CN209603115U - A kind of loess high roadbed cheuch ground discharge structure - Google Patents

A kind of loess high roadbed cheuch ground discharge structure Download PDF

Info

Publication number
CN209603115U
CN209603115U CN201920154772.9U CN201920154772U CN209603115U CN 209603115 U CN209603115 U CN 209603115U CN 201920154772 U CN201920154772 U CN 201920154772U CN 209603115 U CN209603115 U CN 209603115U
Authority
CN
China
Prior art keywords
french drain
main
drain
rubble
layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920154772.9U
Other languages
Chinese (zh)
Inventor
曹杰
郑建国
张继文
刘智
唐国艺
陈冉升
李攀
张龙
乔建伟
周远强
王云南
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Co Ltd Of Mechanical Industry Prospective Design Academy
Chinese Mechanical Equipment Engineering Ltd By Share Ltd
Original Assignee
Co Ltd Of Mechanical Industry Prospective Design Academy
Chinese Mechanical Equipment Engineering Ltd By Share Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Co Ltd Of Mechanical Industry Prospective Design Academy, Chinese Mechanical Equipment Engineering Ltd By Share Ltd filed Critical Co Ltd Of Mechanical Industry Prospective Design Academy
Priority to CN201920154772.9U priority Critical patent/CN209603115U/en
Application granted granted Critical
Publication of CN209603115U publication Critical patent/CN209603115U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Revetment (AREA)

Abstract

The utility model discloses a kind of loess high roadbed cheuch ground discharge structures, including the main french drain that tap drain extending direction is laid on former loess foundation along original land in gully and the secondary french drain that Zhigou extending direction is laid on former loess foundation and is connected to main french drain along original land in gully, secondary french drain and the basal surface elevation at main french drain communicating position are equal with the basal surface elevation of main french drain at the position, secondary french drain and main french drain include the outer layer geotextile protective layer being successively laid with from outside to inside, interlayer particulate rubble filter protection layer, internal layer geotechnical fibre filter layer and kernel coarse grain drainage blanket, the cross sectional area of kernel coarse grain drainage blanket in secondary french drain is less than the cross sectional area of the kernel coarse grain drainage blanket in main french drain, the cross section of secondary french drain and the cross section of main french drain are full rubble section.The utility model stabilized structure, porosity are big, draining is unobstructed, silting blocking performance is strong, can effectively solve the original gully karness base drainage problem of existing loess high roadbed engineering.

Description

A kind of loess high roadbed cheuch ground discharge structure
Technical field
The utility model belongs to loess high roadbed cheuch ground technical field of drainage, and in particular to a kind of loess high roadbed ditch Valley floor base discharge structure.
Background technique
As economy rapid development in China's is quickly propelled with urbanization process, that construction land all occur in many areas is tight Open this situation.Under the premise of moderate solution, the embankments engineering such as " cut mountain and fill out ditch ", " control ditch and make ground " becomes China's land resources One of the important decision and developing direction of development and utilization and deposit protection.The area will be changed after loess high roadbed engineering filling construction The free drainage condition in domain, if earlier drainage system setting is unreasonable, the engineering later period easily causes level of ground water to rise, and jeopardizes Filling body stability.Especially " the water-sensitive characteristic " of loess so that entire loess high roadbed engineering to the variation of water environment extremely Sensitivity, not at that time, water level, which rises, easily to be caused slope instability, makes the sedimentation of ground large area etc. now for original gully karness base draining setting As to influence the quality safety and practicability of engineering.
There are two types of types for the essential structure of conventional weeper drain: one is the blind drainage structure that full rubble fills, this It is class structural form stable structure, solid, it is not easy to collapse, but setting was not easy to happen silting, failure at that time;Another kind is rubble packet The structure type for wrapping up in major diameter culvert pipe forms hollow weeper drain, although the short-term internal drainage of the structure is unobstructed, culvert pipe is mixed Solidifying soil and steel reinforcement cage easily corrode, get rusty, and upper cover may be under round culvert pipe, especially culvert pipe under high roadbed load action Semi-circular portions cause to cleave, collapse, destroy, and shorten french drain service life, collapse so that top be made to make ground formation.
Utility model content
The technical problem to be solved by the utility model is in view of the deficiency of the prior art, provide a kind of loess High roadbed cheuch ground discharge structure, it is novel in design reasonable, it is outer by being arranged on the outside of interlayer particulate rubble filter protection layer Layer geotextile protective layer has stress buffer, compatibility of deformation, coarse granule filtering triple role, by interlayer particulate rubble Internal layer geotechnical fibre filter layer is set on the inside of filter protection layer, and fine grained reverse filter effect guarantees that water quality is limpid, guarantees kernel coarse grain Drainage blanket by silting, not can effectively solve the original gully karness base drainage problem of existing loess high roadbed engineering, avoid the engineering later period Water level rising causes the excessive slaking deformation of engineering and sedimentation, the construction quality and safety of loess high roadbed engineering is effectively ensured, just In popularization and use.
In order to solve the above technical problems, the technical solution adopted in the utility model is: a kind of loess high roadbed cheuch ground Discharge structure, it is characterised in that: blind including tap drain extending direction is laid on former loess foundation along original land in gully master Ditch and the secondary french drain that Zhigou extending direction is laid on former loess foundation and is connected to main french drain along original land in gully, it is secondary blind Ditch and the basal surface elevation at main french drain communicating position are equal with the basal surface elevation of main french drain at the position, secondary french drain and master French drain includes the outer layer geotextile protective layer being successively laid with from outside to inside, interlayer particulate rubble filter protection layer, internal layer soil The cross sectional area of work fabric loaded filter and kernel coarse grain drainage blanket, the kernel coarse grain drainage blanket in secondary french drain is less than in main french drain Kernel coarse grain drainage blanket cross sectional area, the cross section of the cross section of secondary french drain and main french drain is full rubble section, institute It states full rubble section and is square full rubble section;The quantity of the secondary french drain is multiple.
A kind of above-mentioned loess high roadbed cheuch ground discharge structure, it is characterised in that: the outer layer geotextile protection Geotextile specification in layer and internal layer geotechnical fibre filter layer is not less than 300g/m2, outer layer geotextile protective layer and interior Geotextile tensile strength in layer geotechnical fibre filter layer is not less than 6kN/m, outer layer geotextile protective layer and internal layer soil Geotextile infiltration coefficient in work fabric loaded filter is 5 × 10-2Cm/s~5 × 10-1cm/s。
A kind of above-mentioned loess high roadbed cheuch ground discharge structure, it is characterised in that: the interlayer particulate rubble anti-filter The partial size of particulate rubble is less than 5cm in protective layer, and the partial size of coarse grain is 5cm~20cm in the kernel coarse grain drainage blanket, described The clay content of interlayer particulate rubble filter protection layer and the kernel coarse grain drainage blanket is no more than 5%.
Above-mentioned a kind of loess high roadbed cheuch ground discharge structure, it is characterised in that: the square of the main french drain is complete Rubble cross dimensions is not less than 2.5m × 2.5m, and the full rubble cross dimensions of the square of secondary french drain is not less than 1.5m × 1.5m.
Above-mentioned a kind of loess high roadbed cheuch ground discharge structure, it is characterised in that: the secondary french drain and main french drain The gradient is 3 °~45 °.
Above-mentioned a kind of loess high roadbed cheuch ground discharge structure, it is characterised in that: have in the original loess foundation Multiple steep basement rock, steep basement rock are located between adjacent two sections french drain segments or adjacent two sections of main french drain segments, and the steep basement rock is high Degree is not more than 2m, and the highly steep basement rock no more than 2m is trimmed to the slope base that height is not more than 2m by way of manual amendment Rock, the gradient of the slope basement rock are 30 °~45 °, and oblique main french drain segment or oblique french drain segment are laid on the slope basement rock On, adjacent two sections french drain segments pass through oblique main french drain segment by tiltedly time french drain segment connection, adjacent two sections of main french drain segments Connection.
A kind of above-mentioned loess high roadbed cheuch ground discharge structure, it is characterised in that: the steep basement rock height is greater than 2m, The secondary french drain segment or main french drain segment of steep basement rock two sides are spread between the straight french drain of transition and steep basement rock by transition straight french drain connection It is lined with rubble transition body, the partial size of the rubble in the rubble transition body is 10cm~30cm, and the rubble transition body contains mud Amount is not more than 5%, and the gradient of the straight french drain of transition is 40 °~45 °, the cross section of the cross-sectional configuration of the straight french drain of transition and time french drain The cross-sectional configuration of structure and main french drain is all the same.
A kind of above-mentioned loess high roadbed cheuch ground discharge structure, it is characterised in that: the edge of the original loess foundation Cheuch slopes have steep rock matter slopes, are provided with vertical drainage french drain on the steep rock matter slopes inner wall, vertical drainage is blind The size of ditch is not more than the size of time french drain, and the bottom of vertical drainage french drain is main by being connected at the top of main even french drain and main french drain Even the size of french drain is not more than the size of time french drain, and the gradient of main even french drain is 3 °~5 °.
A kind of above-mentioned loess high roadbed cheuch ground discharge structure, it is characterised in that: the top of the steep rock matter slopes Portion has time french drain, and the top of vertical drainage french drain connects french drain by time and is connected to time french drain, and the size of secondary even french drain is not more than The gradient of the size of secondary french drain, secondary even french drain is 3 °~5 °, the cross section of the cross-sectional configuration of vertical drainage french drain, main even french drain The cross-sectional configuration of structure and secondary even french drain is identical as the cross-sectional configuration of secondary french drain.
Compared with the prior art, the utility model has the following advantages:
1, the utility model is according to original water system situation, Combining with terrain concrete condition, not change or destroy original water system Condition be principle, protect original cheuch water system environment not to be destroyed, convenient for promote the use of.
2, the utility model on the outside of interlayer particulate rubble filter protection layer by being arranged outer layer geotextile protective layer, tool Standby stress buffer, compatibility of deformation, coarse granule filter triple role, in being arranged on the inside of interlayer particulate rubble filter protection layer Layer geotechnical fibre filter layer, fine grained reverse filter effect guarantee that water quality is limpid, guarantee that kernel coarse grain drainage blanket not by silting, passes through Kernel coarse grain drainage blanket specially undertakes drainage, and partial size is coarse, and porosity is high, drains unobstructed, reliable and stable, using effect It is good.
3, the utility model is full rubble section using time cross section of french drain and the cross section of main french drain, and full rubble is disconnected Face is square full rubble section, and construction technology is easy, and it is original to can effectively solve existing loess high roadbed engineering for strong operability Cheuch ground drainage problem avoids the rising of engineering later period water level from causing the excessive slaking deformation of engineering and sedimentation, loess is effectively ensured The construction quality and safety of high roadbed engineering.
In conclusion the utility model is novel in design rationally, by being arranged on the outside of interlayer particulate rubble filter protection layer Outer layer geotextile protective layer has stress buffer, compatibility of deformation, coarse granule filtering triple role, by broken in interlayer particulate Internal layer geotechnical fibre filter layer is set on the inside of stone filter protection layer, and fine grained reverse filter effect guarantees that water quality is limpid, guarantees that kernel is thick Grain drainage blanket can effectively solve the original gully karness base drainage problem of existing loess high roadbed engineering, after avoiding engineering not by silting The rising of phase water level causes the excessive slaking deformation of engineering and sedimentation, the construction quality of loess high roadbed engineering and complete is effectively ensured, just It is promoted the use of in during engineering practice.
Below by drawings and examples, the technical solution of the utility model is described in further detail.
Detailed description of the invention
Fig. 1 is the arrangement schematic diagram for the discharge structure that the utility model uses.
Fig. 2 is the main french drain of the utility model, secondary french drain, transition french drain, vertical drainage french drain, main even french drain and secondary even french drain Structure section schematic diagram.
Fig. 3 is the connectivity structure schematic diagram of the main french drain of the utility model and time french drain.
Fig. 4 is the connection relationship diagram of the straight french drain of the utility model transition and main french drain or secondary french drain.
Fig. 5 is the connection relationship diagram of the utility model vertical drainage french drain and main french drain and time french drain.
Description of symbols:
1-outer layer geotextile protective layer;2-interlayer particulate rubble filter protection layers;
3-internal layer geotechnical fibre filter layers;4-kernel coarse grain drainage blankets;
5-former loess foundations;6-steep basement rock;7-embankment soil layers;
8-rubble transition bodies;9-main french drains;10-secondary french drains;
The straight french drain of 11-transition;12-vertical drainage french drains;13-main even french drains;
14-secondary even french drains;15-steep rock matter slopes.
Specific embodiment
As shown in Figure 1 to Figure 3, a kind of loess high roadbed cheuch ground discharge structure described in the utility model, including edge Tap drain extending direction is laid on the main french drain 9 on former loess foundation 5 and the Zhigou along original land in gully in original land in gully The secondary french drain 10 that extending direction is laid on former loess foundation 5 and is connected to main french drain 9, secondary french drain 10 are connected to position with main french drain 9 The basal surface elevation for setting place is equal with the basal surface elevation of main french drain 9 at the position, secondary french drain 10 and main french drain 9 include by Outer outer layer geotextile protective layer 1, the interlayer particulate rubble filter protection layer 2, internal layer geotechnical fibre filter being successively laid in Layer 3 and kernel coarse grain drainage blanket 4, the cross sectional area of the kernel coarse grain drainage blanket 4 in secondary french drain 10 are less than interior in main french drain 9 The cross sectional area of core coarse grain drainage blanket 4, the cross section of secondary french drain 10 and the cross section of main french drain 9 are full rubble section, institute It states full rubble section and is square full rubble section;The quantity of the secondary french drain 10 is multiple.
It should be noted that tap drain extending direction is laid on the main french drain 9 on former loess foundation 5 along original land in gully With along original land in gully Zhigou extending direction be laid on former loess foundation 5 and the secondary french drain 10 that is connected to main french drain 9 Purpose, not change or destroy original water-based condition as principle, is protected according to original water system situation, Combining with terrain concrete condition Original cheuch water system environment has been protected not to be destroyed;Basal surface elevation and the position at secondary french drain 10 and main 9 communicating position of french drain The basal surface elevation of the main french drain 9 at place is equal, guarantees the stabilization that time french drain 10 is drained to main french drain 9, avoids different water level pressures Difference is interfered caused by main french drain 9, and secondary french drain 10 and main french drain 9 include that the outer layer geotextile being successively laid with from outside to inside is prevented Sheath 1, interlayer particulate rubble filter protection layer 2, internal layer geotechnical fibre filter layer 3 and kernel coarse grain drainage blanket 4, by interlayer Outer layer geotextile protective layer 1 is set on the outside of particulate rubble filter protection layer 2, has stress buffer, compatibility of deformation, coarse granule mistake Triple role is filtered, by the way that internal layer geotechnical fibre filter layer 3 is arranged on the inside of interlayer particulate rubble filter protection layer 2, fine grained is anti- Filter effect guarantees that water quality is limpid, guarantees that kernel coarse grain drainage blanket 4 not by silting, passes through the special row of undertaking of kernel coarse grain drainage blanket 4 Water effect, partial size is coarse, and porosity is high, and draining is unobstructed, reliable and stable;Kernel coarse grain drainage blanket 4 in secondary french drain 10 it is cross-section The purpose that face area is less than the cross sectional area of the kernel coarse grain drainage blanket 4 in main french drain 9 is to avoid the draining pair of time french drain 10 The impact of main french drain 9, the cross section of secondary french drain 10 and the cross section of main french drain 9 are full rubble section, the full rubble section It is square full rubble section, construction technology is easy, and strong operability can effectively solve existing loess high roadbed engineering primitive groove Valley floor base drainage problem avoids the rising of engineering later period water level from causing the excessive slaking deformation of engineering and sedimentation, loess height is effectively ensured The construction quality and safety of embankment engineering.
Geotextile rule in the present embodiment, in the outer layer geotextile protective layer 1 and internal layer geotechnical fibre filter layer 3 Lattice are not less than 300g/m2, the geotextile tension in outer layer geotextile protective layer 1 and internal layer geotechnical fibre filter layer 3 is strong Degree is not less than 6kN/m, the geotextile infiltration coefficient in outer layer geotextile protective layer 1 and internal layer geotechnical fibre filter layer 3 It is 5 × 10-2Cm/s~5 × 10-1cm/s。
In the present embodiment, the partial size of particulate rubble is less than 5cm in the interlayer particulate rubble filter protection layer 2, described interior The partial size of coarse grain is 5cm~20cm in core coarse grain drainage blanket 4, and the interlayer particulate rubble filter protection layer 2 and the kernel are thick The clay content of grain drainage blanket 4 is no more than 5%.
In the present embodiment, the full rubble cross dimensions of the square of the main french drain 9 is not less than 2.5m × 2.5m, secondary french drain 10 The full rubble cross dimensions of square be not less than 1.5m × 1.5m.
In the present embodiment, the gradient of the secondary french drain 10 and main french drain 9 is 3 °~45 °.
It should be noted that the gradient of secondary french drain 10 and main french drain 9 is configured according to actual terrain slope, secondary french drain 10 and main french drain 9 the gradient be 3 °~45 °, when actual terrain slope be greater than 45 ° when, adjusted by way of artificial correction to In 3 °~45 ° range of grade.
As shown in figure 4, there are multiple steep basement rock 6 in the original loess foundation 5, steep basement rock 6 is located at adjacent in the present embodiment Between two sections french drain segments or adjacent two sections of main french drain segments, steep 6 height of basement rock is not more than 2m, highly no more than 2m's Steep basement rock 6 is trimmed to the slope basement rock that height is not more than 2m by way of manual amendment, and the gradient of the slope basement rock is 30 ° ~45 °, oblique main french drain segment or oblique french drain segment are laid on the slope basement rock, and adjacent two sections french drain segments pass through oblique Secondary french drain segment connection, adjacent two sections of main french drain segments pass through tiltedly main french drain segment connection.
It is not more than it should be noted that steep basement rock 6 of the height no more than 2m is trimmed to height by way of manual amendment The slope basement rock of 2m in practice of construction, is cut brokenly steep basement rock 6 by the way of explosion.
In the present embodiment, steep 6 height of basement rock is greater than 2m, the secondary french drain segment or main french drain segment of steep 6 two sides of basement rock It is connected to by the straight french drain 11 of transition, place mat has rubble transition body 8, the rubble transition between the straight french drain 11 of transition and steep basement rock 6 The partial size of rubble in body 8 is 10cm~30cm, and the clay content of the rubble transition body 8 is not more than 5%, the straight french drain 11 of transition The gradient is 40 °~45 °, the cross-sectional configuration of the cross-sectional configuration of the straight french drain 11 of transition and secondary french drain 10 and main french drain 9 it is cross-section Face structure is all the same.
It should be noted that, according to the mode of explosion, the explosive charge for needing to consume is big when steep 6 height of basement rock is greater than 2m, There are security risks for construction, therefore, carry out support pad to steep basement rock 6 using rubble transition body 8, guarantee that main french drain or secondary french drain are laid with Steadily.
As shown in figure 5, the marginal ditch brae body of the original loess foundation 5 has steep rock matter slopes 15 in the present embodiment, Vertical drainage french drain 12 is provided on steep 15 inner wall of rock matter slopes, the size of vertical drainage french drain 12 is not more than time french drain 10 size, the bottom of vertical drainage french drain 12 at the top of main even french drain 13 and main french drain 9 by being connected to, the size of main even french drain 13 No more than the size of secondary french drain 10, the gradient of main even french drain 13 is 3 °~5 °.
In the present embodiment, the top of the steep rock matter slopes 15 has time french drain 10, the top of vertical drainage french drain 12 It is connected to by secondary even french drain 14 with time french drain 10, the size of secondary even french drain 14 is not more than the size of time french drain 10, secondary even french drain 14 The gradient be 3 °~5 °, the cross-sectional configuration of vertical drainage french drain 12, it is main even french drain 13 cross-sectional configuration and it is secondary even french drain 14 Cross-sectional configuration it is identical as the cross-sectional configuration of secondary french drain 10.
It should be noted that having steep rock matter slopes 15 in construction area, draining reinforcement solutions need to be carried out, are close to steep Vertical drainage french drain 12 is arranged in rock matter slopes 15, is connected to, is prevented by main even french drain 13 between vertical drainage french drain 12 and main french drain 9 Only the native rock interface of filling body and slopes forms the artificial lower bleed-through road of relative displacement and natural rain, avoids engineering later period water Position, which rises, causes the excessive slaking deformation of engineering and sedimentation, and the construction quality and safety of loess high roadbed engineering is effectively ensured.
The utility model construct when, with do not destroy primitive groove bottom water system and do not change it is original flow direction for basic principle, foundation Original land in gully, to 5 topsoil of loess foundation cleaning former in construction area;And to tap drain in original land in gully and branch bank Line carries out terrain prospecting, reconnoitres out in original land in gully and goes up steep basement rock present in former loess foundation 5 along tap drain and Zhigou 6;
It is control point with the steep basement rock 6 in former loess foundation 5 upper along tap drain in original land in gully, at 6 liang of steep basement rock Excavate main french drain groove in the former loess foundation 5 of side along tap drain along original land in gully;Be segmented in main french drain groove into Row is laid with outer layer geotextile protective layer 1, and the lap of splice between adjacent two sections of outer layer geotextiles protective layer 1 is not less than 30cm;The bottom that interlayer particulate rubble filter protection layer 2 is filled in outer layer geotextile protective layer 1, in interlayer particulate rubble Internal layer geotechnical fibre filter layer 3 is laid on the bottom of filter protection layer 2, between adjacent two sections of internal layer geotechnical fibre filters layer 3 The lap of splice is not less than 30cm, kernel coarse grain drainage blanket 4 is filled on internal layer geotechnical fibre filter layer 3, while in outer layer geotechnique The middle layer of interlayer particulate rubble filter protection layer 2 is filled between fabric protective layer 1 and internal layer geotechnical fibre filter layer 3;Outside multistage In layer geotextile protective layer 1 close to one section of steep basement rock 6 and its close to one end of steep basement rock 6 to be reserved with outer layer geotextile anti- Sheath segment, the length of the outer layer geotextile protective layer segment are not less than 30cm, in multistage internal layer geotechnical fibre filter layer 3 Close to one section of steep basement rock 6 and it close to one end of steep basement rock 6 is reserved with internal layer geotechnical fibre filter layer segment, the internal layer soil The length of work fabric loaded filter segment is not less than 30cm;
Kernel coarse grain drainage blanket 4 and interlayer particulate rubble filter protection layer 2 are filled to main french drain groove top surface, and turnup covers The lap width of lid internal layer geotechnical fibre filter layer 3, internal layer geotechnical fibre filter layer 3 is not less than 30cm;Then in internal layer geotechnique 3 top layer of fabric loaded filter is laid with the top layer of interlayer particulate rubble filter protection layer 2, and turnup covers outer layer geotextile protective layer 1, The lap width of outer layer geotextile protective layer 1 is not less than 30cm, forms one section of main french drain segment;The height of steep basement rock 6 is measured, When steep 6 height of basement rock is not more than 2m, steep basement rock 6 is trimmed to height by way of the steep basement rock 6 of explosion and is not more than the oblique of 2m Slope basement rock, the gradient of the slope basement rock are 30 °~45 °, are connected to two sections of steep 6 two sides of basement rock by one section of oblique main french drain segment Main french drain segment, oblique main french drain segment are laid on the slope basement rock, structure and the main french drain segment of oblique main french drain segment Structure is identical;When steep 6 height of basement rock is greater than 2m, the main french drain segment of steep 6 two sides of basement rock is connected to by the straight french drain 11 of transition, mistake Crossing place mat between straight french drain 11 and steep basement rock 6 has rubble transition body 8, and the partial size of the rubble in the rubble transition body 8 is 10cm ~30cm, the clay content of the rubble transition body 8 are not more than 5%, and the gradient of the straight french drain 11 of transition is 40 °~45 °, and transition is directly blind The cross-sectional configuration of ditch 11 is identical as the cross-sectional configuration of main french drain 9;
It is control point with the steep basement rock 6 in former loess foundation 5 upper along Zhigou in original land in gully, at 6 liang of steep basement rock Excavate time french drain groove in the former loess foundation 5 of side along Zhigou along original land in gully, secondary french drain 10 construct process with Main french drain 9 to construct process consistent;
Kernel coarse grain drainage blanket 4 in secondary french drain 10 is connected to the kernel coarse grain drainage blanket 4 in main french drain 9, secondary french drain The consistency of thickness of interlayer particulate rubble filter protection layer 2 in 10 and the interlayer particulate rubble filter protection layer 2 in main french drain 9 and It is interconnected, keeps the substrate of time french drain 10 with the basal surface elevation at main 9 communicating position of french drain and the main french drain 9 at the position Face elevation is equal;
Geological prospecting is carried out to the cheuch slopes in high roadbed construction area, whether there is steep rock in survey and construction region Matter slopes 15, when steep rock matter slopes 15 are not present in cheuch slopes, construction terminates;When there are steep rock matter in cheuch slopes When slopes 15, it is close to steep rock matter slopes 15 and vertical drainage french drain 12 is set, pass through between vertical drainage french drain 12 and main french drain 9 Main even french drain 13 is connected to, and the structure size of the main even french drain 13 is consistent with secondary french drain 10, the gradient of the main even french drain 13 It is 3 °~5 °;The laying of vertical drainage french drain 12 is synchronous with 7 filling construction of embankment soil layer, using embankment work surface as workbench, Guarantee that the french drain measuring height of section of vertical drainage french drain 12 is higher than the work surface 30cm or more that bankets, it is blind to the vertical drainage for being exposed to outer The french drain section broken stone of ditch 12 is protected, and the french drain section broken stone filler of Loess Filling incorporation vertical drainage french drain 12 is prevented In;
There is no when time french drain 10 at the top of steep rock matter slopes 15, vertical drainage french drain 12 along cheuch slopes construct to Embankment soil layer 7 bankets 20 meters of stoppings constructions below top surface;
When there is time french drain 10 at the top of steep rock matter slopes 15, vertical drainage french drain 12 by time even french drain 14 with it is steep The secondary french drain 10 at 15 top of rock matter slopes is connected, and the structure size of secondary even french drain 14 is consistent with secondary french drain 10, the secondary company The gradient of french drain 14 is 3 °~5 °;
When 15 regional scopes of steep rock matter slopes are wide, being close to steep rock matter slopes 15, that multiple tracks vertical drainage is arranged in parallel is blind The spacing of ditch 12, adjacent twice vertical drainage french drain 12 is 50m~100m, and main company is respectively set in multiple tracks vertical drainage french drain 12 French drain 13 is connected with main french drain 9.
The utility model clear thinking, design are reasonable, step is concise, strong operability, according to original land in gully, tap drain It is laid with main french drain, Zhigou is laid with time french drain, forms dendroid blind drainage system, and prominent for cheuch the lowest point regional area topography When change, artificial treatment and transition are carried out, guarantees the whole gradient of drain line, then carry out french drain laying, is rock in cheuch slopes It is special to prevent the native rock interface of filling body and slopes from forming artificially lower bleed-through road, setting vertical drainage french drain 12 when matter side slope Item pumping equipment, stabilized structure, porosity are big, draining is unobstructed, silting blocking performance is strong.
The above is only the preferred embodiment of the utility model, not imposes any restrictions to the utility model, all According to any simple modification to the above embodiments of the utility model technical spirit, change and equivalent structural changes, still Belong in the protection scope of technical solutions of the utility model.

Claims (9)

1. a kind of loess high roadbed cheuch ground discharge structure, it is characterised in that: including along original land in gully tap drain extend The main french drain (9) and Zhigou extending direction is laid on former Huang along original land in gully that direction is laid on former loess foundation (5) Base at the secondary french drain (10) being connected on soil base (5) and with main french drain (9), secondary french drain (10) and main french drain (9) communicating position Bottom surface elevation is equal with the basal surface elevation of main french drain (9) at the position, and secondary french drain (10) and main french drain (9) include by outer It is anti-to interior outer layer geotextile protective layer (1), interlayer particulate rubble filter protection layer (2), the internal layer geotextile being successively laid with The cross sectional area of filtering layer (3) and kernel coarse grain drainage blanket (4), the kernel coarse grain drainage blanket (4) in secondary french drain (10) is less than master The cross sectional area of kernel coarse grain drainage blanket (4) in french drain (9), the cross section of secondary french drain (10) and main french drain (9) it is cross-section Face is full rubble section, and the full rubble section is square full rubble section;The quantity of the secondary french drain (10) is multiple.
2. a kind of loess high roadbed cheuch ground discharge structure described in accordance with the claim 1, it is characterised in that: the outer layer soil Geotextile specification in work fabric protective layer (1) and internal layer geotechnical fibre filter layer (3) is not less than 300g/m2, outer layer soil Geotextile tensile strength in work fabric protective layer (1) and internal layer geotechnical fibre filter layer (3) is not less than 6kN/m, outer layer Geotextile infiltration coefficient in geotextile protective layer (1) and internal layer geotechnical fibre filter layer (3) is 5 × 10-2Cm/s~5 ×10-1cm/s。
3. a kind of loess high roadbed cheuch ground discharge structure described in accordance with the claim 1, it is characterised in that: the interlayer is thin The partial size of particulate rubble is less than 5cm in grain rubble filter protection layer (2), the partial size of coarse grain in the kernel coarse grain drainage blanket (4) For 5cm~20cm, the clay content of the interlayer particulate rubble filter protection layer (2) and the kernel coarse grain drainage blanket (4) is not Greater than 5%.
4. a kind of loess high roadbed cheuch ground discharge structure described in accordance with the claim 1, it is characterised in that: the main french drain (9) the full rubble cross dimensions of square is not less than 2.5m × 2.5m, and the full rubble cross dimensions of the square of secondary french drain (10) is not Less than 1.5m × 1.5m.
5. a kind of loess high roadbed cheuch ground discharge structure described in accordance with the claim 1, it is characterised in that: the secondary french drain (10) and the gradient of main french drain (9) is 3 °~45 °.
6. a kind of loess high roadbed cheuch ground discharge structure described in accordance with the claim 1, it is characterised in that: the original loess Regional area has steep basement rock (6) in ground (5), and steep basement rock (6) is located at adjacent two sections french drain segments or adjacent two sections of masters are blind Between ditch segment, the steep basement rock (6) is highly not more than 2m, is highly not more than the side that the steep basement rock (6) of 2m passes through manual amendment Formula is trimmed to the slope basement rock that height is not more than 2m, and the gradient of the slope basement rock is 30 °~45 °, oblique main french drain segment or oblique Secondary french drain segment is laid on the slope basement rock, and adjacent two sections french drain segments are connected to by tiltedly time french drain segment, and adjacent two The main french drain segment of section passes through tiltedly main french drain segment connection.
7. a kind of loess high roadbed cheuch ground discharge structure according to claim 6, it is characterised in that: the steep basement rock (6) highly it is greater than 2m, the secondary french drain segment or main french drain segment of steep basement rock (6) two sides are connected to by the straight french drain of transition (11), mistake Crossing place mat between straight french drain (11) and steep basement rock (6) has rubble transition body (8), the grain of the rubble in the rubble transition body (8) Diameter is 10cm~30cm, and the clay content of the rubble transition body (8) is not more than 5%, the gradient of the straight french drain of transition (11) is 40 °~ 45 °, the cross-sectional configuration of the straight french drain of transition (11) and time cross-sectional configuration of french drain (10) and the cross-sectional configuration of main french drain (9) It is all the same.
8. a kind of loess high roadbed cheuch ground discharge structure described in accordance with the claim 1, it is characterised in that: the original loess The marginal ditch brae body of ground (5) has steep rock matter slopes (15), is provided on steep rock matter slopes (15) inner wall perpendicular To weeper drain (12), the size of vertical drainage french drain (12) is not more than the size of time french drain (10), vertical drainage french drain (12) Bottom by be connected at the top of main even french drain (13) and main french drain (9), the size of main even french drain (13) is no more than secondary french drain (10) Size, it is main even french drain (13) the gradient be 3 °~5 °.
9. a kind of loess high roadbed cheuch ground discharge structure according to claim 8, it is characterised in that: the steep rock The top of matter slopes (15) has time french drain (10), and the top of vertical drainage french drain (12) passes through secondary even french drain (14) and time french drain (10) it being connected to, the size of secondary even french drain (14) is not more than the size of time french drain (10), and the gradient of secondary even french drain (14) is 3 °~5 °, The cross section knot of the cross-sectional configuration of vertical drainage french drain (12), the main even cross-sectional configuration of french drain (13) and secondary even french drain (14) Structure is identical as the cross-sectional configuration of secondary french drain (10).
CN201920154772.9U 2019-01-29 2019-01-29 A kind of loess high roadbed cheuch ground discharge structure Active CN209603115U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920154772.9U CN209603115U (en) 2019-01-29 2019-01-29 A kind of loess high roadbed cheuch ground discharge structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920154772.9U CN209603115U (en) 2019-01-29 2019-01-29 A kind of loess high roadbed cheuch ground discharge structure

Publications (1)

Publication Number Publication Date
CN209603115U true CN209603115U (en) 2019-11-08

Family

ID=68402619

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920154772.9U Active CN209603115U (en) 2019-01-29 2019-01-29 A kind of loess high roadbed cheuch ground discharge structure

Country Status (1)

Country Link
CN (1) CN209603115U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109610435A (en) * 2019-01-29 2019-04-12 中国机械设备工程股份有限公司 A kind of loess high roadbed cheuch ground discharge structure and its laying method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109610435A (en) * 2019-01-29 2019-04-12 中国机械设备工程股份有限公司 A kind of loess high roadbed cheuch ground discharge structure and its laying method
CN109610435B (en) * 2019-01-29 2023-09-12 中国机械设备工程股份有限公司 Loess high fill valley foundation drainage structure and laying method thereof

Similar Documents

Publication Publication Date Title
CN109610435A (en) A kind of loess high roadbed cheuch ground discharge structure and its laying method
CN103953008B (en) A kind of modified mixed dam being applicable to Tailings Dam
CN205152889U (en) Reservoir falling zone stable structure
CN110080166B (en) Geotextile bag dam reinforcing method
CN111691438A (en) Anti-skidding-drainage comprehensive treatment method for landslide of large-scale accumulation body
CN101914882B (en) Low embankment structure in phreatic high slity soil region and construction method thereof
CN109914445A (en) A kind of level of ground water alternately changes the construction method of location expensive soil cutting
CN112144584A (en) Self-flowing drainage pressure-limiting anti-floating structure and construction method
CN112746624A (en) Novel comprehensive water lowering and draining method and device for mudstone subway station
CN111139840A (en) Ecological restoration method for tableland slope of fixed ditch in gully region of loess plateau of longdong
CN111648383A (en) Internal drainage method for loess high-fill side slope
CN111119154A (en) River valley type debris flow ditch waste slag land-making structure and construction method
CN209603115U (en) A kind of loess high roadbed cheuch ground discharge structure
CN210482339U (en) Embankment side slope protection system
CN112195965A (en) Expansive soil cutting retaining wall
CN216275788U (en) Drainage device used after failure of water interception curtain of deep foundation pit
CN212428840U (en) Water-rich stratum underground tunnel floating control engineering remediation system
CN112523272B (en) Anti-floating blind ditch for strongly weathered rock stratum and construction method thereof
CN206034603U (en) Airport height fill construction three -dimensional drainage system
CN211523176U (en) River valley type debris flow ditch waste slag and land making structure
CN211228563U (en) Assembled groundwater drainage blind ditch drainage system that oozes
CN212405178U (en) Deep water falling hole processing structure of backfill foundation in large karst depression
CN211144529U (en) Rich water loess tunnel precipitation construction structures
CN209353360U (en) The anti-floating drainage arrangement of basement structure
CN208072453U (en) High-speed railway, highway pile foundation joist buttress type pallet subgrade support retainer structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant