Prior art keywords
arc groove
guan
tube coupling
pipe base
prefabricated pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201822170344.3U
Other languages
Chinese (zh)
Inventor
皇甫风雷
朱民
杨定锦
石银
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
YUTENG GROUP
Original Assignee
YUTENG GROUP
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by YUTENG GROUP filed Critical YUTENG GROUP
Priority to CN201822170344.3U priority Critical patent/CN209397622U/en
Application granted granted Critical
Publication of CN209397622U publication Critical patent/CN209397622U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Sewage (AREA)

Abstract

The utility model discloses a kind of Guan Ji for Pipe installing, comprising: prefabricated pipe base forms match with the outer circle wall of tube coupling and along the arc groove of the tube coupling being axially distributed thereon;It is at least a pair of for adjusting the elevation fine adjustment block of gap size between the tube coupling outer circle wall and the arc groove, it is symmetrically plugged on the prefabricated pipe base, and the adjustment hole for running through and being connected to the arc groove for the elevation fine adjustment block is formed on the prefabricated pipe base;And the restraint zone that the prefabricated pipe base and the tube coupling are tightened together;Wherein, formed in the elevation fine adjustment block one with the outer circle wall of the tube coupling against the straight plane of inclination.The Guan Ji for being used for Pipe installing has the advantages that structure is simple, lifting is convenient.

Description

A kind of Guan Ji for Pipe installing
Technical field
The utility model relates to pipe of concrete base technical fields, the more particularly, to Guan Ji of Pipe installing.
Background technique
The installation of road pipeline at present uses two methods: first is that using cast-in-place Guan Ji, the method for rear pipe laying; Second is that prefabricated Guan Ji is hung in foundation trench, then again hang in pipeline in foundation trench and is installed to the method on Guan Ji.Method one Although the method for cast-in-place Guan Ji can achieve the purpose that supporting pipeline in, still have following problem: cast-in-place pipe base needs Formwork supporting plate at the construction field (site), armored concrete also needs to arrange reinforcing bar, thus increases the workload of construction site, the duration compared with It is long.In method two after first installing pipe base pipe laying method, increase the number of lifting, work efficiency is relatively low, and in pipeline The Guan Ji that damages is easy during lifting, in addition, whole installation process is implemented in foundation trench, increase worker working strength and Security risk coefficient, therefore, it is necessary to study a kind of Guan Ji for Pipe installing.
Utility model content
Shortcoming present in view of the above technology, the utility model provide it is a kind of be easy to lift for pipeline pacify The Guan Ji of dress.
The technical scheme adopted by the utility model to solve the technical problem is as follows: a kind of Guan Ji for Pipe installing, packet Include: prefabricated pipe base forms match with the outer circle wall of tube coupling and along the arc groove of the tube coupling being axially distributed thereon;Extremely It is few a pair of for adjusting the elevation fine adjustment block of gap size between the tube coupling outer circle wall and the arc groove, symmetrically plug On the prefabricated pipe base, is formed on the prefabricated pipe base and run through for the elevation fine adjustment block and be connected to the arc groove Adjustment hole;And the restraint zone that the prefabricated pipe base and the tube coupling are tightened together;Wherein, in the elevation fine adjustment block Form one with the outer circle wall of the tube coupling against the straight plane of inclination.
Preferably, dead ring is fixedly installed on the prefabricated pipe base, the dead ring is located at the opposite of the arc groove Two sides, the restraint zone are arranged on the prefabricated pipe base by the dead ring.
Preferably, the quantity of the elevation fine adjustment block is set as 4, and the elevation fine adjustment block is symmetricly set on the arc two-by-two The two sides of shape slot.
Preferably, the elevation fine adjustment block is square long cylinder, and the adjustment hole is square hole.
Preferably, it is formed on the arc cell wall of the arc groove convenient for being in the milk between the tube coupling and the arc groove Grout groove, the grout groove along the tube coupling circumferencial direction be distributed.
Preferably, be fixedly installed on the one end of the prefabricated pipe base several reinforcing rods, on opposite the other end at Type has a pair of of grout hole, wherein the reinforcing rod is symmetrically distributed in the two sides of the arc groove, and the grout hole is symmetrically distributed in The two sides of the arc groove also offer the preformed hole being connected to the grout hole on the prefabricated pipe base vertically, described reserved Hole is also symmetrically distributed in the two sides of the arc groove.
Preferably, one is also formed on the end of the grout hole for accommodating the annular groove of sealing joint strip.
Preferably, the groove depth of the annular groove is 5mm.
The utility model compared with prior art, the beneficial effect is that: it is provided by the utility model for Pipe installing Guan Ji can be by prefabricated pipe base and tube coupling together by once lifting by fastening band connection between prefabricated pipe base and tube coupling Hang in foundation trench, have the advantages that structure is simple, lifting is convenient, and can be avoided in hoisting process tube coupling and prefabricated pipe base it Between collision, effectively protect tube coupling and prefabricated pipe base;Elevation fine adjustment block on prefabricated pipe base can adjust tube coupling excircle Gap size between wall and arc groove, effectively raises construction precision;Hollow tube sheet can effectively mitigate prefabricated pipe base Self weight, effectively saved resource.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the main view direction of the Guan Ji described in the utility model for Pipe installing;
Fig. 2 is the structural schematic diagram of the side-looking direction of the Guan Ji described in the utility model for Pipe installing;
Fig. 3 is the structural schematic diagram of the overlook direction of the Guan Ji described in the utility model for Pipe installing;
Fig. 4 is the positional diagram between the prefabricated pipe base of the utility model and tube coupling;
Fig. 5 is the structural schematic diagram of the elevation fine adjustment block of the utility model.
In figure: 10, prefabricated pipe base;11, arc groove;111, grout groove;12, adjustment hole;13, grout hole;131, annular is recessed Slot;14, reinforcing rod;15, preformed hole;20, restraint zone;30, dead ring;40, elevation fine adjustment block;41, straight plane is tilted;50, it manages Section;60, hollow tube sheet;70, hanging ring.
Specific embodiment
The following describes the utility model in further detail with reference to the accompanying drawings, to enable those skilled in the art referring to explanation Book text can be implemented accordingly.
As shown in Figures 1 to 5, the utility model provides a kind of Guan Ji for Pipe installing, comprising: prefabricated pipe base 10, it forms matched with the outer circle wall of tube coupling 50 and along the arc groove 11 of the tube coupling 50 being axially distributed thereon;At least A pair is symmetrical for adjusting the elevation fine adjustment block 40 of gap size between 50 outer circle wall of tube coupling and the arc groove 11 Be plugged on the prefabricated pipe base 10, formed on the prefabricated pipe base 10 for the elevation fine adjustment block 40 run through and with the arc The adjustment hole 12 that shape slot 11 is connected to;And the restraint zone 20 that the prefabricated pipe base 10 and the tube coupling 50 are tightened together; Wherein, formed in the elevation fine adjustment block 40 one with the outer circle wall of the tube coupling 50 against the straight plane 41 of inclination.
As an embodiment of this programme, as shown in Figure 1, being fixedly installed dead ring 30, institute on the prefabricated pipe base 10 The opposite two sides that dead ring 30 is located at the arc groove 11 are stated, the restraint zone 20 is arranged by the dead ring 30 described pre- On tubulation base 10, specifically, one end of the restraint zone 20 ties up on dead ring 30 described in side, the other end bypasses the tube coupling It is tied up to after 50 on dead ring 30 described in the other side, it, can will be described after the prefabricated pipe base 10 and the tube coupling 50 are embedded to foundation trench Restraint zone 20 is taken off from the dead ring 30 to realize recycling.
As an embodiment of this programme, as depicted in figs. 1 and 2, the quantity of the elevation fine adjustment block 40 is set as 4, institute State the two sides that elevation fine adjustment block 40 is symmetricly set on the arc groove 11 two-by-two.
As an embodiment of this programme, as depicted in figs. 1 and 2, the elevation fine adjustment block 40 is square long cylinder, described Adjustment hole 12 is square hole.
As an embodiment of this programme, as shown in figure 3, being formed on the arc cell wall of the arc groove 11 convenient in institute State the grout groove 111 being in the milk between tube coupling 50 and the arc groove 11, the grout groove 111 along the tube coupling 50 circumference side To distribution.
As an embodiment of this programme, as shown in Figures 2 and 3, it is fixedly installed on the one end of the prefabricated pipe base 10 There are several reinforcing rods 14, form a pair of of grout hole 13 on opposite the other end, wherein the reinforcing rod 14 is symmetrically distributed in The two sides of the arc groove 11, the grout hole 13 are symmetrically distributed in the two sides of the arc groove 11, on the prefabricated pipe base 10 The preformed hole 15 being connected to the grout hole 13 is also offered vertically, and the preformed hole 15 is also symmetrically distributed in the arc groove 11 Two sides.
As an embodiment of this programme, as shown in Fig. 2, also forming one on the end of the grout hole 13 for accommodating The annular groove 131 of sealing joint strip.
As an embodiment of this programme, the groove depth of the annular groove 131 is 5mm.
As an embodiment of this programme, as shown in Fig. 2, being also preset on the prefabricated pipe base 10 several along its axial direction point The hollow tube sheet 60 of cloth.
As an embodiment of this programme, hanging ring 70 is further fixedly arranged on the prefabricated pipe base 10.
Although the embodiments of the present invention have been disclosed as above, it is not limited in institute in specification and embodiments Column use, it can be applied to various fields suitable for the present invention completely, for those skilled in the art, can Easily realize other modification, therefore without departing from the general concept defined in the claims and the equivalent scope, this is practical It is novel to be not limited to specific details and legend shown and described herein.

Claims (8)

1. a kind of Guan Ji for Pipe installing characterized by comprising
Prefabricated pipe base (10) forms match with the outer circle wall of tube coupling (50) and along the axial direction of the tube coupling (50) point thereon The arc groove (11) of cloth;
At least a pair of elevation for adjusting gap size between the tube coupling (50) outer circle wall and the arc groove (11) is micro- Adjustable block (40) is symmetrically plugged on the prefabricated pipe base (10), is formed on the prefabricated pipe base (10) micro- for the elevation The adjustment hole (12) that adjustable block (40) runs through and is connected to the arc groove (11);And
So that the restraint zone (20) that the prefabricated pipe base (10) and the tube coupling (50) tighten together;
Wherein, formed on the elevation fine adjustment block (40) one with the outer circle wall of the tube coupling (50) against the straight plane of inclination (41).
2. being used for the Guan Ji of Pipe installing as described in claim 1, which is characterized in that fixation is set on the prefabricated pipe base (10) It is equipped with dead ring (30), the dead ring (30) is located at the opposite two sides of the arc groove (11), and the restraint zone (20) passes through The dead ring (30) is arranged on the prefabricated pipe base (10).
3. being used for the Guan Ji of Pipe installing as described in claim 1, which is characterized in that the quantity of the elevation fine adjustment block (40) 4 are set as, the elevation fine adjustment block (40) is symmetricly set on the two sides of the arc groove (11) two-by-two.
4. being used for the Guan Ji of Pipe installing as described in claim 1, which is characterized in that the elevation fine adjustment block (40) is square Long cylinder, the adjustment hole (12) are square hole.
5. being used for the Guan Ji of Pipe installing as described in claim 1, which is characterized in that the arc cell wall of the arc groove (11) On form convenient for the grout groove (111) that is in the milk between the tube coupling (50) and the arc groove (11), the grout groove (111) it is distributed along the circumferencial direction of the tube coupling (50).
6. being used for the Guan Ji of Pipe installing as described in claim 1, which is characterized in that the one end of the prefabricated pipe base (10) On be fixedly installed several reinforcing rods (14), form a pair of of grout hole (13) on opposite the other end, wherein the reinforcing bar Item (14) is symmetrically distributed in the two sides of the arc groove (11), and the grout hole (13) is symmetrically distributed in the arc groove (11) Two sides also offer the preformed hole (15) being connected to the grout hole (13) on the prefabricated pipe base (10) vertically, described reserved Hole (15) is also symmetrically distributed in the two sides of the arc groove (11).
7. being used for the Guan Ji of Pipe installing as claimed in claim 6, which is characterized in that on the end of the grout hole (13) also One is formed for accommodating the annular groove (131) of sealing joint strip.
8. being used for the Guan Ji of Pipe installing as claimed in claim 7, which is characterized in that the groove depth of the annular groove (131) For 5mm.
CN201822170344.3U 2018-12-24 2018-12-24 A kind of Guan Ji for Pipe installing Expired - Fee Related CN209397622U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201822170344.3U CN209397622U (en) 2018-12-24 2018-12-24 A kind of Guan Ji for Pipe installing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201822170344.3U CN209397622U (en) 2018-12-24 2018-12-24 A kind of Guan Ji for Pipe installing

Publications (1)

Publication Number Publication Date
CN209397622U true CN209397622U (en) 2019-09-17

Family

ID=67895764

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201822170344.3U Expired - Fee Related CN209397622U (en) 2018-12-24 2018-12-24 A kind of Guan Ji for Pipe installing

Country Status (1)

Country Link
CN (1) CN209397622U (en)

Similar Documents

Publication Publication Date Title
CN209397622U (en) A kind of Guan Ji for Pipe installing
CN206874969U (en) Concrete pump pipe fixing device
CN106149744A (en) Pile foundation steel bar cage skeletal support device and construction method
CN206971689U (en) Support operating platform that is detachable and recycling
CN201627200U (en) Blockage-slurry strengthening earth anchor
CN209397623U (en) A kind of Guan Ji of water supply drainage pipeline
CN204038921U (en) Super High tower crane wall-attaching equipment
CN207435906U (en) For the bracket of bridge construction
CN206360720U (en) A kind of novel flexible filling isolation barricade
CN202467152U (en) Clamp type embedded part structure of shape steel overhanging scaffold
CN206071075U (en) A kind of Steel Structure Installation line-up clamp
CN205975610U (en) Insert precast pile anchor clamps
CN107152026B (en) A kind of the mud jacking pipe support and its distribution method of steel-pipe pile
CN103498685A (en) Retaining and protecting device for pressure relief windows of base plate and two edges of extremely soft rock roadway
CN209780303U (en) Face limit guard bar and face limit protective screen
CN207314348U (en) A kind of fixed structure of flare template
CN201217249Y (en) Prestressed concrete side-assist press enhancement type precast pile steel form
CN211973565U (en) City utility tunnel dowel steel fixing device
CN102720288A (en) Method for connecting solderless curtain wall dry pendant
CN205476507U (en) Inside pump line fixing device of jacking platform
CN204825954U (en) A subassembly for being directed at hoop prestressing force is applyed to basic connection of fan
CN204326495U (en) A kind of structure of tool-type anchored end of Overhanging Outside Scaffold section steel beam
CN214091025U (en) Concrete wall straightness controlling means that draws to one side that hangs down
CN105114707B (en) The fixed structure of roofing equipment pipe
CN107352386A (en) The simple lifting tool and its application method of steel structural roof combined hanging

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190917

CF01 Termination of patent right due to non-payment of annual fee