CN209354193U - Constructing tunnel moves pump drainage water installations - Google Patents
Constructing tunnel moves pump drainage water installations Download PDFInfo
- Publication number
- CN209354193U CN209354193U CN201822129166.XU CN201822129166U CN209354193U CN 209354193 U CN209354193 U CN 209354193U CN 201822129166 U CN201822129166 U CN 201822129166U CN 209354193 U CN209354193 U CN 209354193U
- Authority
- CN
- China
- Prior art keywords
- pump
- water
- storage device
- pedestal
- pump drainage
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 239000003657 drainage water Substances 0.000 title claims abstract description 43
- 238000009434 installation Methods 0.000 title claims abstract description 41
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 70
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 claims abstract description 32
- 238000009825 accumulation Methods 0.000 claims abstract description 3
- 229910000831 Steel Inorganic materials 0.000 claims description 16
- 239000010959 steel Substances 0.000 claims description 16
- 238000010276 construction Methods 0.000 abstract description 17
- 238000009412 basement excavation Methods 0.000 abstract description 5
- 238000005086 pumping Methods 0.000 description 3
- 230000005641 tunneling Effects 0.000 description 3
- 238000007599 discharging Methods 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 230000037230 mobility Effects 0.000 description 2
- 241001669679 Eleotris Species 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000004880 explosion Methods 0.000 description 1
- 239000000284 extract Substances 0.000 description 1
- 230000005484 gravity Effects 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 239000010865 sewage Substances 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Landscapes
- Structures Of Non-Positive Displacement Pumps (AREA)
Abstract
The utility model relates to Municipal Engineering Construction fields, disclose a kind of removable pump drainage water installations of constructing tunnel, which includes: rectangle plane pedestal;The draining pump and water storage device being set to before and after the length direction of the pedestal on the pedestal, the water storage device is the hollow cavity structure that top has opening, there is the water storage device water outlet and the water inlet for being connected to the suction pump for being set to constructing tunnel water accumulation part, the draining pump to be connected to the water outlet of the water storage device.It can be avoided by the removable pump drainage water installations of constructing tunnel provided by the present application and excavate reservoir while tunnel excavation, reduce labor intensity and engineering cost, it is convenient, simplified to take out draining, it accelerates construction progress.
Description
Technical field
The utility model relates to Municipal Engineering Construction fields, and in particular to a kind of removable pump drainage water installations of constructing tunnel.
Background technique
In constructing tunnel, especially returned in inclined shaft constructing tunnel slope pump drainage water be it is essential, it is in the prior art
Taking out draining is that reservoir is excavated in tunnel, and sewage in hole is extracted into reservoir with suction pump, then is plugged into steel with draining pump
Pipe will be handled outside the water discharge hole in reservoir, it is therefore desirable to calculate the lift of suction pump, the capacity of reservoir and selection
Matched draining pump, and the constructing tunnel period is long, after tunnel excavates forward a segment length, in order to meet construction needs, Yao Chongxin
New reservoir is excavated forward, increases construction cost and labor intensity, extends construction period.
Utility model content
Construction cost is high when in order to overcome tunnel drainage in the prior art and large labor intensity, the technology of long construction period are asked
Topic, the utility model are provided a kind of removable pump drainage water installations of constructing tunnel, can be avoided using the device in tunnel excavation
While excavate reservoir, substantially reduce labor intensity and engineering cost, it is convenient, simplify and take out draining, accelerate construction progress.
To achieve the above object, it includes: rectangle plane that constructing tunnel provided by the utility model, which moves pump drainage water installations,
Pedestal;The draining pump and water storage device being set to before and after the length direction of the pedestal on the pedestal, the water storage device
For top have opening hollow cavity structure, the water storage device have water outlet and for be set to constructing tunnel product
The water inlet of suction pump connection at water, the draining pump are connected to the water outlet of the water storage device.
Preferably, the pedestal has bottom plate and panel, and the panel is welded on the bottom plate, and the bottom plate is by more
A I-steel welds be made side by side, and the panel is made of steel plate.
Preferably, the pump drainage water installations further include: draining pump mount base, the draining pump are pacified by the draining pump mount base
On the panel of the pedestal, the draining pump mount base includes shockproof plate and base lugs, and the base lugs are fixed on institute
It states on panel, the shockproof plate is arranged between the base lugs and the bottom of the draining pump.
Preferably, the pump drainage water installations further include hanging ring, and the hanging ring is set to the top of the water storage device.
Preferably, the pump drainage water installations further include multiple pull rings, and the multiple pull ring is respectively arranged at the pedestal edge
Two sides in width direction.
Preferably, water inlet pipe mouth is provided on the connecting pipe between the water outlet of the water storage device and the draining pump
Control flange gate valve.
Preferably, effluent pipe mouth control flange gate valve is provided at the drain pipe port of the draining pump.
By technical solution provided by the utility model, the utility model is at least had the following technical effect that
The constructing tunnel of the application, which moves pump drainage water installations, has draining pump and discharging device, with tunnelling, takes out
Drainage arrangement can be moved forward with the progress of engineering, avoided excavation cavern pond while tunneling, can be subtracted
Few labour's investment, greatly reduces engineering cost and the labor intensity of staff, conveniently, simplifies pumping draining, add
Fast construction speed.
Other features and advantages of the utility model will the following detailed description will be given in the detailed implementation section.
Detailed description of the invention
Fig. 1 is the schematic diagram that constructing tunnel provided by the utility model moves pump drainage water installations.
Description of symbols
1 pedestal, 2 water storage device
3 draining pumps 4 drain pump mount base
5 hanging ring, 6 pull ring
7 water inlet pipe mouth control flange gate valve, 8 effluent pipe mouth control flange gate valve
11 bottom plate, 12 panel
41 shockproof 42 base lugs of plate
Specific embodiment
It is described in detail below in conjunction with specific embodiment of the attached drawing to the utility model embodiment.It should be understood that
It is that specific embodiment described herein is merely to illustrate and explains the utility model embodiment is not limited to this reality
Use new embodiment.
It should be noted that in the absence of conflict, the feature in the embodiments of the present invention and embodiment can
To be combined with each other.
In the present invention, in the absence of explanation to the contrary, the noun of locality used such as " upper and lower, top, bottom " is usually
Be for direction shown in the drawings either for it is vertical, vertically or on gravity direction for each component mutual alignment
Relationship description word.
The utility model will be described in detail below with reference to the accompanying drawings and embodiments.
Referring to FIG. 1, the utility model provides a kind of removable pump drainage water installations of constructing tunnel, which includes: rectangle
Flat base 1;The draining pump 3 and water storage device 2 being set to before and after the length direction of the pedestal 1 on the pedestal 1, it is described
Water storage device 2 be top have opening hollow cavity structure, the water storage device 2 have water outlet and for be set to
The water inlet of the suction pump connection of constructing tunnel water accumulation part, the draining pump 3 are connected to the water outlet of the water storage device 2.
Specifically, in the embodiment of the present application, draining pump 3 and water storage device 2 are provided on pedestal 1, water storage device 2 is middle control
Cavity body structure offers water outlet and water inlet on water storage device 2, and water inlet is by water-supply-pipe and setting in constructing tunnel product
Suction pump connection at water, when carrying out tunnelling, suction pump extracts ponding into water storage device 2, stands a period of time,
Silt in ponding is precipitated, draining pump 3 is then turned on, the ponding in water storage device 2 is discharged outside tunnel, water storage device 2
Top be provided with opening, the silt that construction personnel can will be deposited on 2 bottom of water storage device by opening is discharged.According to one kind
Embodiment, water storage device 2 are welded by the steel plate of 6mm thickness, the long 2.5m of steel plate, width 1.5m, high 1.2m, water storage device 2
Opening is reinforced by angle steel.
Pump drainage water installations are moved by constructing tunnel provided by the embodiments of the present application, with tunnelling, pump drainage water dress
Excavation cavern pond while tunneling can be avoided as the progress of engineering moves forward by setting, and reduced labour and thrown
Enter, greatly reduce engineering cost and the labor intensity of staff, conveniently simplify pumping draining, accelerate construct into
Degree.And the pump drainage water installations are simple and reasonable for structure, it is easy to operate.
Preferably, the pedestal 1 has bottom plate 11 and panel 12, and the panel 12 is welded on the bottom plate 11, institute
It states bottom plate 11 and is welded side by side by multiple I-steel and is made, the panel 12 is made of steel plate.
Specifically, in the embodiment of the present application, bottom plate 11 is welded side by side by multiple I-steel and is made, and panel 12 is welded on bottom plate
On 11.According to a kind of embodiment, bottom plate 11 selects the welding of model I20 I-steel to be made, between adjacent two I-steel
It is separated by 1m to be fixed with stull, panel 12 is 5.5m long, width 1.5m, steel plate thickness 10mm.
The removable pump drainage water installations understructure of constructing tunnel provided by the embodiments of the present application is simple, and stability is good, improves
The mobilitys of pump drainage water installations, increases the service life of pump drainage water installations.
Preferably, the pump drainage water installations further include: draining pump mount base 4, the draining pump 3 pass through the draining pump mount base
4 are mounted on the panel 12 of the pedestal 1, and the draining pump mount base 4 includes shockproof plate 41 and base lugs 42, the pedestal branch
Foot 42 is fixed on the panel 12, the shockproof plate 41 be arranged in the base lugs 42 and the draining pump 3 bottom it
Between.
Specifically, at work, since power is larger, the vibration of generation is also very big, and panel 12 is by steel system for draining pump 3
At can generate strong vibration to pedestal 1, cause huge construction noise, and stronger seismaesthesia also will affect the use of pedestal 1
Service life.Therefore in the embodiment of the present application, draining pump mount base 4 is installed between draining pump 3 and panel 12, draining pump mount base 4 includes
Shockproof plate 41 and base lugs 42, draining pump 3, shockproof plate 41, base lugs 42 and panel 12 are set according to sequence from top to bottom
It sets.According to a kind of embodiment, base lugs 42 are made of the channel steel of long 1.5m, width 12cm, and shockproof plate 41 is by long 1.5m, width
0.25m, high 0.2m sleeper are made.
Pump drainage water installations are moved by constructing tunnel provided by the embodiments of the present application, draining pump 3 is can reduce and is working
When the huge vibration that generates, reduce construction noise, improve the service life of pump drainage water installations.
Preferably, the pump drainage water installations further include hanging ring 5, and the hanging ring 5 is set to the top of the water storage device 2.
Specifically, the top of water storage device 2 is provided with hanging ring 5, it, can be in hanging ring 5 after water storage device 2 completes
Wirerope is penetrated, water storage device 2 is lifted on pedestal 1 with crane, and is welded with pedestal 1 integral.
Pump drainage water installations are moved by constructing tunnel provided by the embodiments of the present application, the peace of pump drainage water installations can be facilitated
Dress improves the mobility of pump drainage water installations.
Preferably, the pump drainage water installations further include multiple pull rings 6, and the multiple pull ring 6 is respectively arranged at the pedestal 1
Two sides in the width direction.
Specifically, as tunnel excavates forward, pump drainage water installations also will be moved forward and then, mobile for convenience, this Shen
It please be provided with multiple pull rings 6 on pedestal 1 in embodiment, pull ring 6 can be fixed on by construction machinery by wirerope and (for example dug
Pick machine, loading machine and forklift) on, by the mobile pump drainage water installations of construction machinery, the movement for greatly improving pump drainage water installations is motor-driven
Property.
Preferably, water inlet pipe is provided on the connecting pipe between the water outlet and the draining pump 3 of the water storage device 2
Mouth control flange gate valve 7.
Specifically, it in the embodiment of the present application, is set on the connecting pipe between the water outlet and draining pump 3 of water storage device 2
It is equipped with water inlet pipe mouth control flange gate valve 7, water inlet pipe mouth control flange gate valve 7 can control the going out to draining pump 3 of water storage device 2
Water speed rate prevents hydraulic pressure excessive to damage caused by draining pump 3, improves the service life of draining pump 3.
Preferably, effluent pipe mouth control flange gate valve 8 is provided at the drain pipe port of the draining pump 3.
Specifically, effluent pipe mouth control flange gate valve is additionally provided in the embodiment of the present application at the drain pipe port of draining pump 3
8, effluent pipe mouth control flange gate valve 8 and water inlet pipe mouth control flange gate valve 7 cooperate, to the drainage rates of draining pump 3 into
Row control, controls the internal pressure of drainpipe, avoids draining pipe explosion, improves working security, guarantees civilized construction.
The constructing tunnel of the application, which moves pump drainage water installations, has draining pump and discharging device, with tunnelling, takes out
Drainage arrangement can be moved forward with the progress of engineering, avoided excavation cavern pond while tunneling, can be subtracted
Few labour's investment, greatly reduces engineering cost and the labor intensity of staff, conveniently, simplifies pumping draining, add
Fast construction speed.
Preferred embodiments of the present invention, still, the utility model and unlimited are described in detail in conjunction with attached drawing above
Detail in above embodiment can be to the skill of the utility model in the range of the technology design of the utility model
Art scheme carries out a variety of simple variants, these simple variants belong to the protection scope of the utility model.
It is further to note that specific technical features described in the above specific embodiments, in not lance
It in the case where shield, can be combined in any appropriate way, in order to avoid unnecessary repetition, the utility model is to each
No further explanation will be given for the possible combination of kind.
In addition, any combination can also be carried out between a variety of different embodiments of the utility model, as long as it is not disobeyed
The thought for carrying on the back the utility model, equally should be considered as content disclosed in the utility model.
Claims (7)
1. a kind of constructing tunnel moves pump drainage water installations, which is characterized in that the pump drainage water installations include:
Rectangle plane pedestal (1);
The draining pump (3) and water storage device (2) being set to before and after the length direction of the pedestal (1) on the pedestal (1), institute
State water storage device (2) be top have opening hollow cavity structure, the water storage device (2) have water outlet and for
It is set to the water inlet of the suction pump connection of constructing tunnel water accumulation part, the water outlet of the draining pump (3) and the water storage device (2)
Mouth connection.
2. pump drainage water installations according to claim 1, which is characterized in that the pedestal (1) has bottom plate (11) and panel
(12), the panel (12) is welded on the bottom plate (11), and the bottom plate (11) is welded side by side by multiple I-steel to be made,
The panel (12) is made of steel plate.
3. pump drainage water installations according to claim 2, which is characterized in that the pump drainage water installations further include:
It drains pump mount base (4), the draining pump (3) is mounted on the panel of the pedestal (1) by draining pump mount base (4)
(12) on, the draining pump mount base (4) includes shockproof plate (41) and base lugs (42), and the base lugs (42) are fixed on institute
It states on panel (12), the shockproof plate (41) is arranged between the base lugs (42) and the bottom of the draining pump (3).
4. pump drainage water installations according to claim 1, which is characterized in that the pump drainage water installations further include hanging ring (5), institute
State the top that hanging ring (5) is set to the water storage device (2).
5. pump drainage water installations according to claim 1, which is characterized in that the pump drainage water installations further include multiple pull rings
(6), the multiple pull ring (6) be respectively arranged at the pedestal (1) in the width direction on two sides.
6. pump drainage water installations according to claim 1, which is characterized in that the water outlet of the water storage device (2) with it is described
Water inlet pipe mouth control flange gate valve (7) is provided on connecting pipe between draining pump (3).
7. pump drainage water installations according to claim 1, which is characterized in that be arranged at the drain pipe port of the draining pump (3)
There is effluent pipe mouth control flange gate valve (8).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201822129166.XU CN209354193U (en) | 2018-12-18 | 2018-12-18 | Constructing tunnel moves pump drainage water installations |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201822129166.XU CN209354193U (en) | 2018-12-18 | 2018-12-18 | Constructing tunnel moves pump drainage water installations |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209354193U true CN209354193U (en) | 2019-09-06 |
Family
ID=67799374
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201822129166.XU Expired - Fee Related CN209354193U (en) | 2018-12-18 | 2018-12-18 | Constructing tunnel moves pump drainage water installations |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209354193U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110836124A (en) * | 2020-01-02 | 2020-02-25 | 伍和龙 | Movable drainage device for tunnel construction |
CN110966040A (en) * | 2019-12-25 | 2020-04-07 | 中国矿业大学徐海学院 | Stable-performance drainage device for coal mine goaf |
CN111828280A (en) * | 2020-06-29 | 2020-10-27 | 浙江勤奋建设有限公司 | Flood control and waterlogging drainage equipment and drainage process thereof |
-
2018
- 2018-12-18 CN CN201822129166.XU patent/CN209354193U/en not_active Expired - Fee Related
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110966040A (en) * | 2019-12-25 | 2020-04-07 | 中国矿业大学徐海学院 | Stable-performance drainage device for coal mine goaf |
CN110836124A (en) * | 2020-01-02 | 2020-02-25 | 伍和龙 | Movable drainage device for tunnel construction |
CN111828280A (en) * | 2020-06-29 | 2020-10-27 | 浙江勤奋建设有限公司 | Flood control and waterlogging drainage equipment and drainage process thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN209354193U (en) | Constructing tunnel moves pump drainage water installations | |
CN104711994A (en) | Foundation pit deep well rainfall and plugging construction method | |
CN102704872B (en) | Gas-lift reverse circulation slurry circulation system | |
CN202560319U (en) | Tunnel drainage and pressure reduction structure | |
CN204738302U (en) | Multi -storey frame formula double row pile supporting construction | |
CN109736812A (en) | A kind of slag tapping method during shaft excavation | |
CN201447715U (en) | Excavator bucket | |
CN105040648A (en) | Reservoir emptying tunnel for over 200-meter ultrahigh dam and arrangement method and application thereof | |
CN112502174A (en) | Quick dewatering device for deep foundation pit | |
CN208965557U (en) | Removable internal support of foundation pit system | |
CN211200626U (en) | U-shaped communication pipeline for drainage of adverse slope in construction site | |
CN114016511A (en) | Excavation system of deep foundation pit and excavation construction method of deep foundation pit | |
CN206736940U (en) | A kind of water conservancy rushes heavy well construction equipment | |
CN208934101U (en) | A kind of pump lock foundation pit enclosure structure | |
CN207079608U (en) | Pool Bridge cushion cap foundation ditch subregion vacuum precipitation system | |
CN216689420U (en) | Excavation system of deep foundation pit | |
CN204570806U (en) | A kind of pipe-pile concrete water intaking structure being applicable to underwater operation | |
CN218880920U (en) | High-efficient foundation ditch tubular well precipitation structure | |
CN109853651A (en) | A kind of mill tailings library waterpower takes sand method | |
RU54379U1 (en) | SHAFT MINE HYDRAULIC POWER PLANT | |
CN212374934U (en) | Vacuum water-gas separator | |
CN220150358U (en) | Fixing device for well point downcomer of deep foundation pit | |
CN212078165U (en) | Effective drainage structure of construction branch tunnel | |
CN204210706U (en) | A kind of clear thin riverway sludge ship | |
CN219527661U (en) | Deep foundation pit mucky soil supporting equipment |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190906 |