CN209368809U - It is a kind of suitable for mixed mud tubular pole, the prefabricated pile cover of steel-pipe pile - Google Patents
It is a kind of suitable for mixed mud tubular pole, the prefabricated pile cover of steel-pipe pile Download PDFInfo
- Publication number
- CN209368809U CN209368809U CN201822227696.8U CN201822227696U CN209368809U CN 209368809 U CN209368809 U CN 209368809U CN 201822227696 U CN201822227696 U CN 201822227696U CN 209368809 U CN209368809 U CN 209368809U
- Authority
- CN
- China
- Prior art keywords
- pile cover
- ontology
- tubular pole
- pile
- steel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
The utility model relates to one kind to be suitable for mixed mud tubular pole, the prefabricated pile cover of steel-pipe pile, including pile cover ontology and tubular pole ontology, the inside of the pile cover ontology is respectively arranged with connecting column and connecting cylinder, pile cover ontology is socketed at the top of the tubular pole ontology, and the middle position of pile cover body bottom portion is provided with the connecting column with tubular pole ontology internal diameter interference fit, it is evenly arranged on the outside of the connecting column and the mutually matched annular fixture block of annular slot, pile cover body bottom portion on the outside of the connecting column is provided with connecting cylinder, and the inside of connecting cylinder is evenly arranged with ring stiffener, the pile cover ontology is internally provided with rectangular steel reinforcement cage, the pile cover outer body is fixed with tilted block, connectivity of the utility model between increase pile cover ontology and tubular pole ontology, to promote the stability between tubular pole pile cover, it is convenient to pipe simultaneously It constructs between stake pile cover, it is easy to use, increase the intensity of pile cover ontology, improves the service life of pile cover ontology.
Description
Technical field
The utility model relates to tubular pole pile cover technical field, it is specially a kind of suitable for mixed mud tubular pole, steel-pipe pile it is pre-
Pile cover processed.
Background technique
Tubular pole pile cover is a kind of building prefabricated components, can be big using tubular pole pile cover for traditional site operation
It is big to improve speed of application, the amount of labour of construction worker is reduced, improves construction quality, but existing tubular pole pile cover has connection not
Securely, installation is complicated, and difficulty of construction is high, cannot connect well with top concrete slab, and be not connected firmly, and stability is poor,
Strength and stiffness are low.
Existing tubular pole pile cover be it is simple pile cover is covered into tubular pole, thus being not connected firmly between tubular pole pile cover,
It is inconvenient for use simultaneously to influence the stabilization of tubular pole pile cover, while installation of the inconvenience to tubular pole pile cover during construction,
The contact area of pile cover and top concrete can not be increased in use, to reduce tubular pole pile cover and top concrete
Stability.
Utility model content
The purpose of this utility model is to provide a kind of suitable for mixed mud tubular pole, the prefabricated pile cover of steel-pipe pile, to solve
Existing tubular pole pile cover mentioned above in the background art be it is simple pile cover is covered into tubular pole, thus between tubular pole pile cover
It is not connected firmly, while to influence the stabilization of tubular pole pile cover, while peace of the inconvenience to tubular pole pile cover during construction
Dress, it is inconvenient for use, the contact area of pile cover and top concrete can not be increased in use, to reduce tubular pole pile cover
With the stability problem of top concrete.
To achieve the above object, the utility model provides the following technical solutions:
It is a kind of suitable for mixed mud tubular pole, the prefabricated pile cover of steel-pipe pile, including pile cover ontology and tubular pole ontology, the stake
The inside of cap ontology is respectively arranged with connecting column and connecting cylinder, is evenly arranged with annular snap on the inner wall of tubular pole ontology one end
Slot, the outside setting of the tubular pole ontology are socketed with pile cover at the top of the tubular pole ontology there are four mutual corresponding limiting slot
Ontology, and the middle position of pile cover body bottom portion is provided with the connecting column with tubular pole ontology internal diameter interference fit, the connection
It is evenly arranged on the outside of column and is set with the mutually matched annular fixture block of annular slot, the pile cover body bottom portion on the outside of the connecting column
It is equipped with connecting cylinder, and the inside of connecting cylinder is evenly arranged with ring stiffener, on the connecting cylinder at the limit groove location uniformly
Be provided with the mutually matched limited bolt of limiting slot, and one end of limited bolt extends to the inside of limiting slot, and the annular is reinforced
Pile cover body bottom portion two sides on the outside of muscle are all equipped with upgrading slot, and the pile cover ontology is internally provided with rectangular steel reinforcement cage, described
Pile cover outer body is fixed with tilted block, and extending column, and the centre of extending column are evenly arranged at the top of the pile cover ontology
Connection ring is all provided at position, the top of the extending column is equipped with and barb-shaped link block.
Preferably, integral structure made of the pile cover ontology and tubular pole ontology are all poured by concrete.
Preferably, the through-hole with limited bolt interference fit is all provided on the connecting cylinder at the limited bolt position.
Preferably, the inside of the rectangular steel reinforcement cage passes through transverse steel respectively and is welded to each other with longitudinal reinforcement.
Preferably, the tilted block is in upside-down trapezoid structure distribution, increases the contact area between pile cover ontology and ground,
To increase the stabilization between pile cover ontology and ground.
Compared with prior art, the utility model has the beneficial effects that
One, the prefabricated pile cover for being suitable for mixed mud tubular pole, steel-pipe pile of the utility model, by tubular pole ontology one end
Inner wall on be uniformly arranged annular slot, and four mutual corresponding limiting slots are set in the outside of tubular pole ontology, and in tubular pole
The top of ontology is socketed pile cover ontology, and the middle position setting of pile cover body bottom portion and tubular pole ontology internal diameter interference fit
Connecting column, and be uniformly arranged on the outside of connecting column with the mutually matched annular fixture block of annular slot, and on the outside of connecting column
Connecting cylinder is arranged in pile cover body bottom portion, and is uniformly arranged and the mutually matched limit of limiting slot on the connecting cylinder at limit groove location
Position bolt, and one end of limited bolt extends to the inside of limiting slot, convenient for increasing the connectivity between pile cover ontology and tubular pole ontology,
To promote the stability between tubular pole pile cover, while conveniently constructing between tubular pole pile cover, it is easy to use.
Two, the prefabricated pile cover for being suitable for mixed mud tubular pole, steel-pipe pile of the utility model, by the inside of connecting cylinder
It is uniformly arranged ring stiffener, and rectangular steel reinforcement cage is set in the inside of pile cover ontology, and the inside of rectangular steel reinforcement cage leads to respectively
It crosses transverse steel to be welded to each other with longitudinal reinforcement, convenient for increasing the intensity of pile cover ontology, that improves pile cover ontology uses the longevity
Life.
Three, the prefabricated pile cover for being suitable for mixed mud tubular pole, steel-pipe pile of the utility model, by pile cover outer body
Constant tilt block, and tilted block be in upside-down trapezoid structure distribution, convenient for increase pile cover ontology and ground contact area, improve
Stability between tubular pole pile cover.
Four, the prefabricated pile cover for being suitable for mixed mud tubular pole, steel-pipe pile of the utility model, by the top of pile cover ontology
Portion is uniformly arranged extending column, and connection ring is all arranged in the middle position of extending column, and in the setting of the top of extending column and hangnail
Shape link block, convenient for increasing the contact area of pile cover ontology and top concrete, to increase the stability in pipe pile crown portion.
Detailed description of the invention
Fig. 1 is the whole interior structural schematic diagram of the utility model;
Fig. 2 is the integral outer structural schematic diagram of the utility model.
In figure: 1- connecting column, 2- annular slot, 3- limiting slot, 4- annular fixture block, 5- upgrading slot, 6- pile cover ontology, the side 7-
Shape steel reinforcement cage, 8- extending column, 9- connection ring, 10- barb-shaped link block, 11- tilted block, 12- ring stiffener, 13- limited bolt,
14- connecting cylinder, 15- tubular pole ontology.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model
Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole
Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work
Every other embodiment obtained, fall within the protection scope of the utility model.
As depicted in figs. 1 and 2 is a kind of suitable for mixed mud tubular pole, the prefabricated pile cover of steel-pipe pile, including pile cover ontology 6
With tubular pole ontology 15, the inside of pile cover ontology 6 is respectively arranged with connecting column 1 and connecting cylinder 14, the inner wall of 15 one end of tubular pole ontology
On be evenly arranged with annular slot 2, there are four mutual corresponding limiting slot 3, tubular pole ontologies 15 for the outside setting of tubular pole ontology 15
Top be socketed with pile cover ontology 6, and the middle position of 6 bottom of pile cover ontology is provided with and matches with the 15 internal diameter interference of tubular pole ontology
The connecting column 1 of conjunction, the outside of connecting column 1 are evenly arranged with and the mutually matched annular fixture block 4 of annular slot 2,1 outside of connecting column
6 bottom of pile cover ontology be provided with connecting cylinder 14, and the inside of connecting cylinder 14 is evenly arranged with ring stiffener 12, limiting slot 3
Be evenly arranged on connecting cylinder 14 at position with the mutually matched limited bolt 13 of limiting slot 3, and limited bolt 13 one end extend
To the inside of limiting slot 3,6 two sides of the bottom of pile cover ontology in 12 outside of ring stiffener are all equipped with upgrading slot 5, pile cover ontology 6
It is internally provided with rectangular steel reinforcement cage 7,6 outside of pile cover ontology is fixed with tilted block 11, and the top of pile cover ontology 6 is evenly arranged with
Extending column 8, and the middle position of extending column 8 is all provided with connection ring 9, the top of extending column 8 is equipped with and barb-shaped link block
10。
In the present invention, integral structure made of pile cover ontology 6 and tubular pole ontology 15 are all poured by concrete, limit
The through-hole being interference fitted with limited bolt 13, the inner part of rectangular steel reinforcement cage 7 are all provided on connecting cylinder 14 at 13 position of bolt of position
It is not welded to each other by transverse steel and longitudinal reinforcement, tilted block 11 is in upside-down trapezoid structure distribution.
The working principle of the utility model are as follows: tubular pole ontology 15 is embedded in specified location in advance first, then logical
The clamping jaw crossed on loop wheel machine hooks upgrading slot 5 to lift by crane pile cover ontology 6, then by pile cover ontology 6 and tubular pole ontology 15
It is socketed, to connecting column 1 be extended among the internal diameter of tubular pole ontology 15, by between annular slot 2 and annular fixture block 4
Mutual cooperation be clamped, increase the compactness between connecting column 1 and tubular pole ontology 15, then connect passing through limited bolt 13
Through-hole in connect cylinder 14, and extend to inside limiting slot 3, to increase the contact between connecting cylinder 14 and tubular pole ontology 15, mention
Stability between high pile cover ontology 6 and tubular pole ontology 15, while conveniently being applied between pile cover ontology 6 and tubular pole ontology 15
Work, while tilted block tilted block 11 is in upside-down trapezoid structure distribution, increases the contact area between pile cover ontology 6 and ground, from
And increase the stabilization between pile cover ontology 6 and ground, it, can be by prolonging between extending column 8 and connection ring 9 during construction
Inside concrete is extended to, to increase the contact area that pile cover ontology 6 and top concrete carry out, increase pile cover ontology 6 and mix
Stability between solidifying soil, while by contacting with each other between barb-shaped link block 10 and concrete, to increase pile cover ontology 6
Fastness is carried out with concrete, it during use, can be by being welded to each other by transverse steel and longitudinal reinforcement into side
Ring stiffener 12 inside shape steel reinforcement cage 7 and connecting cylinder 14 improves its safety to increase the whole intensity of pile cover ontology 6
Can, increase service life.
The above descriptions are merely preferred embodiments of the present invention, is not intended to limit the utility model, although ginseng
The utility model is described in detail according to previous embodiment, it for those skilled in the art, still can be with
It modifies the technical solutions described in the foregoing embodiments or equivalent replacement of some of the technical features, it is all
Within the spirit and principles of the present invention, any modification, equivalent replacement, improvement and so on should be included in practical
Within novel protection scope.
Claims (5)
1. a kind of suitable for mixed mud tubular pole, the prefabricated pile cover of steel-pipe pile, including pile cover ontology (6) and tubular pole ontology (15), institute
The inside for stating pile cover ontology (6) is respectively arranged with connecting column (1) and connecting cylinder (14), it is characterised in that: the tubular pole ontology
(15) it is evenly arranged on the inner wall of one end annular slot (2), there are four mutually right for the outside setting of the tubular pole ontology (15)
The limiting slot (3) answered is socketed with pile cover ontology (6) at the top of the tubular pole ontology (15), and the centre of pile cover ontology (6) bottom
It is provided with the connecting column (1) with tubular pole ontology (15) internal diameter interference fit at position, is uniformly arranged on the outside of the connecting column (1)
Have and is provided with annular slot (2) mutually matched annular fixture block (4), pile cover ontology (6) bottom on the outside of the connecting column (1)
Connecting cylinder (14), and the inside of connecting cylinder (14) is evenly arranged with ring stiffener (12), the company at limiting slot (3) position
Be evenly arranged in connect cylinder (14) with limiting slot (3) mutually matched limited bolt (13), and one end of limited bolt (13) extends to
The inside of limiting slot (3), pile cover ontology (6) two sides of the bottom on the outside of the ring stiffener (12) are all equipped with upgrading slot (5), institute
Being internally provided with rectangular steel reinforcement cage (7) for pile cover ontology (6) is stated, is fixed with tilted block (11) on the outside of the pile cover ontology (6),
It is evenly arranged with extending column (8) at the top of the pile cover ontology (6), and the middle position of extending column (8) is all provided with connection
The top of ring (9), the extending column (8) is equipped with and barb-shaped link block (10).
2. a kind of suitable for mixed mud tubular pole, the prefabricated pile cover of steel-pipe pile according to claim 1, it is characterised in that: described
Integral structure made of pile cover ontology (6) and tubular pole ontology (15) are all poured by concrete.
3. a kind of suitable for mixed mud tubular pole, the prefabricated pile cover of steel-pipe pile according to claim 1, it is characterised in that: described
The through-hole with limited bolt (13) interference fit is all provided on connecting cylinder (14) at limited bolt (13) position.
4. a kind of suitable for mixed mud tubular pole, the prefabricated pile cover of steel-pipe pile according to claim 1, it is characterised in that: described
The inside of rectangular steel reinforcement cage (7) passes through transverse steel respectively and is welded to each other with longitudinal reinforcement.
5. a kind of suitable for mixed mud tubular pole, the prefabricated pile cover of steel-pipe pile according to claim 1, it is characterised in that: described
Tilted block (11) is in upside-down trapezoid structure distribution.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201822227696.8U CN209368809U (en) | 2018-12-27 | 2018-12-27 | It is a kind of suitable for mixed mud tubular pole, the prefabricated pile cover of steel-pipe pile |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201822227696.8U CN209368809U (en) | 2018-12-27 | 2018-12-27 | It is a kind of suitable for mixed mud tubular pole, the prefabricated pile cover of steel-pipe pile |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209368809U true CN209368809U (en) | 2019-09-10 |
Family
ID=67827913
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201822227696.8U Expired - Fee Related CN209368809U (en) | 2018-12-27 | 2018-12-27 | It is a kind of suitable for mixed mud tubular pole, the prefabricated pile cover of steel-pipe pile |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209368809U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112832230A (en) * | 2021-02-25 | 2021-05-25 | 贺好 | Anti-sinking building concrete pipe pile and installation method |
CN113089646A (en) * | 2021-04-15 | 2021-07-09 | 上海工程技术大学 | Concrete combined pile and manufacturing method thereof |
-
2018
- 2018-12-27 CN CN201822227696.8U patent/CN209368809U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112832230A (en) * | 2021-02-25 | 2021-05-25 | 贺好 | Anti-sinking building concrete pipe pile and installation method |
CN113089646A (en) * | 2021-04-15 | 2021-07-09 | 上海工程技术大学 | Concrete combined pile and manufacturing method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN209368809U (en) | It is a kind of suitable for mixed mud tubular pole, the prefabricated pile cover of steel-pipe pile | |
CN208072776U (en) | Connect the upset locking type concrete component joint structure of end bar | |
CN205895507U (en) | A tower section of thick bamboo and fan | |
CN207419232U (en) | A kind of traffic bridge column | |
CN208718219U (en) | A kind of steel-structured circular tubing string | |
CN208430851U (en) | A kind of steel tube concrete column feet node | |
CN208363078U (en) | A kind of assembled steel pile cover | |
CN203008391U (en) | Reversed T-shaped hoisting connecting piece for prefabricated part hoisting | |
CN109457868A (en) | A kind of steel tube concrete column feet node and its construction method | |
CN213204094U (en) | Simple to operate's steel reinforcement cage | |
CN210340091U (en) | Column main reinforcement hoisting tool of concrete cast-in-place steel rib column | |
CN208251085U (en) | A kind of building engineering construction prestress pulling resistant pilework | |
CN211850258U (en) | Steel construction prefabricated assembly formula floor | |
CN216195503U (en) | Metal embedded part capable of uniformly dispersing pressure | |
CN207959893U (en) | The operation platform of wind power tower | |
CN202482854U (en) | Pure mechanical connection structure between piles | |
CN206545389U (en) | A kind of side template fixing device for building outer beams | |
CN202689531U (en) | Flexible and retractable climbing shuttering system for single-cylinder-body structure | |
CN206752496U (en) | A kind of communications tower steel structure base | |
CN215702616U (en) | Pin hoisting ring device | |
CN211523186U (en) | Prestressed concrete hollow pipe pile | |
CN205276255U (en) | Reinforcing bar cage for building | |
CN109505304A (en) | A kind of permafrost soil area assembled type base for power transmission line iron tower prefab-form | |
CN214245335U (en) | Arch bridge pier fixing equipment | |
CN210340266U (en) | A simple and easy type auxiliary construction dolly for settling concrete drainage ditch apron |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190910 Termination date: 20201227 |