CN209482822U - Assembling type fence in concrete - Google Patents

Assembling type fence in concrete Download PDF

Info

Publication number
CN209482822U
CN209482822U CN201822007271.6U CN201822007271U CN209482822U CN 209482822 U CN209482822 U CN 209482822U CN 201822007271 U CN201822007271 U CN 201822007271U CN 209482822 U CN209482822 U CN 209482822U
Authority
CN
China
Prior art keywords
crossbeam
pedestal
column
concrete
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201822007271.6U
Other languages
Chinese (zh)
Inventor
袁雪峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Sanhe Pile Co Ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201822007271.6U priority Critical patent/CN209482822U/en
Application granted granted Critical
Publication of CN209482822U publication Critical patent/CN209482822U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Fencing (AREA)

Abstract

The utility model discloses a kind of assembling type fence in concrete, including crossbeam, it is used to support the pedestal of crossbeam and the column being fixed on above crossbeam, enclosing structure is equipped between adjacent columns, corresponding position on the upside of the both ends of the crossbeam is equipped with the first notch, adjacent crossbeam seam crossing is set to form the first through hole of connection crossbeam inner space and column inner space, corresponding position on the downside of the both ends of crossbeam also is provided with the second notch, adjacent crossbeam seam crossing is set to form the second through-hole, concrete link block is equipped between crossbeam and pedestal, the crossbeam and pedestal with concrete link block adhesion.The utility model is using pre-tensioning system centrifugation steam curing process production, while guaranteeing component strength, vast resources is saved, while alleviating member dead weight, reduces the requirement of bottom surface bearing capacity, simple and quick construction, construction quality is guaranteed, uses based on prefabricated components, the mode supplemented by second pouring, while guaranteeing bonding strength and construction convenience, cost is reduced.

Description

Assembling type fence in concrete
Technical field
The utility model relates to a kind of concrete earthen walls, and in particular to a kind of assembling type fence in concrete and construction party Method.
Background technique
After traditional enclosure wall is masonry walls or live formwork concreting, levelling facing is painted, construction period is long;In recent years Carrying out concrete earthen wall and obtains a degree of application, existing concrete enclosure wall own wt is big, and construction labor intensity is high, and It has a single function, is not able to satisfy country and saves resource, the requirement of the industrial policy of Green Development.
Utility model content
The it is proposed of the utility model in view of the above problems, and a kind of assembling type fence in concrete of researching and designing and construction party Method.The technological means that the utility model uses is as follows:
A kind of assembling type fence in concrete including crossbeam, is used to support the pedestal of crossbeam and is fixed on vertical above crossbeam Column, enclosing structure is equipped between adjacent columns, and the crossbeam and column are pre-tensioning system centrifugation hollow structure, the base supports In the lower section of adjacent beams seam, the upside of the crossbeam is equipped with the of the inner space of connection crossbeam and the inner space of column One through-hole, the first through hole is set to the end of crossbeam or the first notch by adjacent beams end is arranged in is spliced, Corresponding position on the downside of the both ends of the crossbeam is equipped with the second notch, and adjacent crossbeam seam crossing is made to form the second through-hole, so that The main reinforcement end of the crossbeam of second through-hole two sides corresponding position, which is extend out in the second through-hole, forms the first reinforced steel, the crossbeam Concrete link block is equipped between pedestal, the crossbeam and pedestal reinforce steel with concrete link block adhesion, described first Muscle is fixed in concrete link block, and the second reinforced steel is equipped between the pedestal and concrete link block, and described second adds Gu reinforcing bar is bending reinforcing steel bar structure, second reinforced steel is hung on the first reinforced steel.
Further, the main reinforcement end of the crossbeam is equipped with tensioning sleeve, is equipped with screw thread, the base in the tensioning sleeve It being set on seat there are two the second reinforced steel, two ends that two the second reinforced steels are embedded in base interior are connected with each other, and two A second reinforced steel is hung on two the first reinforced steels respectively and is carried out by the tensioning sleeve of the first reinforced steel end Limit, the column are fixed on the top of adjacent beams seam or are fixed on above the end of crossbeam, and the crossbeam is equipped with fixed Position groove, the column are set in positioning groove.
Further, the upper surface of the pedestal is equipped with the supporting element of more than two adjustment heights.
Further, the inside of the pedestal is embedded with band internal thread screwed pipe, forms spiral shell in the upper surface of pedestal Line blind hole, the supporting element are threaded rod, and the threaded rod and screwed pipe are screwed on cooperation, and can adjust spiral shell by rotating threaded rod The height of rasp bar stretching pedestal upper surface.
Further, the side out of plumb of one or two end face of the crossbeam and crossbeam.
Further, the end face of the one end of the beam and the side of crossbeam are in 45 degree of angles.
Further, the lower end surface of the column is equipped with more than two fixed columns, and the crossbeam is equipped with and fixed column Corresponding fixation hole, the fixed column are fixed in fixation hole.
Further, the fixed column is the main reinforcement of bar planting or end stretching column end face that one end is embedded in column, Fixing pipe is equipped in the fixation hole.
Further, the fixed column is inserted link, is equipped with holding firmware in the fixation hole, the inserted link can be inserted into fixation hole And it is fixed in fixation hole by holding firmware.
A kind of construction method of assembling type fence in concrete is the construction party of any one enclosure wall described in the utility model Method includes the following steps:
A. the pedestal that upper end is equipped with reinforcing bar hanging ring is hung to the unwrapping wire position location of construction site and cuts reinforcing bar hanging ring Two the second reinforced steels are formed, or base of the unwrapping wire position location cast in situs with the second rinforcement bar at the construction field (site) Seat;
B. crossbeam is placed on pedestal, the second reinforced steel of bending is hung on the second reinforced steel on the first reinforced steel;
C. it is poured concrete into the second through-hole, the concrete of casting is made not have the first reinforced steel and second to reinforce steel Muscle;
D. column is mounted on crossbeam, and enclosing structure is installed.
Compared with the prior art, assembling type fence in concrete described in the utility model has the advantage that
1, crossbeam and column are hollow structure, are produced using centrifuging process, and concrete strength is high, and structure is more densely cross-linked, In the identical situation of sectional area, material consumption is substantially reduced, anti-rotten, the freeze proof and durability of product is effectively improved, solves Traditional enclosure wall because climate reasons intolerant to burn into it is easy to fall off and not durable caused by crack many quality problems such as avalanche;
2, crossbeam and column use pretensioned prestressing main reinforcement and cold-drawn stirrup, are substantially reducing the same of material consumption just now When, effectively raise the bending resistance cracking resistance of crossbeam and column concrete;
3, crossbeam and column are all made of centrifugation steam curing process production, with short production cycle, flat appearance is smooth, are not necessarily to two Secondary levelling painting improves construction efficiency while reducing site environment pollution;
4, enclosure wall is fabricated construction, and weatherproof of constructing, simple and quick construction, construction quality is guaranteed, saves A large amount of labor costs, maintenance and repair are at low cost;
5, the mode based on prefabricated components, supplemented by second pouring is used, guarantees bonding strength and convenience of constructing Meanwhile reducing cost;
6, laying channel of the inner space of enclosure wall exocentric structure as cable and pipeline, reduces the construction and excavation in soil, Efficiently solve the problems, such as the use space in soil.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the utility model embodiment one.
Fig. 2 is the top view of Fig. 1.
Fig. 3 is the A-A cross-sectional view of Fig. 2 (without enclosing structure).
Fig. 4 is the structural schematic diagram of crossbeam described in the utility model embodiment one and embodiment two.
Fig. 5 is the right view of Fig. 4.
Fig. 6 is the left view of Fig. 4.
Fig. 7 is the structural schematic diagram of column described in the utility model embodiment.
Fig. 8 is the top view of Fig. 7.
Fig. 9 is the bottom view of Fig. 7.
Figure 10 is the structural schematic diagram of pedestal described in the utility model embodiment one.
Figure 11 is the top view of Figure 10.
Figure 12 is the structural schematic diagram of two adjacent crossbeam junctions in the utility model embodiment one.
Figure 13 is the structural schematic diagram of the junction of pedestal described in the utility model embodiment one and crossbeam.
Figure 14 is the position connection relationship of the first reinforced steel and the second reinforced steel described in the utility model embodiment Schematic diagram.
Figure 15 is the structural schematic diagram of a crossbeam of right angle crook in the utility model embodiment.
Figure 16 is the structural schematic diagram of another crossbeam of right angle crook in the utility model embodiment.
Figure 17 is the structural schematic diagram of the two crossbeam junctions in right angle crook in the utility model embodiment.
Figure 18 is the C-C partial sectional view of Figure 17.
Figure 19 is the structural schematic diagram of the utility model embodiment two.
Figure 20 is the structural schematic diagram of two adjacent crossbeam junctions in the utility model embodiment two.
Figure 21 is the structural schematic diagram of the junction of pedestal described in the utility model embodiment two and crossbeam.
Figure 22 is the structural schematic diagram of the utility model embodiment three.
Figure 23 is the structural schematic diagram that the crossbeam of first through hole is arranged in the utility model embodiment three.
Figure 24 is the right view of Figure 23.
Figure 25 is the left view of Figure 24.
Figure 26 is the structural schematic diagram that the crossbeam of first through hole is not provided in the utility model embodiment three.
Figure 27 is the right view of Figure 26.
Figure 28 is the left view of Figure 26.
Specific embodiment
Embodiment one
As shown in figs. 1 to 14, a kind of assembling type fence in concrete including crossbeam 1, is used to support 2 and of pedestal of crossbeam 1 It is fixed on the column 3 of 1 top of crossbeam, is equipped with enclosing structure 4 between adjacent columns 3, the crossbeam 1 and column 3 are pre-tensioning system Be centrifuged hollow structure, pre-tensioning system be concrete formation before prestressing force main reinforcement is stretched with reduce reinforcing bar extend simultaneously at The production method that type concrete applies compression, the column 3 are fixed on the top of 1 seam of adjacent beams, and the pedestal 2 supports Corresponding position on the upside of the lower section of 1 seam of adjacent beams, the both ends of the crossbeam 1 is equipped with the first notch 11, makes adjacent Crossbeam seam crossing forms the first through hole 12 of connection crossbeam inner space and column inner space, the both ends downside of the crossbeam 1 Corresponding position also be provided with the second notch 13, so that adjacent 1 seam crossing of crossbeam is formed the second through-hole 14, so that 14 liang of the second through-hole The main reinforcement end of the crossbeam 1 of side corresponding position extend out in the second through-hole 14 and forms the first reinforced steel 16, the crossbeam 1 and base Concrete link block 5 is equipped between seat 2, the crossbeam 1 and pedestal 2 reinforce steel with 5 adhesion of concrete link block, described first Muscle 16 is fixed in concrete link block 5, and the second reinforced steel 21 is equipped between the pedestal 2 and concrete link block 5, described Second reinforced steel 21 is bending reinforcing steel bar structure, and second reinforced steel 21 is hung on the first reinforced steel 16.The enclosing Structure 4 can be iron skill fence or fiber concrete coaming plate, be also possible to other enclosing structures, as long as being able to achieve the enclosing of enclosure wall Function.
The main reinforcement end of the crossbeam 1 is equipped with tensioning sleeve 18, is equipped with screw thread, the crossbeam 1 in the tensioning sleeve 18 It is equipped with positioning groove 19, the column 3 is set in positioning groove 19.Second reinforced steel there are two being set on the pedestal 2 21, two the second reinforced steels 21 are embedded in the interconnection of two ends inside pedestal 2, form integral structure, that is to say, that Practical two ends that the reinforcing bar in pedestal 2 is embedded in for a middle part of two the second reinforced steels 1, certain two second reinforcings Reinforcing bar 21 or independent two reinforcing bars, two the second reinforced steels are hung on two the first reinforced steels respectively and pass through The tensioning sleeve of first reinforced steel end is limited, that is to say, that the second reinforced steel is hung on the first reinforced steel simultaneously The second reinforced steel is kept off on the first reinforced steel by the tensioning sleeve of end.For the present embodiment, two second reinforcings The manufacturing process of reinforcing bar are as follows: 2 upper end of pedestal is embedded with reinforcing bar hanging ring, in transport and construction for carrying out hanging behaviour to pedestal 2 Make, after pedestal 2 is hung to required position, hanging ring is cut, forms two the second reinforced steels.The pedestal 2 of the present embodiment is flat The upper surface of base-like structure, the pedestal 2 is equipped with groove corresponding with the second through-hole 14, and second reinforced steel is located at Bottom portion of groove.
The lower end surface of the column 3 is equipped with more than two fixed columns 31, and the crossbeam is equipped with corresponding with fixed column 31 Fixation hole 17, the fixed column 31 is fixed in fixation hole 17.The fixed column 31 is that one end is embedded in the bar planting in column 3 Or the main reinforcement of column end face is stretched out in end, is equipped with fixing pipe 17 in the fixation hole 17.The fixed column 31 can also be inserted link, Holding firmware is equipped in the fixation hole 17, the inserted link can be inserted into fixation hole 17 and fix in fixation hole 17 by holding firmware. The inserted link and holding firmware form grafting joint structure, the grafting connector can for patent [2015204447851], 【2015207122349】、【2015206485006】、【2016200084213】、【2018210459188】、 Grafting connector described in [201821211028X], [2018108476777] or [2018108443237].The top of the column 3 End is equipped with headlamp 32, and the upper end of the column is equipped with lampshade, headlamp fixed plate 33 is equipped in lampshade, and the headlamp 32 is solid It is scheduled in headlamp fixed plate 33.Column 3 is connected to the inner space of ground beam 1 by first through hole 12, can be used as headlamp 32 cable passage, the inner space of ground beam 1 can also be used as gardening irrigation or fire demand water pipe passage.
In order to adapt to different construction requirements, one or two end face of the crossbeam 1 can be vertical with the side of crossbeam 1 Can also be with out of plumb, the end face of normal stalk crossbeam is vertical with side, and crossbeam is sequentially connected non-stalk, for bending wall or arc Shape wall, then end face and side be at an angle.For the right angle crook of enclosure wall, the end face of the one end of the beam and crossbeam Side is in 45 degree of angles, then two adjacent crossbeams docking, is in an angle of 90 degrees, as shown in FIG. 15 to 18.
A kind of construction method of assembling type fence in concrete is the construction party of any one enclosure wall described in the utility model Method includes the following steps:
A. the pedestal 2 that upper end is equipped with reinforcing bar hanging ring is hung to construction location, reinforcing bar hanging ring is cut, formed two second and add Gu reinforcing bar 21 digs base seat groove on ground, levelling to base seat groove progress before placing pedestal 2, or unwrapping wire at the construction field (site) is fixed Position location site pours the pedestal 2 with the second rinforcement bar 21;
B. crossbeam 1 is placed on pedestal 2, the second reinforced steel 21 of bending makes the second reinforced steel 21 be hung on the first reinforcing steel On muscle 16, two the second reinforced steels 21 are hung on respectively on two the first reinforced steels 16;
C. it is poured concrete into the second through-hole, the concrete of casting is made not have the first reinforced steel and second to reinforce steel Muscle, that is, second pouring operation is carried out, concrete link block 5 is formed after the concrete setting of second pouring, while will be adjacent Two crossbeams 1 be connected and fixed with pedestal 2;
D. column is mounted on crossbeam, and enclosing structure is installed, it is recessed to the top of crossbeam junction before column is installed Modified epoxy glue is smeared in slot, and will inject modified epoxy glue in fixation hole 17, and column 3 is placed on crossbeam connection In the upper grooves at place, meanwhile, fixed column 31 is inserted into fixation hole 17, and modified epoxy glue extra in fixation hole 17 is squeezed It is depressed into the gap between column and crossbeam, is formed and be tightly connected, guarantee the fastness of connection, while enhancing antiseptic property, protect Demonstrate,prove the safety of enclosure wall inside cable route.
Embodiment two
As shown in Figure 19 to Figure 21, the assembling type fence in concrete of the present embodiment and embodiment one the difference is that, The pedestal 2 includes Base body 23 and the back taper pilum 24 for being set to 23 lower section of Base body, is had suitable for the north freeze proof The construction site of layer.The upper surface of the pedestal 2 is equipped with the supporting element 22 of more than two adjustment heights.The pedestal 2 it is interior Portion is embedded with band internal thread screwed pipe 23, forms tapped blind hole in the upper surface of pedestal 2, the supporting element 22 is screw thread Bar, the threaded rod and screwed pipe are screwed on cooperation, and can pass through the height of rotating threaded rod adjustment threaded rod stretching 2 upper surface of pedestal Degree.The other structures of the present embodiment are the same as example 1.
A kind of construction method of assembling type fence in concrete is the construction party of any one enclosure wall described in the utility model Method includes the following steps:
A. the pedestal 2 that upper end is equipped with reinforcing bar hanging ring is hung to construction location, base seat groove is dug on ground, by the pilum of pedestal 2 24 are driven underground in pedestal trench bottom, and reinforcing bar hanging ring is cut, and form two the second reinforced steels 21;
B. the height progress for adjusting supporting element 22 is levelling, and crossbeam 1 is placed on pedestal 2, and the second reinforced steel 21 of bending makes Second reinforced steel 21 is hung on the first reinforced steel 16, and two the second reinforced steels 21 are hung on two the first reinforced steels respectively On 16;
C. it is poured concrete into the second through-hole, the concrete of casting is made not have the first reinforced steel and second to reinforce steel Muscle, that is, second pouring operation is carried out, concrete link block 5 is formed after the concrete setting of second pouring, while will be adjacent Two crossbeams 1 be connected and fixed with pedestal 2;
D. column is mounted on crossbeam, and enclosing structure is installed, it is recessed to the top of crossbeam junction before column is installed Modified epoxy glue is smeared in slot, and will inject modified epoxy glue in fixation hole 17, and column 3 is placed on crossbeam connection In the upper grooves at place, meanwhile, fixed column 31 is inserted into fixation hole 17, and modified epoxy glue extra in fixation hole 17 is squeezed It is depressed into the gap between column and crossbeam, is formed and be tightly connected, guarantee the fastness of connection, while enhancing antiseptic property, protect Demonstrate,prove the safety of enclosure wall inside cable route.
Embodiment three
As shown in Figure 22 to Figure 28, the present embodiment and embodiment one the difference is that: the column 3 is fixed on crossbeam The first through hole 12 and positioning groove 19 are set to the end of crossbeam 1 above 1 end, and it is two kinds that crossbeam 1, which is divided to, and one kind is two End is respectively provided with the crossbeam of first through hole, and another kind is the crossbeam for being not provided with first through hole, and two kinds of girder spaces are arranged, correspondingly, The crossbeam that first through hole 12 is arranged is fixedly arranged above two columns 3, is not provided with being not provided with column above the crossbeam of first through hole, by The end of crossbeam is set in first through hole 12, although not coaxial with the second through-hole, horizontal distance is close, so still may be used To carry out second pouring concrete to the second through hole by first through hole 12.In addition, in order to make effectively to be propped up below column 3 Support, the pedestal that 2 size of pedestal of the present embodiment is greater than embodiment one eats size, so that the vertical projection of 3 lower end surface of column is in base In the supporting surface of seat 2.The other structures and construction method of the present embodiment are the same as example 1.
Embodiment described above is only that preferred embodiments of the present invention are described, not practical to this Novel range is defined, and under the premise of not departing from the spirit of the design of the utility model, those of ordinary skill in the art are to this The various changes and improvements that the technical solution of utility model is made should all fall into the protection that the utility model claims book determines In range.

Claims (9)

1. a kind of assembling type fence in concrete, including crossbeam, the column that is used to support the pedestal of crossbeam and is fixed on above crossbeam, Enclosing structure is equipped between adjacent columns, it is characterised in that: the crossbeam and column are pre-tensioning system centrifugation hollow structure, described Base supports are equipped with the inner space of connection crossbeam and the inside of column in the lower section of adjacent beams seam, the upside of the crossbeam The first through hole in space, the first through hole is set to the end of crossbeam or the first notch by adjacent beams end is arranged in is spelled It connects, the corresponding position on the downside of the both ends of the crossbeam is equipped with the second notch, so that adjacent crossbeam seam crossing is formed second logical Hole, so that the main reinforcement end of the crossbeam of the second through-hole two sides corresponding position, which is extend out in the second through-hole, forms the first reinforced steel, Be equipped with concrete link block between the crossbeam and pedestal, the crossbeam and pedestal with concrete link block adhesion, described the One reinforced steel is fixed in concrete link block, and the second reinforced steel, institute are equipped between the pedestal and concrete link block Stating the second reinforced steel is bending reinforcing steel bar structure, and second reinforced steel is hung on the first reinforced steel.
2. assembling type fence in concrete according to claim 1, it is characterised in that: the main reinforcement end of the crossbeam, which is equipped with, opens It helps pull a cart cylinder, screw thread is equipped in the tensioning sleeve, set that there are two the second reinforced steel, two the second reinforced steels on the pedestal Two ends for being embedded in base interior are connected with each other, and two the second reinforced steels are hung on two the first reinforced steels simultaneously respectively It is limited by the tensioning sleeve of the first reinforced steel end, the column is fixed on top or the fixation of adjacent beams seam Above the end of crossbeam, the crossbeam is equipped with positioning groove, and the column is set in positioning groove.
3. assembling type fence in concrete according to claim 2, it is characterised in that: the upper surface of the pedestal is equipped with two The supporting element of a above adjustment height.
4. assembling type fence in concrete according to claim 3, it is characterised in that: the inside of the pedestal, which is embedded with, to be had The screwed pipe of internal screw thread forms tapped blind hole in the upper surface of pedestal, and the supporting element is threaded rod, the threaded rod and screw thread Pipe is screwed on cooperation, and can pass through rotating threaded rod and adjust the height that threaded rod stretches out pedestal upper surface.
5. assembling type fence in concrete according to claim 1, it is characterised in that: one or two end face of the crossbeam With the side out of plumb of crossbeam.
6. assembling type fence in concrete according to claim 5, it is characterised in that: the end face of the one end of the beam and crossbeam Side be in 45 degree of angles.
7. assembling type fence in concrete as claimed in any of claims 1 to 6, it is characterised in that: the column Lower end surface is equipped with more than two fixed columns, and the crossbeam is equipped with fixation hole corresponding with fixed column, and the fixed column is fixed In fixation hole.
8. assembling type fence in concrete according to claim 7, it is characterised in that: the fixed column is embedded in vertical for one end The main reinforcement of column end face is stretched out in bar planting or end in column, is equipped with fixing pipe in the fixation hole.
9. assembling type fence in concrete according to claim 7, it is characterised in that: the fixed column is inserted link, described solid Determine to be equipped with holding firmware in hole, the inserted link can be inserted into fixation hole and fix in fixation hole by holding firmware.
CN201822007271.6U 2018-11-29 2018-11-29 Assembling type fence in concrete Active CN209482822U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201822007271.6U CN209482822U (en) 2018-11-29 2018-11-29 Assembling type fence in concrete

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201822007271.6U CN209482822U (en) 2018-11-29 2018-11-29 Assembling type fence in concrete

Publications (1)

Publication Number Publication Date
CN209482822U true CN209482822U (en) 2019-10-11

Family

ID=68117571

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201822007271.6U Active CN209482822U (en) 2018-11-29 2018-11-29 Assembling type fence in concrete

Country Status (1)

Country Link
CN (1) CN209482822U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109296256A (en) * 2018-11-29 2019-02-01 袁雪峰 Assembling type fence in concrete and construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109296256A (en) * 2018-11-29 2019-02-01 袁雪峰 Assembling type fence in concrete and construction method

Similar Documents

Publication Publication Date Title
CN207194006U (en) A kind of prefabricated concrete retaining wall
CN106284655B (en) Precast concrete beam stud connects connecting node and connection method
CN103850363B (en) Prefabricated through hole assembly type reinforced concrete shear wall and construction method of prefabricated through hole assembly type reinforced concrete shear wall
CN105040829A (en) Prefabricated concrete main beam and secondary beam connecting structure and construction method thereof
CN103046463B (en) Assembly type saddle-shell-shaped bottom plate continuous box girder bridge and construction method thereof
CN208363404U (en) A kind of prefabricated panel and its connection structure
CN109763604A (en) A kind of central steel cast steel Special-Shaped Column
CN105298040A (en) Light assembly type stairway and construction method thereof
CN205875394U (en) Antidetonation concrete beam column that dry process is connected
CN103711232B (en) L-shaped frame component and lightweight concrete wall prefabricated type shear wall and connection construction method
CN105220792A (en) A kind of prefabricated concealed bracings energy-consuming shear wall and assemble method thereof
CN110409900A (en) Hybrid connection precast prestressed concrete circle warehouse structure
CN106284644B (en) A kind of residential architecture structural system and its method of construction suitable for industrialized production
CN206110331U (en) Prefabricated assembly building of lightweight steel construction lightweight concrete
CN203769116U (en) Prefabricated through hole assembly type reinforced concrete shear wall
CN209178792U (en) A kind of urban landscape bridge that setting Variable Section Steel structural ornament encircles
CN205531016U (en) Precast concrete post component and connected node
CN209482822U (en) Assembling type fence in concrete
CN206769200U (en) First wear formula post stretching vertical prestressing cast-in-place concrete rod structure
CN108086134A (en) A kind of assembled hollow steel pipe constrains armored concrete pillar height pier
CN103967129B (en) The coupled column assembled beam frame of built-in pipe high-strength concrete stem stem and constructional method thereof
CN107100322B (en) Post stretching vertical prestressing cast-in-place concrete rod structure and construction method
CN206396892U (en) Building block and building structure
CN206015882U (en) The steel structure of housing system that a kind of lateral resisting and antigravity separate
CN211815595U (en) Lower tower column tension and compression structure for cable tower

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20191012

Address after: Tongxing road 528400 Guangdong city of Zhongshan Province Dongsheng Town, No. 30

Patentee after: GUANGDONG SANHE PILES CO., LTD.

Address before: 434000 Jingzhou city of Hubei province Shashi Town Village two groups Cen Chen No. 370

Patentee before: Yuan Xue Feng

TR01 Transfer of patent right