technology, makes external circuit Electrical isolation is carried out by optocoupler with control circuit 2.The advantage of doing so is that avoiding the electromagnetic interference of external circuit introducing control Device improves the reliability of control.
Preferably, simulation is cut-off circuit 3 and is cut-off and three distant function test platforms for building capacity;The simulation is cut-off back One or two fusion devices are connected in test loop by the true interrupting process of breaker in 3 simulating grid of road.
As shown in Figure 2, it is preferred that it may include CCB combined floodgate breaker 11, ACB backup shutdoun that circuit 3 is cut-off in the simulation Device 12, R0 frequency modulation resistance 13, C0 frequency modulation capacitor 14, Rogows ki coil 15, RVDT resitstance voltage divider 16, RCVDT resistive-capacitive voltage divider Device 17;Wherein, CCB combined floodgate breaker 11, ACB auxiliary circuit breaker 12, R0 frequency modulation resistance 13, C0 frequency modulation capacitor 14, Rogows ki Coil 15, RVDT resitstance voltage divider 16 are linked in sequence;C0 frequency modulation capacitor 14 is also connect with RCVDT RC divider 17;
RVDT resitstance voltage divider 16 participates in composition current source, and current source is for generating high current;RCVDT RC divider 17 Composition voltage source is participated in, voltage source is for generating high voltage;Rogows ki coil is for measuring major loop drop-out current.
The utility model embodiment can be used for the fused transmission agency detection of a secondary device panel switches, can be right One or two times fusion after distribution switchgear carry out capacity cut-off, be remotely controlled, remote signalling, telemetry function test.
Detectable three distant function (i.e. remote control, remote signalling, telemetry function) of the system includes: (1) remote control division brake test; (2) remote control operation record check;(3) remote signalling of divide-shut brake location status is tested;(4) power supply status remote signalling is tested;(5) energy storage state Remote signalling test;(6) telemetering three-phase current, zero-sequence current, line voltage, residual voltage, active power, reactive power.
Control circuit in the system is cut-off circuit with simulation and is connect, and cut-offs circuit by the simulation of divide-shut brake breaker control The generation of middle high current and high voltage, control circuit, which is that one or two fusion device transmissions are synchronous with signal converting transmission device, to be believed Number, while by the information data monitored and breaker current state, it is transferred to monitoring host computer.The switch of control circuit inputs mould Block can carry out innovative design using photoelectric isolation technology, make external circuit and control loop by optocoupler progress electrically every From, avoid external circuit electromagnetic interference introduce controller, improve control reliability.
It includes current source and voltage source that simulation, which cut-offs circuit mainly, and the two is respectively used to generate high current and high voltage.In Simulation is cut-off in circuit, and R0, C0 adjust the amplitude and frequency of transient recovery voltage TRV jointly.The both ends A, B in circuit are cut-off in simulation It is connected to breaker, before breaker actuation, investment current source generates power current, the practical electricity of the route for mimic-disconnecting switch Stream, cut-offs about 0.5ms before zero passage, and investment voltage source generates TRV and is applied to fracture both ends, route when analog switch cabinet cuts off electric current The TRV of generation, test process meet circuit-breaker synthesizing test equivalence principle.
The utility model embodiment by simulation cut-offs circuit and builds capacity and cut-off to be opened with three distant function test platforms, simulation One or two fusion devices are connected in test loop, match for the true interrupting process of breaker in simulating grid by disconnected circuit Electric automation terminal is connected to monitoring host computer by signal transmission and conversion equipment, and control circuit cut-offs circuit for controlling simulation And synchronization signal is sent to one or two fusion devices, the high-voltage probe, electronic current sensor in hookup hold for acquiring Voltage, the current signal in breaking test are measured, and the communication data of the distribution power automation terminal carried with breaker compares.
The utility model embodiment is completed capacity by the cooperation that one or two fusion breakers cut-off circuit with simulation and is cut-off With three distant functional test tests, the control of breaker is issued by monitoring host computer, and fusion device receives and executes to form transmission, distribution Automatization terminal detection circuit-breaker status simultaneously returns to monitoring host computer composition closed loop, ensure that control reliability and convenience.This is System can carry out system test to one or two fused power distribution network switchgears, cut-off circuit by high-potting simulation and carry out Capacity cut-off with three distant Function detections, judge the complete machine operational reliability of one or two fusion panel switches and steady according to testing result It is qualitative.
The application scenarios of the utility model embodiment may is that
When carrying out transmission agency detection, experimental rig is connected according to Fig. 1, by one or two accurate companies of fusion device It is connected in hookup, removes earth brace, carry out unloaded transmission breaking test, rated capacity breaking test, capacity of short circuit respectively Breaking test, simulation, which cut-offs circuit 3 and one or two time and merges the breaker that tie in could complete under actual condition, cut-offs examination It tests, records the collected data of distribution power automation terminal 5 after the completion of cut-offfing.
When carrying out unloaded transmission breaking test, synchronous divide-shut brake letter is sent to one or two fusion devices by control circuit 2 Number, distribution power automation terminal 5 passes through the divide-shut brake that control operating mechanism controls breaker 4, distribution after receiving divide-shut brake signal Automatization terminal 5 can acquire the information such as 4 current state of breaker and voltage and current value and pass through signal transmission and conversion equipment 10 It is transferred to monitoring host computer 1.
When carrying out rated capacity breaking test, 3 Fig. 1 capacitor of circuit is cut-off by 2 pairs of control circuit simulations and is charged, root The capacitance voltage that current source is determined according to drop-out current determines the voltage of voltage source capacitor according to the voltage rating of switch.
The triggering key for pressing control circuit 2 cut-offs the simulation of circuit 3 by signal transmission through fiber control simulation and actually opens It is disconnected, and synchronization signal is sent simultaneously to one or two fusion devices, row control, the mesh of synchronization signal are put by the way that distant control function is split Be one or two fusions switch cut-off at the time of suitable, interrupting process neutralization cut-off after the completion of one or two fusion devices It answers working properly.
It checks that breaker 4 cut-offs state by distribution power automation terminal 5, is checked at monitoring host computer end 1 by remote signaling function Voltage and current value when 4 state of breaker and breaker 4 act.
In conclusion the system is cut-off circuit 3 and is cooperated by monitoring host computer 1, control circuit 2, simulation, it can be to one The capacity of distribution switchgear cut-offs and is remotely controlled after secondary fusion, remote signalling, telemetry function are tested, to judge to melt for one or two times Close panel switches complete machine operational reliability and stability.
The system can use the P6139B probe acquisition current divider voltage signal that bandwidth is 500MHz, dry to weaken radio frequency The influence of signal and stray parasitic signal to measurement circuit is disturbed, improves the accuracy of measurement result, all acquisition signals pass through Fiber isolation sampling system enters DPO4054 four-way 500MHz bandwidth digital oscillograph.
The utility model is from using in purpose, and in efficiency, the viewpoints such as progressive and novelty are illustrated, and what is had is practical Progressive, oneself meets the function that Patent Law emphasized and promotes and using important document, more than the utility model explanation and attached drawing, only The preferred embodiment of the utility model and oneself, the utility model is not limited to this, therefore, it is all with the utility model structure It makes, device, it is wait the approximations, identical such as levy, i.e., all according to equivalent replacement made by the utility model patent application range or modification etc., Within the scope of the patent application protection that the utility model should all be belonged to.
It should be noted that in the absence of conflict, the feature in the embodiments of the present invention and embodiment can To be combined with each other.Although the utility model has been carried out a degree of description, it will be apparent that, in the essence for not departing from the utility model Under conditions of mind and range, the appropriate variation of each condition can be carried out.It is appreciated that the utility model is not limited to the embodiment party Case, and it is attributed to the scope of the claims comprising the equivalent replacement of each factor.It will be apparent to those skilled in the art that Various other corresponding changes and deformation can be made according to the above description of the technical scheme and ideas, and all these Change and deformation all should belong within the protection scope of the utility model claims.

Claims (10)

1. a kind of one or two fusion panel switches integration transmission agency detection systems, which is characterized in that including sequential connection Circuit (3) and one or two fusion devices are cut-off in monitoring host computer (1), control circuit (2), simulation.
2. one or two fusions panel switches integration transmission agency detection system according to claim 1, which is characterized in that One or two fusion devices include breaker (4), distribution power automation terminal (5), electromagnetic current transducer (6), electronics electricity Flow sensor (7), electromagnetic potential transformer, electronic voltage sensor (8), high-voltage probe (9), signal transmission and conversion equipment One of (10) or it is a variety of.
3. one or two fusions panel switches integration transmission agency detection system according to claim 2, which is characterized in that Control circuit (2) cut-offs the generation of high current and high voltage in circuit (3) by breaker (4) control simulation.
4. one or two fusions panel switches integration transmission agency detection system according to claim 3, which is characterized in that Control circuit (2) is also transmitted with signal and is connect with conversion equipment (10), and control circuit (2) is transmitted by signal and conversion equipment (10) synchronization signals are sent to one or two fusion devices, while by the information data transmission monitored to monitoring host computer (1).
5. one or two fusions panel switches integration transmission agency detection system according to claim 4, which is characterized in that The current state of breaker (4) is also transferred to monitoring host computer with conversion equipment (10) by signal transmission by control circuit (2) (1)。
6. according to described in any item one or the two fusions panel switches integration transmission agency detection systems of claim 2-5, It is characterized in that, distribution power automation terminal (5) is also connected to monitoring host computer (1) with conversion equipment (10) by signal transmission.
7. one or two fusions panel switches integration transmission agency detection system according to claim 6, which is characterized in that High-voltage probe (9), electronic current sensor (7) are respectively used to voltage signal, current signal in acquisition capacity breaking test, and It is compared with the communication data of distribution power automation terminal (5).
8. one or two fusions panel switches integration transmission agency detection system according to claim 1, which is characterized in that The input module switch of the control circuit (2) is designed using photoelectric isolation technology, makes external circuit and control circuit (2) Electrical isolation is carried out by optocoupler.
9. one or two fusions panel switches integration transmission agency detection system according to claim 1, which is characterized in that Simulation is cut-off circuit (3) and is cut-off and three distant function test platforms for building capacity;
The true interrupting process of breaker in circuit (3) simulating grid is cut-off in the simulation, and one or two fusion devices are connected It is connected in test loop.
10. one or two fusions panel switches integration transmission agency detection system according to claim 9, feature exist In, it is described simulation cut-off circuit (3) include CCB combined floodgate breaker (11), ACB auxiliary circuit breaker (12), R0 frequency modulation resistance (13), C0 frequency modulation capacitor (14), Rogows ki coil (15), RVDT resitstance voltage divider (16), RCVDT RC divider (17);
Wherein, CCB combined floodgate breaker (11), ACB auxiliary circuit breaker (12), R0 frequency modulation resistance (13), C0 frequency modulation capacitor (14), Rogows ki coil (15), RVDT resitstance voltage divider (16) are linked in sequence;C0 frequency modulation capacitor (14) also with RCVDT resistive-capacitive voltage divider Device (17) connection;
RVDT resitstance voltage divider (16) participates in composition current source, and current source is for generating high current;RCVDT RC divider (17) Composition voltage source is participated in, voltage source is for generating high voltage;Rogows ki coil is for measuring major loop drop-out current.
CN201822243779.6U 2018-12-28 2018-12-28 One or two fusion panel switches integration transmission agency detection systems Active CN209624731U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201822243779.6U CN209624731U (en) 2018-12-28 2018-12-28 One or two fusion panel switches integration transmission agency detection systems

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201822243779.6U CN209624731U (en) 2018-12-28 2018-12-28 One or two fusion panel switches integration transmission agency detection systems

Publications (1)

Publication Number Publication Date
CN209624731U true CN209624731U (en) 2019-11-12

Family

ID=68447876

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201822243779.6U Active CN209624731U (en) 2018-12-28 2018-12-28 One or two fusion panel switches integration transmission agency detection systems

Country Status (1)

Country Link
CN (1) CN209624731U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112379252A (en) * 2020-11-03 2021-02-19 南方电网数字电网研究院有限公司 Primary and secondary fusion pole switch test system
WO2021147281A1 (en) * 2020-01-20 2021-07-29 中国电力科学研究院有限公司 Device and method for performing quantitative evaluation testing of power distribution switch
CN113759199A (en) * 2021-09-26 2021-12-07 淮安苏达电气有限公司 Testing device and testing method for primary and secondary fusion equipment acting on power distribution network
CN114184950A (en) * 2021-12-08 2022-03-15 国网四川省电力公司电力科学研究院 Voltage and current acquisition assembly based on distribution automation fusion switch
CN115327360A (en) * 2022-08-09 2022-11-11 北京南凯自动化系统工程有限公司 Intelligent testing method and system for direct control device of isolating switch of railway contact network

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2021147281A1 (en) * 2020-01-20 2021-07-29 中国电力科学研究院有限公司 Device and method for performing quantitative evaluation testing of power distribution switch
CN112379252A (en) * 2020-11-03 2021-02-19 南方电网数字电网研究院有限公司 Primary and secondary fusion pole switch test system
CN112379252B (en) * 2020-11-03 2021-07-06 南方电网数字电网研究院有限公司 Primary and secondary fusion pole switch test system
CN113759199A (en) * 2021-09-26 2021-12-07 淮安苏达电气有限公司 Testing device and testing method for primary and secondary fusion equipment acting on power distribution network
CN114184950A (en) * 2021-12-08 2022-03-15 国网四川省电力公司电力科学研究院 Voltage and current acquisition assembly based on distribution automation fusion switch
CN115327360A (en) * 2022-08-09 2022-11-11 北京南凯自动化系统工程有限公司 Intelligent testing method and system for direct control device of isolating switch of railway contact network
CN115327360B (en) * 2022-08-09 2024-06-07 北京南凯自动化系统工程有限公司 Intelligent testing method and system for direct control device of railway contact net isolating switch

Similar Documents

Publication Publication Date Title
CN209624731U (en) One or two fusion panel switches integration transmission agency detection systems
CN102510131B (en) Method and device for testing overall performance of intelligent transformer substation
CN102937685B (en) The integrated testing platform of a kind of transformer station based on Real-time Simulation Technology
CN202488214U (en) Intelligent substation simulation system
Kezunovic Smart fault location for smart grids
CN102072996B (en) System for realizing automatic digital protection and closed loop moving die test
CN104749466B (en) A kind of intelligent substation relay protection test system, method of testing and implementation method
CN102520288B (en) Primary-rising based current differential protection synchronization performance testing system and testing method
CN108982996B (en) Outdoor scene substitution type extra-high voltage direct current protection field testing device
CN103076520A (en) Dynamic analogue simulation detection platform and analogue simulation method for secondary system of intelligent substation
CN103713214A (en) Intelligent transformer station relay protection closed loop test system
CN203117313U (en) Dynamic simulation and emulation detecting platform for intelligent substation secondary system
CN102721882A (en) Intelligent and conventional transformer substation optical fiber longitudinal difference protection channel joint debugging test method
CN105548948A (en) Device and method for testing digitalization electric energy metering system
CN107741549A (en) The intelligent substation synchronism tester synchronously occurred based on analog quantity and digital quantity
CN102901891A (en) Flexible simulation test platform for electric power system transformer protection devices
CN108089081A (en) Multi-compartment emulation test system based on digital transformer substation field application
CN103840438A (en) Intelligent detecting system for detecting single phase grounding protection function of intelligent switch device based on 10kV neutral non-grounding distribution network system
CN109918725A (en) Integrated test method based on the modeling of emulation platform secondary device
CN104330677A (en) Device and method for testing electronic type current transformer
Knezev et al. Automated circuit breaker monitoring
CN103455678B (en) Quadratic Imaginary loop chart collaborative design method based on the empty terminal of standardization
CN113391145A (en) Test system of distribution automation feeder terminal
CN203164360U (en) Transformer device insulation online monitoring system
CN205263212U (en) Select testing arrangement that closes a floodgate mutually

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant