CN114016511A - Excavation system of deep foundation pit and excavation construction method of deep foundation pit - Google Patents

Excavation system of deep foundation pit and excavation construction method of deep foundation pit Download PDF

Info

Publication number
CN114016511A
CN114016511A CN202111394506.1A CN202111394506A CN114016511A CN 114016511 A CN114016511 A CN 114016511A CN 202111394506 A CN202111394506 A CN 202111394506A CN 114016511 A CN114016511 A CN 114016511A
Authority
CN
China
Prior art keywords
pressure water
foundation pit
water
pump
pipeline
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202111394506.1A
Other languages
Chinese (zh)
Inventor
郭华新
尚文龙
关云常
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hebei 20th Metallurgical Engineering Technology Co ltd
China MCC20 Group Corp Ltd
Original Assignee
Hebei 20th Metallurgical Engineering Technology Co ltd
China MCC20 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hebei 20th Metallurgical Engineering Technology Co ltd, China MCC20 Group Corp Ltd filed Critical Hebei 20th Metallurgical Engineering Technology Co ltd
Priority to CN202111394506.1A priority Critical patent/CN114016511A/en
Publication of CN114016511A publication Critical patent/CN114016511A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/04Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/10Restraining of underground water by lowering level of ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/20Restraining of underground water by damming or interrupting the passage of underground water by displacing the water, e.g. by compressed air
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The invention provides an excavation system of a deep foundation pit and an excavation construction method of the deep foundation pit, wherein the excavation system comprises a diaphragm wall, a water storage tank, a high-pressure water pump, a high-pressure water gun, a mud pump and a mud pit. The diaphragm wall is arranged around the foundation pit to be excavated; the water storage tank is connected with the high-pressure water pump through a pipeline; the water inlet of the high-pressure water pump is connected with the water storage tank through a pipeline, and the water outlet of the high-pressure water pump is connected with the high-pressure water gun through a pipeline; the high-pressure water gun is connected with the water outlet of the high-pressure water pump through a pipeline; the mud pump has pipeline connected to the water inlet and the water outlet, pipeline connected to the water inlet and extending into the foundation pit, pipeline connected to the water outlet and extending into the mud collecting pond, and the mud collecting pond is set outside the foundation pit. The construction equipment is simple, excessive personnel investment is not needed, the digging efficiency of the deep foundation pit can be effectively improved, the construction cost is reduced, and the construction method has high practical application value.

Description

Excavation system of deep foundation pit and excavation construction method of deep foundation pit
Technical Field
The invention relates to the field of building construction, in particular to an excavation system of a deep foundation pit and an excavation construction method of the deep foundation pit.
Background
At present, in the earthwork construction process of a deep foundation pit, a backhoe excavator is generally adopted to dig in the foundation pit, then the abandoned soil dug to establish the foundation pit is lifted out to an automobile outside the foundation pit by using a tower crane, the automobile on the ground is transported out of the field, and finally the backhoe excavator is lifted out from the dug foundation pit by a tower crane. However, in the actual operation process, supports are required to be arranged between the underground diaphragm walls around the foundation pit, the arranged supports are generally dense, and in order to prevent the backhoe from interfering with the supports, a small backhoe must be used for excavating the foundation pit. Therefore, the excavation time of the foundation pit is prolonged, and the construction efficiency of the foundation pit is affected.
Disclosure of Invention
The invention aims to provide an excavation system of a deep foundation pit, which aims to solve the problem that the existing backhoe excavator is poor in foundation pit excavation efficiency.
The invention also aims to provide an excavation construction method of the deep foundation pit, so as to reduce equipment investment and improve the construction efficiency of the foundation pit.
One of the objects of the invention is achieved by: an excavation system for a deep foundation pit, comprising:
the underground diaphragm wall is a continuous reinforced concrete wall built underground and is arranged around a foundation pit to be excavated so as to play roles in intercepting, preventing seepage and retaining water for the foundation pit;
the water storage tank is connected with the high-pressure water pump through a pipeline and used for providing a pumping water source for the high-pressure water pump so as to impact earthwork in the enclosed area of the diaphragm wall;
the water inlet of the high-pressure water pump is connected with the water storage tank through a pipeline, and the water outlet of the high-pressure water pump is connected with a high-pressure water gun through a pipeline and used for pumping water in the water storage tank and converting the water pumped from the water storage tank into high-pressure impact water;
the high-pressure water gun is connected with a water outlet of the high-pressure water pump through a pipeline and used for converting high-pressure impact water pumped by the high-pressure water pump into a high-pressure water column, and a constructor controls the impact direction of the high-pressure water column through the high-pressure water gun so that the high-pressure water column impacts earthwork in the area enclosed by the diaphragm wall and impacts the earthwork into slurry;
the mud pump, connect with the pipeline on its water inlet and water outlet, the pipeline port connected to water inlet stretches into the foundation ditch, the pipeline connected to water outlet stretches into the mud collecting pool, in order to suck the mud in the foundation ditch, and convey the mud sucked to the mud collecting pool through the pipeline; and
and the mud collecting pool is arranged outside the foundation pit area to be excavated and used for collecting the mud pumped by the mud pump.
And the high-pressure water gun is provided with a flow control switch for adjusting the size of the high-pressure water column so as to change the impact force of the high-pressure water column.
The second purpose of the invention is realized by the following steps: a construction method for excavating a deep foundation pit by using the excavation system for the deep foundation pit comprises the following steps:
a. measuring and setting out on the ground where the foundation pit is to be excavated by using a total station, and then excavating a guide wall groove for enclosing a ground connection wall around the foundation pit;
b. hoisting a reinforcing mesh sheet for pouring in the guide wall into the guide wall groove;
c. after the guide wall reinforcing mesh is installed, a guide wall template for pouring a guide wall is erected;
d. after the guide wall template is erected, pouring concrete into the guide wall template;
e. after the concrete is solidified, removing the guide wall template;
f. manufacturing guide wall filling slurry, and filling the slurry into the poured guide wall;
g. digging a groove for pouring the diaphragm wall between the guide walls by using a groover;
h. hoisting a reinforcement cage poured in the diaphragm wall into the groove of the diaphragm wall by using a truck crane;
i. then, placing a concrete guide pipe into the groove of the diaphragm wall by using a truck crane, wherein the concrete guide pipe is arranged in a reinforcement cage in the groove of the diaphragm wall in a penetrating manner;
j. after the concrete guide pipe is installed, pouring concrete into the groove of the underground diaphragm wall through the concrete guide pipe;
k. according to the steps g-j, all the diaphragm walls surrounding the foundation pit are poured, and concrete of the diaphragm walls is waited to be solidified;
after the concrete of the diaphragm wall is solidified, digging a mud collecting pool at a short distance from a foundation pit to be dug;
m, after the sludge collecting pool is dug, arranging a water storage tank, a high-pressure water pump and a high-pressure water gun, connecting a water inlet of the high-pressure water pump with a water outlet of the water storage tank through a pipeline, connecting a water outlet of the high-pressure water gun with the high-pressure water gun, introducing the pipeline connected with the water inlet of the sludge pump into an area of the foundation pit to be dug, and introducing the pipeline connected with the water outlet of the sludge pump into the sludge collecting pool;
n, injecting a certain amount of water for impacting earthwork into the water storage tank;
step o, excavating a pit groove of the foundation pit in a sectional mode from top to bottom, aligning a water outlet of a high-pressure water gun to the uppermost section of earthwork to be impacted, starting a high-pressure water pump, and impacting the uppermost section of earthwork in the area enclosed by the diaphragm wall into slurry by using a high-pressure water column sprayed by the high-pressure water gun;
p, starting a slurry pump, and pumping the slurry formed by impact into a slurry collection pool by the slurry pump through a pipeline;
q, closing the high-pressure water pump and the slurry pump, and arranging a plurality of cross supporting beams between the oppositely arranged underground diaphragm walls exposed in the foundation pit;
and r, repeating the steps o-q until the pit slot of the whole foundation pit is dug, and then pouring the foundation pit in the pit slot.
The invention sprays high-pressure water columns between the diaphragm walls surrounding the foundation pit, impacts earthwork between the diaphragm walls into flowable slurry, and pumps the slurry out through a slurry pump, thereby forming a pit slot of the foundation pit in the surrounding area of the diaphragm walls. The invention can quickly realize the earthwork excavation and transportation in the area surrounded by the diaphragm wall, and the excavation speed and the quality of the foundation pit are superior to those of the excavation quality of the traditional machine. In addition, the equipment used by the invention has low investment cost and does not need other huge construction equipment. The method is simple to operate, does not need excessive personnel allocation, and does not influence the construction of other surrounding projects.
Drawings
Fig. 1 is a schematic structural view of the present invention.
In the figure: 1. a mud collecting pool; 2. a slurry pump; 3. earthwork; 4. a high pressure water gun; 5. a high pressure water pump; 6. a water storage tank; 7. and (4) connecting the ground with the wall.
Detailed Description
The first embodiment is as follows: an excavation system for a deep foundation pit.
As shown in fig. 1, the invention comprises a diaphragm wall 7, a water storage tank 6, a high-pressure water pump 5, a high-pressure water gun 4, a mud pump 2 and a mud collecting tank 1, wherein the diaphragm wall 7 is a continuous reinforced concrete wall built underground and used for surrounding a foundation pit to be excavated and playing roles of intercepting, preventing seepage and retaining water for the foundation pit.
The water storage tank 6 is connected with the high-pressure water pump 5 through a pipeline and used for providing a pumping water source for the high-pressure water pump 5 so as to impact earthwork in the enclosed area of the diaphragm wall 7. The water inlet of the high-pressure water pump 5 is connected with the water storage tank through a pipeline, and the water outlet of the high-pressure water pump 5 is connected with the high-pressure water gun 4 through a pipeline and used for pumping water in the water storage tank 6 so as to change the water pumped from the water storage tank 6 into high-pressure impact water. The high-pressure water gun 4 is connected with a water outlet of the high-pressure water pump 5 through a pipeline and used for converting high-pressure impact water pumped by the high-pressure water pump 5 into a high-pressure water column, so that a constructor controls the impact direction of the high-pressure water column through the high-pressure water gun, the high-pressure water column impacts earthwork in the enclosed area of the diaphragm wall 7 and the earthwork is impacted into slurry.
The water inlet and the water outlet of the mud pump 2 are both connected with pipelines, the pipeline connected to the water inlet of the mud pump 2 extends into a foundation pit enclosed by the ground connecting wall 7 to pump mud in the foundation pit, and the pipeline connected to the water outlet of the mud pump 2 extends to the mud collecting pool 1 to convey the pumped mud to the mud collecting pool.
The mud collecting pool 1 is arranged outside a foundation pit area to be excavated and used for collecting mud pumped by the mud pump 2.
The high-pressure water gun 4 is provided with a flow control switch for adjusting the size of a high-pressure water column sprayed out of the high-pressure water gun 4 so as to change the impact force of the high-pressure water column.
Example two: an excavation construction method of a deep foundation pit.
The embodiment is a construction method for excavating a foundation pit by using the excavation system described in the first embodiment, and specifically includes the following steps:
a. the total station is used to measure the defence lines on the ground of the foundation pit to be excavated and then to excavate the guide wall trench which is used to enclose the diaphragm wall 7 around the foundation pit.
b. Then, a steel bar net piece poured in the guide wall is hung in the guide wall groove to enhance the strength of the guide wall.
c. And after the reinforcing mesh of the guide wall is installed, erecting a guide wall template for pouring the guide wall.
d. And after the guide wall template is erected, pouring concrete into the guide wall template.
e. And after the guide wall concrete is solidified, removing the guide wall template.
f. And (3) manufacturing filling slurry of the guide wall, and filling the slurry into a groove formed between the poured guide walls so as to prevent the guide wall from deforming when a forehead groove of the diaphragm wall 7 is dug.
g. Then, a groove for pouring the diaphragm wall 7 is dug between the guide walls by using a groover.
h. And hoisting the reinforcement cage poured in the diaphragm wall 7 into the groove of the dug diaphragm wall 7 by using a truck crane.
i. Then, a concrete guide pipe is arranged in the groove of the diaphragm wall 7 by using a truck crane, and the concrete guide pipe vertically penetrates through a reinforcement cage in the groove of the diaphragm wall 7.
j. After the concrete guide pipe is installed, concrete is poured into the groove of the underground diaphragm wall 7 through the concrete guide pipe.
k. And g, according to the step g-j, completely pouring the diaphragm walls 7 surrounding the foundation pit until the concrete of all the diaphragm walls 7 is solidified.
And l, after the concrete of the underground diaphragm wall 7 is solidified, digging and setting the mud collecting pool 1 at a short distance from the foundation pit to be dug.
m, after the sludge collecting pool 1 is dug, a water storage tank 6, a high-pressure water pump 5 and a high-pressure water gun 4 are arranged. The water inlet of the high-pressure water gun 4 is connected with the water outlet of the water storage tank 6 through a pipeline, the water outlet of the high-pressure water gun 4 is connected with the high-pressure water gun 4, the pipeline connected with the water inlet of the slurry pump 2 is communicated into an area to be dug and provided with a foundation pit, and finally the pipeline connected with the water outlet of the slurry pump 2 is communicated into the slurry collecting tank 1.
n, then injecting a certain amount of water which is used for impacting the earthwork into the water storage tank 6, wherein the water can be continuously filled after the water is little in the process of impacting the earthwork.
And o, the pit of the foundation pit is dug in a sectional manner from top to bottom, the water outlet of the high-pressure water gun 4 is aligned to the uppermost section of earthwork to be impacted, then the high-pressure water pump is started, so that the high-pressure water gun 4 sprays high-pressure water columns, and the high-pressure water columns impact the uppermost section of earthwork in the area enclosed by the diaphragm wall 7 into slurry.
And p, starting the slurry pump 2, sucking the slurry formed by impact in the area enclosed by the diaphragm wall 7 by the slurry pump 2 through a pipeline, and conveying the slurry into the slurry collecting tank 1.
And q, after the planned section of pit foundation is dug, closing the high-pressure water pump and the slurry pump, and arranging a plurality of cross supporting beams between the oppositely arranged underground diaphragm walls 7 exposed in the foundation pit so as to support the underground diaphragm walls 7 and prevent the underground diaphragm walls 7 from being affected by surrounding soil and sand, so that the underground diaphragm walls 7 are deformed or toppled.
And r, repeating the steps o-q until the pit slot of the whole foundation pit is dug, and then performing subsequent foundation pit pouring work in the pit slot.

Claims (3)

1. An excavation system for a deep foundation pit, comprising:
the underground diaphragm wall is a continuous reinforced concrete wall built underground and is arranged around a foundation pit to be excavated so as to play roles in intercepting, preventing seepage and retaining water for the foundation pit;
the water storage tank is connected with the high-pressure water pump through a pipeline and used for providing a pumping water source for the high-pressure water pump so as to impact earthwork in the enclosed area of the diaphragm wall;
the water inlet of the high-pressure water pump is connected with the water storage tank through a pipeline, and the water outlet of the high-pressure water pump is connected with a high-pressure water gun through a pipeline and used for pumping water in the water storage tank and converting the water pumped from the water storage tank into high-pressure impact water;
the high-pressure water gun is connected with a water outlet of the high-pressure water pump through a pipeline and used for converting high-pressure impact water pumped by the high-pressure water pump into a high-pressure water column, and a constructor controls the impact direction of the high-pressure water column through the high-pressure water gun so that the high-pressure water column impacts earthwork in the area enclosed by the diaphragm wall and impacts the earthwork into slurry;
the mud pump, connect with the pipeline on its water inlet and water outlet, the pipeline port connected to water inlet stretches into the foundation ditch, the pipeline connected to water outlet stretches into the mud collecting pool, in order to suck the mud in the foundation ditch, and convey the mud sucked to the mud collecting pool through the pipeline; and
and the mud collecting pool is arranged outside the foundation pit area to be excavated and used for collecting the mud pumped by the mud pump.
2. The excavation system of a deep foundation pit according to claim 1, wherein the high pressure water gun is provided with a flow control switch for adjusting the size of the high pressure water column to change the impact force of the high pressure water column.
3. A construction method for excavating a deep foundation pit using the excavation system for a deep foundation pit according to claim 1, comprising the steps of:
a. measuring and setting out on the ground where the foundation pit is to be excavated by using a total station, and then excavating a guide wall groove for enclosing a ground connection wall around the foundation pit;
b. hoisting a reinforcing mesh sheet for pouring in the guide wall into the guide wall groove;
c. after the guide wall reinforcing mesh is installed, a guide wall template for pouring a guide wall is erected;
d. after the guide wall template is erected, pouring concrete into the guide wall template;
e. after the concrete is solidified, removing the guide wall template;
f. manufacturing guide wall filling slurry, and filling the slurry into the poured guide wall;
g. digging a groove for pouring the diaphragm wall between the guide walls by using a groover;
h. hoisting a reinforcement cage poured in the diaphragm wall into the groove of the diaphragm wall by using a truck crane;
i. then, placing a concrete guide pipe into the groove of the diaphragm wall by using a truck crane, wherein the concrete guide pipe is arranged in a reinforcement cage in the groove of the diaphragm wall in a penetrating manner;
j. after the concrete guide pipe is installed, pouring concrete into the groove of the underground diaphragm wall through the concrete guide pipe;
k. according to the steps g-j, all the diaphragm walls surrounding the foundation pit are poured, and concrete of the diaphragm walls is waited to be solidified;
after the concrete of the diaphragm wall is solidified, digging a mud collecting pool at a short distance from a foundation pit to be dug;
m, after the sludge collecting pool is dug, arranging a water storage tank, a high-pressure water pump and a high-pressure water gun, connecting a water inlet of the high-pressure water pump with a water outlet of the water storage tank through a pipeline, connecting a water outlet of the high-pressure water gun with the high-pressure water gun, introducing the pipeline connected with the water inlet of the sludge pump into an area of the foundation pit to be dug, and introducing the pipeline connected with the water outlet of the sludge pump into the sludge collecting pool;
n, injecting a certain amount of water for impacting earthwork into the water storage tank;
step o, excavating a pit groove of the foundation pit in a sectional mode from top to bottom, aligning a water outlet of a high-pressure water gun to the uppermost section of earthwork to be impacted, starting a high-pressure water pump, and impacting the uppermost section of earthwork in the area enclosed by the diaphragm wall into slurry by using a high-pressure water column sprayed by the high-pressure water gun;
p, starting a slurry pump, and pumping the slurry formed by impact into a slurry collection pool by the slurry pump through a pipeline;
q, closing the high-pressure water pump and the slurry pump, and arranging a plurality of cross supporting beams between the oppositely arranged underground diaphragm walls exposed in the foundation pit;
and r, repeating the steps o-q until the pit slot of the whole foundation pit is dug, and then pouring the foundation pit in the pit slot.
CN202111394506.1A 2021-11-23 2021-11-23 Excavation system of deep foundation pit and excavation construction method of deep foundation pit Pending CN114016511A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111394506.1A CN114016511A (en) 2021-11-23 2021-11-23 Excavation system of deep foundation pit and excavation construction method of deep foundation pit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111394506.1A CN114016511A (en) 2021-11-23 2021-11-23 Excavation system of deep foundation pit and excavation construction method of deep foundation pit

Publications (1)

Publication Number Publication Date
CN114016511A true CN114016511A (en) 2022-02-08

Family

ID=80065813

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111394506.1A Pending CN114016511A (en) 2021-11-23 2021-11-23 Excavation system of deep foundation pit and excavation construction method of deep foundation pit

Country Status (1)

Country Link
CN (1) CN114016511A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114960814A (en) * 2022-06-24 2022-08-30 广东省第四建筑工程有限公司 Method for conveying solid sludge of deep foundation pit

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1712539A1 (en) * 1987-12-17 1992-02-15 Институт горного дела им.А.А.Скочинского Method of digging a basin above a cable
CN102605791A (en) * 2012-04-12 2012-07-25 中建三局第三建设工程有限责任公司 Method for excavating soil from soft soil foundation
CN106284365A (en) * 2016-07-23 2017-01-04 杭州千城建筑设计有限公司 A kind of WATER-WASHING METHOD of building foundation pit excavation
CN207998850U (en) * 2017-04-01 2018-10-23 武汉科技大学 A kind of pit earthwork hydraulicking system that borders on the sea near a river
CN109989392A (en) * 2019-03-20 2019-07-09 南通勘察设计有限公司 Sand construction of diaphragm wall grooving technology
CN110616712A (en) * 2019-09-24 2019-12-27 中国建筑第八工程局有限公司 Arrangement method of hydraulic machinery for pumping and soil-flushing in deep foundation pit
CN216689420U (en) * 2021-11-23 2022-06-07 中国二十冶集团有限公司 Excavation system of deep foundation pit

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1712539A1 (en) * 1987-12-17 1992-02-15 Институт горного дела им.А.А.Скочинского Method of digging a basin above a cable
CN102605791A (en) * 2012-04-12 2012-07-25 中建三局第三建设工程有限责任公司 Method for excavating soil from soft soil foundation
CN106284365A (en) * 2016-07-23 2017-01-04 杭州千城建筑设计有限公司 A kind of WATER-WASHING METHOD of building foundation pit excavation
CN207998850U (en) * 2017-04-01 2018-10-23 武汉科技大学 A kind of pit earthwork hydraulicking system that borders on the sea near a river
CN109989392A (en) * 2019-03-20 2019-07-09 南通勘察设计有限公司 Sand construction of diaphragm wall grooving technology
CN110616712A (en) * 2019-09-24 2019-12-27 中国建筑第八工程局有限公司 Arrangement method of hydraulic machinery for pumping and soil-flushing in deep foundation pit
CN216689420U (en) * 2021-11-23 2022-06-07 中国二十冶集团有限公司 Excavation system of deep foundation pit

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
程德虎: "大型渠道衬砌水下修复关键技术的试验研究与应用", 30 June 2020, 郑州:黄河水利出版社, pages: 236 - 237 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114960814A (en) * 2022-06-24 2022-08-30 广东省第四建筑工程有限公司 Method for conveying solid sludge of deep foundation pit

Similar Documents

Publication Publication Date Title
CN103114599B (en) Deep basal pit sealing dewatering device and construction method thereof
CN104196034A (en) Foundation pit construction method employing steel sheet piles as support cofferdam
CN104711994A (en) Foundation pit deep well rainfall and plugging construction method
CN111980019A (en) Construction method of steel pipe pile cofferdam with lock on the main bridge of the super bridge
CN110486019B (en) Underground excavation construction method for additionally arranging underground communication channels between new buildings and old buildings
CN107268688B (en) Construction method for reinforcing and sealing I-shaped steel joint of underground continuous wall
CN216342131U (en) Shield tunnel invades limit stake and handles reinforced structure
CN118110193A (en) The whole process construction method of large diameter caisson in complex geological conditions
CN108532586A (en) A kind of construction method of garage parking diaphram wall
CN111236208A (en) Underground diaphragm wall foundation pit construction method
CN114411756A (en) Construction method and construction device for open-cut foundation pit of water-rich sand layer subway station without precipitation
CN101793023A (en) Foundation pit construction method
CN105350575B (en) A kind of reversed construction method of diaphram wall
CN110565686A (en) Construction method for penetrating river channel under pipe gallery
CN107059904B (en) A kind of underground pipe gallery ponding well excavation method
CN102912789A (en) Mechanical hole forming technology applied to karst landform
CN114016511A (en) Excavation system of deep foundation pit and excavation construction method of deep foundation pit
CN216407913U (en) A water intake pipe jacking structure crossing the Linjiang Railway
CN216689420U (en) Excavation system of deep foundation pit
CN115404889A (en) Open caisson construction device and construction method for urban municipal engineering
JP2025123339A (en) Buried object construction method
CN110512649B (en) Underground excavation construction method for additionally arranging basement and communication channel structure under existing building
CN110700270B (en) Construction method for non-drainage earthwork excavation of ultra-deep foundation pit
CN111485888B (en) Prefabricated piecemeal lining tunnel system in advance
CN104480945A (en) Inversed construction method for foundation pit

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20220208