CN209557012U - Device for branch at the beginning of tunnel with mould gunite concrete rapid construction - Google Patents
Device for branch at the beginning of tunnel with mould gunite concrete rapid construction Download PDFInfo
- Publication number
- CN209557012U CN209557012U CN201920145367.0U CN201920145367U CN209557012U CN 209557012 U CN209557012 U CN 209557012U CN 201920145367 U CN201920145367 U CN 201920145367U CN 209557012 U CN209557012 U CN 209557012U
- Authority
- CN
- China
- Prior art keywords
- steel
- sliding bottom
- branch
- tunnel
- mould
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn - After Issue
Links
Abstract
The utility model belongs to technical field of tunnel construction, it is related to a kind of device for branch at the beginning of tunnel with mould gunite concrete rapid construction, including packaged type just props up simple trolley, steel guide rail, driven circularly device, steel template system, spraying system and pipeline control system;Steel guide rail setting is at the beginning of the packaged type on the simple trolley of branch;Steel guide rail is integrally domed;Steel template system and spraying system are successively set on steel guide rail from bottom to top;The setting of driven circularly device is connected on the simple trolley of branch and with steel template system and spraying system respectively at the beginning of the packaged type;Driven circularly device respectively drives steel template system and spraying system moves freely on steel guide rail;Pipeline set-up of control system is connected at the beginning of packaged type on the simple trolley of branch and with driven circularly device.The utility model provide that a kind of construction efficiency is high, labor intensity is low and avoidable rebound object waste for first device of the branch with mould gunite concrete rapid construction in tunnel.
Description
Technical field
The utility model belongs to technical field of tunnel construction, is related to a kind of constructing device and construction method more particularly to one
Kind is for first device of the branch with mould gunite concrete rapid construction in tunnel.
Background technique
In Tunnel casting process, traditional preliminary bracing needs to set up arch, and assembled formwork progress mould is built mixed
Solidifying soil construction, this construction technology low efficiency, cost of labor investment are big.Main construction at this stage is gunite concrete branch
Shield, but the springback capacity sprayed is not easy to control, springs back the recycling heavy workload of object.It influences the construction environment of next stage and applies
Work cost.
To solve the above problems, existing technical staff proposes several solutions, such as Gong Gang utility model one kind
Tunnel bolt-spary supports concrete trolley with mobile pouring forms (publication number is CN 108194106A), by slip form trolley into
The bolt-spary supports of row successively, avoids waste caused by concrete springback;A kind of tunnel of the utility models such as Chen Jianmin just serves as a contrast mould
Pallet vehicle (publication number is CN 104790977A), when pumping liquid concrete, template mechanism forms rigidity arch in lining cutting position,
And rigidity arch is supported on door frame assembly;When during the concrete of pump note being in maintenance, the concrete support of note is pumped in steel
On property arch, and rigidity arch is separated with door frame assembly.
The thinking of existing solution is that single factor test improves, i.e., only considers that a kind of factor is improved, and this respect
It studies less.Therefore, a kind of device for Tunnel with mould gunite concrete rapid construction is developed, it can with realization
The waste of rebound object is reduced, and gunite concrete rapid construction can be used, the important improvement for becoming Tunnel device needs
It asks.
Utility model content
In order to solve the above technical problems in background technology, the utility model provide a kind of construction efficiency it is high,
Labor intensity is low and avoidable rebound object waste for first device of the branch with mould gunite concrete rapid construction in tunnel.
To achieve the goals above, the utility model adopts the following technical solution:
A kind of device for branch at the beginning of tunnel with mould gunite concrete rapid construction, described for tunnel, just branch band mould sprays
The device of rapid concrete construction include packaged type just prop up simple trolley, steel guide rail, driven circularly device, steel template system,
Spraying system and pipeline control system;Steel guide rail setting is at the beginning of packaged type on the simple trolley of branch;The steel guide rail is whole
Body is domed;The steel template system and spraying system are successively set on steel guide rail from bottom to top;The driven circularly dress
It installs at the beginning of the packaged type on the simple trolley of branch and is connected respectively with steel template system and spraying system;The driven circularly
Device respectively drives steel template system and spraying system moves freely on steel guide rail;The pipeline set-up of control system is can
It is connected on the simple trolley of mobile just branch and with driven circularly device.
Above-mentioned steel guide rail includes outside channel steel, inside channel steel, vault fixation steel plate and arch bottom fixation steel plate;The outside
The structure and shape of channel steel and inside channel steel are identical and domed;The vault fixation steel plate be placed in outside channel steel and
The keystone of the formed domes of inside channel steel;Arch bottom fixation steel plate is placed in outside channel steel and inside channel steel is formed
The arch bottom position of domes;Mobile working area is formed between the outside channel steel and inside channel steel;The steel template system
And spraying system is successively set in mobile working area from bottom to top and moves freely in mobile working area.
Above-mentioned steel template system includes punching block panel device sliding bottom, steel form telescoping shoring column and steel form;It is described
Steel form is connected by steel form telescoping shoring column with punching block panel device sliding bottom;The punching block panel device sliding bottom is placed in
By being formed by mobile working area between outside channel steel and inside channel steel;The pipeline control system is filled by driven circularly
Driving punching block panel device sliding bottom is set to move freely in mobile working area.
Above-mentioned punching block panel device sliding bottom includes steel form sliding bottom wheel shaft, steel form sliding bottom, steel form cunning
Dynamic pedestal wheel and punching block panel device sliding bottom singletree;The steel form sliding bottom and steel form sliding bottom vehicle
Wheel is set on steel form sliding bottom wheel shaft;The steel form slides bottom by steel form telescoping shoring column and steel form
Seat is connected;The steel form sliding bottom wheel shaft is placed in by being formed by mobile working area between outside channel steel and inside channel steel
In and moved freely in mobile working area by steel form sliding bottom wheel;The steel form sliding bottom wheel shaft is two
Root;The punching block panel device sliding bottom singletree is placed between two steel form sliding bottom wheel shafts and slides respectively with steel form
Dynamic pedestal wheel shaft is connected.
Above-mentioned steel form telescoping shoring column includes the first telescopic rod and the first pivoting support;First telescopic rod
One end be connected with steel form by the first pivoting support;The other end of first telescopic rod by the first pivoting support with
Steel form sliding bottom is connected.
Above-mentioned spraying system includes injection sliding bottom, telescoping shoring column module, spray gun, gunite concrete machine and coagulation
Native conveyance conduit;The spray gun is connected by telescoping shoring column module with injection sliding bottom;The spout of the spray gun is towards steel
The position of template system supporting;The injection sliding bottom is placed in by being formed by movement between outside channel steel and inside channel steel
In workspace;The pipeline control system is moved in mobile working area freely by driven circularly device driving injection sliding bottom
It is dynamic;The gunite concrete machine is placed in packaged type and just props up on simple trolley;The gunite concrete machine passes through concrete conveyance
Pipeline connects with spray gun.
Above-mentioned injection sliding bottom includes injection sliding bottom wheel shaft, injection sliding bottom idler wheel, spraying equipment sliding bottom
Seat coach wheel and spraying equipment sliding bottom singletree;The injection sliding bottom idler wheel and spraying equipment sliding bottom wheel
It is set on injection sliding bottom wheel shaft;The spray gun passes through telescoping shoring column module and injection sliding bottom idler wheel phase
Even;The injection sliding bottom wheel shaft is placed in by being formed by mobile working area and leading between outside channel steel and inside channel steel
Overspray equipment sliding bottom wheel moves freely in mobile working area;The injection sliding bottom wheel shaft is two;It is described
Spraying equipment sliding bottom singletree be placed between two injection sliding bottom wheel shafts and respectively with injection sliding bottom wheel shaft phase
Even.
Above-mentioned telescoping shoring column module includes the second telescopic rod and the second pivoting support;Second telescopic rod
One end is connected by the second pivoting support with injection sliding bottom idler wheel;The other end of second telescopic rod passes through the second hinge
Support is connect to be connected with spray gun.
Above-mentioned pipeline control system includes infrared ray identification sensor, strong and weak electrical cables and programmable logic controller (PLC);
The infrared ray identification sensor is connected with programmable logic controller (PLC);The driven circularly device includes motor capstan winch, guiding
Wheel and circumferential transmission rope;The motor capstan winch is connected by directive wheel with circumferential transmission rope;It is described circumferential direction transmission rope respectively with
Steel template system and spraying system simultaneously drive steel template system and spraying system to move freely on steel guide rail;It is described to compile
Journey logic controller passes through strong and weak electrical cables and is connected with motor capstan winch.
The utility model replaces existing concrete spraying machine using the first branch band simple trolley of mould gunite concrete, with existing skill
Art is compared, and has following advantage:
1) steel guide rail and formwork injection apparatus group designed is integral, and steel guide rail is placed on simple trolley, keeps its removable
It moves and formwork spraying equipment circumferential direction is assisted to spray, improve construction efficiency, reduce labor intensity.
2) the formwork spraying system designed uses circumferential spray regime to substitute existing shotcrete manipulator dress
It sets, gradually every ring moulds plate circumferential direction can be sprayed, sprayed by formwork, overcome the prior art and spring back object not in gunite concrete
Disadvantage easy to be recycled reduces the waste of rebound object.
3) device designed can operate with different tunnel cross-sections, pass through the scalable of steel template system and spraying system
Bar improves the recycling rate of waterused of device to adapt to corresponding tunnel Internal periphery.
Detailed description of the invention
Below in conjunction with the example diagram in the utility model embodiment, the technical solution of the utility model embodiment is carried out clear
Chu is fully described by, it should be apparent that, the accompanying drawings in the following description is only a part of the embodiment of the utility model, without
It is whole embodiments.Based on the embodiments of the present invention, those of ordinary skill in the art is not making creation
Property labour under the premise of obtain all embodiments, fall within the protection scope of the utility model.
Fig. 1 is the entirety provided by the utility model for first device of the branch with mould gunite concrete rapid construction in tunnel
Structural schematic diagram;
Fig. 2 be sliding bottom used by the utility model construction and with track connection figure;
Fig. 3 is steel form used by the utility model and telescoping shoring column connection figure;A is that steel template system faces knot
Structure schematic diagram;B is the overlooking structure diagram of steel template system;C is the schematic diagram of the section structure of steel template system;
Fig. 4 is spray gun used by the utility model and telescoping shoring column connection figure;A is that the formal structure of spraying system shows
Intention, b are the side structure schematic views of spraying system;C is the overlooking structure diagram of spraying system;
Fig. 5 is the two-dimensional side view of steel form and lance driving device used by the utility model;
Fig. 6 is the two-dimentional schematic cross-sectional view of steel form and lance driving device used by the utility model;
In figure:
1- steel guide rail;Channel steel on the outside of 11-;Channel steel on the inside of 12-;13- vault fixation steel plate;14- encircles bottom fixation steel plate;2- ring
To driving device;21- motor capstan winch;22- directive wheel;23- circumferential direction transmission rope;3- steel template system;The sliding of 31- punching block panel device
Pedestal;311- steel form sliding bottom wheel shaft;312- steel form sliding bottom;313- steel form sliding bottom wheel;314- steel
Die plate equipment sliding bottom singletree;32- steel form telescoping shoring column;The first telescopic rod of 321-;The first pivoting support of 322-;
33- steel form;4- spraying system;41- sprays sliding bottom;411- sprays sliding bottom wheel shaft;412- sprays sliding bottom rolling
Wheel;413- spraying equipment sliding bottom wheel;414- spraying equipment sliding bottom singletree;42- telescoping shoring column module;421-
Second telescopic rod;The second pivoting support of 422-;43- spray gun;44- gunite concrete machine;45- concrete conveying pipe;5- pipe
Line control system;51- infrared ray identification sensor;52- power electrical cables;53- programmable logic controller (PLC);The first branch trolley of 6-
And tunnel structure;61- just props up simple trolley;611- bogie wheels;62- is by spray plane.
Specific embodiment
In the following, being described in further detail but not making to the embodiments of the present invention with reference to the drawings and specific embodiments
For the restriction of the utility model.In the description of the present invention, it should be noted that term "left", "right", "upper", "lower",
The orientation or positional relationship of the instructions such as "bottom" is to be based on the orientation or positional relationship shown in the drawings, it is only for originally convenient for description
Utility model and simplified description, rather than refer in particular to or imply that signified element must have specific orientation, with specific orientation structure
It makes and operates, therefore should not be understood as limiting the present invention.
Such as FIG. 1 to FIG. 6, a kind of device for branch at the beginning of tunnel with mould gunite concrete rapid construction, comprising: steel guide rail 1,
For fixing steel template system and spraying system and two systems circumferential direction being assisted to travel;Driven circularly device 2, for driving punching block
Plate and spraying equipment are travelled along tunnel Internal periphery track circumferential direction;Steel template system 3 and is sprayed for the automatic formwork erection of steel form
Face is formed by spray space;Spraying system 4, supply transmission and automatic injection for concrete;Pipeline control system 5, is used for
The starting of driving device 2, steel template system 3 and spraying system 4 is closed, control signal transmits.
Such as Fig. 1,2, steel guide rail 1 is made of outside channel steel 11 and inside channel steel 12, and is bent into tunnel Internal periphery shape.Steel
Two rings of left and right are arranged altogether in guide rail 1, the fixed steel disc 13 of setting vault at vault, and are divided into twoth area of left and right, two rings to cleaning area
Steel guide rail encircles bottom setting arch bottom fixation steel plate 14, two ring steel tracks is locked, and the starting point as steel form sliding bottom, is protected
It is fixed to keep steady;There are the steel form sliding bottom wheel shafts that gap is used to put steel template system 3 and spraying system 4 between twice channel steel
311 and injection sliding bottom wheel shaft 411, steel form sliding bottom 312, injection are placed on steel form sliding bottom wheel shaft 311
Injection sliding bottom idler wheel 412 is placed on sliding bottom wheel shaft 411, outside channel steel and 12 side of inside channel steel are for placing
The steel form sliding bottom wheel 313 and spraying equipment sliding bottom wheel 413 of steel template system 3 and spraying system 4, punching block
Plate system 3 and spraying system 4 can travel on steel guide rail 1 under the driving of driven circularly device 2;Steel template system 3 and injection
The sliding of punching block panel device is put between two steel form sliding bottom wheel shafts 311 and injection sliding bottom wheel shaft 411 in system 4
Pedestal singletree 314 and spraying equipment sliding bottom singletree 414 keep the stabilization of equipment for fixing relative position.
Such as Fig. 1, driven circularly device 2 by installing motor capstan winch 21, directive wheel 22, circumferential transmission rope 23 on the car,
During the work time, pipeline control system 5 issues instruction, and control electric capstan 21 carrys out back rotation, and is passed by directive wheel 22
Lead ring is moved to transmission rope 23, is further dragged steel template system 3 and the circumferential movement of spraying system 4, is realized the formwork spray just propped up
It penetrates.
As (a is the positive structure diagram of steel template system by Fig. 1, Fig. 3;B is the plan structure signal of steel template system
Figure;C is the schematic diagram of the section structure of steel template system) and Fig. 5, steel template system 3 with lower module by being formed: steel form is set
Standby sliding bottom 31, telescoping shoring column module 32, steel form 33.Punching block panel device sliding bottom 31 is by steel form sliding bottom wheel
Axis 311, the steel form sliding bottom wheel 313 of wheel shaft two sides, the punching block panel device sliding bottom singletree 314 between wheel shaft,
Steel form sliding bottom 312, for assisting the circumferential traveling on steel guide rail 1 of steel template system 3;Steel form telescoping shoring column 32 by
First telescopic rod 321 and the first pivoting support 322 composition, the automatic positioning for template;
Such as Fig. 1, Fig. 4 (side structure schematic view that formal structure schematic diagram that a is spraying system, b are spraying systems;C is
The overlooking structure diagram of spraying system), Fig. 5 and Fig. 6, spraying system 4 with lower module by being formed: injection sliding bottom 41,
Telescoping shoring column module 42, spray gun 43, gunite concrete machine 44 and concrete conveying pipe 45.Sliding bottom 41 is sprayed by spraying
Penetrate sliding bottom wheel shaft 411, spraying equipment sliding bottom wheel 413, the spraying equipment sliding bottom singletree between wheel shaft
414, sliding bottom idler wheel 412 is sprayed, circumferential direction travels on steel guide rail 1 for assisted injection system 4;Telescoping shoring column module 42
It is made of the second telescopic rod 421 and the second pivoting support 422, the positioning for spray gun;Concrete conveying pipe 45 is used for
Delivering concrete.After the metering stirring of cement, aggregate and water, gunite concrete machine 44 is fed, then through concrete conveying pipe 45
It is delivered to nozzle, then is mixed with accelerator, by blast injection to by spray plane.
Pipeline control system 5 is by infrared ray identification sensor 51, forceful electric power weak-current cable 52 and programmable logic controller (PLC)
53 compositions.Infrared ray identification sensor 51 is used for transmission electric energy and transmitting signal for recording advance distance, strong and weak electrical cables 52,
Programmable logic controller (PLC) 53 is used for the transmitting-receiving of signal, controls the rotation of motor capstan winch 21.
As shown in Figure 1, Figure 2, Fig. 3 and Fig. 4, the utility model are quickly applied in offer for branch band mould gunite concrete at the beginning of tunnel
While the device of work, a kind of construction method based on the constructing device is additionally provided, which includes:
1) equipment installation is fixed: packaged type being pushed just to prop up simple trolley 61 to being excavated the initial scar wheel to be formed by spray plane
Profile, locked packaged type just prop up the traveling wheel 611 of simple trolley 61, and steel guide rail 1 is placed in packaged type and just props up simple trolley
On 61, simple 61 binding and fixing of trolley just will be propped up with packaged type at track vault, haunch, then by steel template system 3, injection
System 4 is placed on steel guide rail 1, plugs steel form sliding bottom wheel shaft 311 and injection sliding bottom wheel shaft 411, installation steel
Template sliding bottom wheel 313 and spraying equipment sliding bottom wheel 413, installation punching block panel device sliding bottom singletree
314 and spraying equipment sliding bottom singletree 414 and circumferential transmission rope 23 is connected, makes steel template system 3 and spraying system 4
It is fixed on steel guide rail 1, spray gun 43 connects gunite concrete machine 44 by concrete conveying pipe 45, and packaged type is waited just to prop up
Simple trolley 61 promotes formwork injection;
2) start circumferential formwork injection: after device is powered, transmitting electric energy and control signal by strong and weak electrical cables 52, start steel
Template system 3 and spraying system 4, instruction programmable logic controller (PLC) 53 are opened motor capstan winch 21, are driven by directive wheel 22
Circumferential transmission rope 23, and punching block panel device sliding bottom 31 and injection 41 uniform speed slow of sliding bottom movement are driven, to being sprayed
It is uniformly sprayed in face 62;
3) trolley persistently promotes: after the completion of a circumferential section injection, continuing that packaged type is promoted just to prop up simple trolley
61, infrared ray identification sensor 51 records advance distance and sends programmable logic controller (PLC) 53 to, can after promoting distance to a declared goal
Programmed logic controller 53 issues prompt, stops that packaged type is promoted just to prop up simple trolley 61 at this time, and carry out next ring section
Formwork injection, and so on, the successively section of the every ring of steel form telescoping shoring column 32, until packaged type just props up simple trolley
61 are pushed into entirely to need the section of preliminary bracing.It shuts down at this time and closes formwork spraying system, trolley 61 is pushed out to spacious location,
Wait the injection of next time.
The not detailed place of the utility model is routine techniques known in those skilled in the art.
The preferable specific embodiment of the above, only the utility model, but the protection scope of the utility model is not
It is confined to this, anyone skilled in the art is within the technical scope disclosed by the utility model, practical according to this
Novel technical solution and design is subject to equivalent substitution or change, should be covered within the scope of the utility model.
Claims (9)
1. a kind of device for branch at the beginning of tunnel with mould gunite concrete rapid construction, it is characterised in that: described at the beginning of tunnel
Device of the branch with mould gunite concrete rapid construction includes that packaged type just props up simple trolley (61), steel guide rail (1), driven circularly
Device (2), steel template system (3), spraying system (4) and pipeline control system (5);The steel guide rail (1) is arranged removable
Dynamic formula just props up on simple trolley (61);The steel guide rail (1) is whole domed;The steel template system (3) and spraying system
(4) it is successively set on from bottom to top on steel guide rail (1);Driven circularly device (2) setting is in the simple platform of branch at the beginning of packaged type
It is connected on vehicle (61) and respectively with steel template system (3) and spraying system (4);The driven circularly device (2) respectively drives
Steel template system (3) and spraying system (4) move freely on steel guide rail (1);The pipeline control system (5) setting is can
It is connected on the simple trolley (61) of mobile just branch and with driven circularly device (2).
2. according to claim 1 for first device of the branch with mould gunite concrete rapid construction in tunnel, it is characterised in that:
The steel guide rail (1) includes outside channel steel (11), inside channel steel (12), vault fixation steel plate (13) and arch bottom fixation steel plate
(14);The structure and shape of the outside channel steel (11) and inside channel steel (12) are identical and domed;The vault
Fixation steel plate (13) is placed in the keystone of outside channel steel (11) and inside channel steel (12) formed domes;The arch bottom is solid
Determine the arch bottom position that steel plate (14) is placed in outside channel steel (11) and inside channel steel (12) formed domes;The outside channel steel
(11) and between inside channel steel (12) mobile working area is formed;The steel template system (3) and spraying system (4) from lower and
On be successively set in mobile working area and moved freely in mobile working area.
3. according to claim 2 for first device of the branch with mould gunite concrete rapid construction in tunnel, it is characterised in that:
The steel template system (3) includes punching block panel device sliding bottom (31), steel form telescoping shoring column (32) and steel form
(33);The steel form (33) is connected by steel form telescoping shoring column (32) with punching block panel device sliding bottom (31);It is described
Punching block panel device sliding bottom (31) is placed in by being formed by mobile working between outside channel steel (11) and inside channel steel (12)
Qu Zhong;The pipeline control system (5) is by driven circularly device (2) driving punching block panel device sliding bottom (31) in mobile work
Make to move freely in area.
4. according to claim 3 for first device of the branch with mould gunite concrete rapid construction in tunnel, it is characterised in that:
The punching block panel device sliding bottom (31) includes steel form sliding bottom wheel shaft (311), steel form sliding bottom (312), steel
Template sliding bottom wheel (313) and punching block panel device sliding bottom singletree (314);The steel form sliding bottom
(312) and steel form sliding bottom wheel (313) is set on steel form sliding bottom wheel shaft (311);The punching block
Plate (33) is connected by steel form telescoping shoring column (32) with steel form sliding bottom (312);The steel form sliding bottom wheel
Axis (311) is placed in by being formed by mobile working area between outside channel steel (11) and inside channel steel (12) and passing through steel form
Sliding bottom wheel (313) moves freely in mobile working area;The steel form sliding bottom wheel shaft (311) is two;Institute
State punching block panel device sliding bottom singletree (314) be placed between two steel form sliding bottom wheel shafts (311) and respectively with steel
Template sliding bottom wheel shaft (311) is connected.
5. according to claim 4 for first device of the branch with mould gunite concrete rapid construction in tunnel, it is characterised in that:
The steel form telescoping shoring column (32) includes the first telescopic rod (321) and the first pivoting support (322);Described first can
One end of telescopic rod (321) is connected by the first pivoting support (322) with steel form (33);First telescopic rod (321)
The other end be connected with steel form sliding bottom (312) by the first pivoting support (322).
6. according to claim 2 for first device of the branch with mould gunite concrete rapid construction in tunnel, it is characterised in that:
The spraying system (4) includes injection sliding bottom (41), telescoping shoring column module (42), spray gun (43), gunite concrete machine
(44) and concrete conveying pipe (45);The spray gun (43) passes through telescoping shoring column module (42) and injection sliding bottom
(41) it is connected;The spout of the spray gun (43) is towards the position of steel template system (3) supporting;The injection sliding bottom (41) is set
In by being formed by mobile working area between outside channel steel (11) and inside channel steel (12);The pipeline control system (5)
Injection sliding bottom (41) is driven to move freely in mobile working area by driven circularly device (2);The gunite concrete
Machine (44) is placed in packaged type and just props up on simple trolley (61);The gunite concrete machine (44) passes through concrete conveying pipe
(45) it connects with spray gun (43).
7. according to claim 6 for first device of the branch with mould gunite concrete rapid construction in tunnel, it is characterised in that:
The injection sliding bottom (41) includes injection sliding bottom wheel shaft (411), injection sliding bottom idler wheel (412), spraying equipment
Sliding bottom wheel (413) and spraying equipment sliding bottom singletree (414);The injection sliding bottom idler wheel (412) with
And spraying equipment sliding bottom wheel (413) is set in injection sliding bottom wheel shaft (411);The spray gun (43) passes through
Telescoping shoring column module (42) is connected with injection sliding bottom idler wheel (412);The injection sliding bottom wheel shaft (411) be placed in by
It is formed by between outside channel steel (11) and inside channel steel (12) in mobile working area and by spraying equipment sliding bottom vehicle
Wheel (413) moves freely in mobile working area;The injection sliding bottom wheel shaft (411) is two;The spraying equipment is sliding
Dynamic pedestal singletree (414) be placed between two injection sliding bottom wheel shafts (411) and respectively with injection sliding bottom wheel shaft
(411) it is connected.
8. according to claim 7 for first device of the branch with mould gunite concrete rapid construction in tunnel, it is characterised in that:
The telescoping shoring column module (42) includes the second telescopic rod (421) and the second pivoting support (422);Described second can stretch
One end of contracting bar (421) is connected by the second pivoting support (422) with injection sliding bottom idler wheel (412);Described second can stretch
The other end of contracting bar (421) is connected by the second pivoting support (422) with spray gun (43).
9. according to claim 1 for first dress of the branch with mould gunite concrete rapid construction in tunnel described in -8 any claims
Set, it is characterised in that: the pipeline control system (5) include infrared ray identification sensor (51), strong and weak electrical cables (52) and
Programmable logic controller (PLC) (53);The infrared ray identification sensor (51) is connected with programmable logic controller (PLC) (53);It is described
Driven circularly device (2) includes motor capstan winch (21), directive wheel (22) and circumferential transmission rope (23);The motor capstan winch (21)
It is connected by directive wheel (22) with circumferential transmission rope (23);It is described circumferential direction transmission rope (23) respectively with steel template system (3) and
Spraying system (4) simultaneously drives steel template system (3) and spraying system (4) to move freely on steel guide rail (1);It is described programmable
Logic controller (53) passes through strong and weak electrical cables (52) and is connected with motor capstan winch (21).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920145367.0U CN209557012U (en) | 2019-01-28 | 2019-01-28 | Device for branch at the beginning of tunnel with mould gunite concrete rapid construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920145367.0U CN209557012U (en) | 2019-01-28 | 2019-01-28 | Device for branch at the beginning of tunnel with mould gunite concrete rapid construction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209557012U true CN209557012U (en) | 2019-10-29 |
Family
ID=68307842
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201920145367.0U Withdrawn - After Issue CN209557012U (en) | 2019-01-28 | 2019-01-28 | Device for branch at the beginning of tunnel with mould gunite concrete rapid construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209557012U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109538250A (en) * | 2019-01-28 | 2019-03-29 | 中南大学 | Device and method for branch at the beginning of tunnel with mould gunite concrete rapid construction |
WO2022148809A1 (en) * | 2021-01-08 | 2022-07-14 | Winter Von Adlersfluegel Hubertus Dietrich | Apparatus and method for manufacturing a solid, load-bearing construction from a hardening building material, and recess formwork system |
-
2019
- 2019-01-28 CN CN201920145367.0U patent/CN209557012U/en not_active Withdrawn - After Issue
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109538250A (en) * | 2019-01-28 | 2019-03-29 | 中南大学 | Device and method for branch at the beginning of tunnel with mould gunite concrete rapid construction |
CN109538250B (en) * | 2019-01-28 | 2023-09-15 | 中南大学 | Device and method for quick construction of tunnel primary support with mould sprayed concrete |
WO2022148809A1 (en) * | 2021-01-08 | 2022-07-14 | Winter Von Adlersfluegel Hubertus Dietrich | Apparatus and method for manufacturing a solid, load-bearing construction from a hardening building material, and recess formwork system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109538250A (en) | Device and method for branch at the beginning of tunnel with mould gunite concrete rapid construction | |
CN209557012U (en) | Device for branch at the beginning of tunnel with mould gunite concrete rapid construction | |
CN103032078B (en) | Parallel construction method for shield arrival tunnel portal ring beam and shield crossing station | |
CN109049315B (en) | Prefabricated component production system | |
CN103939114B (en) | A kind of outstanding rail chassis lining construction method | |
CN106013233A (en) | Slippage system used for underground pipe rack cast-in-place construction and construction method of slippage system | |
CN102146799A (en) | Construction equipment for inverted arch of two-track tunnel of high-speed railway | |
CN102146796A (en) | Construction technology for inverted arch of two-track tunnel of high-speed railway | |
CN108972864A (en) | Building concrete wallboard prefabricated components production line | |
CN105736012B (en) | A kind of tunnel lining concrete grouting device | |
CN109653771A (en) | Tunnel arch two lined steel mould trolley integrated with cable duct side wall | |
CN209491929U (en) | Building concrete wallboard prefabricated components production line | |
CN109773952A (en) | A kind of short-term matching segment beam circulation flow production line and its production method | |
CN108086686A (en) | Single oil cylinder all standing distribution device and its construction method | |
CN202017493U (en) | Construction equipment for inverted arch of high-speed railway double-track tunnel | |
CN109355983B (en) | Trackless construction method for urban rail | |
CN108316946B (en) | Open type TBM synchronous lining method and device | |
CN109208533A (en) | Harbour integrated construction system and method based on stake top top pushing platform | |
CN209194586U (en) | A kind of underground pipe gallery removable support template | |
CN105619578B (en) | The equipment and construction method of the automatic dabbing of bridge prefabrication cored slab web concrete | |
CN108547638B (en) | A kind of lining concrete adjustable type watering device of constructing tunnel | |
CN109281320A (en) | Gunite concrete synovial membrane constructing device and method for foundation pit side wall construction of leveling blanket | |
CN111594226A (en) | Movable spraying device for tunnel secondary lining concrete and spraying method thereof | |
CN205295964U (en) | Large -span continuous beam bridge strides existing station traction system for rotation construction | |
CN106194208B (en) | A kind of tunnel lining trolley with ventilation duct |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
AV01 | Patent right actively abandoned | ||
AV01 | Patent right actively abandoned | ||
AV01 | Patent right actively abandoned |
Granted publication date: 20191029 Effective date of abandoning: 20230915 |
|
AV01 | Patent right actively abandoned |
Granted publication date: 20191029 Effective date of abandoning: 20230915 |