CN209356493U - High gradient slope soil erosion Field simulation test macro - Google Patents

High gradient slope soil erosion Field simulation test macro Download PDF

Info

Publication number
CN209356493U
CN209356493U CN201822036763.8U CN201822036763U CN209356493U CN 209356493 U CN209356493 U CN 209356493U CN 201822036763 U CN201822036763 U CN 201822036763U CN 209356493 U CN209356493 U CN 209356493U
Authority
CN
China
Prior art keywords
test
runoff
test material
soil erosion
high gradient
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201822036763.8U
Other languages
Chinese (zh)
Inventor
李永红
高照良
唐林
牛耀斌
娄永才
齐星园
李玉亭婷
武可心
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Northwest A&F University
Original Assignee
Northwest A&F University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Northwest A&F University filed Critical Northwest A&F University
Priority to CN201822036763.8U priority Critical patent/CN209356493U/en
Application granted granted Critical
Publication of CN209356493U publication Critical patent/CN209356493U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The utility model discloses high gradient slope soil erosion high gradient slope soil erosion Field simulation test macros, including energy dissipating water system, test material fill system, runoff and sediment collection system.Energy dissipating water system by forebay, baffle wall style, cross the mouth of a river, after-bay and the buffer area section that discharges water form, which is located at the most top section of test macro, and before the system main function is washes away, the water flows gently, even into test material fill system;Test material fill system immediately energy dissipating drainage system, by abutment wall, raw material compacting zone, test material filling area, infiltrate testing tube, test section mark line forms, be the area Po Duan of entire test macro;Runoff and sediment collection system is located at the end of test material fill system, is made of divider wall, trigonum, runoff bucket, runoff bucket pedestal, valve, drainage ditch, is the lowermost end of whole system.

Description

High gradient slope soil erosion Field simulation test macro
Technical field
The utility model relates to a kind of high gradient slope soil erosion Field simulation test macros, specifically, being related to one kind Measure the high gradient slope soil erosion Field simulation test macro of engineering accumulation body high gradient slope soil erosion.
Background technique
The main reason for engineering accumulation body soil erosion intensity is big, and harm is serious, prediction is difficult and Control Technology lags Be constitute accumulation body slope underlying surface component it is loose, and the gradient is big, and laws of soil erosion is totally different with sloping upland, biography No matter the indoor simulation runoff plots of system are difficult to meet the requirements in length of grade, the gradient and precision aspect, and urgent need establishes Field simulation height Its loss process and Hydrodynamic Parameters are probed into gradient slope runoff plots, to push engineering accumulation body high gradient slope erosion mechanism It discloses and Control Technology correlative study works.
Utility model content
The purpose of the utility model is to provide a kind of high gradient slope soil erosion Field simulation test macros, mainly by Energy dissipating water system, test material filling system, runoff and sediment collection system three parts composition, the either precipitous journey of slope surface The gradation nonuniformity coefficient and coefficient of curvature etc. of degree or filler are to initiate both at home and abroad, have novelty.
Its technical solution is as follows:
A kind of high gradient slope soil erosion Field simulation test macro, including energy dissipating water system 1, test material filling system System 2, runoff and sediment collection system 3.The energy dissipating water system 1, test material fill system 2, runoff and sediment collection system 3 by Height is sequentially connected to low.Energy dissipating water system 1 by forebay 4, baffle wall style 5, cross the mouth of a river 6, after-bay 7 and buffer area 8 from the front to the back according to Secondary composition.Test material fill system 2 by abutment wall 9, test material filling area 10, raw material compacting zone 11, infiltrate testing tube 12, It tests section mark line 13 to form, test material filling area 10 is located on raw material compacting zone 11, and it is embedding to infiltrate testing tube 12 In in test material filling area 10, abutment wall 9 is the outer boundary of test material filling area 10.Runoff and sediment collection system 3 is by being isolated Wall 14, trigonum 15, runoff bucket 17, drainage ditch 18 from top to bottom successively form, and valve 20, drainage ditch are installed in 17 bottom of runoff bucket 18 are located in runoff bucket pedestal 16, the 20 face drainage ditch 18 of valve of 17 bottom of runoff bucket.
Energy dissipating water system 1 is located at the most top section of entire test macro, which is before washing away, by disappearing After energy, the water flows gently even into test material fill system 2.The filling of test material fill system 2 is backfilled according to test request Test material, filling thickness are controlled according to the height of vertical slope surface, and the reality of test macro is disposed in test material filling area 10 When test section equipment, material pile set terminal connects runoff and sediment collection system 3.It uses the trigonum 15 of runoff and sediment collection system 3 To collect the bed load sediment for being easy to precipitate of test material filling area 10, delay is played for the part silt that slope surface generates and is made With;Barricade 21 is located at the front end of the lowermost end of trigonum 15, afflux bucket 17, plays the role of protecting afflux bucket 17;Afflux bucket 17 to collect based on suspended sediment, and afflux bucket 17 is arranged by step, plays the function of collection, sedimentation, test, is located at entire survey The least significant end of test system.
Further preferably, buffer area is filled with Extra-fine sand, the fluid-tight smooth plate 19 in surface, is placed in the table of filling sand Face, with the smooth drop-over of test material fill area top end surface.The compactness of raw material compacting zone is greater than the test material on top Compactness, permeability is less than top test material can be between test material and raw material material if cannot reach requirement Arrange water barrier device.
Further, the arrangement for infiltrating testing tube 12 must be according to quincuncial arrangement, so as to measure test material Different parts and depth infiltrate situation.Infiltrating testing tube must be using the tubing thin and transparent with certain intensity, caliber Such as organic glass, the diameter of pipe is generally relatively carefully not more than 2.5mm, is conducive to the accuracy for just improving test.In placement testing tube When, engaged test material end blocks nozzle using non-woven wraps filter material, to prevent particulate from entering testing tube, blocks pipeline. It is infiltrating in testing tube 12, at distance blocking end 2cm, is filling 5~10mm colored liquid oil column, be accurately to calculate to infiltrate Number.For the divider wall of trigonum and packing material, it is necessary to play the role of antiseepage.It trigonum must be with test material fill area light Sliding, drop-over, being conducive to runoff and sediment can smoothly enter into trigonum.
The utility model has the beneficial effects that
The advantages of this experimental design is improved is to overcome field trial observed result to be difficult to disadvantage that is timely, accurately obtaining End;Interior is overcome to be difficult to meet the requirement for height of high gradient slope;Be conducive to the artificial control to different factors, realize to Dan Yin Element causes the Accurate Analysis of soil losses;It by runoff and infiltrates test and combines, be conducive to the height soil erosion of side slope origin cause of formation Factor coupling analysis.
Detailed description of the invention
Fig. 1 is high gradient slope soil erosion Field simulation test macro plan view;
Fig. 2 is high gradient slope soil erosion Field simulation test macro profilograph;
Fig. 3 is high gradient slope soil erosion Field simulation test macro drawing in side sectional elevation.
Specific embodiment
The technical solution of the utility model is described in more detail with reference to the accompanying drawings and detailed description.
Referring to Fig.1~3, a kind of high gradient slope soil erosion Field simulation test macro, including energy dissipating water system, test Material-filled system, runoff and sediment collection system.Energy dissipating water system is discharged water a section group by forebay, baffle wall style, after-bay and buffer area At the system is located at the most top section of test macro, which is before washing away, and after energy dissipating, the water flows gently, It is even to enter test material fill system;Test material fill system immediately energy dissipating drainage system, by abutment wall, raw material compacting zone, Testing tube, test section mark line composition are infiltrated in test material filling area, are the area Po Duan of entire test macro;Runoff and sediment Collection system is located at the end of test material fill system, is made of divider wall, trigonum, runoff bucket, valve, drainage ditch, is The lowermost end of whole system.
Further preferably, buffer area is filled with Extra-fine sand, and surface is placed in filling with smooth, smooth, fluid-tight plate The surface of sand, with the smooth drop-over of test material fill area top end surface.The compactness of raw material compacting zone is greater than the test on top The compactness of material, permeability is less than top test material can be in test material and raw material material if cannot reach requirement Water barrier device is arranged between material.Arrangement for infiltrating testing tube must be according to quincuncial arrangement, so as to measure test material Material different parts and depth infiltrate situation.Infiltrating testing tube must be using the pipe thin and transparent with certain intensity, caliber Material such as organic glass, the diameter of pipe are generally relatively carefully not more than 2.5mm, are conducive to the accuracy for just improving test.It is tested in placement Guan Shi, engaged test material end block nozzle using non-woven wraps filter material, to prevent particulate from entering testing tube, blocking pipe Road.In testing tube, at distance blocking end 2cm, 5~10mm colored liquid oil column is filled, accurately to calculate infiltrated water.It is right Divider wall in trigonum and packing material, it is necessary to play the role of antiseepage.It trigonum must be smooth, suitable with test material fill area It connects, being conducive to runoff and sediment can smoothly enter into trigonum.
High gradient slope soil erosion Field simulation test macro described in the utility model in the specific application process, including with Lower step:
Step 1, according to test request, the raw material compacting zone of processing test fill area.
Step 2, according to test request, measure the grading curve of test material.
Step 3, the antiseepage situation for checking divider wall.
Step 4, according to test requirements document, fill test material;During filling, testing tube is infiltrated in laying;
Step 5, cleaning trigonum and runoff bucket, to guarantee the accuracy of test;
Step 6 is filled buffer area, is laid with smooth plate 19;
Step 7 discharges water, and observation water flow adjusts smooth plate 19 in the distribution situation of smooth plate 19, so as to as gentle equal as possible It is even to be covered with smooth plate 19;
Step 8 carries out washout test, measures flow velocity according to testing tube arrangement section;The colored liquid for recording testing tube moves Dynamic distance and water surface site, measure test material infiltrates situation, when entire testing tube is filled by water completely, shows test material It has been saturated or has approached saturation;
Step 9 picks up water sample in the water inlet of top runoff bucket every 5~10min;
After the completion of step 10, test, the water sand sample of the silt and runoff bucket of collecting trigonum is handled, and calculates ensemble stream Vector.
The preferable specific embodiment of the above, only the utility model, the protection scope of the utility model are not limited to This, anyone skilled in the art can become apparent in the technical scope that the utility model discloses Technical solution simple change or equivalence replacement each fall in the protection scope of the utility model.

Claims (4)

1. high gradient slope soil erosion Field simulation test macro, which is characterized in that filled out including energy dissipating water system, test material Charging system, runoff and sediment collection system;
Energy dissipating water system by forebay, baffle wall style, cross the mouth of a river, after-bay and the buffer area section that discharges water form, which is located at test system The most top section of system, the system main function are before washing away, and the water flows gently, even into test material fill system;Test material Expect fill system immediately energy dissipating drainage system, by abutment wall, raw material compacting zone, test material filling area, infiltrates testing tube, test Section mark line composition is the area Po Duan of entire test macro;Runoff and sediment collection system is located at test material fill system End is made of divider wall, triangle collecting region, runoff bucket, runoff bucket pedestal, valve, drainage ditch, is the most bottom of whole system End.
2. high gradient slope soil erosion Field simulation test macro according to claim 1, it is characterised in that: use buffer area Extra-fine sand filling, surface is with fluid-tight smooth plate (19).
3. high gradient slope soil erosion Field simulation test macro according to claim 1, it is characterised in that: described to infiltrate The arrangement of testing tube (12) must be according to quincuncial arrangement.
4. high gradient slope soil erosion Field simulation test macro according to claim 1, it is characterised in that: surveyed infiltrating In test tube (12), at distance blocking end 2cm, it is equipped with 5~10mm colored liquid oil column.
CN201822036763.8U 2018-12-05 2018-12-05 High gradient slope soil erosion Field simulation test macro Expired - Fee Related CN209356493U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201822036763.8U CN209356493U (en) 2018-12-05 2018-12-05 High gradient slope soil erosion Field simulation test macro

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201822036763.8U CN209356493U (en) 2018-12-05 2018-12-05 High gradient slope soil erosion Field simulation test macro

Publications (1)

Publication Number Publication Date
CN209356493U true CN209356493U (en) 2019-09-06

Family

ID=67798334

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201822036763.8U Expired - Fee Related CN209356493U (en) 2018-12-05 2018-12-05 High gradient slope soil erosion Field simulation test macro

Country Status (1)

Country Link
CN (1) CN209356493U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109406757A (en) * 2018-12-05 2019-03-01 西北农林科技大学 High gradient slope soil erosion Field simulation test macro and its operating method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109406757A (en) * 2018-12-05 2019-03-01 西北农林科技大学 High gradient slope soil erosion Field simulation test macro and its operating method

Similar Documents

Publication Publication Date Title
CN107505448B (en) Seepage erosion model device, system and test method caused by underground pipeline damage
CN102175585B (en) Method for testing permeability stability of sand gravel material
CN104865371B (en) Reinforcing soft foundation experimental provision and experimental method under a kind of vacuum action
CN103236209B (en) Riverway cross-section two-dimensional underground seepage hydraulic experiment device
CN105092798B (en) Recharge system and test method in one kind simulation varying head permeable ground diving stratum room
CN111103418B (en) Simulation test system and test method for ground settlement caused by extraction of confined water
CN107860528B (en) Fill field isolating membrane blowby area block detection method and device
CN204125898U (en) The experimental rig of Dam Foundation Seepage under a kind of failure under earthquake action
CN103389260B (en) Pile foundation hinders the simulation laboratory test method of seepage action of ground water
CN206470116U (en) A kind of experimental rig for simulating the lower basement bottom board stress of artesian water effect
CN105821909A (en) Tree-like refuse leachate generated in landfill construction and closure as well as landfill gas guide and exhaust system and method
CN203824878U (en) Test device for simulating seepage prevention of embankment foundation engineering soil
CN209356493U (en) High gradient slope soil erosion Field simulation test macro
CN204925080U (en) Simulation becomes indoor system of recharging in flood peak permeable ground dive stratum
CN104947651A (en) Anti-liquefaction method applicable to sand foundation of subway station
CN114486683B (en) Test device for simulating pumping water in foundation pit and recharging groundwater outside foundation pit
CN109406757A (en) High gradient slope soil erosion Field simulation test macro and its operating method
Li et al. The development of sand erosion induced by shield-tunnel joint leakage
CN109540959A (en) Rich water thin silt construction freezing method effect simulation system and method
CN209310790U (en) A kind of combination type sedimentation observation device
CN103105308A (en) Method of fault-striding buried pipeline in-situ test
CN205742300U (en) Immersed tube tunnel basis fills sand equal proportion model test platform
CN109612538A (en) A kind of closed drainage amount test method
Zimmerman Compressibility, hydraulic conductivity, and soil infiltration testing of tire shreds and field testing of a shredded tire horizontal drain
LIU et al. Experimental study on seepage erosion induced by pipeline damage under full pipe flow condition

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190906

Termination date: 20201205