CN209317314U - A kind of high efficiency plasma waste gas treatment equipment - Google Patents
A kind of high efficiency plasma waste gas treatment equipment Download PDFInfo
- Publication number
- CN209317314U CN209317314U CN201821866278.7U CN201821866278U CN209317314U CN 209317314 U CN209317314 U CN 209317314U CN 201821866278 U CN201821866278 U CN 201821866278U CN 209317314 U CN209317314 U CN 209317314U
- Authority
- CN
- China
- Prior art keywords
- gas
- exhaust gas
- gas treatment
- tracheae
- dust
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Treating Waste Gases (AREA)
Abstract
The utility model relates to waste gas treatment equipment technical fields, and disclose a kind of high efficiency plasma waste gas treatment equipment, including exhaust gas pre-processing device, the exhaust gas pre-processing device is fixedly connected with the first tracheae on the left of upper end, the exhaust gas pre-processing device is connected to by the first tracheae with external exhaust gas transmission device, cavity structure is equipped with inside the exhaust gas pre-processing device, and the upper end of cavity structure is fixedly installed with spray head water pipe, the lower end of the spray head water pipe is fixedly installed with spray head.The high efficiency plasma waste gas treatment equipment, pass through the exhaust gas pre-processing device being equipped with, the impurity that water is dissolved in exhaust gas and dust purification can be absorbed, pass through the gas drier being equipped with, it can be by the dry water removal of the purified exhaust gas of exhaust gas pre-processing device, by the dust-extraction unit being equipped with, the processing of secondary dust absorptive collection can be carried out to the exhaust gas after drying, purification enters the waste exhaust gases of plasma apparatus money.
Description
Technical field
The utility model relates to waste gas treatment equipment technical field, specially a kind of high efficiency plasma waste gas treatment equipment.
Background technique
Exhaust-gas treatment is primarily referred to as the industrial waste gas generated for industrial site such as dust particle, flue gas flue dust, different
The work that taste gas, toxic and harmful gas are administered, common waste gas purification have factory's fume and exhaust gas purifying, workshop dust useless
Gas purification, organic waste-gas purification, the purification of exhaust gas peculiar smell, acid-base waste gas purifying, purification of chemical waste gas etc..
For plasma waste gas treatment equipment because of its high treating effect, the features such as operating cost is low, high degree of automation, is extensive
Ground applies to the improvement of foul gas, but when the work of existing plasma waste gas treatment equipment, into the foul waste gas of equipment
Complicated component so that the waste gas treatment process time is long, exhaust treatment efficiency is low, and equipment processing exhaust gas when can generate ozone etc.
Tail gas, as treated, exhaust gas device for transferring can cause secondary pollution to environment to these tail gas.
Utility model content
In view of the deficiencies of the prior art, the utility model provides a kind of high efficiency plasma waste gas treatment equipment, has pair
Exhaust gas into plasma waste gas treatment equipment is pre-processed, and dust and other impurities gas are absorbed, and purifies plasma apparatus
The advantages of tail gas generated when work, it is long to solve the existing plasma waste gas treatment equipment waste gas treatment process time, at exhaust gas
The problem of reason low efficiency, the tail gas that equipment generates when working causes secondary pollution to environment.
The utility model provides the following technical solutions: a kind of high efficiency plasma waste gas treatment equipment, including exhaust gas pretreatment
Equipment, is fixedly connected with the first tracheae on the left of exhaust gas pre-processing device upper end, and the exhaust gas pre-processing device passes through the
One tracheae is connected to external exhaust gas transmission device, is equipped with cavity structure inside the exhaust gas pre-processing device, and cavity structure
Upper end is fixedly installed with spray head water pipe, and the lower end of the spray head water pipe is fixedly installed with spray head, the exhaust gas pre-processing device
Right side is equipped with gas drier, and the right side of exhaust gas pre-processing device upper end passes through on the second tracheae and gas drier
The left side at end is connected to, and the right side of the gas drier is equipped with dust-extraction unit, and the right side of the gas drier upper end is logical
It crosses third tracheae to be connected to the left end of dust-extraction unit, the upper end of the dust-extraction unit is fixedly installed with electrostatic generator, described to remove
The inside of dirt device is equipped with mounting post, and the both ends of mounting post are fixedly connected with the upper and lower ends of dust-extraction unit respectively, the peace
The outer surface of dress column is fixedly installed with static board, and the right side of the dust-extraction unit is equipped with the first blower, and the left end of the first blower
It is connected to by the 4th tracheae with the right end of dust-extraction unit, the right side of first blower is equipped with plasma apparatus, and plasma is set
Standby left end is connected to by the 5th tracheae with the upper end of the first blower, and the right side of the plasma apparatus is equipped with the second blower, and
The upper end of second blower is connected to by the 6th tracheae with the right end of plasma apparatus, and the right side of second blower is equipped at tail gas
Case is managed, the lower surface of the vent gas treatment case is fixedly installed with heating device, and the inside of vent gas treatment case is equipped with tail gas air guide
The left end of pipe, the tail gas gas-guide tube is connected to by the 7th tracheae with the right end of the second blower, and the right end of tail gas gas-guide tube passes through
It wears the side wall on the right side of vent gas treatment case and extends to outside.
Preferably, the quantity of the spray head is several groups, and spray head described in several groups is uniformly arranged along the lower end of spray head water pipe
Column.
Preferably, the shape of the static board is disc structure, and the outer surface of static board is uniformly attached with active carbon
Grain.
Preferably, the quantity of the static board is several groups, and static board described in several groups passes through electric wire and electrostatic generator
Form series loop.
Preferably, the bottom of the vent gas treatment case is equipped with support base structure, and the quantity of the support base structure is
Four groups, and support base structure described in four groups is separately mounted to the quadrangle in vent gas treatment bottom portion.
Preferably, the shape of the tail gas gas-guide tube is bending pipeline, and the inner wall of tail gas gas-guide tube is uniformly attached with work
Property charcoal particle.
Be compared with the prior art, the utility model have it is following the utility model has the advantages that
1, the high efficiency plasma waste gas treatment equipment can will be dissolved in by the exhaust gas pre-processing device being equipped in exhaust gas
The impurity and dust purification of water absorb, can be purified useless by exhaust gas pre-processing device by the gas drier being equipped with
The dry water removal of gas can carry out the processing of secondary dust absorptive collection, purification by the dust-extraction unit being equipped with to the exhaust gas after drying
Into the waste exhaust gases of plasma apparatus money.
2, the high efficiency plasma waste gas treatment equipment can add vent gas treatment case by the heating device being equipped with
Heat treatment keeps constant high temperature in vent gas treatment case, the tail gas such as the ozone generated when plasma apparatus work is decomposed, by being equipped with
Tail gas gas-guide tube can lengthen flow path of the tail gas in vent gas treatment case so that tail gas adequately divides in the high temperature environment
Solution.
Detailed description of the invention
FIG. 1 is a schematic structural view of the utility model;
Fig. 2 is the schematic diagram of internal structure of the utility model Fig. 1;
Fig. 3 is the structural schematic diagram at the utility model A;
Fig. 4 is the structural schematic diagram at the utility model B.
In figure: 1, exhaust gas pre-processing device;2, the first tracheae;3, spray head water pipe;4, spray head;5, gas drier;6,
Second tracheae;7, dust-extraction unit;8, third tracheae;9, electrostatic generator;10, mounting post;11, static board;12, electric wire;13,
One blower;14, the 4th tracheae;15, plasma apparatus;16, the 5th tracheae;17, the second blower;18, the 6th tracheae;19, tail gas
Treatment box;20, the 7th tracheae;21, heating device;22, tail gas gas-guide tube.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model
Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole
Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work
Every other embodiment obtained, fall within the protection scope of the utility model.
Please refer to Fig. 1-4, a kind of high efficiency plasma waste gas treatment equipment, including exhaust gas pre-processing device 1, exhaust gas pretreatment
The first tracheae 2 is fixedly connected on the left of 1 upper end of equipment, exhaust gas pre-processing device 1 is transmitted by the first tracheae 2 with external exhaust gas
Device is connected to, and cavity structure is equipped with inside exhaust gas pre-processing device 1, and the upper end of cavity structure is fixedly installed with spray head water pipe 3,
The lower end of spray head water pipe 3 is fixedly installed with spray head 4, and the quantity of spray head 4 is several groups, and several groups spray head 4 is along spray head water pipe 3
Lower end is evenly distributed, by the exhaust gas pre-processing device 1 being equipped with, the impurity that water is dissolved in exhaust gas and dust purification can be inhaled
It receives, the right side of exhaust gas pre-processing device 1 is equipped with gas drier 5, and the right side of 1 upper end of exhaust gas pre-processing device passes through the second gas
Pipe 6 is connected to the left side of 5 upper end of gas drier, can be by exhaust gas pre-processing device by the gas drier 5 being equipped with
The dry water removal of 1 purified exhaust gas, the right side of gas drier 5 are equipped with dust-extraction unit 7, the right side of 5 upper end of gas drier
Side is connected to by third tracheae 8 with the left end of dust-extraction unit 7, and the upper end of dust-extraction unit 7 is fixedly installed with electrostatic generator 9, removes
The inside of dirt device 7 is equipped with mounting post 10, and the both ends of mounting post 10 are fixedly connected with the upper and lower ends of dust-extraction unit 7 respectively,
The outer surface of mounting post 10 is fixedly installed with static board 11, and the shape of static board 11 is disc structure, and the appearance of static board 11
Face is uniformly attached with active carbon particle, and the quantity of static board 11 is several groups, and several groups static board 11 passes through electric wire 12 and electrostatic
Generator 9 forms series loop, by the dust-extraction unit 7 being equipped with, secondary dust absorption can be carried out to the exhaust gas after drying and is received
Collection processing, purification enter the waste exhaust gases before plasma apparatus 15, and the right side of dust-extraction unit 7 is equipped with the first blower 13, and first
The left end of blower 13 is connected to by the 4th tracheae 14 with the right end of dust-extraction unit 7, and the right side of the first blower 13 is set equipped with plasma
Standby 15, and the left end of plasma apparatus 15 is connected to by the 5th tracheae 16 with the upper end of the first blower 13, plasma apparatus 15
Right side is equipped with the second blower 17, and the upper end of the second blower 17 is connected to by the 6th tracheae 18 with the right end of plasma apparatus 15,
The right side of second blower 17 is equipped with vent gas treatment case 19, and the bottom of vent gas treatment case 19 is equipped with support base structure, support base
The quantity of structure is four groups, and four groups of support base structures are separately mounted to the quadrangle of 19 bottom of vent gas treatment case, vent gas treatment
The lower surface of case 19 is fixedly installed with heating device 21, by the heating device 21 being equipped with, can carry out to vent gas treatment case 19
Heat treatment keeps constant high temperature in vent gas treatment case 19, decomposes the tail gas such as the ozone generated when plasma apparatus 15 works, tail
The inside of gas disposal case 19 is equipped with tail gas gas-guide tube 22, and the shape of tail gas gas-guide tube 22 is bending pipeline, and tail gas gas-guide tube 22
Inner wall be uniformly attached with active carbon particle, the left end of tail gas gas-guide tube 22 passes through the right end of the 7th tracheae 20 and the second blower 17
Connection, and the right end of tail gas gas-guide tube 22 runs through the side wall on 19 right side of vent gas treatment case and extends to outside, passes through the tail being equipped with
Conductance tracheae 22 can lengthen flow path of the tail gas in vent gas treatment case 19, so that tail gas adequately divides in the high temperature environment
Solution.
When equipment works, exhaust gas is sucked in exhaust gas pre-processing device 1 by the first tracheae 2, is given up by the operation of the first blower 13
Spray head 4 is persistently sprayed water in gas pre-processing device 1, by the gaseous impurity for being dissolved in water and dust particles absorptive collection in exhaust gas, warp
The exhaust gas for crossing the processing of exhaust gas pre-processing device 1 is entered in gas drier 5 by the second tracheae 6 is dried water removal, dry
Exhaust gas afterwards is entered by third tracheae 8 carries out the collection of secondary dust granular absorption in dust-extraction unit 7, at dust-extraction unit 7
Exhaust gas after reason is entered in plasma apparatus 15 by the 4th tracheae 14 and the 5th tracheae 16 carries out exhaust-gas treatment, the second blower 17
Operation, by after 15 treatment and purification of plasma apparatus exhaust gas and plasma apparatus 15 work when the tail gas such as the ozone that generates mixing
Gas is imported in the tail gas gas-guide tube 22 inside vent gas treatment case 19 by the 6th tracheae 18 and the 7th tracheae 20, heating device 21
Work decomposes the tail gas such as the ozone in mixed gas, avoids plasma and set so that keeping constant high temperature in vent gas treatment case 19
The tail gas that standby 15 work generates causes secondary pollution to environment.
It should be noted that, in this document, relational terms such as first and second and the like are used merely to a reality
Body or operation are distinguished with another entity or operation, are deposited without necessarily requiring or implying between these entities or operation
In any actual relationship or order or sequence.Moreover, the terms "include", "comprise" or its any other variant are intended to
Non-exclusive inclusion, so that the process, method, article or equipment including a series of elements is not only wanted including those
Element, but also including other elements that are not explicitly listed, or further include for this process, method, article or equipment
Intrinsic element.
While there has been shown and described that the embodiments of the present invention, for the ordinary skill in the art,
It is understood that these embodiments can be carried out with a variety of variations in the case where not departing from the principles of the present invention and spirit, repaired
Change, replacement and variant, the scope of the utility model is defined by the appended claims and the equivalents thereof.
Claims (6)
1. a kind of high efficiency plasma waste gas treatment equipment, including exhaust gas pre-processing device (1), it is characterised in that: the exhaust gas is pre-
It is fixedly connected with the first tracheae (2) on the left of processing equipment (1) upper end, the exhaust gas pre-processing device (1) passes through the first tracheae
(2) it is connected to external exhaust gas transmission device, is equipped with cavity structure inside the exhaust gas pre-processing device (1), and cavity structure
Upper end is fixedly installed with spray head water pipe (3), and the lower end of the spray head water pipe (3) is fixedly installed with spray head (4), and the exhaust gas is located in advance
The right side for managing equipment (1) is equipped with gas drier (5), and the right side of exhaust gas pre-processing device (1) upper end passes through the second gas
Pipe (6) is connected to the left side of gas drier (5) upper end, and the right side of the gas drier (5) is equipped with dust-extraction unit
(7), the right side of gas drier (5) upper end is connected to by third tracheae (8) with the left end of dust-extraction unit (7), described
The upper end of dust-extraction unit (7) is fixedly installed with electrostatic generator (9), and the inside of the dust-extraction unit (7) is equipped with mounting post (10),
And the both ends of mounting post (10) are fixedly connected with the upper and lower ends of dust-extraction unit (7) respectively, the outer surface of the mounting post (10)
It is fixedly installed with static board (11), the right side of the dust-extraction unit (7) is equipped with the first blower (13), and a left side for the first blower (13)
End is connected to by the 4th tracheae (14) with the right end of dust-extraction unit (7), and the right side of first blower (13) is set equipped with plasma
Standby (15), and the left end of plasma apparatus (15) is connected to by the 5th tracheae (16) with the upper end of the first blower (13), it is described etc.
The right side of ion device (15) be equipped with the second blower (17), and the upper end of the second blower (17) by the 6th tracheae (18) with etc. from
The right end of sub- equipment (15) is connected to, and the right side of second blower (17) is equipped with vent gas treatment case (19), the vent gas treatment case
(19) lower surface is fixedly installed with heating device (21), and the inside of vent gas treatment case (19) is equipped with tail gas gas-guide tube (22),
The left end of the tail gas gas-guide tube (22) is connected to by the 7th tracheae (20) with the right end of the second blower (17), and tail gas gas-guide tube
(22) side wall of the right end on the right side of vent gas treatment case (19) simultaneously extends to outside.
2. a kind of high efficiency plasma waste gas treatment equipment according to claim 1, it is characterised in that: the spray head (4)
Quantity is several groups, and spray head described in several groups (4) is evenly distributed along the lower end of spray head water pipe (3).
3. a kind of high efficiency plasma waste gas treatment equipment according to claim 1, it is characterised in that: the static board (11)
Shape be disc structure, and the outer surface of static board (11) is uniformly attached with active carbon particle.
4. a kind of high efficiency plasma waste gas treatment equipment according to claim 1, it is characterised in that: the static board (11)
Quantity be several groups, static board (11) described in several groups forms series loop by electric wire (12) and electrostatic generator (9).
5. a kind of high efficiency plasma waste gas treatment equipment according to claim 1, it is characterised in that: the vent gas treatment case
(19) bottom is equipped with support base structure, and the quantity of the support base structure is four groups, and support base knot described in four groups
Structure is separately mounted to the quadrangle of vent gas treatment case (19) bottom.
6. a kind of high efficiency plasma waste gas treatment equipment according to claim 1, it is characterised in that: the tail gas gas-guide tube
(22) shape is bending pipeline, and the inner wall of tail gas gas-guide tube (22) is uniformly attached with active carbon particle.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821866278.7U CN209317314U (en) | 2018-11-13 | 2018-11-13 | A kind of high efficiency plasma waste gas treatment equipment |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821866278.7U CN209317314U (en) | 2018-11-13 | 2018-11-13 | A kind of high efficiency plasma waste gas treatment equipment |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209317314U true CN209317314U (en) | 2019-08-30 |
Family
ID=67710221
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821866278.7U Expired - Fee Related CN209317314U (en) | 2018-11-13 | 2018-11-13 | A kind of high efficiency plasma waste gas treatment equipment |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209317314U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113101793A (en) * | 2021-04-21 | 2021-07-13 | 南京禄口禽业发展有限公司 | Tail gas treatment device, tail gas treatment method and application thereof |
-
2018
- 2018-11-13 CN CN201821866278.7U patent/CN209317314U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113101793A (en) * | 2021-04-21 | 2021-07-13 | 南京禄口禽业发展有限公司 | Tail gas treatment device, tail gas treatment method and application thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204952563U (en) | Thorough purifier of bad acid mist air is followed to high efficiency | |
CN204996283U (en) | Boiler exhaust -gas treatment apparatus | |
CN209317314U (en) | A kind of high efficiency plasma waste gas treatment equipment | |
CN106861382A (en) | A kind of low-temperature plasma waste gas treatment device | |
CN212362274U (en) | Air purification device with drying and aroma-enhancing functions | |
CN205340444U (en) | Purifier is used in workshop | |
CN205867863U (en) | Flue gas purification treatment device | |
CN104841234A (en) | Washing type waste gas treatment device | |
CN204656264U (en) | A kind of emission-control equipment of rinsing type | |
CN207734819U (en) | A kind of burning boiler emission-control equipment | |
CN207871816U (en) | A kind of simple waste gas treatment equipment | |
CN207356894U (en) | A kind of photocatalytic waste gas treatment device | |
CN207324501U (en) | A kind of desulphurization denitration purifying and dedusting device of flue gas | |
CN205760247U (en) | A kind of multifunctional pulse sack cleaner | |
CN213348302U (en) | Exhaust gas purification device is used in autoclaved brick production | |
CN211133382U (en) | Workshop waste gas dust collector | |
CN208287749U (en) | A kind of recyclable emission-control equipment | |
CN208553695U (en) | A kind of equipment for treating industrial waste gas | |
CN208130693U (en) | Waste gas treatment equipment in a kind of manufacture of cement of environmental protection | |
CN209173737U (en) | A kind of biological treatment exhaust device | |
CN209791264U (en) | High-efficient SOx/NOx control exhaust gas purification device | |
CN207614648U (en) | A kind of device of UV photodissociation processing organic exhaust gas | |
CN207694528U (en) | Industrial tail gas flue dust and formaldehyde comprehensive treatment system | |
CN207169342U (en) | A kind of industrial waste gas purification device | |
CN207605502U (en) | A kind of metabolic water leaching emission-control equipment |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190830 Termination date: 20201113 |
|
CF01 | Termination of patent right due to non-payment of annual fee |