CN209538025U - A kind of separate type bridge guardian column formwork for placing - Google Patents

A kind of separate type bridge guardian column formwork for placing Download PDF

Info

Publication number
CN209538025U
CN209538025U CN201920031625.2U CN201920031625U CN209538025U CN 209538025 U CN209538025 U CN 209538025U CN 201920031625 U CN201920031625 U CN 201920031625U CN 209538025 U CN209538025 U CN 209538025U
Authority
CN
China
Prior art keywords
core plate
side plate
plate
pull rod
external mold
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920031625.2U
Other languages
Chinese (zh)
Inventor
王伟申
彭园
张何
金树坤
侯兆隆
张华武
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Road and Bridge International Co Ltd
China Communications Road and Bridge North China Engineering Co Ltd
Original Assignee
Road and Bridge International Co Ltd
China Communications Road and Bridge North China Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Road and Bridge International Co Ltd, China Communications Road and Bridge North China Engineering Co Ltd filed Critical Road and Bridge International Co Ltd
Priority to CN201920031625.2U priority Critical patent/CN209538025U/en
Application granted granted Critical
Publication of CN209538025U publication Critical patent/CN209538025U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The utility model provides a kind of separate type bridge guardian column formwork for placing, the inner template including two exterior sheathings and between two exterior sheathings, and inner template includes a core plate, and one block of side plate is respectively arranged in core plate two sides;And the height of core plate is higher than both side plate;Two lifting hole(eyelet)s are set at the position that core plate is higher by both side plate, is provided with tension rod thru-hole on core plate and both side plate, the bottom edge of core plate and both side plate is provided with the pull rod card slot of arc;It is arranged from the lower pull rod passed through from the upper connecting rod passed through in tension rod thru-hole and from pull rod card slot by two exterior sheathings and drawing is fixed.After the completion of protective fence concreting, when internal model demoulding, first extracts core plate out, then respectively takes out both side plate.The utility model can solve the problem that separate type bridge guardian column internal model can not be taken out, and internal model is reusable.

Description

A kind of separate type bridge guardian column formwork for placing
Technical field
The utility model belongs to science of bridge building field, and in particular to a kind of for bridge center anticollision barrier pouring construction Template.
Background technique
Affiliated facility of the bridge guardrail as bridge is to ensure that the security-critical safeguard structure of driving, pedestrains safety.It is anti- Guardrail generallys use concrete pouring construction.For being equipped with the bridge in Bidirectional separating lane, protected except being arranged in bridge two sides Marge there is provision of guardian column in bridge center.As shown in Figure 1, separate type bridge 100, which is usually set, controls two width bridges, two Have certain gap 101 among width bridge, and the protective fence 102 in bridge center will also be set as left and right width accordingly, among two width Corresponding gap is set.It, can be fixed using medial and lateral when pouring construction for the two biggish protective fences of width separating distance of left and right Steel form framing is constructed, and for the lesser protective fence of left and right width separating distance, it at present can only be in left and right width protective fence Bamboo slab rubber is placed in gap or other packing materials serve as internal model, then left and right width installation outboard template is constructed simultaneously, this The drawbacks of kind construction method is that internal model can not be taken out after the completion of pouring, and needs to expend lot of materials, not only increases engineering cost, and By packing material stiffness effect, anticollision barrier gap line style is also not readily available control.
Summary of the invention
The purpose of this utility model is that being provided aiming at the problem that left and right smaller internal model of width guardrail intermediate gap can not be taken out A kind of template poured for separate type bridge guardian column, and the side using template progress protective fence pouring construction Method can smoothly take out internal model after the completion of pouring, and reduce construction cost, and guarantee construction quality.
To achieve the above object, the utility model provides a kind of separate type bridge guardian column formwork for placing, including phase To two protective fence exterior sheathings of setting, and the inner template between two exterior sheathings, the outside of two exterior sheathing is set respectively It is equipped with external mold upright bar, and the height of upright bar is higher than the height of the exterior sheathing, it is characterised in that:
The inner template includes a core plate, is close to the core plate two sides and one block of side plate, the core plate and both side plate is respectively arranged Height be above the exterior sheathing, wherein the height of core plate is higher than both side plate again;It is higher by the position of both side plate in core plate, left and right Two lifting hole(eyelet)s are symmetrical arranged, be higher than exterior sheathing in core plate and both side plate and are lower than the position of the external mold upright bar, it is outer described in face Mould upright bar is provided with the tension rod thru-hole through core plate and both side plate, distinguishes in the two external mold upright bar of bottom edge face of core plate and both side plate It is provided with the pull rod card slot of arc;In the upper end of external mold upright bar setting in two external mold upright bars to pull rod, it is described on to drawing Bar is passed through from the tension rod thru-hole on core plate and both side plate;In the lower end of two external mold upright bars, setting is through the lower right of two external mold upright bars Pull rod, it is described lower pull rod to be passed through from the pull rod card slot on core plate and both side plate bottom edge.
The utility model is for left and right small-pitch protective fence, using 3 piece combined templates as protective fence internal model Plate can take out inner template fragment after the completion of pouring, and solve what current separate type bridge guardian column internal model can not be taken out Problem, and internal model is reusable, and construction quality, cost is made to be effectively controlled, and can construct and be provided effectively for such protective fence It uses for reference.
Detailed description of the invention
Fig. 1 is the structural schematic diagram on separate type bridge guardian column;
Fig. 2 is the formwork structure schematic diagram of the utility model;
Fig. 3 is the partial structural diagram of inner template;
Fig. 4 is the planar structure schematic diagram of inner template core plate;
Fig. 5 is the planar structure schematic diagram of inner template side plate;
The template use state diagram of Fig. 6 the utility model.
Specific embodiment
As shown in Fig. 2, the utility model includes two protective fence exterior sheathings 1 being oppositely arranged, and be located at two exterior sheathings it Between inner template 2, the outside of two exterior sheathing 1 is respectively arranged with external mold upright bar 3, and the height of upright bar 3 is higher than the external mold The height of plate 1.
The structure of the inner template 2 is close to the core plate two sides and one piece of side is respectively arranged as shown in figure 3, including a core plate 21 The height of plate 22, the core plate 21 and both side plate 22 is above the exterior sheathing 1, and wherein the height of core plate 21 is higher than both side plate again 22。
The structure of core plate 21 is as shown in figure 4, the structure of side plate 22 is as shown in Figure 5.It is higher by the position of both side plate in core plate 21, Two lifting hole(eyelet)s 23 are symmetrical set, be higher than exterior sheathing in core plate and both side plate and are lower than the position of the external mold upright bar, face The external mold upright bar 3 is provided with the tension rod thru-hole 24 through core plate and both side plate, outside the bottom edge face two of core plate and both side plate Mould upright bar is respectively arranged with the pull rod card slot 25 of arc.
As shown in Figure 1, in the setting of the upper end of external mold upright bar 3 to pull rod 4 in two external mold upright bars, it is described on to pull rod 4 pass through from the tension rod thru-hole 24 on core plate and both side plate;In the lower end of two external mold upright bars 3, setting is under two external mold upright bars It is described lower pull rod 5 to be passed through from the pull rod card slot 25 on core plate and both side plate bottom edge to pull rod 5.
In one embodiment of the utility model, there are the seams of 2cm between bridge median strip protective fence or so width Gap, using the template construction of the utility model, the core plate of inner template uses the steel plate of 125 × 139 × 0.6cm, and both side plate is adopted With the steel plate of 125 × 132 × 0.6cm.Concrete construction method is as follows:
(1) as shown in fig. 6, the framework of steel reinforcement 6 of left and right width protective fence is installed in protective fence design position, in left and right width reinforcing bar
Horizontally disposed 3 row's fixed internal formwork muscle 7 of upper, middle and lower, the internal model on the width framework of steel reinforcement of left and right are respectively welded on skeleton Spacing between 7 end of positioning bar is equal to the spacing between left and right width protective fence.
The main function of fixed internal formwork muscle 7 is the spacing controlled between left and right width protective fence, and fixes inner template.In 3 rows Mould positioning bar 7 is longitudinally disposed along guardrail respectively.In the present embodiment, in each row's fixed internal formwork muscle 7, between adjacent fixed internal formwork muscle Away from for 1.25m, every fixed internal formwork muscle and protective fence framework of steel reinforcement spot-welded.
After the completion of fixed internal formwork muscle 7 welds, the bamboo slab rubber in covering gap is placed in the gap top surface between two width bridges, with It is only starched conducive to protective fence bottom when pouring.The bamboo slab rubber 10cm wide, 1cm used in the present embodiment is thick.
(2) protective fence exterior sheathing 1 is respectively set on the outside of two frameworks of steel reinforcement, and to pull rod 5 that two exterior sheathings 1 are right under installation It draws.
When exterior sheathing 1 is installed, the settable 3cm M10 mortar levelling layer between external mold bottom surface and beam slab top surface.
(3) inner template 2 is installed between the fixed internal formwork muscle 7 on two width frameworks of steel reinforcement 6, the side of inner template is installed first Then plate 22 installs core plate 21, finally installs another side plate, the pull rod card slot on core plate and both side plate bottom edge is stuck in lower to drawing On bar, and it is closely knit to guarantee that core plate and both side plate bottom edge are contacted with the bamboo slab rubber of lower section.
When inner template is installed, one layer of lithium saponify butter can be uniformly brushed between core plate and both side plate, reduce core plate and two Frictional force between side plate can come out core plate and the smooth lifting of side plate when being convenient for demoulding.
(4) install to pull rod 4, on to the tension rod thru-hole 24 passed through among pull rod 4 on core plate and both side plate, both ends difference It is fixed with the upright bar on the outside of exterior sheathing, entire template is installed.
(5) after template is installed, start to pour protective fence concrete.
(6) after the completion of concreting, after concrete strength reaches strength of mould stripping, start form removal.It is common to tear open Mould intensity is that concrete strength reaches 2.5Mpa or more, can guarantee that surface and corner angle are not damaged because of demoulding.
Form removable process is as follows:
Lower pull rod 5, upper connecting rod 4 and two exterior sheathings 1 are successively removed first;
Then two lifting hole(eyelet)s 23 on internal model core plate 21 are passed through with lifting rope, with truck crane by the upward lifting of core plate, by core plate 21 It takes out;
Side plate 22 is agitated again, is detached from the side plate and concrete, is then first passed through the pull rod on the side plate with lifting rope and is led to Hole 24 is hung out the side plate with truck crane;Another side plate is hung out with same method, completes demoulding.One section of protective fence construction After the completion, template next construction location is moved on to be recycled.

Claims (1)

1. a kind of separate type bridge guardian column formwork for placing including two protective fence exterior sheathings being oppositely arranged, and is located at Inner template between two exterior sheathings is respectively arranged with external mold upright bar on the outside of two exterior sheathing, and the height of upright bar is higher than institute State the height of exterior sheathing, it is characterised in that: the inner template includes a core plate, is close to the core plate two sides and one piece of side is respectively arranged The height of plate, the core plate and both side plate is above the exterior sheathing, and wherein the height of core plate is higher than both side plate again;In core plate height The position of both side plate out is symmetrical set two lifting hole(eyelet)s, is higher than exterior sheathing in core plate and both side plate and stands lower than the external mold The position of bar, external mold upright bar described in face is provided with the tension rod thru-hole through core plate and both side plate, at the bottom of core plate and both side plate Face two external mold upright bar in side is respectively arranged with the pull rod card slot of arc;In the upper end of external mold upright bar, setting is through two external mold upright bars On to pull rod, it is described on pull rod is passed through from the tension rod thru-hole on core plate and both side plate;It is arranged in the lower end of two external mold upright bars It is described lower pull rod to be passed through from the pull rod card slot on core plate and both side plate bottom edge through the lower to pull rod of two external mold upright bars.
CN201920031625.2U 2019-01-08 2019-01-08 A kind of separate type bridge guardian column formwork for placing Active CN209538025U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920031625.2U CN209538025U (en) 2019-01-08 2019-01-08 A kind of separate type bridge guardian column formwork for placing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920031625.2U CN209538025U (en) 2019-01-08 2019-01-08 A kind of separate type bridge guardian column formwork for placing

Publications (1)

Publication Number Publication Date
CN209538025U true CN209538025U (en) 2019-10-25

Family

ID=68268973

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920031625.2U Active CN209538025U (en) 2019-01-08 2019-01-08 A kind of separate type bridge guardian column formwork for placing

Country Status (1)

Country Link
CN (1) CN209538025U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109555017A (en) * 2019-01-08 2019-04-02 中交路桥建设有限公司 A kind of separate type bridge guardian column formwork for placing and construction method
CN112523089A (en) * 2020-11-06 2021-03-19 江苏镇江路桥工程有限公司 Template is pour to disconnect-type bridge central authorities rail guard

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109555017A (en) * 2019-01-08 2019-04-02 中交路桥建设有限公司 A kind of separate type bridge guardian column formwork for placing and construction method
CN112523089A (en) * 2020-11-06 2021-03-19 江苏镇江路桥工程有限公司 Template is pour to disconnect-type bridge central authorities rail guard

Similar Documents

Publication Publication Date Title
CN106677049B (en) Assembled steel-concrete combined structure bridge and construction method
CN104594500B (en) Integrated slab column formwork structure system and construction method
CN109555017A (en) A kind of separate type bridge guardian column formwork for placing and construction method
CN108755984A (en) Late poured band support construction method based on concrete square column
CN105804395B (en) Stair continuously poured in one molding construction method based on monoblock type typified form
CN206784913U (en) A kind of two-part superimposed sheet seam hangs die worker's tool
CN105971276B (en) Integral aluminum formwork stair one-step continuous pouring forming structure and construction method
CN209538025U (en) A kind of separate type bridge guardian column formwork for placing
CN105507470B (en) A kind of periphery overlapping overall assembled floor and its construction method
CN103194971A (en) Capping construction method for hollow pier
CN109518858A (en) Fabricated Beam-Slab connection structure and its construction method
CN110172924B (en) Integral hydraulic box girder template construction method
CN205576747U (en) Cast -in -place panel braced system of U type roof beam
CN109610341A (en) A kind of solid section constructing method of Thin-wall Hollow Pier pier top
CN209368686U (en) A kind of wet seam mortar leakage prevention of precast beam quickly pacifies demoulding system
CN205821975U (en) A kind of assembling steel plate composite beam bridge based on bolted steel reinforced concrete combined bridge deck
CN207812307U (en) The construction system of Cable stayed Bridge Main Tower and steel anchor beam
CN108775085A (en) The assembled integral concrete frame structure and its construction method of beam-ends connection
CN108104281A (en) It is a kind of to be used for side form way of the fabricated construction exterior wall without tongue and groove composite beam
CN208918266U (en) One kind exempting from support formula steel plate post-cast strip template structure system
CN213772939U (en) Assembled anticollision wall
CN209538013U (en) A kind of end template for the construction of Thin-wall Hollow Pier pier top solid-section
CN113653239A (en) Construction method of self-supporting steel bar truss template system
CN208202548U (en) Support system structure of transvers plate is exempted from a kind of beam slab post-cast strip
CN208934250U (en) A kind of assembled exempts to tear round beam column concrete blinding open