CN213348302U - Exhaust gas purification device is used in autoclaved brick production - Google Patents

Exhaust gas purification device is used in autoclaved brick production Download PDF

Info

Publication number
CN213348302U
CN213348302U CN202021783928.9U CN202021783928U CN213348302U CN 213348302 U CN213348302 U CN 213348302U CN 202021783928 U CN202021783928 U CN 202021783928U CN 213348302 U CN213348302 U CN 213348302U
Authority
CN
China
Prior art keywords
gas purification
purification device
exhaust gas
pipeline
waste gas
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021783928.9U
Other languages
Chinese (zh)
Inventor
王志和
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yuzhou Shengshi Energy Saving Material Co ltd
Original Assignee
Yuzhou Shengshi Energy Saving Material Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yuzhou Shengshi Energy Saving Material Co ltd filed Critical Yuzhou Shengshi Energy Saving Material Co ltd
Priority to CN202021783928.9U priority Critical patent/CN213348302U/en
Application granted granted Critical
Publication of CN213348302U publication Critical patent/CN213348302U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Treating Waste Gases (AREA)

Abstract

The utility model discloses a steam pressure brick production is with exhaust gas purification device relates to exhaust gas purification technical field, can produce the waste gas that contains the smoke and dust in a large number in solving current steam pressure brick production process, and the direct emission of waste gas can cause air pollution's problem. Sealed enhancement limit is all installed to the both sides of exhaust gas purification device casing, the fixed casing of wind-guiding is all installed in the outside on sealed enhancement limit, two the connection admission line is installed respectively in the outside of the fixed casing of wind-guiding and the fixed pipeline of emission, activated carbon adsorption stopping is all installed to the inside both sides of exhaust gas purification device casing, the water conservancy diversion pipeline is installed to the intermediate position department of the inside top of exhaust gas purification device casing, install the booster pump on the water conservancy diversion pipeline, the dismantlement clearance frame is all installed to the both sides of exhaust gas purification device casing front end, the reposition of redundant personnel pipeline is installed to the below of water conservancy diversion pipeline, the shower head is installed to the below of reposition of redundant personnel pipeline.

Description

Exhaust gas purification device is used in autoclaved brick production
Technical Field
The utility model relates to a waste gas purification technical field specifically is a waste gas purification device is used in autoclaved brick production.
Background
The waste gas purification (flow gas purification) mainly refers to the treatment work of industrial waste gas such as dust particles, smoke and dust, peculiar smell gas and toxic and harmful gas generated in industrial places. The common waste gas purification includes factory smoke and dust waste gas purification, workshop dust waste gas purification, organic waste gas purification, waste gas peculiar smell purification, acid-base waste gas purification, chemical waste gas purification and the like, waste gas discharged in industrial production often has harmful influence on environment and human health, purification measures are adopted to treat the waste gas before the waste gas is discharged into the atmosphere, so that the waste gas meets the requirement of waste gas discharge standard, and the process is called waste gas purification. Common methods for exhaust gas purification are: absorption method, adsorption method, condensation method and combustion method.
However, a large amount of waste gas containing smoke dust is generated in the production process of the existing autoclaved brick, and the air pollution is caused by the direct emission of the waste gas; therefore, the existing requirements are not met, and the waste gas purification device for producing the autoclaved brick is provided for the existing waste gas purification device.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a steam pressure brick waste gas purification device for production to can produce the waste gas that contains the smoke and dust in a large number in solving the current steam pressure brick production process that proposes in the above-mentioned background art, waste gas direct discharge can cause air pollution's problem.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides an exhaust gas purification device is used in autoclaved brick production, includes the exhaust gas purification device casing, sealed enhancement limit is all installed to the both sides of exhaust gas purification device casing, the fixed casing of wind-guiding is all installed in the outside on sealed enhancement limit, two the outside of the fixed casing of wind-guiding is installed respectively and is connected inlet duct and discharge fixed pipeline, activated carbon adsorption stopping is all installed to the inside both sides of exhaust gas purification device casing, the intermediate position department of the inside top of exhaust gas purification device casing installs the water conservancy diversion pipeline, install the booster pump on the water conservancy diversion pipeline, the dismantlement clearance frame is all installed to the both sides of exhaust gas purification device casing front end.
Preferably, connect all install the fan on the admission line and discharge fixed pipeline, and the fan with connect the admission line and discharge the equal sealing connection of fixed pipeline, discharge the opposite side of fixed pipeline and install and purify the discharge line, purify the top of discharge line and install rain-proof cap.
Preferably, the installing and connecting blocks are installed on two sides of the rear end of the shell of the waste gas purification device and connected with the shell of the waste gas purification device through screws, a water inlet connecting pipeline is arranged at the middle position above the shell of the waste gas purification device, and a water drainage connecting pipeline is arranged at the middle position below the shell of the waste gas purification device.
Preferably, the activated carbon adsorption filler passes through the draw-in groove with exhaust gas purification device casing and is connected, the reposition of redundant personnel pipeline is installed to the below of water conservancy diversion pipeline, the shower head is installed to the below of reposition of redundant personnel pipeline, and the shower head is provided with a plurality of, and a plurality of shower head distributes in proper order.
Preferably, the heating block is installed at the middle position inside the shell of the waste gas purification device, the conical water drainage block is installed on two sides of the lower part inside the shell of the waste gas purification device, and the conical water drainage block is connected with the shell of the waste gas purification device through screws.
Preferably, installation limiting clamping edges are installed on two sides of the interior of the shell of the waste gas purification device, and installation limiting clamping grooves are formed between the installation limiting clamping edges.
Preferably, dismantle the inboard of clearance frame and install the spacing of installation, the internally mounted of the spacing of installation has the absorption fixed bolster, and adsorbs the fixed bolster and pass through the draw-in groove with the spacing frame of installation and be connected, the both ends of the spacing frame of installation all are provided with the installation fixed orifices.
Compared with the prior art, the beneficial effects of the utility model are that:
1. the utility model discloses an all install active carbon adsorption stopping in the inside both sides of exhaust gas purification device casing, can effectively adsorb remaining impurity in the waste gas, spray through being provided with spray line, the high temperature that the heating block produced simultaneously can effectively eliminate the harmful position in the waste gas, can better guarantee exhaust-gas treatment emission performance, solved can produce a large amount of waste gases that contain the smoke and dust in the current autoclaved brick production process, the problem that the direct emission of waste gas can cause air pollution;
2. the utility model discloses an all install the fan on the pipeline of both sides, the water conservancy diversion performance of guarantee waste gas that can be better can promote the efficiency of processing to a certain extent, adsorbs the fixed bolster, can be better filter the absorption to harmful substance, the later stage directly to adsorb the fixed bolster change can, structural performance is simple perfect more.
Drawings
FIG. 1 is a front view of a waste gas purifying device for producing autoclaved bricks;
FIG. 2 is a sectional view of the waste gas purifying device for producing autoclaved bricks;
fig. 3 is the structure diagram of the utility model discloses dismantle clearance frame and exhaust gas purification device casing.
In the figure: 1. an exhaust gas purification device casing; 2. sealing the reinforcing edge; 3. the air guide fixing shell; 4. connecting an air inlet pipeline; 5. discharging the fixed pipe; 6. a fan; 7. purifying the discharge pipeline; 8. rain-proof caps; 9. installing a connecting block; 10. a water inlet connecting pipeline; 11. a drain connecting pipe; 12. disassembling the cleaning frame; 13. activated carbon adsorption filler; 14. a diversion pipeline; 15. a booster pump; 16. a diversion pipeline; 17. a shower head; 18. a heating block; 19. a conical watering block; 20. installing a limiting clamping edge; 21. installing a limiting clamping groove; 22. installing a limiting frame; 23. an adsorption fixing pad; 24. and installing a fixing hole.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
Referring to fig. 1-3, the present invention provides an embodiment: the utility model provides a waste gas purification device is used in autoclaved brick production, including waste gas purification device casing 1, sealed enhancement limit 2 is all installed to waste gas purification device casing 1's both sides, sealed fixed casing 3 of wind-guiding is all installed in the outside on enhancement limit 2, the outside of two fixed casings 3 of wind-guiding is installed respectively and is connected admission line 4 and emission fixed pipeline 5, activated carbon adsorption stopping 13 is all installed to waste gas purification device casing 1 inside both sides, the middle position department of waste gas purification device casing 1 inside top installs water conservancy diversion pipeline 14, install booster pump 15 on the water conservancy diversion pipeline 14, dismantlement clearance frame 12 is all installed to the both sides of waste gas purification device casing 1 front end.
Further, connect and all install fan 6 on admission line 4 and the emission fixed pipeline 5, and fan 6 with be connected admission line 4 and the equal sealing connection of emission fixed pipeline 5, the opposite side of emission fixed pipeline 5 is installed and is purified emission pipeline 7, purifies the top of emission pipeline 7 and installs rain-proof cap 8, the stability ability that the guarantee that can be better discharged.
Further, erection joint piece 9 is all installed to the both sides of 1 rear end of exhaust gas purification device casing, and erection joint piece 9 passes through the screw connection with exhaust gas purification device casing 1, and the intermediate position department of 1 top of exhaust gas purification device casing is provided with into water connecting pipe 10, and the intermediate position department of 1 below of exhaust gas purification device casing is provided with drainage connecting pipe 11, and guarantee that can be better sprays the stability ability of water guide.
Further, activated carbon adsorption filler 13 passes through the draw-in groove with exhaust gas purification device casing 1 and is connected, and diversion pipeline 16 is installed to the below of diversion pipeline 14, and shower head 17 is installed to the below of diversion pipeline 16, and shower head 17 is provided with a plurality of, and a plurality of shower head 17 distributes in proper order, and the spraying performance is more stable perfect.
Further, heating block 18 is installed to the inside intermediate position department of exhaust gas purification device casing 1, and toper piece 19 of launching is all installed to the both sides of the inside below of exhaust gas purification device casing 1, and toper piece 19 of launching passes through the screw connection with exhaust gas purification device casing 1, and handling performance has obtained better guarantee, and stability is higher.
Further, installation limiting clamping edges 20 are installed on two sides of the interior of the waste gas purification device shell 1, installation limiting clamping grooves 21 are formed between the two installation limiting clamping edges 20, and the installation limiting stability can be better guaranteed.
Further, dismantle the inboard of clearance frame 12 and install installation spacing 22, the internally mounted of installation spacing 22 has the absorption fixed bolster 23, and adsorbs the fixed bolster 23 and pass through the draw-in groove with installation spacing 22 and be connected, and the both ends of installation spacing 22 all are provided with installation fixed orifices 24, and installation fixity can be more stable perfect, and the practicality is higher.
The working principle is as follows: when in use, the connection air inlet pipeline 4 is hermetically connected with the waste gas pipeline, waste gas enters the waste gas purification device shell 1 through the connection air inlet pipeline 4 and the air guide fixing shell 3, the fan 6 can better ensure the air supply performance, waste gas can enter the middle part through the activated carbon adsorption filler 13 and the adsorption fixing pad 23, the water inlet connecting pipeline 10 and the water discharge connecting pipeline 11 can be respectively hermetically connected with the water inlet pipe and the waste water discharge pipe, spray water passes through the flow guide pipeline 14, the booster pump 15, the flow distribution pipeline 16 and the spray head 17 and is sprayed out through the spray head 17, the spray performance can be better ensured, residual impurities in the waste gas can be adsorbed on the spray water and fall down to be led out through the water discharge connecting pipeline 11, the heating block 18 can heat to eliminate the internal impurities, the waste gas passes through the adsorption fixing pad 23 and the activated carbon adsorption filler 13 on the other side and is led out through the discharge fixing pipeline 5 and the, the processing process is simpler and the efficiency is higher.
It is obvious to a person skilled in the art that the invention is not restricted to details of the above-described exemplary embodiments, but that it can be implemented in other specific forms without departing from the spirit or essential characteristics of the invention. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.

Claims (7)

1. The utility model provides a steam pressure is exhaust gas purification device for brick production, includes exhaust gas purification device casing (1), its characterized in that: sealed enhancement limit (2) are all installed to the both sides of exhaust gas purification device casing (1), sealed fixed casing of wind-guiding (3) are all installed in the outside of strengthening limit (2), two the outside of the fixed casing of wind-guiding (3) is installed respectively and is connected admission line (4) and emission fixed pipeline (5), activated carbon adsorption stopping (13) are all installed to the inside both sides of exhaust gas purification device casing (1), intermediate position department of the inside top of exhaust gas purification device casing (1) installs water conservancy diversion pipeline (14), install booster pump (15) on water conservancy diversion pipeline (14), dismantlement clearance frame (12) are all installed to the both sides of exhaust gas purification device casing (1) front end.
2. The exhaust gas purification device for autoclaved brick production according to claim 1, characterized in that: connect admission line (4) and discharge all install fan (6) on fixed pipeline (5), and fan (6) with be connected admission line (4) and discharge the equal sealing connection of fixed pipeline (5), discharge the opposite side of fixed pipeline (5) and install and purify discharge pipeline (7), it installs rain-proof cap (8) to purify the top of discharging pipeline (7).
3. The exhaust gas purification device for autoclaved brick production according to claim 1, characterized in that: installing connection blocks (9) are installed on the two sides of the rear end of the waste gas purification device shell (1), the installing connection blocks (9) are connected with the waste gas purification device shell (1) through screws, a water inlet connecting pipeline (10) is arranged at the middle position above the waste gas purification device shell (1), and a water drainage connecting pipeline (11) is arranged at the middle position below the waste gas purification device shell (1).
4. The exhaust gas purification device for autoclaved brick production according to claim 1, characterized in that: activated carbon adsorption stopping (13) and exhaust gas purification device casing (1) are connected through the draw-in groove, diversion pipeline (16) are installed to the below of diversion pipeline (14), shower head (17) are installed to the below of diversion pipeline (16), and shower head (17) are provided with a plurality of, and a plurality of shower head (17) distribute in proper order.
5. The exhaust gas purification device for autoclaved brick production according to claim 1, characterized in that: the waste gas purification device is characterized in that a heating block (18) is installed in the middle of the interior of the shell (1), a conical water discharging block (19) is installed on two sides of the lower portion of the interior of the shell (1), and the conical water discharging block (19) is connected with the shell (1) of the waste gas purification device through screws.
6. The exhaust gas purification device for autoclaved brick production according to claim 1, characterized in that: installation limiting clamping edges (20) are installed on two sides of the interior of the waste gas purification device shell (1), and installation limiting clamping grooves (21) are arranged between the installation limiting clamping edges (20).
7. The exhaust gas purification device for autoclaved brick production according to claim 1, characterized in that: dismantle the inboard of clearance frame (12) and install installation spacing frame (22), the internally mounted of installation spacing frame (22) has absorption fixed bolster (23), and adsorbs fixed bolster (23) and is connected through the draw-in groove with installation spacing frame (22), the both ends of installation spacing frame (22) all are provided with installation fixed orifices (24).
CN202021783928.9U 2020-08-24 2020-08-24 Exhaust gas purification device is used in autoclaved brick production Active CN213348302U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021783928.9U CN213348302U (en) 2020-08-24 2020-08-24 Exhaust gas purification device is used in autoclaved brick production

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021783928.9U CN213348302U (en) 2020-08-24 2020-08-24 Exhaust gas purification device is used in autoclaved brick production

Publications (1)

Publication Number Publication Date
CN213348302U true CN213348302U (en) 2021-06-04

Family

ID=76146931

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021783928.9U Active CN213348302U (en) 2020-08-24 2020-08-24 Exhaust gas purification device is used in autoclaved brick production

Country Status (1)

Country Link
CN (1) CN213348302U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117654197A (en) * 2024-01-31 2024-03-08 福建众辉环保设备有限公司 Waste gas treatment device for garbage incineration equipment

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117654197A (en) * 2024-01-31 2024-03-08 福建众辉环保设备有限公司 Waste gas treatment device for garbage incineration equipment

Similar Documents

Publication Publication Date Title
CN105771595A (en) Industrial waste gas in-depth purifying treatment system
CN103446840B (en) A kind of dusty gas and particulate burning purifying treatment system
CN213348302U (en) Exhaust gas purification device is used in autoclaved brick production
CN211411395U (en) Multi-pipeline synchronous waste gas collecting device
CN211051150U (en) Poisonous and harmful gaseous pollutants administers deep purification device
CN202962190U (en) Welding dedusting and purifying device
CN210495866U (en) Environment-friendly exhaust gas purification device for granulating chemical fiber friction material
CN106000001A (en) Efficient waste gas treatment device
CN208959638U (en) A kind of photocatalysis catalyst exhaust treatment system
CN207356894U (en) A kind of photocatalytic waste gas treatment device
CN202427317U (en) Flue gas purifying device
CN214159077U (en) UV photodissociation clarifier for exhaust emission
CN205392132U (en) A carbon fiber absorber for acid mist purification tower
CN205627568U (en) Organic waste gas purifying equipment
CN210070634U (en) Heat treatment oil smoke processing system
CN206424787U (en) Feed Manufacturing exhaust treatment system
CN205461645U (en) Special high -efficient desorption system of adsorbing of spraying waste gas
CN206414950U (en) One kind clamps type high-temp waste gas clarifier
CN213253718U (en) Multifunctional waste gas treatment device
CN217961934U (en) Organic waste gas treatment system
CN220257610U (en) Energy-saving treatment equipment for VOC organic waste gas
CN210410157U (en) Industrial waste gas treatment device
CN205182435U (en) Industrial waste gas treating device
CN219252106U (en) A environmental protection waste gas dust collecting equipment for it is indoor
CN205191744U (en) A air purification equipment for workshop

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant