CN209557012U - Device for branch at the beginning of tunnel with mould gunite concrete rapid construction - Google Patents

Device for branch at the beginning of tunnel with mould gunite concrete rapid construction Download PDF

Info

Publication number
CN209557012U
CN209557012U CN201920145367.0U CN201920145367U CN209557012U CN 209557012 U CN209557012 U CN 209557012U CN 201920145367 U CN201920145367 U CN 201920145367U CN 209557012 U CN209557012 U CN 209557012U
Authority
CN
China
Prior art keywords
steel
sliding bottom
branch
tunnel
mould
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201920145367.0U
Other languages
Chinese (zh)
Inventor
雷明锋
朱立成
李玉峰
曹太波
徐红
黄国富
钟志全
扶亲强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Central South University
China Construction Tunnel Construction Co Ltd
Original Assignee
Central South University
China Construction Tunnel Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Central South University, China Construction Tunnel Construction Co Ltd filed Critical Central South University
Priority to CN201920145367.0U priority Critical patent/CN209557012U/en
Application granted granted Critical
Publication of CN209557012U publication Critical patent/CN209557012U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model belongs to technical field of tunnel construction, it is related to a kind of device for branch at the beginning of tunnel with mould gunite concrete rapid construction, including packaged type just props up simple trolley, steel guide rail, driven circularly device, steel template system, spraying system and pipeline control system;Steel guide rail setting is at the beginning of the packaged type on the simple trolley of branch;Steel guide rail is integrally domed;Steel template system and spraying system are successively set on steel guide rail from bottom to top;The setting of driven circularly device is connected on the simple trolley of branch and with steel template system and spraying system respectively at the beginning of the packaged type;Driven circularly device respectively drives steel template system and spraying system moves freely on steel guide rail;Pipeline set-up of control system is connected at the beginning of packaged type on the simple trolley of branch and with driven circularly device.The utility model provide that a kind of construction efficiency is high, labor intensity is low and avoidable rebound object waste for first device of the branch with mould gunite concrete rapid construction in tunnel.

Description

Device for branch at the beginning of tunnel with mould gunite concrete rapid construction
Technical field
The utility model belongs to technical field of tunnel construction, is related to a kind of constructing device and construction method more particularly to one Kind is for first device of the branch with mould gunite concrete rapid construction in tunnel.
Background technique
In Tunnel casting process, traditional preliminary bracing needs to set up arch, and assembled formwork progress mould is built mixed Solidifying soil construction, this construction technology low efficiency, cost of labor investment are big.Main construction at this stage is gunite concrete branch Shield, but the springback capacity sprayed is not easy to control, springs back the recycling heavy workload of object.It influences the construction environment of next stage and applies Work cost.
To solve the above problems, existing technical staff proposes several solutions, such as Gong Gang utility model one kind Tunnel bolt-spary supports concrete trolley with mobile pouring forms (publication number is CN 108194106A), by slip form trolley into The bolt-spary supports of row successively, avoids waste caused by concrete springback;A kind of tunnel of the utility models such as Chen Jianmin just serves as a contrast mould Pallet vehicle (publication number is CN 104790977A), when pumping liquid concrete, template mechanism forms rigidity arch in lining cutting position, And rigidity arch is supported on door frame assembly;When during the concrete of pump note being in maintenance, the concrete support of note is pumped in steel On property arch, and rigidity arch is separated with door frame assembly.
The thinking of existing solution is that single factor test improves, i.e., only considers that a kind of factor is improved, and this respect It studies less.Therefore, a kind of device for Tunnel with mould gunite concrete rapid construction is developed, it can with realization The waste of rebound object is reduced, and gunite concrete rapid construction can be used, the important improvement for becoming Tunnel device needs It asks.
Utility model content
In order to solve the above technical problems in background technology, the utility model provide a kind of construction efficiency it is high, Labor intensity is low and avoidable rebound object waste for first device of the branch with mould gunite concrete rapid construction in tunnel.
To achieve the goals above, the utility model adopts the following technical solution:
A kind of device for branch at the beginning of tunnel with mould gunite concrete rapid construction, described for tunnel, just branch band mould sprays The device of rapid concrete construction include packaged type just prop up simple trolley, steel guide rail, driven circularly device, steel template system, Spraying system and pipeline control system;Steel guide rail setting is at the beginning of packaged type on the simple trolley of branch;The steel guide rail is whole Body is domed;The steel template system and spraying system are successively set on steel guide rail from bottom to top;The driven circularly dress It installs at the beginning of the packaged type on the simple trolley of branch and is connected respectively with steel template system and spraying system;The driven circularly Device respectively drives steel template system and spraying system moves freely on steel guide rail;The pipeline set-up of control system is can It is connected on the simple trolley of mobile just branch and with driven circularly device.
Above-mentioned steel guide rail includes outside channel steel, inside channel steel, vault fixation steel plate and arch bottom fixation steel plate;The outside The structure and shape of channel steel and inside channel steel are identical and domed;The vault fixation steel plate be placed in outside channel steel and The keystone of the formed domes of inside channel steel;Arch bottom fixation steel plate is placed in outside channel steel and inside channel steel is formed The arch bottom position of domes;Mobile working area is formed between the outside channel steel and inside channel steel;The steel template system And spraying system is successively set in mobile working area from bottom to top and moves freely in mobile working area.
Above-mentioned steel template system includes punching block panel device sliding bottom, steel form telescoping shoring column and steel form;It is described Steel form is connected by steel form telescoping shoring column with punching block panel device sliding bottom;The punching block panel device sliding bottom is placed in By being formed by mobile working area between outside channel steel and inside channel steel;The pipeline control system is filled by driven circularly Driving punching block panel device sliding bottom is set to move freely in mobile working area.
Above-mentioned punching block panel device sliding bottom includes steel form sliding bottom wheel shaft, steel form sliding bottom, steel form cunning Dynamic pedestal wheel and punching block panel device sliding bottom singletree;The steel form sliding bottom and steel form sliding bottom vehicle Wheel is set on steel form sliding bottom wheel shaft;The steel form slides bottom by steel form telescoping shoring column and steel form Seat is connected;The steel form sliding bottom wheel shaft is placed in by being formed by mobile working area between outside channel steel and inside channel steel In and moved freely in mobile working area by steel form sliding bottom wheel;The steel form sliding bottom wheel shaft is two Root;The punching block panel device sliding bottom singletree is placed between two steel form sliding bottom wheel shafts and slides respectively with steel form Dynamic pedestal wheel shaft is connected.
Above-mentioned steel form telescoping shoring column includes the first telescopic rod and the first pivoting support;First telescopic rod One end be connected with steel form by the first pivoting support;The other end of first telescopic rod by the first pivoting support with Steel form sliding bottom is connected.
Above-mentioned spraying system includes injection sliding bottom, telescoping shoring column module, spray gun, gunite concrete machine and coagulation Native conveyance conduit;The spray gun is connected by telescoping shoring column module with injection sliding bottom;The spout of the spray gun is towards steel The position of template system supporting;The injection sliding bottom is placed in by being formed by movement between outside channel steel and inside channel steel In workspace;The pipeline control system is moved in mobile working area freely by driven circularly device driving injection sliding bottom It is dynamic;The gunite concrete machine is placed in packaged type and just props up on simple trolley;The gunite concrete machine passes through concrete conveyance Pipeline connects with spray gun.
Above-mentioned injection sliding bottom includes injection sliding bottom wheel shaft, injection sliding bottom idler wheel, spraying equipment sliding bottom Seat coach wheel and spraying equipment sliding bottom singletree;The injection sliding bottom idler wheel and spraying equipment sliding bottom wheel It is set on injection sliding bottom wheel shaft;The spray gun passes through telescoping shoring column module and injection sliding bottom idler wheel phase Even;The injection sliding bottom wheel shaft is placed in by being formed by mobile working area and leading between outside channel steel and inside channel steel Overspray equipment sliding bottom wheel moves freely in mobile working area;The injection sliding bottom wheel shaft is two;It is described Spraying equipment sliding bottom singletree be placed between two injection sliding bottom wheel shafts and respectively with injection sliding bottom wheel shaft phase Even.
Above-mentioned telescoping shoring column module includes the second telescopic rod and the second pivoting support;Second telescopic rod One end is connected by the second pivoting support with injection sliding bottom idler wheel;The other end of second telescopic rod passes through the second hinge Support is connect to be connected with spray gun.
Above-mentioned pipeline control system includes infrared ray identification sensor, strong and weak electrical cables and programmable logic controller (PLC); The infrared ray identification sensor is connected with programmable logic controller (PLC);The driven circularly device includes motor capstan winch, guiding Wheel and circumferential transmission rope;The motor capstan winch is connected by directive wheel with circumferential transmission rope;It is described circumferential direction transmission rope respectively with Steel template system and spraying system simultaneously drive steel template system and spraying system to move freely on steel guide rail;It is described to compile Journey logic controller passes through strong and weak electrical cables and is connected with motor capstan winch.
The utility model replaces existing concrete spraying machine using the first branch band simple trolley of mould gunite concrete, with existing skill Art is compared, and has following advantage:
1) steel guide rail and formwork injection apparatus group designed is integral, and steel guide rail is placed on simple trolley, keeps its removable It moves and formwork spraying equipment circumferential direction is assisted to spray, improve construction efficiency, reduce labor intensity.
2) the formwork spraying system designed uses circumferential spray regime to substitute existing shotcrete manipulator dress It sets, gradually every ring moulds plate circumferential direction can be sprayed, sprayed by formwork, overcome the prior art and spring back object not in gunite concrete Disadvantage easy to be recycled reduces the waste of rebound object.
3) device designed can operate with different tunnel cross-sections, pass through the scalable of steel template system and spraying system Bar improves the recycling rate of waterused of device to adapt to corresponding tunnel Internal periphery.
Detailed description of the invention
Below in conjunction with the example diagram in the utility model embodiment, the technical solution of the utility model embodiment is carried out clear Chu is fully described by, it should be apparent that, the accompanying drawings in the following description is only a part of the embodiment of the utility model, without It is whole embodiments.Based on the embodiments of the present invention, those of ordinary skill in the art is not making creation Property labour under the premise of obtain all embodiments, fall within the protection scope of the utility model.
Fig. 1 is the entirety provided by the utility model for first device of the branch with mould gunite concrete rapid construction in tunnel Structural schematic diagram;
Fig. 2 be sliding bottom used by the utility model construction and with track connection figure;
Fig. 3 is steel form used by the utility model and telescoping shoring column connection figure;A is that steel template system faces knot Structure schematic diagram;B is the overlooking structure diagram of steel template system;C is the schematic diagram of the section structure of steel template system;
Fig. 4 is spray gun used by the utility model and telescoping shoring column connection figure;A is that the formal structure of spraying system shows Intention, b are the side structure schematic views of spraying system;C is the overlooking structure diagram of spraying system;
Fig. 5 is the two-dimensional side view of steel form and lance driving device used by the utility model;
Fig. 6 is the two-dimentional schematic cross-sectional view of steel form and lance driving device used by the utility model;
In figure:
1- steel guide rail;Channel steel on the outside of 11-;Channel steel on the inside of 12-;13- vault fixation steel plate;14- encircles bottom fixation steel plate;2- ring To driving device;21- motor capstan winch;22- directive wheel;23- circumferential direction transmission rope;3- steel template system;The sliding of 31- punching block panel device Pedestal;311- steel form sliding bottom wheel shaft;312- steel form sliding bottom;313- steel form sliding bottom wheel;314- steel Die plate equipment sliding bottom singletree;32- steel form telescoping shoring column;The first telescopic rod of 321-;The first pivoting support of 322-; 33- steel form;4- spraying system;41- sprays sliding bottom;411- sprays sliding bottom wheel shaft;412- sprays sliding bottom rolling Wheel;413- spraying equipment sliding bottom wheel;414- spraying equipment sliding bottom singletree;42- telescoping shoring column module;421- Second telescopic rod;The second pivoting support of 422-;43- spray gun;44- gunite concrete machine;45- concrete conveying pipe;5- pipe Line control system;51- infrared ray identification sensor;52- power electrical cables;53- programmable logic controller (PLC);The first branch trolley of 6- And tunnel structure;61- just props up simple trolley;611- bogie wheels;62- is by spray plane.
Specific embodiment
In the following, being described in further detail but not making to the embodiments of the present invention with reference to the drawings and specific embodiments For the restriction of the utility model.In the description of the present invention, it should be noted that term "left", "right", "upper", "lower", The orientation or positional relationship of the instructions such as "bottom" is to be based on the orientation or positional relationship shown in the drawings, it is only for originally convenient for description Utility model and simplified description, rather than refer in particular to or imply that signified element must have specific orientation, with specific orientation structure It makes and operates, therefore should not be understood as limiting the present invention.
Such as FIG. 1 to FIG. 6, a kind of device for branch at the beginning of tunnel with mould gunite concrete rapid construction, comprising: steel guide rail 1, For fixing steel template system and spraying system and two systems circumferential direction being assisted to travel;Driven circularly device 2, for driving punching block Plate and spraying equipment are travelled along tunnel Internal periphery track circumferential direction;Steel template system 3 and is sprayed for the automatic formwork erection of steel form Face is formed by spray space;Spraying system 4, supply transmission and automatic injection for concrete;Pipeline control system 5, is used for The starting of driving device 2, steel template system 3 and spraying system 4 is closed, control signal transmits.
Such as Fig. 1,2, steel guide rail 1 is made of outside channel steel 11 and inside channel steel 12, and is bent into tunnel Internal periphery shape.Steel Two rings of left and right are arranged altogether in guide rail 1, the fixed steel disc 13 of setting vault at vault, and are divided into twoth area of left and right, two rings to cleaning area Steel guide rail encircles bottom setting arch bottom fixation steel plate 14, two ring steel tracks is locked, and the starting point as steel form sliding bottom, is protected It is fixed to keep steady;There are the steel form sliding bottom wheel shafts that gap is used to put steel template system 3 and spraying system 4 between twice channel steel 311 and injection sliding bottom wheel shaft 411, steel form sliding bottom 312, injection are placed on steel form sliding bottom wheel shaft 311 Injection sliding bottom idler wheel 412 is placed on sliding bottom wheel shaft 411, outside channel steel and 12 side of inside channel steel are for placing The steel form sliding bottom wheel 313 and spraying equipment sliding bottom wheel 413 of steel template system 3 and spraying system 4, punching block Plate system 3 and spraying system 4 can travel on steel guide rail 1 under the driving of driven circularly device 2;Steel template system 3 and injection The sliding of punching block panel device is put between two steel form sliding bottom wheel shafts 311 and injection sliding bottom wheel shaft 411 in system 4 Pedestal singletree 314 and spraying equipment sliding bottom singletree 414 keep the stabilization of equipment for fixing relative position.
Such as Fig. 1, driven circularly device 2 by installing motor capstan winch 21, directive wheel 22, circumferential transmission rope 23 on the car, During the work time, pipeline control system 5 issues instruction, and control electric capstan 21 carrys out back rotation, and is passed by directive wheel 22 Lead ring is moved to transmission rope 23, is further dragged steel template system 3 and the circumferential movement of spraying system 4, is realized the formwork spray just propped up It penetrates.
As (a is the positive structure diagram of steel template system by Fig. 1, Fig. 3;B is the plan structure signal of steel template system Figure;C is the schematic diagram of the section structure of steel template system) and Fig. 5, steel template system 3 with lower module by being formed: steel form is set Standby sliding bottom 31, telescoping shoring column module 32, steel form 33.Punching block panel device sliding bottom 31 is by steel form sliding bottom wheel Axis 311, the steel form sliding bottom wheel 313 of wheel shaft two sides, the punching block panel device sliding bottom singletree 314 between wheel shaft, Steel form sliding bottom 312, for assisting the circumferential traveling on steel guide rail 1 of steel template system 3;Steel form telescoping shoring column 32 by First telescopic rod 321 and the first pivoting support 322 composition, the automatic positioning for template;
Such as Fig. 1, Fig. 4 (side structure schematic view that formal structure schematic diagram that a is spraying system, b are spraying systems;C is The overlooking structure diagram of spraying system), Fig. 5 and Fig. 6, spraying system 4 with lower module by being formed: injection sliding bottom 41, Telescoping shoring column module 42, spray gun 43, gunite concrete machine 44 and concrete conveying pipe 45.Sliding bottom 41 is sprayed by spraying Penetrate sliding bottom wheel shaft 411, spraying equipment sliding bottom wheel 413, the spraying equipment sliding bottom singletree between wheel shaft 414, sliding bottom idler wheel 412 is sprayed, circumferential direction travels on steel guide rail 1 for assisted injection system 4;Telescoping shoring column module 42 It is made of the second telescopic rod 421 and the second pivoting support 422, the positioning for spray gun;Concrete conveying pipe 45 is used for Delivering concrete.After the metering stirring of cement, aggregate and water, gunite concrete machine 44 is fed, then through concrete conveying pipe 45 It is delivered to nozzle, then is mixed with accelerator, by blast injection to by spray plane.
Pipeline control system 5 is by infrared ray identification sensor 51, forceful electric power weak-current cable 52 and programmable logic controller (PLC) 53 compositions.Infrared ray identification sensor 51 is used for transmission electric energy and transmitting signal for recording advance distance, strong and weak electrical cables 52, Programmable logic controller (PLC) 53 is used for the transmitting-receiving of signal, controls the rotation of motor capstan winch 21.
As shown in Figure 1, Figure 2, Fig. 3 and Fig. 4, the utility model are quickly applied in offer for branch band mould gunite concrete at the beginning of tunnel While the device of work, a kind of construction method based on the constructing device is additionally provided, which includes:
1) equipment installation is fixed: packaged type being pushed just to prop up simple trolley 61 to being excavated the initial scar wheel to be formed by spray plane Profile, locked packaged type just prop up the traveling wheel 611 of simple trolley 61, and steel guide rail 1 is placed in packaged type and just props up simple trolley On 61, simple 61 binding and fixing of trolley just will be propped up with packaged type at track vault, haunch, then by steel template system 3, injection System 4 is placed on steel guide rail 1, plugs steel form sliding bottom wheel shaft 311 and injection sliding bottom wheel shaft 411, installation steel Template sliding bottom wheel 313 and spraying equipment sliding bottom wheel 413, installation punching block panel device sliding bottom singletree 314 and spraying equipment sliding bottom singletree 414 and circumferential transmission rope 23 is connected, makes steel template system 3 and spraying system 4 It is fixed on steel guide rail 1, spray gun 43 connects gunite concrete machine 44 by concrete conveying pipe 45, and packaged type is waited just to prop up Simple trolley 61 promotes formwork injection;
2) start circumferential formwork injection: after device is powered, transmitting electric energy and control signal by strong and weak electrical cables 52, start steel Template system 3 and spraying system 4, instruction programmable logic controller (PLC) 53 are opened motor capstan winch 21, are driven by directive wheel 22 Circumferential transmission rope 23, and punching block panel device sliding bottom 31 and injection 41 uniform speed slow of sliding bottom movement are driven, to being sprayed It is uniformly sprayed in face 62;
3) trolley persistently promotes: after the completion of a circumferential section injection, continuing that packaged type is promoted just to prop up simple trolley 61, infrared ray identification sensor 51 records advance distance and sends programmable logic controller (PLC) 53 to, can after promoting distance to a declared goal Programmed logic controller 53 issues prompt, stops that packaged type is promoted just to prop up simple trolley 61 at this time, and carry out next ring section Formwork injection, and so on, the successively section of the every ring of steel form telescoping shoring column 32, until packaged type just props up simple trolley 61 are pushed into entirely to need the section of preliminary bracing.It shuts down at this time and closes formwork spraying system, trolley 61 is pushed out to spacious location, Wait the injection of next time.
The not detailed place of the utility model is routine techniques known in those skilled in the art.
The preferable specific embodiment of the above, only the utility model, but the protection scope of the utility model is not It is confined to this, anyone skilled in the art is within the technical scope disclosed by the utility model, practical according to this Novel technical solution and design is subject to equivalent substitution or change, should be covered within the scope of the utility model.

Claims (9)

1. a kind of device for branch at the beginning of tunnel with mould gunite concrete rapid construction, it is characterised in that: described at the beginning of tunnel Device of the branch with mould gunite concrete rapid construction includes that packaged type just props up simple trolley (61), steel guide rail (1), driven circularly Device (2), steel template system (3), spraying system (4) and pipeline control system (5);The steel guide rail (1) is arranged removable Dynamic formula just props up on simple trolley (61);The steel guide rail (1) is whole domed;The steel template system (3) and spraying system (4) it is successively set on from bottom to top on steel guide rail (1);Driven circularly device (2) setting is in the simple platform of branch at the beginning of packaged type It is connected on vehicle (61) and respectively with steel template system (3) and spraying system (4);The driven circularly device (2) respectively drives Steel template system (3) and spraying system (4) move freely on steel guide rail (1);The pipeline control system (5) setting is can It is connected on the simple trolley (61) of mobile just branch and with driven circularly device (2).
2. according to claim 1 for first device of the branch with mould gunite concrete rapid construction in tunnel, it is characterised in that: The steel guide rail (1) includes outside channel steel (11), inside channel steel (12), vault fixation steel plate (13) and arch bottom fixation steel plate (14);The structure and shape of the outside channel steel (11) and inside channel steel (12) are identical and domed;The vault Fixation steel plate (13) is placed in the keystone of outside channel steel (11) and inside channel steel (12) formed domes;The arch bottom is solid Determine the arch bottom position that steel plate (14) is placed in outside channel steel (11) and inside channel steel (12) formed domes;The outside channel steel (11) and between inside channel steel (12) mobile working area is formed;The steel template system (3) and spraying system (4) from lower and On be successively set in mobile working area and moved freely in mobile working area.
3. according to claim 2 for first device of the branch with mould gunite concrete rapid construction in tunnel, it is characterised in that: The steel template system (3) includes punching block panel device sliding bottom (31), steel form telescoping shoring column (32) and steel form (33);The steel form (33) is connected by steel form telescoping shoring column (32) with punching block panel device sliding bottom (31);It is described Punching block panel device sliding bottom (31) is placed in by being formed by mobile working between outside channel steel (11) and inside channel steel (12) Qu Zhong;The pipeline control system (5) is by driven circularly device (2) driving punching block panel device sliding bottom (31) in mobile work Make to move freely in area.
4. according to claim 3 for first device of the branch with mould gunite concrete rapid construction in tunnel, it is characterised in that: The punching block panel device sliding bottom (31) includes steel form sliding bottom wheel shaft (311), steel form sliding bottom (312), steel Template sliding bottom wheel (313) and punching block panel device sliding bottom singletree (314);The steel form sliding bottom (312) and steel form sliding bottom wheel (313) is set on steel form sliding bottom wheel shaft (311);The punching block Plate (33) is connected by steel form telescoping shoring column (32) with steel form sliding bottom (312);The steel form sliding bottom wheel Axis (311) is placed in by being formed by mobile working area between outside channel steel (11) and inside channel steel (12) and passing through steel form Sliding bottom wheel (313) moves freely in mobile working area;The steel form sliding bottom wheel shaft (311) is two;Institute State punching block panel device sliding bottom singletree (314) be placed between two steel form sliding bottom wheel shafts (311) and respectively with steel Template sliding bottom wheel shaft (311) is connected.
5. according to claim 4 for first device of the branch with mould gunite concrete rapid construction in tunnel, it is characterised in that: The steel form telescoping shoring column (32) includes the first telescopic rod (321) and the first pivoting support (322);Described first can One end of telescopic rod (321) is connected by the first pivoting support (322) with steel form (33);First telescopic rod (321) The other end be connected with steel form sliding bottom (312) by the first pivoting support (322).
6. according to claim 2 for first device of the branch with mould gunite concrete rapid construction in tunnel, it is characterised in that: The spraying system (4) includes injection sliding bottom (41), telescoping shoring column module (42), spray gun (43), gunite concrete machine (44) and concrete conveying pipe (45);The spray gun (43) passes through telescoping shoring column module (42) and injection sliding bottom (41) it is connected;The spout of the spray gun (43) is towards the position of steel template system (3) supporting;The injection sliding bottom (41) is set In by being formed by mobile working area between outside channel steel (11) and inside channel steel (12);The pipeline control system (5) Injection sliding bottom (41) is driven to move freely in mobile working area by driven circularly device (2);The gunite concrete Machine (44) is placed in packaged type and just props up on simple trolley (61);The gunite concrete machine (44) passes through concrete conveying pipe (45) it connects with spray gun (43).
7. according to claim 6 for first device of the branch with mould gunite concrete rapid construction in tunnel, it is characterised in that: The injection sliding bottom (41) includes injection sliding bottom wheel shaft (411), injection sliding bottom idler wheel (412), spraying equipment Sliding bottom wheel (413) and spraying equipment sliding bottom singletree (414);The injection sliding bottom idler wheel (412) with And spraying equipment sliding bottom wheel (413) is set in injection sliding bottom wheel shaft (411);The spray gun (43) passes through Telescoping shoring column module (42) is connected with injection sliding bottom idler wheel (412);The injection sliding bottom wheel shaft (411) be placed in by It is formed by between outside channel steel (11) and inside channel steel (12) in mobile working area and by spraying equipment sliding bottom vehicle Wheel (413) moves freely in mobile working area;The injection sliding bottom wheel shaft (411) is two;The spraying equipment is sliding Dynamic pedestal singletree (414) be placed between two injection sliding bottom wheel shafts (411) and respectively with injection sliding bottom wheel shaft (411) it is connected.
8. according to claim 7 for first device of the branch with mould gunite concrete rapid construction in tunnel, it is characterised in that: The telescoping shoring column module (42) includes the second telescopic rod (421) and the second pivoting support (422);Described second can stretch One end of contracting bar (421) is connected by the second pivoting support (422) with injection sliding bottom idler wheel (412);Described second can stretch The other end of contracting bar (421) is connected by the second pivoting support (422) with spray gun (43).
9. according to claim 1 for first dress of the branch with mould gunite concrete rapid construction in tunnel described in -8 any claims Set, it is characterised in that: the pipeline control system (5) include infrared ray identification sensor (51), strong and weak electrical cables (52) and Programmable logic controller (PLC) (53);The infrared ray identification sensor (51) is connected with programmable logic controller (PLC) (53);It is described Driven circularly device (2) includes motor capstan winch (21), directive wheel (22) and circumferential transmission rope (23);The motor capstan winch (21) It is connected by directive wheel (22) with circumferential transmission rope (23);It is described circumferential direction transmission rope (23) respectively with steel template system (3) and Spraying system (4) simultaneously drives steel template system (3) and spraying system (4) to move freely on steel guide rail (1);It is described programmable Logic controller (53) passes through strong and weak electrical cables (52) and is connected with motor capstan winch (21).
CN201920145367.0U 2019-01-28 2019-01-28 Device for branch at the beginning of tunnel with mould gunite concrete rapid construction Withdrawn - After Issue CN209557012U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920145367.0U CN209557012U (en) 2019-01-28 2019-01-28 Device for branch at the beginning of tunnel with mould gunite concrete rapid construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920145367.0U CN209557012U (en) 2019-01-28 2019-01-28 Device for branch at the beginning of tunnel with mould gunite concrete rapid construction

Publications (1)

Publication Number Publication Date
CN209557012U true CN209557012U (en) 2019-10-29

Family

ID=68307842

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920145367.0U Withdrawn - After Issue CN209557012U (en) 2019-01-28 2019-01-28 Device for branch at the beginning of tunnel with mould gunite concrete rapid construction

Country Status (1)

Country Link
CN (1) CN209557012U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109538250A (en) * 2019-01-28 2019-03-29 中南大学 Device and method for branch at the beginning of tunnel with mould gunite concrete rapid construction
WO2022148809A1 (en) * 2021-01-08 2022-07-14 Winter Von Adlersfluegel Hubertus Dietrich Apparatus and method for manufacturing a solid, load-bearing construction from a hardening building material, and recess formwork system

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109538250A (en) * 2019-01-28 2019-03-29 中南大学 Device and method for branch at the beginning of tunnel with mould gunite concrete rapid construction
CN109538250B (en) * 2019-01-28 2023-09-15 中南大学 Device and method for quick construction of tunnel primary support with mould sprayed concrete
WO2022148809A1 (en) * 2021-01-08 2022-07-14 Winter Von Adlersfluegel Hubertus Dietrich Apparatus and method for manufacturing a solid, load-bearing construction from a hardening building material, and recess formwork system

Similar Documents

Publication Publication Date Title
CN109538250A (en) Device and method for branch at the beginning of tunnel with mould gunite concrete rapid construction
CN209557012U (en) Device for branch at the beginning of tunnel with mould gunite concrete rapid construction
CN103032078B (en) Parallel construction method for shield arrival tunnel portal ring beam and shield crossing station
CN109049315B (en) Prefabricated component production system
CN103939114B (en) A kind of outstanding rail chassis lining construction method
CN106013233A (en) Slippage system used for underground pipe rack cast-in-place construction and construction method of slippage system
CN102146799A (en) Construction equipment for inverted arch of two-track tunnel of high-speed railway
CN102146796A (en) Construction technology for inverted arch of two-track tunnel of high-speed railway
CN108972864A (en) Building concrete wallboard prefabricated components production line
CN105736012B (en) A kind of tunnel lining concrete grouting device
CN109653771A (en) Tunnel arch two lined steel mould trolley integrated with cable duct side wall
CN209491929U (en) Building concrete wallboard prefabricated components production line
CN109773952A (en) A kind of short-term matching segment beam circulation flow production line and its production method
CN108086686A (en) Single oil cylinder all standing distribution device and its construction method
CN202017493U (en) Construction equipment for inverted arch of high-speed railway double-track tunnel
CN109355983B (en) Trackless construction method for urban rail
CN108316946B (en) Open type TBM synchronous lining method and device
CN109208533A (en) Harbour integrated construction system and method based on stake top top pushing platform
CN209194586U (en) A kind of underground pipe gallery removable support template
CN105619578B (en) The equipment and construction method of the automatic dabbing of bridge prefabrication cored slab web concrete
CN108547638B (en) A kind of lining concrete adjustable type watering device of constructing tunnel
CN109281320A (en) Gunite concrete synovial membrane constructing device and method for foundation pit side wall construction of leveling blanket
CN111594226A (en) Movable spraying device for tunnel secondary lining concrete and spraying method thereof
CN205295964U (en) Large -span continuous beam bridge strides existing station traction system for rotation construction
CN106194208B (en) A kind of tunnel lining trolley with ventilation duct

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned

Granted publication date: 20191029

Effective date of abandoning: 20230915

AV01 Patent right actively abandoned

Granted publication date: 20191029

Effective date of abandoning: 20230915