CN209585591U - A kind of novel climbing frame scaffold board - Google Patents
A kind of novel climbing frame scaffold board Download PDFInfo
- Publication number
- CN209585591U CN209585591U CN201920249827.4U CN201920249827U CN209585591U CN 209585591 U CN209585591 U CN 209585591U CN 201920249827 U CN201920249827 U CN 201920249827U CN 209585591 U CN209585591 U CN 209585591U
- Authority
- CN
- China
- Prior art keywords
- secondary beam
- girder
- steel plate
- checkered steel
- scaffold board
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Joining Of Building Structures In Genera (AREA)
Abstract
A kind of novel climbing frame scaffold board of the utility model, including girder, secondary beam, checkered steel plate, girder are equipped with 2, and girder side is equipped with the secondary beam butt hole not less than 1, and the end of secondary beam is set in secondary beam butt hole;Girder is mutually fixed with secondary beam using self threading pin or bolt;Secondary beam, which is equipped with, is not less than 1, and is set between two girders;Checkered steel plate is layed in the top of 2 girders;Checkered steel plate is not less than 1, is layed in 2 girders and the secondary beam top between girder, and tiling is taken to be connected or be overlapped laying connection between every two panels checkered steel plate, the advantages of the utility model: checkered steel plate scaffold board Rimless, production is simple, and easy to transportation and installation, structure is overall beautiful;It can partly overlap, non-standard is low;It is at low cost, it is convenient for volume production.
Description
Technical field
The utility model relates to construction safety field more particularly to a kind of novel climbing frame scaffold boards.
Background technique
Common climbing frame scaffold board system, generallys use fashioned iron and is welded into frame, checkered steel plate, fashioned iron side are welded on face
Drilling interconnects.Above-mentioned scaffold board the disadvantage is that: component processing link is more, at high cost;Frame shaping specification is more, is unfavorable for standard
Change;It is big to stack volume, not readily transportable and storage.
Summary of the invention
To overcome above-mentioned deficiency, the utility model provides a kind of novel climbing frame scaffold board.
The technical scheme adopted by the utility model to solve the technical problem is as follows: a kind of novel climbing frame scaffold board, including master
Beam, secondary beam, checkered steel plate, it is characterized in that: the girder is equipped with 2;The secondary beam, which is equipped with, is not less than 1, and is set to
Between two girders;The checkered steel plate is layed in the bottom of 2 girders.
The girder side is equipped with the secondary beam butt hole not less than 1, and the end of secondary beam is set in secondary beam butt hole.
The girder is fixed with secondary beam using self threading pin or bolt.
The checkered steel plate is not less than 1, is layed in 2 girders and the secondary beam top between girder, every two panels decorative pattern
Tiling is taken to be connected or be overlapped laying connection between steel plate.
The advantages of the utility model: checkered steel plate scaffold board Rimless, production is simple, easy to transportation and installation, and structure is whole
It is beautiful;It can partly overlap, non-standard is low;It is at low cost, it is convenient for volume production.
Detailed description of the invention:
FIG. 1 is a schematic structural view of the utility model.
Fig. 2 is the utility model side schematic view.
Fig. 3 is the utility model schematic top plan view.
Fig. 4 is the utility model combination of two schematic diagram.
1. girder;2. secondary beam;3. checkered steel plate.
Specific embodiment:
The structural principle of the utility model is described further with reference to the accompanying drawing.
A kind of novel climbing frame scaffold board of the utility model as shown in Figure 1, Figure 2, Figure 3, Figure 4, including girder 1, secondary beam 2, flower
Line steel plate 3, girder 1 are equipped with 2, and 1 side of girder is equipped with 2 butt hole of secondary beam not less than 1, and the end of secondary beam 2 is set to secondary
In 2 butt hole of beam;Girder 1 is mutually fixed with secondary beam 2 using self threading pin or bolt;Secondary beam 2, which is equipped with, is not less than 1, and is set to two
Between root girder 1;Checkered steel plate 3 is layed in the bottom of 2 girders 1;Checkered steel plate 3 is not less than 1, is layed in 2 girders 1
And 2 top of secondary beam between girder 1, take between every two panels checkered steel plate 3 tiling to be connected or be overlapped laying connection.
Claims (4)
1. a kind of novel climbing frame scaffold board, including girder (1), secondary beam (2), checkered steel plate (3), it is characterized in that: the girder
(1) 2 are equipped with;The secondary beam (2), which is equipped with, is not less than 1, and is set between two girders (1);The checkered steel plate
(3) it is layed in the top of 2 girders (1).
2. a kind of novel climbing frame scaffold board according to claim 1, it is characterized in that: described girder (1) side is equipped with
The end of secondary beam (2) butt hole not less than 1, secondary beam (2) is set in secondary beam (2) butt hole.
3. a kind of novel climbing frame scaffold board according to claim 1 or 2, it is characterized in that: the girder (1) and secondary beam
(2) it is fixed using self threading pin or bolt.
4. a kind of novel climbing frame scaffold board according to claim 1, it is characterized in that: the checkered steel plate (3) is not less than 1
Piece is layed in 2 girders (1) and secondary beam (2) top between girder (1), and tiling pair is taken between every two panels checkered steel plate (3)
Connect or be overlapped in succession laying connection.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920249827.4U CN209585591U (en) | 2019-02-26 | 2019-02-26 | A kind of novel climbing frame scaffold board |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920249827.4U CN209585591U (en) | 2019-02-26 | 2019-02-26 | A kind of novel climbing frame scaffold board |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209585591U true CN209585591U (en) | 2019-11-05 |
Family
ID=68370748
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201920249827.4U Expired - Fee Related CN209585591U (en) | 2019-02-26 | 2019-02-26 | A kind of novel climbing frame scaffold board |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209585591U (en) |
-
2019
- 2019-02-26 CN CN201920249827.4U patent/CN209585591U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN203247859U (en) | Alignment device for butt joint perpendicularity of large steel columns | |
CN205393883U (en) | H shaped steel equipment fixture | |
CN209585591U (en) | A kind of novel climbing frame scaffold board | |
CN205077498U (en) | Steel sheet pile is strutted inside H shaped steel and is enclosed purlin combination layer board | |
CN203795589U (en) | Integrated house based on lightweight steel construction | |
CN206569938U (en) | Roofing crane rood beam underframe | |
CN204174785U (en) | The upper and lower syndeton of a kind of precast shear wall | |
CN203238951U (en) | Box girder steel pipe arc bracket | |
CN202706508U (en) | Overhanging strength bearing steel beam construction member of scaffold | |
CN104359539A (en) | Reinforced concrete double-T-beam weighing platform | |
CN204211397U (en) | Assembly type standard knot | |
CN210976326U (en) | Steel-wood roof truss lower chord node | |
CN209369185U (en) | Multidirectional reinforcing steel bar connecting device | |
CN204691216U (en) | Pylon is set up with scale rule and pylon | |
CN203320420U (en) | Temporary locking structure for corrugated steel webs of steel and concrete combined box girder | |
CN204738401U (en) | Assemble integral steel construction secondary beam and absolutely dry formula connection structure of concrete girder lateral part rigid connection | |
CN203699828U (en) | Simple tool-type lifting frame for mounting of steel reinforcement cages | |
CN209585589U (en) | A kind of climbing frame Dense mesh screen horse | |
CN203462651U (en) | Insertion directly-embedded type steel truss connecting structure | |
CN205134556U (en) | Improved connecting piece for steel -structure beam columns | |
CN204847839U (en) | From taking spacing hoist girder and connection structure of end beam | |
CN205369599U (en) | Horizontal bed board waterproof node of steel structure industrial workshop wall | |
CN205276487U (en) | Connection structure of light steel prefabricated exterior wall and major structure with adjustable it is three -dimensional | |
CN204823745U (en) | Two connection structure that drive suspension type crane end beam and girder | |
CN202831699U (en) | Combined type tool house |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20191105 |